Agenda Item No: K.10

AGENDA REPORT
DATE: October 20, 2026
TO: Mayor and Council
FROM: David Gassaway, City Manager
SUBJECT: Resolutions 2026-203 and 2026-204 PW Additional Funding for Shaw Kawasaki Architects for Fire Station 36 and Additional Funding for Shaw Kawasaki Architects for Fire Station 39
Resolution 2026-203 Authorizing the City Manager to Execute Amendment No. 7 to the Professional Services Agreement for Architectural Design Services with Shaw Kawasaki Architects for Fire Station 36; and
Resolution 2026-204 Authorizing the City Manager to Execute Amendment No. 4 to the Professional Services Agreement for Architectural Design Services with Shaw Kawasaki Architects for Fire Station 39
Funding Source: $133,032 ($68,506, CFD 3; $64,526, CFD 2023-1) Contact: Ryan Panganiban, (707) 428-7017

RECOMMENDED ACTION
Adopt resolutions.

STATEMENT OF ISSUE
The City Council previously awarded architectural design contracts to Shah Kawasaki Architects (SKA) for the Fire Station 36 and Fire Station 39 Project (Project). As construction progresses toward completion later this year, contract amendments are necessary to address the Project scope changes and extended durations. Staff recommend executing amendments to the Professional Services Agreement (PSA) for SKA to incorporate: 1) new adjusted rate schedule; 2) additional funding for extended construction administration services; and 3) additional funding for building commissioning scope, covering essential testing and system commissioning services prior to facility occupancy.

DISCUSSION
On August 17, 2021, the council awarded the architectural design contract for Fire Station 36 through Resolution No. 2021-208. Additionally, on September 6, 2022, the council awarded the architectural design contract for Fire Station 39 to SKA through Resolution No. 2022-235. The proposed amendments increase contract authority to cover inflation adjustments associated with the easement acquisition schedule adjustment, extended Construction Administration services, and Commissioning Services. Sufficient funding is available within the existing project budgets; no additional budget appropriation is requested.  Schedule adjustment and related inflation costs: Fire Stations 36 and 39 were planned to be bid together under one construction contract for a prime general contractor to build both facilities. Following SKA’s completion of the final construction documents, including plans, specifications, and cost estimates, the Project’s bidding schedule was adjusted to allow the City to negotiate and secure a property easement from an adjacent property owner on Neitzel Road. The easement enabled a gravity sewer connection for Fire Station 36, eliminating the need for an off-site lift station and its associated long-term operations and maintenance costs. The start dates for SKA’s bidding, negotiation, construction administration, and record documents tasks shifted from October 2022 to April 2025, a period of 30 months. A proposed inflation adjustment of 7.64%, based on Consumer Price Index data published by the United States Bureau of Labor Statistics, accounts for cost escalation during this period. The adjustment totals $54,333.35 for Fire Station 36 and $31,174.29 for Fire Station 39.  Extended Construction Administration: SKA’s original fee for construction administration assumed a 14-month construction duration. However, accounting for the contract’s 300 working days alongside 25 non-working weather days resulted in a total extended duration of 16 months. The cost impact for the two additional months of construction administration support is $7,944 each for Fire Station 36 and Fire Station 39.
 Additional Scope for Commissioning: Commissioning was not included in the original design scope. It is an essential and prerequisite process to ensure that the facilities are delivered operational with full system integration. Amendment No. 7 for Fire Station 36 included this scope of work; however, Fire Station 39 will require additional contract authorization in the amount of $19,541.50 for the commissioning agent services.

Portions of the initial management reserves were used to address earlier Project requirements.

The remaining reserves within the existing contract authorization are $2,386.50 for Fire Station 36 and $4,649 for Fire Station 39. These amounts are insufficient to cover the proposed additional services; therefore, an increase in contract authority is requested. Sufficient funding is available within the existing project budgets, and no additional budget appropriation is requested. The table below provides a breakdown of the proposed contract amendments for each fire station.

Fire Station 36 Fire Station 39

1. Delayed Phase CPI
Adjustment
$54,334 $31,174

2. Extended Construction
Administration
$7,944 $7,944

3. Commissioning Prior amendment $19,541.50
Amendment Request Total $62,278 $58,660
10% Management Reserve $6,228 $5,866
Authorization Request Total $68,506 $64,526
Previous Professional
Services Agreement
Authorization
$1,206,128.00 $665,830.00
Revised Professional Services
Agreement Authorization
Amount
$1,274,634 $730,356

FINANCIAL IMPACT
For Fire Station 36, the total authorization for the amendment is a not-to-exceed amount of $68,506, which is the total amount of the additional scope plus a 10% management reserve. This increases the PSA authorization to $1,274,634. Funding for this amendment is allocated within the Project (CPW010036).

For Fire Station 39, the total authorization for the amendment is a not-to-exceed amount of $64,526, which is the total amount of the additional scope plus a 10% management reserve. This increases the PSA authorization to $730,356. Funding for this amendment is allocated within the Project (CPW010092).

PUBLIC CONTACT/ADVISORY BODY RECOMMENDATION
N/A

ALTERNATIVE ACTION
The council may choose not to approve these amendments. The Project will lack the required design and commissioning support needed to complete the Project in a timely manner, resulting in construction delays, potential contractor claims, and increased overall Project costs.

COORDINATED WITH
Finance Department and Fire Department

STAFF CONTACT
Ryan Panganiban, Assistant Public Works Director and City Engineer (707) 428-7017
[email protected]

ATTACHMENTS
Attachment 2: Proposed Resolution – Fire Station 36
Attachment 3: Proposed Resolution – Fire Station 39
Attachment 4: Amendment No. 7 Fire Station 36
Attachment 5: Amendment No. 4. Fire Station 39
Attachment 6: Original Fire Station 36 Original Agreement Attachment 7: Amendment No. 1 Fire Station 36
Attachment 8: Amendment No. 2 Fire Station 36
Attachment 9: Amendment No. 3 Fire Station 36
Attachment 10: Amendment No. 4 Fire Station 36
Attachment 11: Amendment No. 5 Fire Station 36
Attachment 12: Amendment No. 6 Fire Station 36
Attachment 13: Original Fire Station 39 Original Agreement Attachment 14: Amendment No. 1 Fire Station 39
Attachment 15: Amendment No. 2 Fire Station 39
Attachment 16: Amendment No. 3 Fire Station 39