Agenda Item No: K.11
AGENDA REPORT
DATE: October 20, 2026
TO: Mayor and Council
FROM: David Gassaway, City Manager
SUBJECT: Resolution 2026-205 PW Increasing Authorization and Change Order Authority for West Texas Street Complete Streets Project
Increasing Budget Authorization and Change Order Authority for West Texas Street Complete Streets Project
Funding Source: $677,714 ($340,669, Senate Bill 1; $337,045, State Grant [Active Transportation Program])
Contact: Ryan Panganiban, (707) 428-7017
RECOMMENDED ACTION
Adopt resolution.
STATEMENT OF ISSUE
The attached resolution authorizes a contract adjustment to the West Texas Complete Streets Project (Project). Additional work beyond the initial scope was identified during construction.
This unplanned work was required to improve the pavement’s structural section and enhance traffic safety improvements along the corridor. Authorizing the resolution will allow for an increase in the contract with Ghilotti Brothers, Inc. (GBI) by up to $677,714 for a total amount not to exceed $12,265,424.
DISCUSSION
On April 15, 2025, the City Council adopted Resolution No. 2025-60, awarding the Project construction contract to GBI. Construction began in July 2025 and is currently substantively completed. The Project consists of safety and traffic calming improvements such as installation widened sidewalks, crosswalk rapid flashing beacons, new traffic signal, medians and Class IV separated bike lanes. The Project also includes pavement overlay, new striping, and new Americans with Disabilities Act (ADA) ramp upgrades, curb and gutter replacements and storm drain improvements.
The Project Engineer’s Estimate for the Project was $11,274,000. GBI submitted a bid of $10,084,965, approximately 10% below the Engineer’s Estimate. The Project secured a state grant through the Active Transportation Program in the amount of $10.9 million. To effectively utilize state grant funding available and to leverage Senate Bill 1 funds, Public Works has issued two change orders within the scope of the Project's construction contract:
Change Order Description and Benefits Cost
1) Asphalt
Overlay
Paving Fabric
Moisture barrier, stress absorption, and structural
reinforcement designed to improve pavement durability
and extend its service life.
$340,669
2) Traffic Safety
Improvements
Installation of touchless pedestrian push buttons, traffic cameras, a dedicated left-turn signal at Gregory Street, and upgraded traffic poles to enhance roadway safety and
optimize traffic flow.
$337,045
The Public Works construction team has proactively addressed challenges encountered during the Project and collaborated with the Traffic and Operations Division to improve traffic safety and durability. These efforts have resulted in decreased liability, long-term maintenance costs and optimized traffic flows. The original construction authorization for this project was $11,597,710, which is the total bid amount plus a 15% contingency.
To fund the additional out of scope work, staff recommend that the proposed resolution be approved to increase the amount authorized for the construction contract by $677,714 for a total not-to-exceed amount of $12,265,424. This increased amount is within the approved budget for this Project and has no impact on the budgets of other capital projects.
FINANCIAL IMPACT
The total construction authorization adjustment is $677,714, which will increase the total authorized contract amount to $12,265,424. The Project is budgeted in the Capital Streets Fund (Fund 252, Project CPW070110). The existing Project budget has sufficient reserves to accommodate the increase in authorization.
PUBLIC CONTACT/ADVISORY BODY RECOMMENDATION
N/A
ALTERNATIVE ACTION
The proposed modification is required to complete the Project. If the council has any questions, this request may be delayed so that staff can provide the necessary additional information.
COORDINATED WITH
N/A
STAFF CONTACT
David Vong, Senior Civil Engineer
(707) 428-7784
[email protected]
ATTACHMENTS
Attachment 2: Proposed Resolution