Agenda Item No: K.4
AGENDA REPORT
DATE: October 20, 2026
TO: Mayor and Council
FROM: David Gassaway, city manager
SUBJECT: Resolution 2026-197 PW Vanden Road Widening Phase 1 Design Authorizing the City Manager to Execute a Professional Services Agreement with Carlson, Barbee & Gibson, Inc. to Provide Engineering Design Services for the Vanden Road Widening Improvements Project (Jepson Parkway Segment 17A, 17B, and 18) Phase 1 Embankment, and Authorizing an Update to the Fiscal Year 2026-2027 Budget and 5-Year Capital Improvement Plan Funding Source: $350,000 ($233,333, Northeast Transportation Fund; $116,667, Capital Street Funds Assembly Bill 1600 Streets Fund)
Contact: Ryan Panganiban, (707) 428-7017
RECOMMENDED ACTION
Adopt resolution.
STATEMENT OF ISSUE
Construction of the Vanden Road Widening Improvement Project is planned to be designed and bid in separate phases due to its complexity and traffic impact to existing arterial roadways. The first phase consists of remedial grading for the Union Creek bridge and placement of soil to prepare the embankment for the roadway and future New Canon Road overcrossing. Staff recommend that the City Council authorize the city manager to execute a $164,500 Professional Services Agreement (PSA) with Carlson, Barbee & Gibson, Inc. (CBG) and approve the associated budget amendment within the fiscal year (FY) 2026–2027 Budget. These actions will fund completion of the engineering plans, specifications, and cost estimates for the first phase, allowing it to advance to construction.
DISCUSSION
The cities of Fairfield and Vacaville have been working with Solano County and the Solano Transportation Authority (STA) since 1999 to develop a common vision for a regional alternative to Interstate 80 through eastern Suisun, Fairfield, and Vacaville. STA adopted the concept plan for this roadway, known as Jepson Parkway, in 2000. The planned four to six lane arterials will provide an efficient alternative to Interstate 80 for local travel and improve connectivity between communities.
The Vanden Road Widening Improvement Project is part of the Jepson Parkway corridor and will widen and realign Vanden Road to accommodate an ultimate roadway configuration of four to six lanes. In 2018, the city completed widening improvements from Peabody Road to approximately 645 feet south of Lake Trail. The next phase extends northeasterly from that point to beyond existing Canon Road and includes approximately 4,650 linear feet of roadway improvements, embankment grading, a new bridge over Union Creek, underground utilities, drainage facilities, sidewalks, streetlights, and intersection improvements. This portion of the corridor is designated as Jepson Parkway Segments 17A, 17B, and 18 (Project) in plans and funding documents.
The Project will be constructed in multiple phases to align with available funding and to minimize traffic impacts on existing arterial roadways. Phase 1 of the Project involves preliminary grading to stabilize the underlying soils and the placement of fill to construct the embankment for the future roadway and the New Canon Road overcrossing of the Union Pacific Railroad. Existing overhead utility poles intersect with the proposed Vanden Road widening and will need to remain in place and be protected during grading until the ground elevations at their designated relocation sites are established. Completing this grading phase will enable Pacific Gas and Electric Company (PG&E) to relocate the utility poles and prepare the corridor for subsequent construction activities.
Staff recommend CBG as the most qualified firm to provide engineering design services for Phase 1 of the Project based on its extensive familiarity with the improvements of Vanden Road. CBG previously prepared the roadway plan lines and initial concept-level design in 2013 and served as the engineer of record for the adjoining segment completed in 2018. This prior experience ensures continuity with previous design work and supports efficient coordination of the proposed grading with utility relocations and subsequent roadway improvements. The proposed PSA with CBG, in the amount of $164,500, will provide engineering design services for the Phase 1 Project, including supplemental surveying, preparation of grading plans, technical specifications, bid documents, and supporting coordination.
Geotechnical studies and remedial grading design are excluded from CBG’s scope of work and will be addressed through a separate agreement with ENGEO. ENGEO is familiar with the Phase 1 Project and has conducted site reconnaissance, laboratory testing, and provided recommendations related to grading, slope stability, retaining walls, and settlement. ENGEO have also delivered 30% design-level remedial grading and ground improvement plans. Staff request an allocation of $100,000 to facilitate negotiations with ENGEO regarding scope of work and fees to update and finalize the necessary geotechnical analyses.
The preliminary construction cost estimate for the Phase 1 Project ranges from $8.2 million to $8.5 million and will be refined as the design progresses. Phase 1 of the Project is identified in the citywide AB1600 and Northeast Specific Plan development impact fee programs. Staff are developing a funding plan that identifies all Phase 1 Project costs including construction management, testing and inspection, etc. and will return to council at a future date for budget authorization needed before proceeding with construction.
FINANCIAL IMPACT
Total authorization for the engineering design services for the Phase 1 Project is $350,000, which includes the total contract amount with CBG ($164,500) plus an allowance for ENGEO ($100,000) plus a management reserve of $85,500 for unforeseen technical or required work that may arise during completion of the plans, specifications, and engineer’s estimates. Costs will be split between $116,667 Assembly Bill (AB) 1600 Streets (Fund 261) and $233,333 Northeast Transportation (Fund 290).
The Vanden Road Widening Phase 1 Project (CPW070134) was not included in the FY 2026-2027 Capital Budget. Therefore, a budget adjustment is required to authorize a transfer of $116,666.67 from AB 1600 Streets (Fund 261) and $233,333.30 Northeast Transportation (Fund 290) and an increase appropriations to the Street Capital Fund (Fund 252). Sufficient fund balance is available, and no General Fund contribution is required.
PUBLIC CONTACT/ADVISORY BODY RECOMMENDATION
N/A
ALTERNATIVE ACTION
The council may choose not to approve the proposed PSA with CBG and the associated budget adjustment. This alternative is not recommended because it would delay completion of the Project Phase 1 grading design and subsequent utility relocations and roadway construction.
The council may choose to direct staff to initiate a separate procurement process to hire a different consultant to complete the required engineering and design for the roadway. However, this is not recommended as pursuing a new consultant contract would result in additional time for solicitation, selection, and contract execution.
COORDINATED WITH
Finance Department
STAFF CONTACT
Ryan Panganiban, Assistant Public Works Director and City Engineer (707) 428-7017
[email protected]
ATTACHMENTS
Attachment 2: Proposed Resolution
Attachment 3: Proposed Agreement
Attachment 4: Project Exhibit (Project Limits)