NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
1 NBR Water Treatment Expansion
Vacaville/Fairfield Joint Exercise of Powers Agreement
Supplemental Memorandum of Understanding Deal Points
I. Cost Allocation
The following categories represent the anticipated capital, operational, and administrative expenditures associated with the rehabilitation, restoration, and expansion components of the North Bay Regional Water Treatment Plant project (the “Project”). Consistent with the 1987 Joint Exercise of Powers Agreement (“JEPA”), any identified “sole benefit” cost that may arise in connection with any of the below categories is to be allocated 100% to the solely benefitting party, and any identified “partial sole benefit” costs are to be specifically allocated by separate mutual agreement of the Joint Powers Policy Committee (“JPPC”). At present, the engineer’s estimate associated with the Project is $XX,
1 although the parties recognize that this amount may change as the Project progresses, and any such updates will be memorialized and shared with each party’s governing body as applicable.

1. Capital Expenditures
a. Replacement, rehabilitation, and other capital expenditures2 associated with the initial facilities3 will be divided as follows:
i. If in excess of $5,000.00:

1. Per the JEPA as defined in Table 1, Cost Allocation, same as peak day capacity allocation at time cost authorized.
ii. If $5,000.00 or below:

1. Per the JEPA as defined in Table 1, Cost Allocation, amounts borne by each party will be based on the parties’ proportion of actual water use in the preceding month.

1 Note: This dollar amount has not been finalized as of the date of these deal points, but will be final before the parties execute the ultimate Supplemental MOU. Each City’s City Council will be asked to approve the Supplemental MOU and will be made aware of the engineer’s estimate for the Project as part of that process. 2 Defined in the JEPA as expenditures other than for operation and maintenance costs, to include but not be limited to: construction projects, equipment, facility or equipment replacement or rehabilitation, and contributions to major maintenance reserves, including associated predesign, design, and start-up costs if separable from general operation and maintenance costs. 3 This term is defined in the JEPA, but may be generally understood to encompass the existing NBR Water Treatment Plant as it presently exists, in its non-expanded state.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
2 b. Capital expenditures associated with restoring the initial facilities’ ability to attain a treatment capacity of 40 million gallons per day (“mgd”),4 which the initial facilities are presently rated to attain but are not in fact attaining, will be divided as follows:
i. 2/3 of cost to be borne by Fairfield
ii. 1/3 of cost to be borne by Vacaville
c. Capital expenditures for expanding the joint facilities to increase capacity, as contemplated by Section VIII of the JEPA, will be divided based on each party’s proportional increase in capacity, using an assumption of expansion from 40 mgd to 47 mgd.5 i. Fairfield’s capacity will remain at 26.66 mgd, representing a 0% share of the increased capacity, and therefore Fairfield will bear 0% of capital expenditures for the expansion.
ii. Vacaville’s capacity will increase by 7 mgd (from 13.33 to 20.33 mgd6), representing a

65.57% increase, and therefore Vacaville will bear 100% of the capital expenditures for expansion.
d. The cost of shared facilities required to support the initial facilities and the expansion (e.g., intake, electrical upgrades, and site improvements) will be allocated using an engineering cost-of-service (“ECOS”) methodology to ensure that each party pays an amount proportional to the capacity or benefit it receives. The ECOS methodology, including processes for resolving any disputes between the parties on the methodology, is to be more specifically addressed as part of the Supplemental MOU. At present, the parties anticipate a cost share that will be directly proportionate to the capacity or benefit received by that party (i.e., each party will pay its “fair share” as determined by mutual arrangement of the parties with reference to an objective methodology standard in the Supplemental MOU). e. Cost allocation associated with post-expansion operations (e.g., replacement of facilities and equipment once the Project is complete) will be addressed through a separate amendment to the JEPA or additional Supplemental MOU, as the parties may deem appropriate, and subject to separate review and approval by each party’s governing body.

4 Defined in the JEPA and West Yost business case. (Development of the Supplemental MOU will summarize the difference between nominal and actual capacity.)
5 If this assumption changes during the Project, the cost-share formula will be revisited and any necessary updates to the Supplemental MOU document will be made. At present, the facility attains treatment capacity of 30 mgd; the parties plan to formally address restoration of the ability to attain its rated capacity of 40 mgd as part of the Supplemental MOU.
6 30 mgd is the maximum capacity allocation Vacaville may reach under the JEPA; any future agreements to expand Vacaville’s capacity further will require the parties to amend the JEPA.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
3 2. Fixed and Variable Operation and Maintenance Costs a. Prior to any design work or construction commencing on the expansion, fixed and variable operation and maintenance costs will continue to be borne in the manner set out in Table 1 of the JEPA (i.e., no change from present).
b. For the duration of the design work and construction of the expansion, fixed and variable operation and maintenance costs will continue to be borne in the manner set out in Table 1 of the JEPA. For fixed operation and maintenance costs, that means each party will pay in proportion to its peak day capacity allocation at the time the cost is authorized. For variable operation and maintenance costs (except for treated water pumping power costs and construction management costs), that means each party will pay based on its projected water use, adjusted retroactively each month according to actual water use. For treated water pumping power costs, each party will pay based on its actual metered power use. For construction management costs during design and construction phases for the expansion, Fairfield will bear 50% of the overall cost, and Vacaville will bear 50% of the overall cost, reflecting each party’s share of increased capacity in the expanded facility. i. Processes for resolving any disputes between the parties relating to construction management costs during design and construction phases are to be more specifically addressed as part of the Supplemental MOU.
c. After expansion is complete:
i. Fixed operation and maintenance costs will be allocated according to each party’s post-expansion facility ownership percentage.
ii. Variable operation and maintenance costs and ongoing repair and replacement costs associated with the expanded facilities will be allocated according to each party’s projected water use, adjusted retroactively each month according to actual water use.

3. Administrative and General Costs
a. Prior to and during design and construction of the expansion, direct and indirect administrative costs (including, but not limited to, permitting expenses, salaries and wages, insurance, and related incidental expenses) are considered a “fixed operation and maintenance cost” per Sections I and IV.C. of the JEPA, and the Administering Party7 will

7 The JEPA presently designates the City of Fairfield as the Administering Party.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
4 have those costs reimbursed out of the JPA Fund8 except for fees, taxes, or in lieu fees or taxes incurred for the sole benefit of the Administering Party. b. After expansion is complete, direct and indirect administrative and general costs will still be considered fixed operation and maintenance costs and will be allocated (in alignment with Section I.2.c.i. of this deal points document, above) according to each party’s post-expansion facility ownership percentage. i. Through the Supplemental MOU, the parties will establish a staffing review process to evaluate current staffing capabilities and demands associated with the Project, any proposed new positions to be created, or other material changes to baseline staffing.

This process will include, at a minimum, requiring written justification before making any staffing changes that sets out operational need addressed by the proposed change, cost impacts, and what alternatives were considered. The process will also include a defined review period for both parties to consider the requested change(s) and seek additional information as needed prior to a formal approval or rejection of the request by the JPPC.

II. Design and Delivery of Expansion

1. Delivery. The parties agree to use a progressive design-build delivery method for the Project, or such other mutually agreeable competitive contracting mechanism for Project delivery as may be authorized under state public contract law and the parties’ procurement policies.

2. Design Specifications.
a. The basis for the design of the Project will be specified through “Design Specifications and Performance Requirements,” documented in a “Benchmark Design Report” and subject to approval by the JPPC.
i. Design specifications may be refined and adjusted to improve quality or control costs as mutual agreed by the parties until the Project’s design is completed. Such adjustments are subject to approval by the JPPC.
b. Provisions for Future Expansion (beyond the current project scope) i. Space for future expansion will be identified and reserved within the existing site boundary, in accordance with the Design Specifications and Performance Requirements to be adopted.

8 Defined in the JEPA as the fund created to cover the financial needs of the joint facilities; deposits to the JPA fund by each party are covered in Section XI of the JEPA.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
5 ii. Design for current Project will identify any features associated with future expansion that should be constructed now to minimize operational disruption during the future expansion, in accordance with the Design Specifications and Performance Report to be adopted.

3. Design Review and Approval.
a. The parties agree to follow the design review process for the expansion as is set forth in Section VII.C. of the JEPA, with potential modifications to accommodate the expansion project, to be detailed in the Supplemental MOU.
9 Any dispute resolution processes
regarding design specifications and review that may arise are to be more specifically addressed as part of the Supplemental MOU.
b. Operation, maintenance, and engineering staff from both party agencies will be afforded the opportunity to provide input during development of the detailed design for the expansion, subject to review and approval under the guidelines set forth in the JEPA and Supplemental MOU.
c. The JPPC will have final design approval authority over Projects within the property boundary of the water treatment plant, as depicted in Exhibit A. d. Outside the property boundary of the water treatment plant, as depicted in Exhibit A, the City of Vacaville’s Utilities Department or designee thereof will have final design approval over the “Vacaville Transmission Main” component of the Project. e. Outside the property boundary of the water treatment plant, as depicted in Exhibit A, the City of Fairfield’s Municipal Utility or designee thereof will have final design approval over the “Fairfield Transmission Main” component of the Project.

III. Contract Negotiation and Construction Management.

1. Terms and Price Negotiation.
a. The JPPC has authority to negotiate and approve all terms of the contract, including price. b. The JPPC will agree on a guaranteed maximum price and will recommend that value for approval by the respective City Councils or other appropriate bodies as needed. This is not intended to affect either party’s ability to secure debt financing based upon the approved

9 For example, the parties may decide to update the JEPA’s current $40,000 cap for reimbursement (and/or clarify its interpretation as applied to the Project) from the JPA Fund for each party’s independent design review (JEPA § VII.C) if such action would not require a JEPA amendment and/or refer to the Owners Rep contract independent design review. To clarify, the parties are applying the JEPA design review process designated for initial facility planning, design, and construction to the current project phase, i.e., expansion.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
6 guaranteed maximum price if needed, or to otherwise interfere with otherwise applicable approval processes under local policies or public contracting laws. c. The Supplemental MOU will further detail the abilities of each party to independently seek financing in connection with the Project, identify how the parties anticipate obtaining such financing (e.g., bonds, other debt mechanisms), and clarify the allocation of any debt service associated with the Project.

2. Construction Management. The parties agree to follow the construction management process for the expansion as is set forth in Section VII.E. of the JEPA, subject to clarification of that process as it applies to the Project in the Supplemental MOU, so long as such clarification is consistent with the intent and plain language of the JEPA. 10 Any dispute resolution processes
regarding construction management that may arise are to be more specifically addressed as part of the Supplemental MOU.

3. Change Approval Authority.
a. Modifications to, or deviations from, the adopted Design Specifications and Performance Requirements will require approval by the JPPC, except that as set forth in II.3.e. hereof, the City of Vacaville’s Utilities Director or designee will review and approve any such modifications or deviations as they pertain to the Vacaville Transmission Main component of the Project that is outside of the property boundary of the water treatment plant, as depicted in Exhibit A.
b. All construction change orders are subject to final approval of the JPPC and shall follow the Administering Party’s applicable local policies and procedures, and any applicable state or federal laws.
c. The progressive design-build contract for the Project will include allowances, as mutually agreed upon by the parties and as may be authorized under state public contract law and the parties’ procurement policies, to appropriately allocate risk. The Project budget will include an owner-controlled contingency to facilitate any unanticipated cost-effective opportunities to improve the Project as may arise during design and construction.

IV. Real Property and Facility Ownership

10 To clarify, the parties are applying the JEPA construction management process designated for initial facility planning, design, and construction to the current project phase, i.e., expansion.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
7 1. Joint property11 will continue to be governed by the JEPA. This means the parties will each own every item of joint property in proportion to the amount each party paid through the JPA Fund12 to acquire that item unless the parties agree otherwise in writing.

2. In accordance with the JEPA, should any additional land acquisition be required in connection with the Project (such as an expansion of the current Vacaville pipeline easement), each party will deposit its share of the JPPC’s estimated cost for that acquisition, including a 10% contingency.

V. Reflecting Current Operational and Administrative Practices in Supplemental MOU

1. Through the Supplemental MOU, the parties will memorialize their understanding that the existing JEPA allows Fairfield, in its capacity as the Administering Party of the JEPA, to contract on behalf of both agencies for purposes of delivering the Project and may otherwise act as a recipient for any grants or loans for the Project.

2. Through the Supplemental MOU, the parties will clearly document their understanding as to the expanded facility’s operational capabilities and each party’s share of the overall facility ownership to the extent it differs from what is documented in the JEPA.

3. Through the Supplemental MOU, the parties will determine whether the subject of emergency exceedances of their respective allocations may be negotiated and resolved in connection with the Supplemental MOU, or if an amendment to the JEPA is required.

4. The Supplemental MOU will identify a specific process for dispute resolution should the JPPC, as an entity made up of two persons holding equal voting power, reach a deadlock on any issue referred to it.

VI. General Terms of Supplemental MOU

1. Term and Termination. The Supplemental MOU will contain provisions regarding the anticipated term, how it may be terminated, what happens if a party seeks to withdraw from the Project, and the consequences of default or nonperformance.

2. Environmental Review. The Supplemental MOU will clarify each party’s responsibilities pertaining to any necessary environmental review associated with the Project.

3. Permitting and Regulatory Compliance. The Supplemental MOU will address anticipated permitting needs and how the parties will collaborate to obtain necessary permits and

11 Defined in the JEPA as any property acquired as a result of the parties jointly exercising their powers under the terms of the JEPA.
12 Defined in the JEPA as the fund created to cover the financial needs of the joint facilities (water pipelines, pumps, reservoirs, land associated with the Project, etc.) NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.
8 entitlements, how prevailing wage and labor compliance matters will be handled, and related topics.

4. Miscellaneous. The Supplemental MOU will address how the parties may amend the Supplemental MOU, notice provisions, venue for any legal purposes, and related administrative matters.

NOTE: This document is in draft form; it does not constitute an offer, and is not binding on any party.