ID Task Name Duration Start Finish
1 2 Planning 165 days Tue 2/22/22 Mon 10/10/22
3 City Review 3 wks Tue 2/22/22 Mon 3/14/22
4 DAB 0 days Mon 3/14/22 Mon 3/14/22
5 Modifications (Shared Lobby) 9 wks Tue 3/15/22 Mon 5/16/22 6 City Review 5 wks Tue 5/17/22 Mon 6/20/22
7 DAB Approval 4 wks Tue 6/21/22 Mon 7/18/22
8 Staff Report 4 wks Tue 7/19/22 Mon 8/15/22
9 Planning Commission Notice 4 wks Tue 8/16/22 Mon 9/12/22 10 Planning Commission 0 days Mon 9/12/22 Mon 9/12/22
11 City Council Notice 4 wks Tue 9/13/22 Mon 10/10/22
12 City Council Approval (MUST HIT GPA CYCLE) 0 days Mon 10/10/22 Mon 10/10/22 13 14 Environmental 101 days? Mon 2/28/22 Mon 7/18/22
15 Submit Initial Study 35 days Mon 2/28/22 Fri 4/15/22 16 City Review 7 wks Mon 2/28/22 Fri 4/15/22
17 Revise IS (Shared Lobby) 5 wks Mon 4/18/22 Fri 5/20/22 18 City Review 3 wks Mon 5/23/22 Fri 6/10/22
19 Public Review 4 wks Mon 6/13/22 Fri 7/8/22
20 Final IS Production 1 wk Mon 7/11/22 Fri 7/15/22
21 City Review 1 day? Mon 7/18/22 Mon 7/18/22
22 23 Final Engineering / Architecture 220 days Tue 2/1/22 Mon 12/5/22 24 Prepare Plans 20 wks Tue 2/1/22 Mon 6/20/22
25 City Review & Approval 6 mons Tue 6/21/22 Mon 12/5/22 26 Permit 0 days Mon 12/5/22 Mon 12/5/22
27 28 Begin Construction (expect 1 year for Phase 1) 0 days Mon 12/5/22 Mon 12/5/22 3/14
9/12
10/10
12/5
12/5
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2022 2023
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
FONTANA SQUARE With Shared Lobby
PROJECT SCHEDULE
Date Prepared: April 15, 2022
Project: Feb 2, 2022 Fontana Square S
Date: Tue 4/19/22