Revised – RP -09/22/2022
SUBDIVISION IMPROVEMENT AGREEMENT
Tract Map No.:
THIS AGREEMENT is between the City of Fontana, a municipal corporation, County of San Bernardino, State of California ("City") and
("Subdivider" ):
WHEREAS, the application for tentative Tract Map No. , was conditionally approved on ; and
WHEREAS, Subdivider is the owner of that certain parcel of land defined by the Final Map and Subdivider proposes to do and perform certain work of improvement thereon as set forth in this agreement; and
WHEREAS, City desires to assure that the proposed improvements will be done in a good workmanlike manner and in accordance with the laws and standards now in force and effect in the City, the terms and conditions of which are incorporated herein by reference; and
WHEREAS, Subdivider declares acknowledgement the pertinent regulations contained in the City Code and in the Subdivision Map Act (Government Code Sections 66410 to 66500) and agrees to comply therewith; and
WHEREAS, a Fi nal Map of the subdivision, prepared in accordance with the City's Subdivision Ordinance, has been filed by Subdivider with City for approval by the City Council;
NOW THEREFORE, in consideration of the approval and acceptance of the Final Map by the City Council and the acceptance of easements therein offered for dedication for street, utility, and other public purposes and the covenants herein contained, the parties hereto mutually covenant and agree as follows:
1. General requirements:
Subdivider shall, at its own cost and expense, provide all required tests, design work, equipment, materials and labor in order to complete all of the improvements as associated with the requirements per the approved project or to the satisfac tion of the City Engineer of the City of Fontana.
All required improvements have an estimated cost of construction totaling ____________________________________________________________ ($ ) as shown on Exhibit " A".
Improvements are shown on approved plans on file with City Engineer.
The estimated cost of construction set forth in Exhibit “A” is for estimation purposes only, and for calculation of the amount of securities 20397
Inland Senior Development LLC
20397
August 16th, 2022
Twenty Nine Thousand One Hundred Seventy Eight Dollars and 99/100 29,178.90
Revised – RP -09/22/2022
required pursuant to the provisions of section (2), below. Subdivider’s obligation to complete the improvements, or any portion of them, is not limited in any way by the estimated cost of construction, and the obligation of Subdivider’s surety in connection with the securities required pursuant to the provisions of section (2), below.
2. Security:
Subdivider shall, at all times, guarantee its performance of this agreement by furnishing to City and maintaining good and sufficient security as required by the State Subdivision Map Act on forms approved by City for the purposes and in the amounts as follows:
a. To ensure a faithful performance of this agreement in regard to the improvements in the amount of 100% of the estimated cost of construction of the improvements; and
b. To secure payment to any contractor, sub- contractor, pers ons renting equipment or furnishing labor or materials for the improvements required to be constructed or installed pursuant to this agreement in the additional amount of 100% of the estimated cost of construction of the improvements; and
c. To guarantee or warranty the work done pur suant to this agreement for a period of one (1) year following acceptance thereof by City Council of the City of Fontana against any defective work or labor done or defective materials furnished in the amount of 20% of the esti mated cost of construction of the improvements; and
d. To warranty the setting of required subdivision monuments within one - year following recordation of the Final Map in the amount of 100% of the estimated cost of setting subdivision monuments as shown in Exhibit "A".
e. To guarant ee the landscape maintenance of all landscape improvements for a period of one year (1) year following acceptance of thereof by the City.
The securities required by this agreement shall be kept on file with the City Clerk.
The terms of the security documents required by this agreement are hereby incorporated in this agreement by reference and copies attached hereto.
The security, which guarantees performance, can be released upon acceptance of the improvements by the City Council. The security which guarantees payment to contractor, sub- contractors and to persons furnishing labor, materials or equipment will be released 6 months after acceptance of the improvements by the
Revised – RP -09/22/2022
City Council, less the total of all claims to which the City has been given proper notice.
Securities may be released upon the final completion and acceptance of the work subject to the provisions herein. The City Council, in its absolute discretion, may release a portion of the security given for faithful performance of the improvement work as the improvement progresses upon application thereof by the Subdivider.
3. Time of Completion:
All of the required improvements shall be completed within 24 months from the effective date of this agreement. If the work is not completed within the specified time period because of acts of God, the public enemy, the City, or because of fire, flood, epidemic, quarantine restrictions, strikes or freight embargoes, the Subdivider shall be entitled to an extension beyond the specified time period for a period equal to the length of such delay within ten days from the beginning of such delay.
In addition to the extension for the reasons referenced in the foregoing paragraph, Subdivider may submit a written request , Exhibit “B” , for a discretionary extension of the time for completion of the improvements to the City Engineer.
The City Engineer may grant or reject such extension, in whole or in part or with conditions, in his sole discretion. If an extension of time is granted it shall in no way af fect the validity of this contract or release the surety on the securities referenced herein.
In the event that Subdivider fails to complete the improvements within the required period or any approved extension, the City may complete the work and shall be entitled to recover the full cost and expenses thereof from Subdivider, or his surety as herein provided. If City pursues completion of the improvement work, it may require Subdivider, or his surety, to pay the City in advance, sufficient monies to cover the City's cost in completing construction of the improvements.
Any limitations period provided by law related to breach of this Agreement or the terms thereof shall not commence running until Subdivider, or Subdivider’s surety pursuant to Section 2 of this Agreement, has provided the City Engineer with written notice of Subdivider’s intent to abandon or otherwise not complete the improvements.
4. Effective Date of Agreement:
This Agreement shall not become effective unless and until the Subdivision Ma p has been approved by the City Council of the City of Fontana and also accepted
Revised – RP -09/22/2022
the Final Map for reco rdation by the County Recorder of the County of San Bernardino.
5. Utility Deposits - Statements:
Prior to the commencemen t of any work to be performed within the area delineated on the Final Map, the Subdivider must file a written statement with the City Clerk and the City Engineer, signed by the Subdivider, and each public utility involved, to the effect that Subdivider has made all deposits legally required by such public utility for the connection/extension of any and all public serving utilities to be provided to or within the subdivision.
6. Permits - Compliance with Law:
Subdivider shall, at Subdivider's expense, obt ain all necessary permits and licenses, pay all charges, fees and taxes, and give all necessary and incidental notices to the due and lawful prosecution of the work.
7. Definition and Ownership of Improvements:
The term "improvements" means: grading, paving, curbs and gutters, pathways, storm drains, sanitary sewers, utilities, drainage facilities, traffic controls, landscaping, street lights, and all other required facilities as shown in detail upon plans, profiles and specifications which have been prepared or are now in final preparation by engineers acting for Subdivider subject to approval by the City Engineer of the City of Fontana. No work on the improvements shall be commenced until plans and/or profiles therefore have been submitted, approved and permitted by the City Engineer. All required public improvements constructed or installed pursuant to this Agreement shall become the sole exclusive property of the City, without payment therefore, upon acceptance of the improvements by the City Council.
8. Obligations of Subdivider:
Notwithstanding the fact that Subdivider's plans and specifications, completion of the work, and other acts are subject to approval of the City, it is understood and agreed that any approval by the City thereof shall in no way relieve Subdivider of satisfactorily performing all work on the related obligations hereunder. The construction shall be done strictly in accordance with the plans and specifications prepared by Subdivider or its engineer, and as approved by the City as being consistent with the City Code and Standards. Subdivider warrants that its plans and specifications conform as a minimum to all City codes and standards and that they are adequate to accomplish the work in a good workmanlike manner and in accordance with responsible construction practices.
Revised – RP -09/22/2022
9. Superintendence by Subdivider:
Subdivider shall personally supervise all work involved in the improvements, or shall designate a competent foreman or superintendent, satisfactory to the City Engineer, to supervise the work at all times during progress, with authority to act for Subdivider. In the event satisfactory superintendence is not being exercised by the Subdivider, the City Engineer may order suspension of all work within the subdivision until the deficiency is adequately corrected.
10. Repair and Replacements:
Subdivider shall replace, or have replaced, or repair, or have repaired, as the case may be, or pay to the owner the entire cost of replacement or repairs, for all survey monuments or for any and all property damaged or destroyed by reason of any work done hereunder, whether such property be owned by the United States or any agency thereof, or by the City or by any public or private corporation, or by any person whomsoever or by combination of such owners. Any such re pair or replacement shall be completed in a reasonable manner and subject to the approval of the City Engineer and affected property owner.
11. Inspection by City:
Subdivider shall at all times maintain proper facilities a nd provide safe access for inspection by City to all parts of the work and to the shops where the work is in preparation. The cost of inspections shall be paid by the Subdivider.
12. Approval by City Engineer.
All required improvements shall be constructed under the inspection of and subject to approval of the City Engineer. Therefore, it is mutually agreed by the parties hereto that the City Engineer shall have the right to reject any or all of the work to be performed under this contract if such work does not conform to the plans and specifications set forth herein or the City's Codes and standards. Any damage to the improvements (existing or new) that occurs during the course of work performed under this Agreement shall be repaired or replaced, by the Subdivider, to the satisfaction of the City Engineer before the final acceptance of completed work and release of security.
13. Liability for Performance Injury or Damage:
Neither the City nor any of its officers or agents shall be liable to Subdivider or its contractors for any error or omission arising out of or in connection with any work to be performed under this contract. Additionally, the City shall not be liable to the Subdivider or to any other person, firm, or corporation whatsoever, for any injury or damage that may result to any person or property by or from any
Revised – RP -09/22/2022
cause whatsoever in, on, or about the subdivision of said land covered by this Agreement, or any part thereof.
14. Indemnification and Release:
Prior to the commencement of any work pursuant to this contract, Subdivider's contractors shall furnish to City satisfactory evidence of an insurance policy written upon a form and by a company (which meets with the approval of City) insuring City, its officers, agents, and employees agains t loss or liability which may ar ise during the work or which may result from any of the work herein required to be done, including all costs of defending and claim arising as a result thereof. Minimum liability and property damage insurance shall not be less than $250,000 for all damages arising out of bodily injury to a death of one person and not less than $1,000,000 for all damages arising out of bodily injuries to or death of more than one person in any occurrence; and not less than $250,000 for all damages and/or destruction of property in any one occurrence and not less than $500,000 for all damages and/or destruction of property during the policy period.
Such policy shall be in favor of Subdivider or its contractors and of the City, its officers, agents, and employees and shall be maintained in full force and effect during the life of this contract. The policy shall state by its terms and by an endorsement that it shall not be cancelled until City shall have had at least ninety (90) days' notice in writing of such cancellation.
The Subdivider hereby releases and agrees to indemnify and save the City harmless from and against any and all injuries to and deaths of persons and injuries to property, and all claims, demands, costs, loss, damage and liabi lity, howsoever the same may be caused and whensoever the same may appear, resulting directly or indirectly from the performance or non- performance of any of or all work to be done in and upon premises adjacent thereto pursuant to this Agreement, and also from any and all injuries to and deaths of persons and injuries to property or other interests and all claims, demands, costs, loss, damage, and liability, howsoever same may be caused and whensoever the same may appear, either directly or indirectly made or suffered by the Subdivider, t he Subdivider's agents, employees, and sub- contractors, while engaged in the performance if the work.
15. Liability of Subdivider:
The Subdivider agrees that the use for any purpose and by any person of any and all of the streets, easements and improvements herein specified shall be at the sole and exclusive risk of the Subdivider at all times prior to final acceptance by the City of the completed street and other improvements thereon and therein; provided that acceptance by the City shall in no way eliminate or lessen any of Subdivider's obligations or undertakings contained in this Agreement. The issuance of any occupancy permits (if granted) by the City for buildings located within the subdivision shall not be construed in any manner to constitute an
Revised – RP -09/22/2022
acceptance and approval of any or all of the required improvements in said subdivision.
16. Relationship of Contractors:
It is hereby mutually covenanted and agreed by the parties hereto that Subdivider's contractors are not agents of the City, if any, are those of independent contractors.
17. Repair or Reconstruction of Defective Work:
If, within a period of up to one year after City Council acceptance of the improvement work performed under this Agreement, any of the improvements for work done under t his Agreement fails to fulfill any of the requirements of this Agreement, or the specifications referred to herein, Subdivider shall without delay and without any cost to the City (upon receipt of written notice from the Cit y), repair or replace or reconst ruct any defective of otherwise unsatisfactory part or parts of the work or structure. Should Subdivider fail to act promptly or in accordance with this requirement, or should the exigencies of the case require repairs or replacements to be made before Su bdivider can be notified, City may, at its own option, make the necessary repairs or replacements or perform the necessary work and offset that amount against any security pledged by Subdivider for faithful performance, labo r and materials, or warranty obl igations under this agreement.
18. Warranty:
Without limiting the foregoing, Subdivider warrants and guarantees: materials used and workmanship performed on said work for a period of one (1) year after completion and accep tance thereof by the City, and t he setting of all required Final Map monuments.
19. Assignment:
This agreement shall not be assignable by Subdivider without written consent of City.
Revised – RP -09/22/2022
IN WITNESS WHEREOF, this agreement shall for all purposes be deemed an original thereof, having been duly executed by the Subdivider herein named on the day of , 20 being duly signed by its undersigned representative(s) pursuant to authority of its governing body.
SUBDIVIDER CITY OF FONTANA
By: By:
City Manager
Name ___________________________ Print Name
Title
By: Attest:
City Clerk
______________________________
Name _____________________________ Print Name
Title
APPROVED AS TO FORM:
By:
Best Best & Krieger LLP
City Attorney
Print Name
APPROVED AS TO CONTENT:
By:
City Engineer
_____________________________
Print Name
Matthew Ballantyne
Germaine McClellan Key
Ruben Duran
Gia Kim
Revised – RP -09/22/2022
Attachments: (1) Exhibit "A" – Cost Estimate
(2) Exhibit "B" – Time Extension
(3) Securities
DATE:
DEVELOPER
ENGINEER
PHONE NO.
UNIT
QUANTITY UNIT COST AMOUNT
L.F. 17.00 0.00
150 L.F. 19.00 2850.00
S.F. 11.00 0.00
900 S.F. 7.00 6300.00
EA 5,000.00 0.00
S.F. 11.00 0.00
51 L.F. 11.00 561.00
S.F. 0.10 0.00
C.Y. 10.00 0.00
S.F. 0.50 0.00
30.4 TON 150.00 4560.00
10.1 TON 150.00 1515.00
L.F. 16.00 0.00
EA 500 0.00
EA 300.00 0.00
EA 250.00 0.00
L.F. 40.00 0.00
L.F. 5.00 0.00
S.F. 0.66 0.00
138 L.F. 6.00 828.00
L.F. 5.00 0.00
L.F. 40.00 0.00
L.F. 50.00 0.00
TON 30.00 0.00
EA 70.00 0.00
L.F. 40.00 0.00
L.F. 3.50 0.00
EA 100.00 0.00
EA 250.00 0.00
EA 0.00
EA 0.00
EA 0.00
EA 0.00
$16,614.00
** P.C.C. PORTLAND CONCRETE CEMENT
STREET IMPROVEMENT SUBTOTAL
* A.C. ASPHALTIC CONCRETE
GUARD PANEL (WOOD)
SAWCUT
REFLECTORS AND POSTS
STREET SIGNS
*REMOVAL OF A.C. BERM
RETAINING WALL H=2 1/2 FT. OR LESS
BLOCK WALL H=6 FEET
AGGREGATE BASE
GUARD POSTS
ADJUST WATER VALVES TO GRADE
BARRICADES
2 X 4 REDWOOD HEADER
*REMOVAL OF A.C. PAVEMENT
**REMOVAL OF P.C.C. CURB
*A.C.
*A.C.OVERLAY(0.20 THICKNESS)
PER CITY STANDARD
**PCC CURB ONLY (MEDIAN)
ADJUST SEWER MANHOLE TO GRADE
ADJUST SEWER CLEAN OUT TO GRADE
DRIVE WAY APPROACHES
ASPHALT CONCRETE DIKES
FOG SEAL
IMPORTED EMBANKMENT
PREPARATION OF SUBGRADE
6" CURB & GUTTER
8" CURB & GUTTER
8" THICK CROSS GUTTER
4" SIDEWALK
ACCESS RAMP
(949) 339-5332 PARCEL MAP NO.
STREET IMPROVEMENTS
ITEM
Inland Senior Development, LLC PROJECT NAME Serena Village East MFKessler TRACT MAP NO. 20397
STAFF USE ONLY
ENGINEERING PC NO.
_______________________
CITY OF FONTANA
ENGINEERING DEPARTMENT
COST ESTIMATE - EXHIBIT "A"
09/12/22
ELPC21-000070
CITY OF FONTANA
ENGINEERING
PRELIMINARILY APPROVED
BY
DATE
CONSTRUCTION APPROVED
CORRECTIONS
FINAL APPROVED
FOR INFORMATION ONLY
✔
Henry Pham
10/19/2022
UNIT
QUANTITY U
N COST AMOUNT
* 18" RCP L.F. 90.00 0.00
* 24" RCP L.F. 110.00 0.00
* 30" RCP L.F. 250.00 0.00
* 36" RCP L.F. 250.00 0.00
* 42” RCP L.F. 250.00 0.00
* 48" RCP L.F. 260.00 0.00
* 54" RCP L.F. 280.00 0.00
* 60" RCP L.F. 300.00 0.00
* 66” RCP L.F. 320.00 0.00
* 78” RCP L.F. 340.00 0.00
* 24” CMP L.F. 90.00 0.00
* 60” CMP L.F. 320.00 0.00
0.00 W=7 EA 4,000.00 0.00
W=10 EA 4,500.00 0.00
W=14 EA 6,000.00 0.00
W=21 EA 11,000.00 0.00
W=28 EA 14,000.00 0.00
3,200.00 0.00
2,800.00 0.00
EA 2,800.00 0.00
EA 2,500.00 0.00
EA 1,250.00 0.00
EA 2,100.00 0.00
EA 0.00
EA 0.00
EA 0.00
$0.00
UNIT
QUANTITY U
N COST AMOUNT
EA 4,500.00 0.00
EA 4,000.00 0.00
EA 4,500.00 0.00
EA 100.00 0.00
EA 600.00 0.00
EA 950.00 0.00
L.F. 50.00 0.00
L.F. 60.00 0.00
L.F. 70.00 0.00
L.F. 80.00 0.00
L.F. 90.00 0.00
L.F. 100.00 0.00
L.F. 0.00
L.F. 0.00
$0.00SANITARY SEWER IMPROVEMENT SUBTOTAL
** VITRIFIED CLAY PIPE
** 10" VCP
** 12" VCP
** 15" VCP
CLEANOUTS
REMODELING OF EXISTING
MANHOLE
** 4" VCP
** 6" VCP
** 8" VCP
ITEM
MANHOLES 60" DIAMETER
MANHOLES 48" DIAMETER
DROP MAN HOLES
WYES
STORM DRAIN IMPROVEMENT SUBTOTAL
* REINFORCE CONCRETE PIPE
SANITARY SEWER IMPROVEMENTS
DISCHARGE STRUCTURE
MANHOLES
LOCAL DEPRESSION
GRATE INLET STRUCTURE
STORM DRAIN IMPROVEMENTS
ITEM
CATCH BASIN /CURB INLET:
JUNCTION STRUCTURE
TRAFFIC TYPE JUNCTION
STRUCTURE
UNIT
ITEM QUANTITY UNIT COST AMOUNT
TRAFFIC SIGNAL MODIFICATION:
ONE CORNER
L.S.
75,000.00 $0.00
TWO CORNERS
L.S.
100,000.00 $0.00
TRAFFIC SIGNAL NEW
L.S.
400,000.00 $0.00
PAINT TRAFFIC STRIPE (1 COAT) L.F. 2.40 $0.00
PAINT TRAFFIC STRIPE(2 COATS) L.F. 0.65 $0.00
PEDESTRIAN CROSSWALK STRIPING L.F. 0.65 $0.00
PAVEMENT MARKER
(NON REFLECTIVE) EA
2.50 $0.00
PAVEMENT MARKER (REFLECTIVE) EA 4.00 $0.00
REFLECTORS AND POSTS EA 100.00 $0.00
STREET SIGNS EA 250.00 $0.00
$0.00
$0.00
$0.00
AREA LANDSCAPED S.F. $12.00 $0.00
CENTER MEDIAN S.F. $12.00 $0.00
$0.00
SUBTOTALS:
$16,614.00
$0.00
$0.00
$0.00
$16,614.00
$0.00
1 EA $5,000.00 $5,000.00
$21,614.00
$7,564.90
$29,178.90
ADD 35%
BONDING TOTAL
CFD LANDSCAPE IMPROVEMENTS
SUBDIVISION MONUMENT GUARANTEE $1,200 + $50/LOT
STREET LIGHTS
CUCAMONGA COUNTY WATER DISTRICT FACILITIES
IMPROVEMENT SUBTOTAL
STORM DRAIN IMPROVEMENTS SUBTOTAL
SANITARY SEWER IMPROVEMENTS SUBTOTAL
TRAFFIC SIGNAL/SIGNS/STRIPING SUBTOTAL
IMPROVEMENT SUBTOTAL
(*USE THIS TOTAL FOR PLAN CHECK & PERMITTING PURPOSES*)
TRAFFIC SIGNALS/SIGN/STRIPING
TRAFFIC SIGNAL/SIGNS/STRIPING SUBTOTAL
CFD LANDSCAPE IMPROVEMENTS (BONDING PURPOSES ONLY)
LANDSCAPING IMPROVEMENTS SUBTOTAL
STREET IMPROVEMENT SUBTOTAL
CITY OF FONTANA
ENGINEERING
PRELIMINARILY APPROVED
BY
DATE
CONSTRUCTION APPROVED
CORRECTIONS
FINAL APPROVED
FOR INFORMATION ONLY
✔
Henry Pham
10/19/2022
SIGNING & STRIPING DWG. NO.
SEWER IMP. DWG. NO.
STORM DRAIN IMP. DWG. NO.
TRAFFIC SIGNAL DWG. NO.
APPROVED PUBLIC IMPROVEMENT PLANS:
STREET IMP. DWG. NO.
STREET LIGHT DWG. NO.
6220
6220LT
Revised – RP -09/22/2022
SUBDIVISON IMPROVEMENT AGREEMENT
Tract Map No.:
Exhibit “B”
I,
(Subdivider’s name here)
am the owner of the property to which this Request is being made for of a Time Extension for Project No. .
Name:
Subdivider’s Signature:
Subdivider’s Address:
Date:
(Attached Notary Acknowledgment)
CITY OF FONTANA
BY: DATE:
City Engineer
Print Name
[ ] DENY
[ ] APPROVED
NEW DATE: