ATTACHMENT B CITY OF FONTANA

AMERICAN RESCUE PLAN ACT (ARPA) EXPENDITURE PLAN UPDATE DETAIL MARCH 31, 2023
Project Recommended
Amount
Expended As of
3/31/23
Federal Use Category Description Est. Project Start
Date
Est. Project End
Date
Est. Project Cost Project Update
Administrative Costs 250,000 12,047 Uniform Administrative Requirement, Cost Principles, and Audit Requirements for
Federal Awards (2 CFR Part 200)
To cover the administrative direct and indirect costs
associated with the ARPA program.
2021-22 12/31/2024 250,000 Administrative costs to cover the implementation and oversight of the City's ARPA Expenditure Plan. Costs include but are not limited to City staff time, consultant services including HdL, and City Attorney costs.

Cypress Storm Drain Project 5,840,000 - Water, Sewer, and Broadband Infrastructure
Construction of a storm drain facility along Foothill Blvd between Sierra Ave and Cypress Ave and Cypress Ave between Foothill Blvd and Orange Way to connect to the newly constructed West Fontana Channel along the Metrolink railroad track. The project also includes landscaped median on Foothill Blvd, reconstruction of AC pavement, and ADA compliant sidewalks and curb ramps upgrades.

In Progress 12/30/2024 20,500,000 The project is currently in utility coordination phase. The project will be constructed in two phases:
- Phase 1 will be on Foothill Blvd between Sierra Ave and Cypress Ave, and on Cypress Ave between Foothill Blvd and Orange Way ($14.0 million) - Phase 2 will be on Cypress Ave between Miller Ave and Foothill Blvd and on Juniper Ave between Miller Ave and Foothill Blvd ($6.5 million) ARPA funds will be used towards the first phase. Phase 2 will be constructed once funding is identified in the future. The total project cost for Phase 1 is funded by ARPA, Local Measure I, Storm Drain, and Landscape.

Data Security & Threat Detection 250,000 157,927 Water, Sewer, and Broadband Infrastructure
A software suite that integrates with our servers and Office 365 to detect, report, and alert on permissions and activity to help detect unauthorized access.
7/1/2022 8/25/2022 160,000 Varonis DatAdvantage software suite was deployed and is currently in use to monitor the City's file servers and Office 365 environment. Approved via consent calendar during the June 28, 2022 City Council meeting. PO #22300174.

Endpoint Detection & Response Solution 75,000 154,806 Water, Sewer, and Broadband Infrastructure
A technology solution that would help detect, alert, and potentially respond automatically to anomalous or malicious network activity on the City's network.

In Progress 6/30/2024 75,000 Combined with Network Detection and Response solution. Purchased Arctic Wolf Managed Detection and Response (MDR) solution to monitor network traffic to alert on malicious or suspicious activity. Approved via consent calendar during the June 14, 2022 City Council Meeting. PO # 22300235.

Fiber to City facilities 2,000,000 7,041 Water, Sewer, and Broadband Infrastructure
This project would run City owned fiber to our 6 facilities with leased lines, 1police substation with a leased line, 4 of our larger parks that currently have no connectivity, and 1 police substation that currently has no connectivity. This would help facilitate the use of technology at the locations (Wi-Fi, security cameras, irrigation systems, etc.). 1/1/2023 6/1/2023 2,000,000 The IT and Engineering departments are currently working on the bid specifications.

Sites to be connected are: Palm Court Substation, Southridge Substation, Cypress Center, Don Day Center, Heritage Center, Jack Bulik Center, Martin Tudor Park, Mary Vagle Nature Center, Bill Martin Park, Central City Park, Ralph M. Lewis Sports Complex, South Fontana Park, and Veteran's Park.

REVISED: Fontana Forward Grant Program 300,000 189,339 Public Health & Economic Response Council approved program to grant Covid Impacted or Disproposationate residents $100 to $600 depending on family size and income.

REVISED: a decrease of $2.7 million is recommended based upon the current trend of the program and to support other projects where cost estimates are coming in higher than anticipated.
10/1/2022 12/31/2025 300,000 Total Applications Submitted: 225 First 100 applicants to be funded mid-April.

Homelessness Prevention Resources and
Care Center
8,000,000 100 Public Health & Economic Response The design and construction of a homeless shelter to serve the homeless population of the City.
9/1/2022 11/1/2024 12,000,000 Additional funding of $4,000,000 is required and potential sources include:
- Homeless Prevention, Resource, and Care Center $750,000 -4,750,000 - Courtplace Housing Development $4,000,000
- Pacific Electric Trail Improvement Project $750,000
Project will provide transitional housing and wrap around services (24 hour managed care) for up to 30 chronically homeless individuals as well as housing and appropriate support services for up to 16 families.

Page 1 of 5 ends

ATTACHMENT B CITY OF FONTANA

AMERICAN RESCUE PLAN ACT (ARPA) EXPENDITURE PLAN UPDATE DETAIL MARCH 31, 2023
Project Recommended
Amount
Expended As of
3/31/23
Federal Use Category Description Est. Project Start
Date
Est. Project End
Date
Est. Project Cost Project Update
REVISED: Leveraged Project: Support
Government Employment (hiring above the pre-
pandemic baseline)
4,950,281 1,651,401 Public Health & Economic Response Per the Treasury Final Rule, the City may hire above the pre- pandemic baseline and use SLFRF funds to pay for payroll and covered benefits associated with the recipient increasing its number of budgeted FTEs up to 7.5 percent above its pre-pandemic baseline.

REVISED: a decrease of $922,249 is recommended to make available appropriation in the current fiscal year for both the Accela and Fontana 311 projects.
2022-23 2023-24 4,950,281 All costs associated with new positions approved by Council can be considered for this leveraged project, including by not limited to the new Police Department positions added in 2021-22 and 2022-23.

Metrolink Station Security Cameras 60,000 60,000 Public Health & Economic Response Installation of 8 security cameras at the Fontana Metrolink station to help keep the area more secure. The station currently has no operational cameras, nor any City owned cameras.
4/1/2022 10/1/2022 67,000 Project is underway. Currently waiting on camera delivery which is delayed due to supply chain issues. As much work as possible is being done, such as electrical work and network cabling, so that once the cameras arrive, installation will be completed as quick as possible. PO # 22200836.

Network Detection & Response Solution 75,000 - Water, Sewer, and Broadband Infrastructure
A technology solution that would help detect, alert, and respond to unauthorized activity on the staff computers throughout the City. This would fill the gap between what anti-virus software will detect and our network defenses.
7/1/2022 9/1/2022 75,000 Combined with the Endpoint Detection and Response project. Purchased Arctic Wolf Managed Detection and Response (MDR) solution to monitor network traffic to alert on malicious or suspicious activity. Approved via consent calendar during the June 14, 2022 City Council Meeting. PO # 22300235.

New Leveraged Project: Accela 3,600,000 2,596,119 Water, Sewer, and Broadband Infrastructure
This is a new project and it is recommended that it is funded in the amount of $3.6 million in an effort to leverage funds for projects originally requested in the Revenue Loss category.
2021-22 2023-24 3,600,000 In 2021 the Innovation and Technology Department began efforts to improve business processes in the land management and permitting systems. During the pandemic, it became clear that paper processes were no longer an effective way of serving our residents or business partners. The city wished to replace the existing solution with an improved digital solution to meet the needs of city employees, residents, and businesses.

Over the course of a year, city staff reviewed processes and gathered requirements for a new solution.

A new solution was selected in late 2021 to help improve processes in the land management and permitting system space. Throughout 2022 the IT department has continued to lead this project, working alongside almost every city department to ensure the new solution will be tailored to meet the city of Fontana’s needs in this space. This project has been a 3-year effort, and we are now nearing the tail-end of the project. The new, improved solution will seamlessly connect with surrounding systems, assist customers with an easy-to-use interface, ensure city employees process requests in a consistent and efficient manner, and provide dynamic insights to internal operations. The new solution is expected to go-live in the spring of 2023.

Page 2 of 5 ends

ATTACHMENT B CITY OF FONTANA

AMERICAN RESCUE PLAN ACT (ARPA) EXPENDITURE PLAN UPDATE DETAIL MARCH 31, 2023
Project Recommended
Amount
Expended As of
3/31/23
Federal Use Category Description Est. Project Start
Date
Est. Project End
Date
Est. Project Cost Project Update
New Leveraged Project: Fontana 311 3,150,000 921,265 Water, Sewer, and Broadband Infrastructure
This is a new project and it is recommended that it is funded in the amount of $3.2 million in an effort to leverage funds for projects originally requested in the Revenue Loss category.
2021-23 2023-25 3,150,000 The City of Fontana developed and implemented the Fontana 311 system to improve communication and streamline services to its Residents and Businesses by bringing all customer interactions to one central location.

The Fontana 311 system will be a one-stop shop for businesses and residents to file complaints, get answers to questions, keep residents informed and overall improve citizen engagement. The Innovation and Technology department led the project to develop this new system and was sponsored by our Communications and Marketing office. Throughout 2022 and 2023, there has been extensive work with almost every city department to ensure all city services are captured within the application.

Residents will be able to call 311, use a website, or our 311 app to make that first request and then see it through to completion. The Fontana 311 system will allow staff to track requests from initiation to completion. Fontana 311 offers digital government services and makes interacting with government a much smoother process for our residents and businesses. The Fontana 311 system went live in December of 2022 and is now entering phase 2 of the project, which will bring an IVR with AI to assist our residents when they call for services.

Park Improvements 4,079,892 105,160 Public Health & Economic Response Various projects needed to replace and/or upgrade aging infrastructure in our City's parks.
10/1/2022 7/1/2023 4,059,500 Improvements are being recommended at the following 10 parks:
- Veteran's Park (installation of ballfield dugout shade structures) - Veteran's West Park (installation of new ballfield backstops, ballfield dugout shade structures, shade structures for spectator areas)
- Miller Park (installation of new park gazebo)
- Seville Park (installation of new ADA Inclusive playground structure) - Fernandez Park (installation of playground shade structure and ADA inclusive equipment)
- Bill Martin Park (installation of new ballfield backstops, ballfield dugout shade structures, and shade structures for spectator areas)
- Northgate Park (installation of playground shade structure and ADA inclusive playground equipment)
- North Tamarind Park (installation of new jumbo park gazebo for large groups, a new ADA inclusive playground structures, and rubber playground safety surfacing) - Lemon Pepper Park (installation of playground shade structure) - Carmela Park (installation of playground shade structure) Parking Structure 10,000,000 170,048 Revenue Loss The project will construct a new parking structure within the parking lot of the Fontana HR Office.

In progress 3/30/2025 15,000,000 The proposed project is to be constructed within the existing parking lot of the City’s Human Resources Department Building located at 8491 Sierra Avenue, Fontana, CA 92335, and shall consist of a 4-tier parking structure. Each tier will have a footprint of approximately 130 feet by 230 feet with two vehicular entrances, one along Learner Lane and the other along Wheeler Avenue. The City anticipates the structure to include 311 vehicular parking spaces and two elevators. The intent of the structure is to serve as both public and employee parking for the civic center campus as well as the planned downtown area which is to be revitalized. Funding includes $10.0 million in ARPA funds and $5.0 million General Fund.

Page 3 of 5 ends

ATTACHMENT B CITY OF FONTANA

AMERICAN RESCUE PLAN ACT (ARPA) EXPENDITURE PLAN UPDATE DETAIL MARCH 31, 2023
Project Recommended
Amount
Expended As of
3/31/23
Federal Use Category Description Est. Project Start
Date
Est. Project End
Date
Est. Project Cost Project Update
REVISED: Part-Time Employee Retention 250,000 77,609 Premium Pay Project includes recruitment and retention bonuses for part-time personnel.

REVISED: Previously included with Citywide vaccine bonuses but was recategorized as Premium Pay for reporting purposes. 2022-23 2022-23 250,000 Project includes recruitment and retention bonuses for part-time personnel with a current allocation of $250,000.

Public Safety Premium Pay 1,549,486 887,901 Premium Pay Project includes public safety retention bonuses which were previously categorized as Employee Retention/Incentive as Public Health & Economic Response.
2021-22 2022-23 1,549,486 Project includes public safety retention bonuses.

Septic to Sewer 2,000,000 - Water, Sewer, and Broadband Infrastructure
The project will provide septic to sewer conversion in a disadvantaged communities (DAC) area in the city.

In Progress 6/30/2025 6,000,000 County will not participate the project cost. The city in the process of finalizing project limits and scope of work. Once finalzied, RFP will be issued to select design firm. The funding for this project includes $2.0 million from ARPA and the balance of $4.0 million is to be determined as staff wil continue tol pursue additional grant opportunities.

Sewer and Storm Drain Infrastructure
Masterplan
375,130 180,903 Water, Sewer, and Broadband Infrastructure
For consultant provided services in order to develop a masterplan document to forecast future infrastructure needs.
9/30/2022 9/30/2023 375,130 Contract with David Evans and Associates. for $375,130 was approved on October 10, 2022. Contract is being funded by ARPA. Work is ongoing with completion expected by September 2023.

REVISED: Supervisory Control and Data
Acquisition (SCADA) - Sewer
- - Water, Sewer, and Broadband Infrastructure
Purchase and installation of a Supervisory Control and Data Acquisition (SCADA) system to monitor the City's sewer lift/pump station network.

REVISED: it is recommended that this project be unappropriated as it was funded through another revenue source.

It is recommended that this project be unappropriated as it was funded through another revenue source.

Update Master Infrastructure Plans 424,870 210,457 Water, Sewer, and Broadband Infrastructure
Storm Drain and Sewer master plans update. With completed projects and various changes since the last update, the master plans are due for an update.
9/30/2022 9/30/2023 478,502 Contract with Albert A. Webb Associates, Inc. for $478,502 was approved on October 3, 2022. Contract is being funding by ARPA and $53,632 from Fund 702. An addendum for $40,000 is approved by the City Council from Fund 702 to provide more detailed analysis of the Downtown Area with the funds being drawn from the Sewer Capital Projects Fund. Work is ongoing with completion expected by September 2023.

REVISED: Vaccine Bonus 527,454 489,398 Public Health & Economic Response Project includes a citywide vaccine bonus.

REVISED: a decrease of $422,767 is recommended based about actual costs of the project which ended December 31, 2022. 2022-23 2022-23 527,454 Project includes a citywide vaccine bonus. Citywide Vaccine Bonus, 40 hours per full- time employee with a current allocation of $950,221 and a recommended decrease of $422,767 based about actual costs of the project which ended December 31, 2022.

Page 4 of 5 ends

ATTACHMENT B CITY OF FONTANA

AMERICAN RESCUE PLAN ACT (ARPA) EXPENDITURE PLAN UPDATE DETAIL MARCH 31, 2023
Project Recommended
Amount
Expended As of
3/31/23
Federal Use Category Description Est. Project Start
Date
Est. Project End
Date
Est. Project Cost Project Update
Ventilation Upgrade for City Facilities 2,500,000 1,561,613 Public Health & Economic Response Upgrades to existing HVAC equipment to provide better protection to employees from Covid-19.
10/1/2022 4/30/2023 2,500,000 Project went out to bid and closed August 23rd. Bid responses were evaluated by Purchasing and contract was presented to council for consideration in September. The Project was awarded to Alliance Building Solutions. Installation began January 2023 and is set to be completed by the end of April 2023. Roughly 650 Portable Air Purifiers and Air Monitors will be installed throughout the interior of 18 City owned facilities.

Total 50,257,113 9,433,133 REVISED: Helicopter Purchase 3,000,000 3,000,000 General Fund This request is for an A-Star helicopter which will allow for a more available fleet and readied aircraft while one or more are down for scheduled or unscheduled maintenance. The A-Star can fly in windy conditions and eliminate the current loss of approximately 30% of hours due to inclement weather. Additionally, the upgraded program could provide for the ability to support an officer down rescue.

The increased functionality of the A-Star will allow for integrated maps to support in pursuits and tactical situations; recording capabilities to assist in evidence, training, and civil litigations; the ability to fly at higher altitudes to assist in covert surveillances to aid the Narcotics Unit, Fugitive Apprehension Team, and other units in the special operations division. Additionally, the A-Star will also provide air support to the Fire District including fire patrol and real- time tactical assessments improving response times and decreasing loss of property.
5/27/2022 7/30/2022 3,000,000 The AirBus Helicopter was purchased and delivered in May 2022 as well as the Chopper Stopper. The balance of the expenditures are outstanding and will be presented to Council for approval in September 2022. Project details include the following:
- 2011 Air Bus AS350B2 ($1,670,125)
- Chopper Stopper ($22,760)
- 5 Year Impound Fees ($625,000)
- 12 Year Maintenance ($225,000)
- FY 21/22 Prorated Premium Insurance ($3,962)
- FY 22/23 Insurance ($43,557)
- Cargo Hook Kit/Bambi Bucket ($100,000)
Additionally, there are on-going associated costs related to increased fuel, maintenance, storage, flight hours, and insurance premiums that will be requested in the first quarter.

Remaining outstanding items to be purchased included: Remaining Impound Fees, 12 Year Maintenance, and Cargo Hook Kit/Babmi Bucket.

Pavement Rehabilitation 5,000,000 TBD General Fund For annual work related to the City's Pavement Management Plan. 3/1/2023 8/30/2024 5,000,000 Project is currently in the planning stage and a comprehensive project list is being developed for Council’s consideration.

LEVERAGED PROJECTS FUNDED BY THE GENERAL FUND

Page 5 of 5 ends