CITY OF FONTANA
PROFESSIONAL SERVICES AGREEMENT
SP-81-DE-23
This Agreement is made and entered into as of May 9, 2023 by and between the City of Fontana, a public agency organized and operating under the laws of the State of California with its principal place of business at 8353 Sierra Avenue, Fontana, California 92335 (“City”), and EXP US Services Inc., a Corporation with its principal place of business at 451 East Vanderbilt Way, Suite 375, San Bernardino, CA 92408 (hereinafter referred to as “Consultant”). City and Consultant are sometimes individually referred to as “Party” and collectively as “Parties” in this Agreement.
RECITALS
A. City is a public agency of the State of California and is in need of professional services for the following project:
Citrus Avenue Widening at SR-210 Project (hereinafter referred to as “the Project”).
B. Consultant is duly licensed and has the necessary qualifications to provide such services.
C. The Parties desire by this Agreement to establish the terms for City to retain Consultant to provide the services described herein.
AGREEMENT
NOW, THEREFORE, IT IS AGREED AS FOLLOWS:
1. Services.
Consultant shall provide the City with the services described in the Scope of Services attached hereto as Exhibit “A.”
2. Compensation.
a. Subject to paragraph 2(b) below, the City shall pay for such services in accordance with the Schedule of Charges set forth in Exhibit “B.” b. In no event shall the total amount paid for services rendered by Consultant under this Agreement exceed the sum of $ 249,705.47. This amount is to cover all printing and related costs, and the City will not pay any additional fees for printing expenses. Periodic payments shall be made within 30 days of receipt of an invoice which includes a detailed description of the work performed. Payments to Consultant for work performed will be made on a monthly billing basis.
3. Additional Work.
If changes in the work seem merited by Consultant or the City, and informal consultations with the other party indicate t hat a change is warranted, it shall be processed in the following manner: a letter outlining the changes shall be forwarded to the City by Consultant with a statement of estimated changes in fee or time schedule. An amendment to this Agreement shall
2 16498.00150\32126437.1
be prepared by the City and executed by both Parties before performance of such services, or the City will not be required to pay for the changes in the scope of work. Such amendment shall not render ineffective or invalidate unaffected portions of this Agreement.
4. Maintenance of Records.
Books, documents, papers, accounting records, and other evidence pertaining to costs incurred shall be maintained by Consultant and made available at all reasonable times during the contract period and for four (4) years fr om the date of final payment under the contract for inspection by City.
5. Term
The term of this Agreement shall be from May 9, 2023 to May 9, 202 5, unless earlier terminated as provided herein. The Parties may, by mutual, written consent, extend the term of this Agreement if necessary to complete the Project. Consultant shall perform its services in a prompt and timely manner within the term of th is Agreement and shall commence performance upon receipt of written notice from the City to proceed (“Notice to Proceed”). The Notice to Proceed shall set forth the date of commencement of work.
6. Delays in Performance.
a. Neither City nor Consultant shall be considered in default of this Agreement for delays in performance caused by circumstances beyond the reasonable control of the non - performing party. For purposes of this Agreement, such circumstances include but are not limited to, abnormal weather conditions; floods; earthquakes; fire; epidemics; war; riots and other civil disturbances; strikes, lockouts, work slowdowns, and other labor disturbances; sabotage or judicial restraint.
b. Should such circumstances occur, the non -performing party shall, within a reasonable time of being prevented from performing, give written notice to the other party describing the circumstances preventing continued performance and the efforts being made to resume performance of this Agreement.
7. Compliance with Law.
a. Consultant shall comply with all applicable laws, ordinances, codes and regulations of the federal, state and local government, including Cal/OSHA requirements. b. If required, Consultant shall assist the City, as requested, in obtaining and maintaining all permits required of Consultant by federal, state and local regulatory agencies. c. If applicable, Consultant is responsible for all costs of clean up and/ or removal of hazardous and toxic substances spilled as a result of his or her services or operations performed under this Agreement.
8. Standard of Care
3 16498.00150\32126437.1
Consultant’s services will be performed in accordance with generally accepted professional practices and principles and in a manner consistent with the level of care and skill ordinarily exercised by members of the profession currently practicing under similar conditions.
9. Assignment and Subconsultant
Consultant shall not assign, sublet, or transfer this Agreement or any rights under or interest in this Agreement without the written consent of the City, which may be withheld for any reason. Any attempt to so assign or so transfer without such consent shall be void and without legal effect and shall constitute grounds for termination. Subcontracts, if any, shall contain a provision making them subject to all provisions stipulated in this Agreement. Nothing contained herein shall prevent Consultant from employing independent associates, and subconsultants as Consultant may deem appropriate to assist in the performance of services hereunder.
10. Independent Contractor
Consultant is retained as an independent contractor and is not an employee of City. No employee or agent of Consultant shall become an employee of City. The work to be performed shall be in accordance with the work described in this Agreement, subject to such directions and amendments from City as herein provided.
11. Insurance. Consultant shall not commence work for the City until it has provided evidence satisfactory to the City it has secured all insurance required under this section. In addition, Consultant shall not allow any subcontractor to commence work on any subcontract until it has secured all insurance required under this section. a. Commercial General Liability
(i) The Consultant shall take out and maintain, during the performance of all work under this Agreement, in amounts not less than specified herein, Commercial General Liability Insurance, in a form and with insurance companies acceptable to the City. (ii) Coverage for Commercial General Liability insurance shall be at least as broad as the following:
(1) Insurance Services Office Commercial General Liability coverage (Occurrence Form CG 00 01) or exact equivalent. (iii) Commercial General Liability Insurance mu st include coverage for the following:
(1) Bodily Injury and Property Damage
(2) Personal Injury/Advertising Injury
(3) Premises/Operations Liability
(4) Products/Completed Operations Liability
(5) Aggregate Limits that Apply per Project
(6) Explosion, Col lapse and Underground (UCX) exclusion deleted
(7) Contractual Liability with respect to this Agreement (8) Property Damage
(9) Independent Contractors Coverage
4 16498.00150\32126437.1
(iv) The policy shall contain no endorsements or provisions limiting coverage for (1) contractual liability; (2) cross liability exclusion for claims or suits by one insured against another; (3) products/completed operations liability; or (4 ) contain any other exclusion contrary to the Agreement.
(v) The policy shall give City, its officials, officers, employees, agents and City designated volunteers additional insured status using ISO endorsement forms CG 20 10 10 01 and 20 37 10 01, or endorsements providing the exact same coverage. (vi) The general liability program may utilize either deductibles or provide coverage excess of a self -insured retention, subject to written approval by the City, and provided that such deductibles shall not apply to the City as an additional insured. b. Automobile Liability
(i) At all times during the performance of the work under this Agreement, the Consultant shall maintain Automobile Liability Insurance for bodily injury and property damage including coverage for owned, non-owned and hired vehicles, in a form and with insurance companies acceptable to the City.
(ii) Coverage for automobile liability insurance shall be at least as broad as Insurance Services Office Form Number CA 00 01 covering automobile liability (Coverage Symbol 1, any auto).
(iii) The policy shall give City, its officials, officers, employees, agents and City designated volunteers additional insured status. (iv) Subject to written approval by the City, the automobile liability program may utilize deductibles, provided that such deductibles shall not apply to the City as an additional insured, but not a self-insured retention.
c. Workers’ Compensation/Employer’s Liability
(i) Consultant certifies that he/she is aware of the provisions of Section 3700 of the California Labor Code which requires e very employer to be insured against liability for workers’ compensation or to undertake self -insurance in accordance with the provisions of that code, and he/she will comply with such provisions before commencing work under this Agreement.
(ii) To the extent Consultant has employees at any time during the term of this Agreement, at all times during the performance of the work under this Agreement, the Consultant shall maintain full compensation insurance for all persons employed directly by him/her to carry out the work contemplated under this Agreement, all in accordance with the “Workers’ Compensation and Insurance Act,” Division IV of the Labor Code of the State of California and any acts amendatory thereof, and Employer’s Liability Coverage in amounts indicated herein. Consultant shall require all subconsultants to obtain and maintain, for the period required by this Agreement, workers’ compensation coverage of the same type and limits as specified in this section.
d. Professional Liability (Errors and Omissions)
At all times during the performance of the work under this Agreement the Consultant shall
5 16498.00150\32126437.1
maintain professional liability or Errors and Omissions insurance appropriate to its profession, in a form and with insurance companies acceptable to the City and in an amount indicated herein.
This insurance shall be endorsed to include contractual liability applicable to this Agreement and shall be written on a policy form coverage specifically designed to protect against acts, errors or omissions of the Consultant. “Covered Professional Services” as designated in the policy must specifically include work performed under this Agreement. The policy must “pay on behalf of” the insured and must include a provision establishing the insurer's duty to defend. e. Minimum Policy Limits Required
(i) The following insurance limits are required for the Agreement:
Combined Single Limit
Commercial General Liability $1,000,000 per occurrence/ $2,000,000 aggregate for bodily injury, personal injury, and property
damage
Automobile Liability $1,000,000 combined single limit Employer’s Liability $1,000,000 per accident or disease Professional Liability $1,000,000 per claim and aggregate (errors and omissions)
(ii) Defense costs shall be payable in addition to the limits. (iii) Requirements of specific coverage or limits contained in this section are not intended as a limitation on coverage, limits, or other requirement, or a waiver of any coverage normally provided by any insurance. Any available coverage shall be provided to the parties required to be named as Additional Insured pursuant to this Agreement. f. Evidence Required
Prior to execution of the Agreement, the Consultant shall file with the City evidence of insurance from an insurer or insurers certifying to the coverage of all insurance required herein. Such evidence shall include original copies of the ISO CG 00 01 (or insurer’s equivalent) signed by the insurer’s representative and Certificate of Insurance (Acord Form 25 -S or equivalent), together with required endorsements. All evidence of insurance shall be signed by a properly authorized officer, agent, or qualified representative of the insurer and shall certify the names of the insured, any additional insureds, where appropriate, the type and amount of the insurance, the location and operations to which the insurance applies, and the expiration date of such insurance.
g. Policy Provisions Required
(i) Consultant shall provide the City at least thirty (30) days prior written notice of cancellation of any policy required by this Agreement, except that the Consultant shall provide at least ten (10) days prior writte n notice of cancellation of any such policy due to non-payment of premium. If any of the required coverage is cancelled or expires during the term of this Agreement, the Consultant shall deliver renewal certificate(s) including the General
6 16498.00150\32126437.1
Liability Additional Insured Endorsement to the City at least ten (10) days prior to the effective date of cancellation or expiration.
(ii) The Commercial General Liability Policy and Automobile Policy shall each contain a provision stating that Consultant’s policy is primary insurance and that any insurance, self-insurance or other coverage maintained by the City or any named insureds shall not be called upon to contribute to any loss.
(iii) The retroactive date (if any) of each policy is to be no later than the effective date of this Agreement. Consultant shall maintain such coverage continuously for a period of at least three years after the completion of the work under this Agreement. Consultant shall purchase a one (1) year extended reporting period A) if the retroa ctive date is advanced past the effective date of this Agreement; B) if the policy is cancelled or not renewed; or C) if the policy is replaced by another claims -made policy with a retroactive date subsequent to the effective date of this Agreement.
(iv) All required insurance coverages , except for the professional liability coverage, shall contain or be endorsed to provide a waiver of subrogation in favor of the City, its officials, officers, employees, agents, and volunteers or shall specifically allow Consultant or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. Consultant hereby waives its own right of recovery against City, and shall require similar written express waivers and insurance clauses from each of its subconsultants.
(v) The limits set forth herein shall apply separately to each insured against whom claims are made or suits are brought, except with respect to the limits of liability.
Further the limits set forth herein shall not be construed to relieve the Consultant from liability in excess of such coverage, nor shall it limit the Consultant’s indemnification obligations to the City and shall not preclude the City from taking such other actions available to the City under other provisions of the Agreement or law.
h. Qualifying Insurers
(i) All policies required shall be issued by acceptable insurance companies, as determined by the City, which satisfy the following minimum requirements:
(1) Each such policy shall be f rom a company or companies with a current A.M. Best's rating of no less than A:VII and admitted to transact in the business of insurance in the State of California, or otherwise allowed to place insurance through surplus line brokers under applicable provisions of the California Insurance Code or any federal law.
i. Additional Insurance Provisions
(i) The foregoing requirements as to the types and limits of insurance coverage to be maintained by Consultant, and any approval of said insurance by the City, is not intended to and shall not in any manner limit or qualify the liabilities and obligations otherwise assumed by the Consultant pursuant to this Agreement, including but not limited to, the provisions concerning indemnification.
(ii) If at any time during the life of the Agreement, any policy of insurance required under this Agreement does not comply with these specifications or is
7 16498.00150\32126437.1
canceled and not replaced, City has the right but not the duty to obtain the insurance it deems necessary and any premium paid by City will be promptly reimbursed by Consultant or City will withhold amounts sufficient to pay premium from Consultant payments. In the alternative, City may cancel this Agreement.
(iii) The City may require the Consultant to provide complete copies of all insurance policies in effect for the duration of the Project. (iv) Neither the City nor any of its officials, officers, employees, agents or volunteers shall be personally responsible for any liability arising under or by virtue o f this Agreement.
j. Subconsultant Insurance Requirements . Consultant shall not allow any subcontractors or subconsultants to commence work on any subcontract until they have provided evidence satisfactory to the City that they have secured all insurance required under this section.
Policies of commercial general liability insurance provided by such subcontractors or subconsultants shall be endorsed to name the City as an additional insured using ISO form CG 20 38 04 13 or an endorsement providing the exact same coverage. If requested by Consultant, City may approve different scopes or minimum limits of insurance for particular subcontractors or subconsultants.
12. Indemnification.
a. To the fullest extent permitted by law, Consultant shall defend (with counsel of City’s choosing), indemnify and hold the City, its officials, officers, employees, volunteers, and agents free and harmless from any and all claims, demands, causes of action, costs, expenses, liability, loss, damage or injury of any kind, in law or equity, to property or persons, including wrongful death, in any manner arising out of, pertaining to, or incident to any acts, errors or omissions, or willful misconduct of Consul tant, its officials, officers, employees, subcontractors, consultants or agents in connection with the performance of the Consultant’s services, the Project or this Agreement, including without limitation the payment of all damages, expert witness fees and attorney’s fees and other related costs and expenses. Consultant's obligation to indemnify shall not be restricted to insurance proceeds, if any, received by Consultant, the City, its officials, officers, employees, agents, or volunteers.
b. If Consultant’s obligation to defend, indemnify, and/or hold harmless arises out of Consultant’s performance of “design professional” services (as that term is defined under Civil Code section 2782.8), then, and only to the extent required by Civil Code secti on 2782.8, which is fully incorporated herein, Consultant’s indemnification obligation shall be limited to claims that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of the Consultant, and, upon Consultant obtain ing a final adjudication by a court of competent jurisdiction, Consultant’s liability for such claim, including the cost to defend, shall not exceed the Consultant’s proportionate percentage of fault.
13. California Labor Code Requirements.
a. Consultant is aware of the requirements of California Labor Code Sections 1720 et seq. and 1770 et seq., which require the payment of prevailing wage rates and the performance of other requirements on certain “public works” and “maintenance” projects (“Prevailing Wage Laws”). If the services are being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and if the total
8 16498.00150\32126437.1
compensation is $1,000 or more, Consultant agrees to fully comply with such Prevail ing Wage Laws. Consultant shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claims, liabilities, costs, penalties or interest arising out of any failure or alleged failure to comply with th e Prevailing Wage Laws . It shall be mandatory upon the Consultant and all subconsultants to comply with all California Labor Code provisions, which include but are not limited to prevailing wages (Labor Code Sections 1771, 1774 and 1775), employment of apprentices (Labor Code Section 1777.5), certified payroll records (Labor Code Sections 1771.4 and 1776), hours of labor (Labor Code Sections 1813 and 1815) and debarment of contractors and subcontractors (Labor Code Section 1777.1) . The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4. b. If the services are being performed as part of an applicable “public works” or “maintenance” project, then pursuant to Labor Code Sections 1725.5 and 1771.1, the Consultant and all subconsultants performing such services must be register ed with the Department of Industrial Relations. Consultant shall maintain registration for the duration of the Project and require the same of any subconsultants, as applicable. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1. c. This Agreement may also be subject to compliance monitoring and enforcement by the Department of Industrial Relations. It shall be Consultant’s sole responsibility to comply with all applicable registration and labor compliance requirements. Any stop orders issued by the Department of Indust rial Relations against Consultant or any subcontractor that affect Consultant’s performance of services, including any delay, shall be Consultant’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Consultant caused delay and shall not be compensable by the City. Consultant shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Departme nt of Industrial Relations against Consultant or any subcontractor.
14. Verification of Employment Eligibility.
By executing this Agreement, Consultant verifies that it fully complies with all requirements and restrictions of state and federal law respec ting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time, and shall require all subconsultants and sub-subconsultants to comply with the same.
15. Reserved.
16. Laws and Venue.
This Agreement shall be interpreted in accordance with the laws of the State of California.
If any action is brought to interpret or enforce any term of this Agreement, the action shall be brought in a state or federal court situated in the County of San Bernardino, State of California.
17. Termination or Abandonment
9 16498.00150\32126437.1
a. City has the right to termin ate or abandon any portion or all of the work under this Agreement by giving ten (10) calendar days written notice to Consultant. In such event, City shall be immediately given title and possession to all original field notes, drawings and specifications, written reports and other documents produced or developed for that portion of the work completed and/or being abandoned. City shall pay Consultant the reasonable value of services rendered for any portion of the work completed prior to termination. If s aid termination occurs prior to completion of any task for the Project for which a payment request has not been received, the charge for services performed during such task shall be the reasonable value of such services, based on an amount mutually agreed to by City and Consultant of the portion of such task completed but not paid prior to said termination. City shall not be liable for any costs other than the charges or portions thereof which are specified herein. Consultant shall not be entitled to paym ent for unperformed services, and shall not be entitled to damages or compensation for termination of work.
b. Consultant may terminate its obligation to provide further services under this Agreement upon thirty (30) calendar days’ written notice to City only in the event of substantial failure by City to perform in accordance with the terms of this Agreement through no fault of Consultant.
18 Documents. Except as otherwise provided in “Termination or Abandonment,” above, all original field notes, written reports, Drawings and Specifications and other documents, produced or developed for the Project shall, upon payment in full for the services described in this Agreement, be furnished to and become the property of the City.
19. Organization
Consultant shall assign Syed Raza, PE, as Project Manager. The Project Manager shall not be removed from the Project or reassigned without the prior written consent of the City.
20. Limitation of Agreement.
This Agreement is limited to and includes only the work included in the Project described above.
21. Notice
Any notice or instrument required to be given or delivered by this Agreement may be given or delivered by depositing the same in any United States Post Office, certified mail, return receipt requested, postage prepaid, addressed to:
CITY:
City of Fontana
8353 Sierra Avenue
Fontana, California 92335
Attn: Jeffrey Kim, Department of Engineering
CONSULTANT:
EXP US Services, Inc.
451 E Vanderbilt Way, Suite 375
San Bernardino, CA 92408
Attn: Syed Raza
and shall be effective upon receipt thereof.
10 16498.00150\32126437.1
22. Third Party Rights
Nothing in this Agreement shall be construed to give any rights or benefits to anyone other than the City and the Consultant.
23. Equal Opportunity Employment.
Consultant represents that it is an equal opportunity employer and that it shall not discriminate against any employee or applicant for employment because of race, religion, color, national origin, ancestry, sex, age or other interests protected by the State or Federal Constitutions. Such non-discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination.
24. Entire Agreement
This Agreement, with its exhibits, represents the entire understanding of City and Consultant as to those matters contained herein, and supersedes and cancels any prior or contemporaneous oral or written understanding, promises or representations with resp ect to those ma tters covered hereunder. Each P arty acknowledges that no representations, inducements, promises or agreements have been made by any person which are not incorporated herein, and that any other agreements shall be void. This Agreement may n ot be modified or altered except in writing signed by both Parties hereto. This is an integrated Agreement.
25. Severability
The unenforceability, invalidity or illegality of any provision(s) of this Agreement shall not render the remaining provisions unenforceable, invalid or illegal.
26. Successors and Assigns
This Agreement shall be binding upon and shall inure to the benefit of the successors in interest, executors, admi nistrators and assigns of each P arty to this Agreement. However, Consultant shall not assign or transfer by operation of law or otherwise any or all of its rights, burdens, duties or obligations without the prior written consent of City. Any attempted assignment without such consent shall be invalid and void.
27. Non-Waiver
None of the provisions of this Agreement shall be considered waived by either P arty, unless such waiver is specifically specified in writing.
28. Time of Essence
Time is of the essence for each and every provision of this Agreement.
29. City’s Right to Employ Other Consultants
City reserves its right to employ other consultants, including engineers, in connection with this Project or other projects.
30. Prohibited Interests
11 16498.00150\32126437.1
Consultant maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Consultant, to solicit or secure this Agreement. Further, Consultant warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Consultant, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. Fo r breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the term of this Agreement, no director, official, officer or employee of City, during the term of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom.
[SIGNATURES ON FOLLOWING PAGE]
12 16498.00150\32126437.1
SIGNATURE PAGE FOR PROFESSIONAL SERVICES AGREEMENT
CITY OF FONTANA
By:
Matthew C. Ballantyne
City Manager
EXP US Services Inc.
By:
[INSERT NAME]
[INSERT TITLE]
Attest:
By:
Germaine McClellan Key
City Clerk
By:
[INSERT NAME]
[INSERT TITLE]
Approved as to form:
Best Best & Krieger LLP
City Attorney
IN COMPLIANCE WITH CONTRACT INSURANCE REQUIREMENTS
By: ______________________________
Rakesha Thomas
Human Resources & Risk Management Director
IN COMPLIANCE WITH PURCHASING AND CONTRACT ADMINISTRATION POLICIES/PROCEDURES
___________________________________
Chief Financial Officer
Purchasing Office
13 16498.00150\32126437.1
EXHIBIT A
Scope of Services
submitted by
EXP U.S. Services, Inc.
451 East Vanderbilt Way, Suite 375, San Bernardino, CA 92408 | USA t: +1 909.751.3250
citrus avenue widening at sr-210 project
Request for Proposal for Design Services
SP-81-DE-23
City of Fontana
Closing: 2 PM, February 16, 2023
table of contents
1. Cover Letter
2. Work Plan, Scope of Work, and Deliverables 1-7
3. Organization and Staffing Plan 8-9
4. References 10
5. Appendix
• Appendix A: Staff Resumes
• Appendix B: Cost Proposal Sheets
1 Cover Letter
February 16, 2023
Sid Lambert
Purchasing Office
City of Fontana
8353 Sierra Avenue
Fontana, California 92335
[email protected]
(909) 350-7678
re: Proposal for City of Fontana RFP for Design Services for Citrus Avenue Widening at SR-210 Project | SP-81-DE-23 Dear Mr. Lambert,
EXP US Services Inc (EXP) is pleased to submit this proposal to the City of Fontana (City) to provide Design Services for Citrus Avenue Widening at State Route 210 (SR-210) Project.
EXP has assembled a strong and locally experienced team of professionals led by our seasoned Project Manager, Syed Raza, PE. s
Syed has also served as Project Manager on several large and small projects involving government agencies in the Inland Empire. His proactive project management approach, communication and problem-solving skills, and his ability to build consensus make him a perfect choice to lead this project for the City.
EXP recognizes that the City is seeking the services of a well-qualified consultant to perform design services for the project. The EXP team consists of experts from various disciplines and is uniquely qualified to develop the most cost-effective design and implementation strategies for the City. EXP commits to delivering the project within 12 months after receiving the Notice to Proceed.
TECHNICAL EXPERTISE
EXP is a large multi-disciplinary firm with significant in-house technical expertise in various areas including traffic signal design, roadway design, sidewalk, civil, traffic and construction engineering. EXP is committed to excellence in everything it does. EXP has over 90 offices in North America, including 25+ offices across the United States. In California, EXP has offices in the cities of San Bernardino, San Diego, Glendale and San Francisco.
IDENTIFICATION OF OFFEROR
The project will be managed and delivered out of EXP’s San Bernardino office:
a: 451 E Vanderbilt Way, Suite 375, San Bernardino, CA
p: 909.751.3250 | f: N/ A | e: [email protected]
EXP
451 East Vanderbilt Way, Suite 375, San Bernardino, CA 92408 | USA t: +1 909.751.3250 | exp • com
As Project Manager, Syed will take full advantage of his most recent and relevant experience of working on SR-71/Pine Avenue Ramp Widening Project in the City of Chino Hills and SBCTA’s SR-210 Waterman Avenue Interchange Project in the City of San Bernardino. The scope of work for the Citrus Avenue Widening Project and the Caltrans process to be followed is almost identical to these other projects. All the lessons learned from these projects will be applied to this project to ensure that it is delivered efficiently and expeditiously without any surprises.
COVER LETTER
41+
years of
experience
EXP
Re: Citrus Avenue Widening at SR-210 Project
Date: February 16, 2023
PROJECT MANAGER / PROPOSAL CONTACT INFORMATION
The EXP team is fully committed to providing the services outlined in the RFP and we look forward to the opportunity to discuss our team’s qualifications with you. For any questions regarding our solicitation response, please contact:
Syed Raza, PE
Project Manager
a: 451 E Vanderbilt Way, Suite 375, San Bernardino, CA
p: 909.217.5779 | e: [email protected]
Syed is also authorized to negotiate the contract on behalf of the firm.
CONTRACT SIGNATORIES
I certify than I am an officer of EXP authorized to bind the firm to the information contained herein and that our proposal is valid for ninety (90) days from the date of submittal. EXP is prepared to submit insurance certificates to the City of Fontana prior to contract execution. Our signature on this letter attests that all information submitted in this proposal is true and correct and that the person signing this letter is an officer of EXP and is authorized to bind the firm to the terms of the proposal.
Respectfully Submitted,
Khalil Saba, PE
Vice President | Principal-In-Charge
COVER LETTER
2 Work plan, Scope of work,
And deliverables
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
WORK PLAN / APPROACH / UNDERSTANDING | 1WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 1
2. WORK PLAN, SCOPE OF WORK, AND DELIVERABLES
PROJECT UNDERSTANDING
Introduction
The City of Fontana (City) in collaboration with the California Department of Transportation (Caltrans) is requesting
proposals to provide Design Services to widen northbound Citrus Avenue from South Highland Avenue to eastbound
State Route 210 (SR-210) on-ramp and extend southbound left- turns to South Highland Avenue.
Project Background
SR-210 is an urban freeway that begins at I-5 in Los Angeles County and ends at I-10 in the City of Redlands. Within District 8, the limits of SR-210 are from the Los Angeles/San Bernardino County Line to I-10. SR-210 is one of the busiest freeways in California with an ADT of over 371,000 vehicles per day (vpd) near Pasadena transitioning to an ADT between 149,000 vpd and 167,000 vpd at the SR-210/Citrus Avenue Interchange per Caltrans 2020 Traffic Volumes Report. This interchange also has moderate amount of truck traffic with latest Caltrans data indicating 5% truck volume on SR-210.
Citrus Avenue is a north-south oriented street that begins at Beech Avenue south of I-10 and ends just east of I-15 in the City of Fontana with freeway interchanges on I-10 and SR-210.
According to City’s General Plan, the ADT on Citrus Avenue ranges between 30,000 vpd and 35,000 vpd.
Existing Conditions
Within the project limits, SR-210 is a eight-lane depressed freeway, consisting of three general purpose (GP) and one High Occupancy Vehicle (HOV) lane in each direction. The mainline traffic is separated by a paved median with a concrete median barrier. The interchange configuration is a tight diamond with both off-ramps beginning as a single lane at the gore point, widening to three lanes (one left, one left/through/right and one right) at the signalized intersection with Citrus Avenue.
Both on-ramps have two lanes up to the ramp metering line and are metered before merging with the mainline.
The interchange was constructed in 2001. The overcrossing bridge (BR. No. 54-0672) is a two-span concrete box girder bridge with open end abutments. It is 246’ 1” long and 99’ 1” wide. The minimum vertical clearance for the overcrossing is 16’ 11” exceeding Caltrans minimum vertical clearance standard of 16’ 6” . The lane configuration on the bridge consists of two through lanes in each direction with back-to-back double left- turn lanes. A six foot sidewalk exists on the west side of the bridge.
Citrus Avenue is functionally classified as a Major Highway within the project limits from South Highland Avenue to Sierra Lakes Parkway. It has two lanes in each direction which widens to provide dual left-turn lanes at the two ramp intersections and at South Highland Avenue.
TRAFFIC ANALYSIS
Data Collection
One of the first orders of work after receiving the Notice To Proceed (NTP), will be to obtain new traffic counts for the project to establish the existing baseline conditions. The traffic data will also include classification data to determine the breakdown of passenger cars, buses/RVs, and trucks (by axles) in the traffic stream. This data will be needed for other technical studies, including air and noise, and for traffic index calculations. In addition, pedestrian and bicycle data will be collected.
Prepare Forecast Volumes Report
The current version (2019) of the Southern California
Association of Governments (SCAG) RTP travel demand model (TDM) will be utilized to perform travel demand forecasts for the existing, opening and horizon years. The land use data will be further refined at the local level to reflect any new development in and around the SR-210 corridor. This will include a review and update of the socio-economic
data to reflect the most recent available projections.
Model development will also entail an update to roadway improvements expected by 2025 and 2045, based on a review of the SCAG 2016 LRTP and associated Amendments.
Existing Year Model Runs
A review of the existing year model volumes along the SR- 210 corridor will be performed to assess the reasonableness of modeled volumes compared to the existing counts. Any required localized network enhancements will be coded in the model. Potential issues requiring additional localized highway network enhancements or changes that might require additional post-processing will be identified.
Future No Build Model Runs
Future year traffic forecasts would be required for both the opening year (2025) and design year (2045). The closest SCAG RTP model year available will be run and extrapolated/ interpolated as needed to represent the project analyses years. The Future No Build model network will be reviewed to identify any future local projects that may not have been included in the RTP but need to be added or removed from the current highway network.
Future with Project Model Runs
The project alternatives will be coded into the model
networks and any additional link segments that need to
be extracted for post-processing will be identified. The model will be run and raw model volumes extracted for all pertinent locations including mainline, ramps and arterials. The appropriate TDM model year assignment data will then be adjusted to provide year 2025 and year 2045 future forecasts.
WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 2
Future forecast volumes will be converted to PCE (passenger car equivalent) for use in the operational analysis.
Operational Analysis
A Traffic Operations Analysis Report will be prepared
documenting the results of traffic analysis performed for existing conditions (2023), Opening Year (2025) and Design Year (2045) for No Build and Build Alternatives using existing and proposed geometrics. Traffic simulation software Synchro will be used in assessing the operational benefits of the proposed improvements.
No freeway merge, diverge and mainline analysis will be performed as part of this Study as no improvements are
proposed on the mainline.
ROADWAY DESIGN APPROACH
EXP has developed two conceptual alternatives for the
proposed widening of northbound Citrus Avenue between
South Highland Avenue and SR-210 eastbound ramps as
described below:
Alternative 1 | Under this alternative, the northbound to eastbound right turn lane will start at the intersection of South Highland/Citrus Avenue and will end at the intersection of eastbound SR-210/Citrus Avenue ramp intersection. The proposed lane will be 12’ wide with a standard 4’ shoulder. No sidewalk is proposed since they do not exist on the bridge over SR-210. It is also proposed to shorten the raised median on Citrus Avenue to extend the southbound to eastbound left turn lanes to provide an additional 100 feet of storage for each lane. The conceptual layout plan for Alternative 1 is shown in Figure 1.
Alternative 2 | Under this alternative, the northbound to eastbound right turn lane will be shorter and begin after the catch basin just north of the intersection of South Highland/ Citrus Avenue. It will include a bay taper and have a shorter storage length than Alternative 1. The lane will end similar to Alternative 1 at the intersection of eastbound SR-210/Citrus Avenue ramp intersection. All other features will remain the same as Alternative 1 including lane width, shoulder width, sidewalk, and the length of the southbound to eastbound left turn lanes. The conceptual layout plan for Alternative 2 is shown in Figure 2.
CALTRANS PROCESS
It is anticipated that Caltrans will review the project using Encroachment Permit Application Process (EPAP) and not the Quality Management Assessment Process (QMAP) Design
Engineering Evaluation Report (DEER) process. The EXP team will complete all the forms and checklist to get Caltrans approval early on for the EPAP process. EXP recently assisted SBCTA to get Caltrans approval for the EPAP process instead of the QMAP DEER process for SR-210/Waterman Avenue
Interchange.
Project Schedule
The detailed project schedule identifying major milestones and tasks is shown on page 7. EXP commits to delivering the project within 12 months from NTP. We have allowed enough time in our schedule for all deliverables to be peer reviewed by the City and for two rounds of reviews by Caltrans.
Efficient Project Delivery
As Project Manager, Syed will take full advantage of his most recent and relevant experience of working on SBCTA’s SR- 210/Waterman Avenue Interchange Project in the City of
San Bernardino. The scope of work of SR-210/Citrus Avenue Widening Project and the Caltrans process to be followed are Figure 2 | Alternative 2 citrus avenue
widening beginning 90’ north of south
highland avenue
Figure 1 | Alternative 1 citrus avenue
widening beginning at south highland
avenue
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 3
almost identical to the other project. To take advantage of this experience, EXP has made only one change to the team that is working on the other project. All the lessons learned will be applied to this project to ensure that it is delivered efficiently and expeditiously without any surprises.
MANAGEMENT APPROACH
Throughout the development and delivery of the PA&ED
and PS&E phases of the project, the EXP team’s management approach will be based on three core principles. You have our assurance that Syed and every individual working on the team including all sub-consultants will embrace these principles:
Our project management approach will be based on
building consensus, not only in the early stages of project development, but on an ongoing basis. An example of this can be found in Figure 3 on the right. As the City’s consultant, we know that we have the responsibility and the obligation to proactively coordinate with all stakeholders, to identify and resolve issues, and to move the project forward. Our Project Manager’s 29 years of experience with Caltrans, his extensive background in project delivery, and his in-depth understanding of the encroachment permit process gives the EXP team a unique advantage.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
1. COLLABORATE
We will work closely and collaboratively with the City
of Fontana and Caltrans in a true team environment, to
identify and resolve issues, to communicate effectively, to reach consensus, and to ultimately deliver a successful project to the satisfaction of all stakeholders.
2. DELIVER QUALITY WORK
We will prepare and strictly implement a rigorous
project Quality Plan and procedures to insure that every deliverable is thoroughly reviewed and checked prior to submitting it for approval, and will facilitate the overall approval process.
3. LOOK FOR WAYS TO SAVE TIME & MONEY
We will always strive to be efficient and identify
potential opportunities that would help save time and
money.
Figure 3 | Issue Resolution / Consensus Building Process 9 Present Options & Solutions to the City of Fontana
9 Discuss Pros and Cons of each Solution
9 Decide on a Course of Action
9 Present the Issue Very Honestly
9 Present Solution(s) Preferred by City
9 Obtain & Document Concurrence by PDT
9 Use Past Experience
9 Look Ahead to Anticipate
9 Think Proactively & Ask Questions
EARLY ISSUE
IDENTIFICATION
1. STRATEGIZE WITH
CITY STAFF
3. PDT
DISCUSSION &
CONCURRENCE
4. 9 Research and Understand the Issue
9 Determine How & Why the Issue Occurred
9 Develop Options to Address the Issue
PREPARE
SOLUTIONS
2. WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 4 Risk Management
EXP will prepare a robust Risk Register for the project to assist the project team to identify, analyze, and manage risks. Our Project Manager, Syed Raza has extensive experience in this area and has provided leadership in the preparation/implementation of Risk Management Plans for various projects in Caltrans District 8.
Work Plan
The work plan has been prepared taking into account our recent experience with the City of Chino’s SR-71/Pine Avenue Interchange Project and SBCTA’s SR-210/Waterman Avenue Interchange Project. We have identified the following activities below that will be performed within first four months after receiving NTP from the City:
Proposed Staffing and Project Organization
The EXP Team has been assembled to provide the City with the personnel and project experience required to successfully deliver the SR-210/Citrus Avenue Widening Project. In addition to technical and managerial expertise, we provide a highly qualified team that includes the following:
• Local Inland Empire experience providing similar services for various agencies, including Caltrans District 8. • A team with the right skill set and attitude ready to work cooperatively with all stakeholders to successfully deliver the project.
Our Organization Chart, shown on page 8, shows our integrated team for performance of services required for this project. The Organization Chart also indicates the functional authority, lines of communications, and responsibility of the positions. Our key CONDUCT OVER THE
SHOULDER REVIEW
PRODUCE
PROJECT
DELIVERABLE
PERFORM FIELD
REVIEW
CONDUCT PEER
REVIEWS & AUDITS
SUBMIT DELIVERABLE
TO CITY OF FONTANA
PERFORM
DISCIPLINE QA
CHECK
PERFORM
INTERDISCIPLINARY
REVIEW
MAY BE PERFORMED
CONCURRENTLY
PERFORM
CONSTRUCTABILITY
REVIEW
PERFORM VISUAL
CHECK
PERFORM QA
REVIEW
Figure 4 | QA/QC Review Process
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
Quality
EXP has established an internal Quality Management System (QMS) and continually maintains and improves its effectiveness in accordance with the requirements of the International Organization for Standardization (ISO) 9001. Syed Raza, PE, our Project Manager, will be responsible for developing and maintaining a Quality Management Plan (QMP). He will use EXP’s QMS as a basis to prepare a QMP, specific for this project. The QMP will contain procedures to address all of City’s requirements. Figure 4 below depicts the proven and successful quality assurance/quality control (QA/QC) review process that will be followed:
Figure 5 | Proposed First Four Month’s Goal: SR-21o / Citrus Avenue Widening Project MONTH 1 MONTH 2 MONTH 3 MONTH 4
1. Prepare Traffic Methodology Memo
2. Request SCAG Data
3. Prepafe Traffic Operations Analysis Report
4. Obtain Survey Data
5 . Prepare Basemaps
6. Prepare Environmental Technical Studies
7. Perform Utility Coordination
WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 5
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
personnel form the framework of the organization, and the additional staff represents further resources available for the project.
environmental approach
The City will serve as the California Environmental Quality Act (CEQA) lead agency for the project. The EXP team
has conducted an independent assessment of the project
alternatives and determined that a Categorical Exemption (CE) will be the appropriate environmental document for the project under CEQA. It will be supported by following technical studies:
Noise Study | It is understood that the proposed addition of a right-turn lane on Citrus Avenue and extending the southbound left-turn lanes are not considered as capacity increasing and therefore not expected to generate noise levels greater than ambient noise. The primary source of noise will be construction equipment The following outlines the noise technical memorandum that will be prepared for the project:
• Acquire ambient noise measurements at 1-2 locations in proximity to the project site. The data will be used to establish baseline noise conditions and identify the presence of noise sensitive receptors in proximity to the study area.
• Characterize and quantify on-site construction activities to determine local construction noise and vibration effects • Determine the significance of effects based on the City’s Noise Element, Noise Ordinance, and CEQA guidelines.
• Develop recommendations and measures if necessary to mitigate possible significant construction and operational effects to below threshold levels.
The results will be documented in a Noise Memorandum
describing the methodology and results.
Air Quality Study, Energy and Greenhouse Gas Emissions | An air quality, energy and greenhouse gas emissions analysis will be performed for the project per CEQA requirements. It will include the following tasks:
• Calculate daily construction emissions using the most current version of the California Emissions Estimator Model (CalEEMod) 2020.4.0
• Compare temporary daily emissions generated during site preparation, and construction to S.Coast Air Quality Management District significance thresholds;
• Quantify carbon dioxide equivalent (CO2e ) (i.e., GHG emissions) units
• Compare GHG emission with SCAQMD significance thresholds. • Based on CalEEMod output, BPG will calculate diesel and gasoline demand associated with the construction activity.
Environmental Analysis | EXP will evaluate existing conditions, potential adverse effects of project implementation (both individual and cumulative), and measures to mitigate such effects.
The Environmental Analysis will thoroughly discuss the existing conditions for each applicable environmental issue area and identify short-term construction and long-term operational impacts associated with the project. The impact analysis will be consistent with environmental factors, as presented in Appendix G of the CEQA Guidelines. The Environmental Analysis sections will provide vital supporting information for the conclusions rendered for the Environmental Checklist.
The following topics are considered applicable based on the current understanding of the project:
• Air Quality
• Cultural Resources
• Energy
• Geology and Soils
• Greenhouse Gas Emissions
• Land Use and Planning
• Noise
• Transportation
• Tribal Cultural Resources
• Mandatory Findings of Significance
Cultural Resources | Cultural Resources analysis will be performed pursuant to CEQA for the project site. It will consist of the following:
1. Cultural resources records search of the project site and a one-half mile buffer in the California Historical Resources Information System (CHRIS) at the South Central Coastal Information Center (SCCIC).
2. Paleontological resources records search and literature review from the San Bernardino County Museum.
3. Pedestrian survey of the Project site
4. Assistance completing the cultural resources section of the CE.
Initial Site Assessment (ISA) | As ISA will be prepared following the standard practices of the ASTM International (ASTM) Phase I Environmental Site Assessment Process (Standard E1527-13/- 21). It will include the following:
• Review of regulatory agency records to help identify recognized environmental conditions in connection with the property. • Review of USGS 7.5 Minute Topographical Map (or equivalent) to describe the physical setting.
• Historical use information will be obtained from aerial photographs, fire insurance maps, city building permits and USGS topographical maps
• Visual survey of property and adjacent sites for indications of potential for contamination or contamination generators. • Prepare ISA Report and Checklist
CE Determination | The determination page will conclude the appropriate action (expected to be a CE based upon the environmental analysis).
right of way approach
The City is in the process of obtaining property rights from the adjacent parcel on the east side of Citrus Avenue in Fontana, Parcel No. (APN) 0240-011-38-0000, Owner (Assessor) SAGE CITRUS FONTANA LLC, depicted by green outline in Figure 6.
Once the City obtains the property rights, the EXP team will prepare real estate documents and coordinate with Caltrans, as necessary, to transfer property deeds from the City to Caltrans.
Utility Research and Identification
Utility research will help determine prior rights and liabilities, identify potentially high cost utility relocations, and coordinate the utility clearance process for on-time project certification.
Initial review of possible utility conflicts within the project limits have identified the following six utility owners:
1. AT&T - overhead and/or underground fiber optic communications
2. MCI-Verizon Business - overhead and/or underground fiber optic communications
3. Crown Castle - overhead and/or underground fiber optic communications
4. Fontana Water Company – potable water line and water services
5. Southern California Gas Company– transmission and distribution
6. Southern California Edison – electrical transmission, distribution and telecommunication.
One of the first tasks will be the early identification and verification of utilities in the project area and obtain confirmation from the utility owners. To identify all the utilities in the project area, the EXP team will prepare and mail verification requests to utility owners and follow-up letters requesting current information on any existing facilities. The EXP team has established relationships and trust with the utility companies within the boundaries of this project and Caltrans District 8 which will allow it to engage efficiently with utilities and accomplish project goals.
Positive Utility Identification (Pothole) Coordination
EXP will coordinate the potholing services to determine positive horizontal and vertical locations of underground utilities in accordance with Caltrans’ High and Low Risk Policies and Procedures. Notification letters will be sent to affected utility owners. Potholing will be performed to positively identify any underground utility that may be in conflict.
The following two notable utility impacts are anticipated for the project:
1. SCE Vault (V5456955) – For Alternative 1, SCE vault (Figure 7) will require adjustment to grade w/ traffic-rated lid and vent relocation behind new curb at a minimum or the vault and appurtenances will require relocation behind the new curb.
2. Communications manhole – The communications manhole (Figure 8) near the eastbound SR-210 on-ramp appears to be located within Caltrans right of way and will be required to be relocated outside of Caltrans right of way in accordance with Local Agency Procedures Manual (LAPM) and Caltrans Right of Way Manual guidelines.
WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 6
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
Figure 6 | The City is already in the process of obtaining property rights from the adjacent parcel on the east side of Citrus Avenue, APN 0240-011-38-0000 owned by SAGE
CITRUS FONTANA LLC.
Figure 7 | The SCE vault is located on the northeast
corner of Citrus Avenue and South Highland Avenue.
Figure 8 | The communications manhole near the
eastbound SR-210 on-ramp.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
WORK PLAN, SCOPE OF WORK, AND DELIVERABLES | 7
ID Task Name Duration Start Finish
1 NOTICE TO PROCEED (NTP) 0 days Mon 4/3/23 Mon 4/3/23
2 PROJECT MANAGEMENT 249 days Mon 4/3/23 Thu 3/14/24
3 Prepare PMP 10 days Mon 4/3/23 Fri 4/14/23
4 QC Review and Revisions 7 days Mon 4/17/23 Tue 4/25/23 5 City of Fontana Review and Approval 20 days Wed 4/26/23 Tue 5/23/23 6 Prepare QMP 5 days Mon 4/3/23 Fri 4/7/23
7 QC Review and Revisions 7 days Mon 4/10/23 Tue 4/18/23 8 City of Fontana Review and Approval 10 days Wed 4/19/23 Tue 5/2/23 9 Communication / Coordination 249 days Mon 4/3/23 Thu 3/14/24 10 SURVEY & MAPPING 20 days Mon 4/17/23 Fri 5/12/23
11 Supplemental Survey & Mapping 20 days Mon 4/17/23 Fri 5/12/23 12 TRAFFIC STUDIES 60 days Mon 5/1/23 Fri 7/21/23
13 Prepare Traffic Operations Analysis
Report (TOAR)
20 days Mon 5/1/23 Fri 5/26/23
14 QC Review and Revisions 20 days Mon 5/29/23 Fri 6/23/23 15 City of Fontana Review 20 days Mon 6/26/23 Fri 7/21/23 16 GEOTECHNICAL 112 days Mon 5/29/23 Tue 10/31/23
17 Obtain CE for Geotech Borings 30 days Mon 5/29/23 Fri 7/7/23 18 Prepare Caltrans Encroachment Permit 2 days Mon 7/10/23 Tue 7/11/23 19 Caltrans Review and Approval 20 days Wed 7/12/23 Tue 8/8/23 20 Prepare Materials, Foundation,
Geotechnical Report
40 days Wed 8/9/23 Tue 10/3/23
21 QC Review and Revisions 5 days Wed 10/4/23 Tue 10/10/23 22 City of Fontana Review 10 days Wed 10/11/23 Tue 10/24/23 23 Revise and Resubmit Materials,
Foundation, Geotechnical Report
5 days Wed 10/25/23 Tue 10/31/23
24 HYDROLOGY / HYDRAULICS 85 days Mon 7/24/23 Fri 11/17/23 25 Prepare Storm Water Data Report (SWDR) 25 days Mon 7/24/23 Fri 8/25/23 26 QC Review and Revisions 5 days Mon 8/28/23 Fri 9/1/23 27 City of Fontana Review 10 days Mon 9/4/23 Fri 9/15/23 28 Prepare Drainage Report (DR) 25 days Mon 9/18/23 Fri 10/20/23 29 QC Review and Revisions 10 days Mon 10/23/23 Fri 11/3/23 30 City of Fontana Review 10 days Mon 11/6/23 Fri 11/17/23 31 ENVIRONMENTAL COMPLIANCE 140 days Mon 4/17/23 Fri 10/27/23 32 Research & Investigation 30 days Mon 4/17/23 Fri 5/26/23 33 Technical Memo & CE Form 90 days Mon 5/29/23 Fri 9/29/23 34 Notice of Determination Filed 20 days Mon 10/2/23 Fri 10/27/23 35 UTILITY COORDINATION 130 days Mon 5/29/23 Fri 11/24/23 36 Obtain Utilities As-Built Plans 40 days Mon 5/29/23 Fri 7/21/23 37 Notifications 10 days Mon 7/24/23 Fri 8/4/23
38 Receive Responses 80 days Mon 8/7/23 Fri 11/24/23
39 Prepare Caltrans Encroachment Permit 10 days Mon 5/29/23 Fri 6/9/23 40 Caltrans Review and Approval 60 days Mon 6/12/23 Fri 9/1/23 41 Field Potholing 10 days Mon 9/11/23 Fri 9/22/23
42 Update Utility Info on Plans 10 days Mon 9/25/23 Fri 10/6/23 43 65% PS&E PACKAGE 70 days Mon 5/15/23 Fri 8/18/23
44 Prepare Base Maps 10 days Mon 5/15/23 Fri 5/26/23
45 Prepare 65% Plans, Specs, & Estimate 40 days Mon 5/29/23 Fri 7/21/23 46 QC Review and Revisions 10 days Mon 7/24/23 Fri 8/4/23 47 City of Fontana Review 10 days Mon 8/7/23 Fri 8/18/23 48 95% PS&E PACKAGE 45 days Mon 8/21/23 Fri 10/20/23
49 Prepare 95% Plans, Specs, & Estimate 30 days Mon 8/21/23 Fri 9/29/23 50 QC Review and Revisions 5 days Mon 10/2/23 Fri 10/6/23 51 City of Fontana Review 10 days Mon 10/9/23 Fri 10/20/23 52 100% PS&E 45 days Mon 10/23/23 Fri 12/22/23
53 Prepare 100% Plans, Specs, & Estimate 20 days Mon 10/23/23 Fri 11/17/23 54 QC Review and Revisions 5 days Mon 11/20/23 Fri 11/24/23 55 City of Fontana Review 10 days Mon 11/27/23 Fri 12/8/23 56 Revise 100% PS&E 10 days Mon 12/11/23 Fri 12/22/23
57 CALTRANS ENCROACHMENT PERMIT 60 days Mon 12/25/23 Fri 3/15/24 58 Encroachment Permit Approval 60 days Mon 12/25/23 Fri 3/15/24 59 Project Ready to List 0 days Fri 3/15/24 Fri 3/15/24 4/3
3/14
Prepare PMP
QC Review and Revisions
City of Fontana Review and Approval
Prepare QMP
QC Review and Revisions
City of Fontana Review and Approval
Communication / Coordination
5/12
Supplemental Survey & Mapping
7/21
Prepare Traffic Operations Analysis Report (TOAR)
QC Review and Revisions
City of Fontana Review
10/31
Obtain CE for Geotech Borings
Prepare Caltrans Encroachment Permit
Caltrans Review and Approval
Prepare Materials, Foundation, Geotechnical Report
QC Review and Revisions
City of Fontana Review
Revise and Resubmit Materials, Foundation, Geotechnical Report 11/17
Prepare Storm Water Data Report (SWDR)
QC Review and Revisions
City of Fontana Review
Prepare Drainage Report (DR)
QC Review and Revisions
City of Fontana Review
10/27
Research & Investigation
Technical Memo & CE Form
Notice of Determination Filed
11/24
Obtain Utilities As-Built Plans
Notifications
Receive Responses
Prepare Caltrans Encroachment Permit
Caltrans Review and Approval
Field Potholing
Update Utility Info on Plans
8/18
Prepare Base Maps
Prepare 65% Plans, Specs, & Estimate
QC Review and Revisions
City of Fontana Review
10/20
Prepare 95% Plans, Specs, & Estimate
QC Review and Revisions
City of Fontana Review
12/22
Prepare 100% Plans, Specs, & Estimate
QC Review and Revisions
City of Fontana Review
Revise 100% PS&E
3/15
Encroachment Permit Approval
3/15
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2023
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
CITY OF FONTANA - CITRUS AVE WIDENING AT SR-210
City of Fontana
Citrus Ave Widening at SR-210
EXP PROPOSED TASK SCHEDULE / SCHEDULE OF DEADLINES
The EXP team has prepared an aggressive schedule for the project to help the City complete the improvements as soon as possible.
Developments are planned or in progress on the west and east side of Citrus Avenue south of SR-210. The proposed improvements are critical to alleviate anticipated congestion on Citrus Avenue. EXP is committed to delivering the project in less than a year. The Gantt chart (Figure 9) shows detailed schedule for various tasks anticipated for the project.
Figure 9 | S chedule
3 organization and Staffing Plan
3. ORGANIZATION AND STAFFING PLAN
PROJECT UNDERSTANDING | 8ORGANIZATION AND STAFFING PLAN | 8
CITY OF FONTANA
PROJECT MANAGER
*Syed Raza, PE | EXP
ROADWAY / TRAFFIC DESIGN
*Christine Brown, PE | EXP
Jose Carrillo | EXP
TRAFFIC OPERATIONS
ANALYSIS REPORT
Mitsuru Tanaka, PE (OR) | EXP
Ben Hashemloo, PE (NV) | EXP
GEOTECHNICAL
Hashmi Quazi, PhD, PE, GE | CON
QA/QC MANAGER
Luis Betancourt, PE | EXP
DELIVERY TEAM
FIGURE 10 | PROJECT TEAM ORGANIZATIONAL CHART
DESIGN LEAD
*Gabriel Rodriguez, PE | EXP
EXP EXP U.S. Services, Inc.
CLS CL Surveying & Mapping
CON Converse
DEA David Evans & Associates
EPIC Epic Land Solutions, Inc.
VCS VCS Environmental
* denotes key personnel
LEGEND:
PROPOSED STAFFING
The EXP Team has been assembled to provide the City with the personnel and project experience required to successfully deliver the SR-210/Citrus Avenue Widening Project. In addition to technical and managerial expertise, we provide a highly qualified team that includes the following:
• Local Inland Empire experience providing similar services for various agencies, including Caltrans District 8. • A team with the right skill set and attitude ready to work cooperatively with all stakeholders to successfully deliver the project.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
STORMWATER & DRAINAGE DESIGN
*Portia Gonzalez, PE | EXP
Christina Agustin | EXP
TRAFFIC SIGNAL/LIGHTING
Mitsuru Tanaka, PE (OR) | EXP
ENVIRONMENTAL
*Eric Turner | VCS
Joel Martinez | VCS
LANDSCAPE EROSION CONTROL
Kim S. Rhodes, PLA | DEA
CALTRANS PERMIT
*Christine Brown, PE | EXP
CONSTRUCTION STAGING /
TRAFFIC HANDLING
Shubhee Saxena, EIT | EXP
Parakh Jaiswal, EIT | EXP
SURVEYING
Daniel Cavillo | CLS
RW & UTILITIES
*Michael Mays | EPIC
Darcy Mendoza, RWA | EPIC
ORGANIZATION AND STAFFING PLAN | 9
Figure 11 | dedicated key staff resources for the project Key STAFF PROJECT ROLE CURRENT ASSIGNMENTS AVAILABILITY Syed Raza, PE | EXP Project Manager, Caltrans Coordination • SBCTA, SR-210/Waterman Avenue Interchange Improvements
• City of Chino, Euclid/Pine Avenue
Intersection Improvement Project
• City of Perris, Ellis Avenue
Overcrossing PA&ED & PS&E
50%
Gabriel Rodriguez, PE | EXP Design Lead • SBCTA, Segment 5 • SBCTA, I-215 Landscape Project
• Phelan Rd. Widening
50%
Christine Brown, PE | EXP Roadway/Traffic Design, Caltrans Permit
• SBCTA, SR-210/Waterman Avenue
Interchange Improvements
• City of Seal Beach Blvd. Pavement
Rehabilitation
• City of Perris, Ellis Avenue
Overcrossing PA&ED & PS&E
50%
Portia Gonzalez, PE, QSP/QSD | EXP Stormwater & Drainage Design • City of Beaumont MDP Plan • City of Ontario, San Antonio
Stormdrain
50%
Eric Turner | VCS Environmental • Mt Vernon
• I-15 Corridor
• I-10 Truck Climbing Lane
• I-10 Corridor
• Metro I-105 Express Lanes
• Kindred Bridge-housing
• Seal Beach NEPA document
25%
Joel Martinez | VCS Environmental • Seal Beach NEPA document:
Preliminary Environmental Study
• Kindred Bridge-housing: NEPA
Document: Environmental
Assessment
• I-10 Eastbound Truck Climbing
Lanes
• I-10 Corridor
40%
Michael Mays | EPIC Right of Way & Utilities • SBCTA I-10 Mt Vernon Ave Interchange
• OCTA 91 Freeway Segments 1, 2,
and 3
50%
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
4 References
REFERENCES | 10
SBCTA | SR-210 / WATERMAN AVENUE
INTERCHANGE PROJECT, SAN
BERNARDINO, CA
EXP is providing professional services for
San Bernardino County Transportation
Authority (SBCTA) for the Design
Engineering Evaluation Report (DEER)/
Environmental Document (ED), Plans,
Specifications and Estimate (PS&E), Right-
of-Way (ROW) and Construction Support
for the State Route 210 (SR-210) Waterman
Avenue Interchange Project. The EXP
Team is providing roadway and structural
engineering, traffic analysis, drainage
environmental, geotechnical, surveying, and
utility coordination. The purpose of the
project is to improve traffic operations and
local circulation at the SR210 / Waterman
Avenue interchange. The eastbound on-
ramp will be widened from one lane to
two lanes. Additionally, the median along
Waterman Avenue will be removed, and the
intersection of Waterman Avenue and East
30th Street will be restriped to allow for
two left-turn lanes in the northbound and
southbound direction. This project requires
approval from Caltrans District 8 Oversight.
CLIENT REFERENCE
Paul Melocoton, Project Manager
1170 West Third Street, 2nd Floor, San
Bernardino, CA 92410
t: 909.884.8276
e: [email protected]
PROVEN TEAM EXPERIENCE | The proposed
EXP team, Including Converse and CL
Surveying & Mapping, is currently
working on sr-210 / waterman avenue
interchange together.
CITY OF CHINO | PINE AVENUE
EXTENSION TO STATE ROUTE 71, CHINO,
CA
The project consists of widening SR-71
northbound and southbound off ramps to
increase the ramps capacities, install a traffic
signal at the SR-71 northbound off ramp to
Pine Avenue and restripe the overcrossing
between the SR-71 northbound and
southbound off ramps in the cities of Chino
and Chino Hills in San Bernardino County.
The need and purpose of the project is
to improve the operational efficiency of
the interchange. The addition of a right-
turn lane at both off-ramps, is expected
to significantly improve the operation of
the intersections. by reducing delays and
queues and improve the overall level of
service of the intersection. EXP team is
responsible for the Engineering Studies and
Right of Way/Utilities, Project Management
and complete PS&E package.
CLIENT REFERENCE
Maria Fraser
13220 Central Avenue, Chino, CA 91710
t: 909.334.3310
e: [email protected]
PROVEN TEAM EXPERIENCE | The proposed
EXP team, Including Epic and CL
Surveying & Mapping, is currently
working on pine avenue Extension to
SR-71 Ramp Widening together.
CITY OF CHINO | EUCLID AVENUE
RESTRIPING PROJECT, CHINO, CA
EXP as a sub-consultant to Z&K
Consultants, Inc. for the City of Chino
On-Call is providing design services for
Euclid Avenue (SR-83) Restriping Project
between Pine and Bickmore Avenue. EXP’s
tasks include preparing a Traffic Report and
preparing the PS&E package for the project.
The scope of work for the project consists
of shifting lanes to the west by restriping to
create room to add a second northbound
through lane. A 14-foot continuous two-way
left-turn lane is proposed between north
and southbound lanes. The addition of a
second northbound through lane expected
to significantly increase the capacity for
this movement as there is currently only
one northbound lane. The proposed
improvements will help reduce delay and
improve overall level of service on the
corridor.
CLIENT REFERENCE
Maria Fraser
13220 Central Avenue, Chino, CA 91710
t: 909.334.3310
e: [email protected]
4. REFERENCES
EXP’s ultimate success is owed to our strong client partnerships on unique infrastructure programs. EXP is proud of our schedule and budget performance and quality culture evidenced by more than 50 recent awards we have won for our infrastructure and transportation work. Ranked #26 in the Top 500 Design Firms, ENR 2021, EXP is consistently recognized in the industry and by our clients for the quality of our services.
EXP brings this reputation to bear in the Inland Empire where we have been building a practice of locally experienced transportation professionals since 2018, focused on exemplary delivery for municipal and DOT clients.
Below we are showing our references, and also demonstrating our experience with similar kinds of work, our innovative and advanced techniques, as well as technical ability.
City of Fontana | RFP For Design Services | Citrus Ave.
Widening at SR-210 Project | SP+-81-DE-23
5 Appendix
• Appendix A | Resumes
• Appendix B | Cost Proposal Sheet
• Resumes
appendix a
A
APPENDIX A | xi
Project Experience
State Route 71/Pine Avenue Interchange, Chino, CA/ Caltrans District 8 The project consists of widening SR-71 northbound and southbound off ramps to increase the ramps capacity, install a traffic signal at the SR-71 northbound off ramp to Pine Avenue and restripe the overcrossing between the SR-71 northbound and southbound off ramps in the cities of Chino and Chino Hills in San Bernardino County. As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
State Route 210/Waterman Avenue Interchange Project, San Bernardino, CA The project consists of widening SR-210 eastbound on-ramps to increase the ramps capacity, restripe the overcrossing between the ramps and modify the existing traffic signals in the City of San Bernardino. As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
Euclid/Pine Avenue Intersection Improvement Project, Chino, CA/ Caltrans District 8
The project consists of adding left and right turn lanes at the intersections including modifying traffic signal, adding sidewalk, curb ramps, bike lanes and safety lighting. . As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
City of Chino, Euclid Avenue Restriping Project, Chino, CA Served as EXP’s Design Lead for EXP for the City of Chino On-Call. EXP is providing design services for Euclid Avenue (SR-83) Restriping Project between Pine and Bickmore Avenue. EXP’s tasks include preparing a Traffic Report and preparing the PS&E package for the project. The scope of work for the project consists of shifting lanes to the west by restriping to create room to add a second northbound through lane. A 14-foot continuous two-way left-turn lane is proposed between north and southbound lanes. The addition of a second northbound through lane is expected to significantly increase the capacity for this movement as there is currently only one northbound lane. The proposed improvements will help reduce delay and improve overall level of service on the corridor.
Syed has over 41 years of executive,
management and technical experience
in the areas of transportation/traffic
engineering and program/project
management. During his career, he
has led many multi-functional teams
and successfully delivered high-
profile, state of the art complex
transportation projects. Syed was
responsible for the delivery of all
capital projects at Caltrans District 8
and oversaw the delivery of over 300
in-house and locally funded capital
projects valued at over $15 billion.
His proactive management approach,
communication and problem-solving
skills, ability to build consensus and
strong leadership skills has helped
District 8 successfully meet its project
delivery commitments year after year.
Syed was instrumental in assisting
RTPAs, counties and cities deliver their
portfolio of projects on the State
Highway System including processing
of the projects through the District
Office of Local Assistance.
Professional Registrations +
Certifications
• Professional Engineer (Civil), CA
C53579
Education + Training
• Master of Science, Civil Engineering,
Texas A&M University, College
Station, Texas 1991
• Bachelor of Science, Civil
Engineering, NED Engineering
University, Karachi
Syed Raza, PE
Project Manager
SPECIALTY EXPERIENCE
• roadway design
• intersection design
• traffic design
• traffic handling
• construction staging
• stakeholder
coordination
SCOPE TECHNICAL AREA EXPERTISE
• project management
• program management
• highway design
• pavement delineation design
detour design
• agency coordination 3
years with EXP
41+
years of
experience
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xii
San Bernardino County, Phelan Road Widening, San Bernardino County, CA Syed is serving as Roadway Design Lead. EXP is providing preliminary engineering and environmental consulting services for the Phelan Road Widening Project. Phelan Road is currently a two-lane road that serves the communities of Phelan and Hesperia and is often a thoroughfare and diversion route for those experiencing closures or traffic congestion on nearby Interstate 15 (I-15). The project proposes to widen approximately 12.1 miles of Phelan Road from two (2) lanes to a five (5) lane major highway designation with the center serving as one (1) continuous left turn lane.
San Bernardino County Transportation Authority (SBCTA), I-215 Landscaping Project Served as the Traffic Lead for SBCTA’s 5.1 mile long $11 million I-215 Bi-County Landscape Project to provide a distinctive cohesive landscape design between San Bernardino and Riverside Counties. Prepared 100% plans, specifications and estimate for Construction Staging, Traffic Handling, Construction Area Signs and Motorist Information Signs for the project.
California Department of Transportation (Caltrans), District 8 Project Management On-Call EXP was selected as the prime consultant by Caltrans District 8 to provide Project Management support services for capital projects. Prepared detailed project schedules and cost estimates. Ensured all necessary regulatory permits were obtained.
Prepared project status reports, cooperative agreements and amendments. Prepared and reviewed technical reports, plans, specifications and estimate for completeness and accuracy. Ensured that projects were delivered on time, within budget, approved scope of work and met performance objectives. Prepared complex technical engineering reports for management review and approval. Prepared allocation request for California Transportation Commission (CTC) approval including Programing Change Requests and Supplemental Fund Request. Prepared and submitted grant applications for various federal and state funding programs.
Syed Raza, PE – continued
Project Manager
*Work performed at previous firm.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xiii
Project Experience
Phelan Road Widening Project, for County of San Bernardino, San Bernardino County, CA
Gabriel is serving as the project manager for the Phelan Road Widening project and is leading the design team which includes roadway and structural engineering, drainage, environmental, geotechnical, surveying, utility coordination and public outreach.
The purpose of the project is to widen 12.1 miles of Phelan Road to accommodate for the increased population and resulting traffic in the region. The project design will include geometrics and vertical profiles for the widening from two lanes to five lanes, hydrology and hydraulic analysis of 26 culvert crossings, bridge improvements at Sheep Creek, traffic and traffic signal design, utility relocations, and environmental planning and permitting. The project will also require coordination with stakeholders including Caltrans District 8, Union Pacific Railroad, the California Public Utilities Commission, regulatory permitting agencies, and the City of Hesperia.
Lakewood Boulevard and Imperial Highway Intersection Improvement Project, for City of Downey, Downey, CA
Gabriel is serving as project manager for the Lakewood Boulevard and Imperial Highway Intersection Improvement project and is responsible for leading the project design team to develop the roadway and storm drain improvement plans. The project located in the City of Downey, proposes to add dual left turn pockets in both directions on Imperial Highway to improve the traffic level of service of the intersection. The project design includes the roadway geometry and vertical profile for the widening of Imperial Highway, PCC improvements, storm drain lateral design, water appurtenance relocations, and private property improvements. The project will also require approval by Los Angeles County for the relocation of the County owned catch basin at the southwest corner of the intersection.
I-215 Segment 5 Landscape Project, San Bernardino County, CA Gabriel is serving as the project manager for the I-215 Segment 5 Landscape project and is responsible for leading the project design team which includes landscape architecture, environmental, stormwater, traffic, electrical, utilities, and cost estimating through the Project Approval and Environmental Document (PA/ED) phase as well as final Plan, Specifications, and Estimate (PS&E). This 1-mile-long project will provide a palms to pines themed landscape transition along I-215 between Highland Avenue and State Route (SR) 210 in the City of San Bernardino. The project will require significant coordination with SBCTA and several functional units at Caltrans District 8 including Landscape Architecture, Maintenance, Construction, Traffic, and Water Quality.
Gabriel has more than 24 years of civil
engineering experience in the design
and management of transportation
and public infrastructure projects.
His project experience includes
street improvements, state system
improvements, storm drain facilities,
sanitary sewer and water distribution
infrastructure, storm water management
and analysis, and dry utility coordination.
He has executed projects from
preliminary engineering and alternative
analysis through final design and
construction management.
Gabriel brings experience with a number
of agencies, including SBCTA, Riverside
County Transportation Department,
Riverside Transit Agency, LA Metro,
Orange County Public Works as well
as local agencies such as the Cities of
Palmdale, Irvine, Fontana and Colton.
Professional Registrations
• Professional Engineer (Civil): CA
69948
Education + Training
• B.S., Civil Engineering, California
Polytechnic State University at
Pomona, 2001
SPECIALTY EXPERIENCE
• roadway design
• civil engineering
• public infrastructure
• street improvements
• state system
improvements
SCOPE TECHNICAL AREA EXPERTISE
• roadway design
• civil engineering
• street improvements
24+
years of
experience
*Work performed at previous firm.
4+
years with EXP
Gabriel Rodriguez, PE
Design Lead
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xiv
Gabriel Rodriguez, PE – continued
Design Lead
*Work performed at previous firm.
Santa Gertrudis Creek Phase II Bike Trail Project, for City of Temecula, Temecula, CA Gabriel is serving as project manager for the Santa Gertrudis Creek Phase II Bike Trail project and is responsible for leading the project design team which includes, civil, drainage, and structural engineering, environmental planning, surveying and mapping, geotechnical, and utility coordination. The project located along the Santa Gertrudis Creek proposes to grade separate the bike trail under the existing Margarita Road bridge. This will improve safety for bicyclists and pedestrians continuing on the trail by eliminating the interface with vehicles at the Margarita Road at grade street crossing. The project design includes the trail geometry and vertical profile, retaining walls and the relocation of a 20-inch reclaimed water line that is owned and maintained by Rancho California Water District.
Marina Drive Resurfacing Project, for City of Seal Beach, Seal Beach, CA Gabriel served as project manager for the Marina Drive Resurfacing project and was responsible for leading the project design team to develop paving improvements plans, traffic control plans, estimates, and specifications. The project located in the City of Seal Beach proposed to rehabilitate the existing asphalt paving on Marina Drive between 1st Street and State Route (SR) 1. The project included milling and overlay, full depth structural section replacement, ADA improvements, cross gutter and driveway replacements, and signing and striping.
Annual Local Paving Program, for City of Seal Beach, Seal Beach, CA Gabriel served as project manager for the FY 19-20 Annual Local Paving Program and was responsible for leading the project design team to develop paving and street improvements plans, traffic control plans, estimates, and specifications. The project located in the City of Seal Beach proposed to rehabilitate the existing asphalt paving for five local streets including Main Street and realign a curb return and replace handicap ramps at the intersection of 1st Street and Welcome Lane. The project is scheduled to begin construction in April 2020.
SBCTA I-215 Bi-County Landscaping PA&ED and PA&E, San Bernardino County, CA Gabriel is serving as the project manager for the I-215 Bi-County Landscape project and is responsible for leading the project design team which includes landscape architecture, environmental, roadway, traffic, electrical, right-of-way, utilities, and cost estimating through the Project Approval and Environmental Document (PA/ED) phase as well as final Plan, Specifications, and Estimate (PS&E). This 5.1 long project will provide a themed landscape transition along the I-215 between the San Bernardino County and Riverside County line and Orange Show Road in the City of San Bernardino. The project will require significant coordination with Caltrans District 8 as well the stakeholder cities of Colton, San Bernardino, and Grand Terrace in order to build consensus and ultimately gain approval of the landscape design and environmental document.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xv
Project Experience
*Brightline High Speed Passenger Rail from Victorville to Las Vegas, San Bernardino County, CA
Served as the Caltrans HQ oversight engineer for geometric standards and project delivery. This $4.8 billion privately funded new high-speed passenger rail project will connect the City of Victorville, California to Las Vegas Nevada. The project is primarily proposed in the median of Interstate 15 (I-15) within Caltrans right of way. Caltrans HQ and District 8’s role is to provide oversight for the project and ensure all Federal and State requirements and standards are met. The project will use alternative delivery method (CMGC)and innovative financing using sale of private equity bonds to fund the majority of the project cost. This passenger train is expected to reduce vehicular traffic on I-15 and help improve the efficiency, safety and operations of traffic between Southern California and Las Vegas. The project is currently in environmental revalidation and preliminary engineering phase.
*State Route 91 Corridor Improvement Project, Corona, CA Served as the Caltrans HQ oversight engineer for geometric standards and project delivery of the RCTC $1.3 billion SR-91 Corridor Improvement Project. The project scope of work included adding two express lanes and one general purpose lane in each direction of SR-91 for 12 miles. In addition, the project included adding a direct express lane to express lane connector in the median of I-15 and SR-91, interchange reconfiguration, multiple bridge widening, collector-distributor roads, retaining walls, soundwalls, landscape and hardscape improvements, traffic signal modifications, ADA and pedestrian facilities upgrade and safety lighting upgrade.
Coordinated with CT HQ, District 8 and FHWA to secure all the necessary approvals for major project deliverables. Assisted with the approval of geometric design standards and major project deliverables.
*Caltrans HQ Office of Project Delivery, Sacramento, CA Served as the Caltrans HQ Project Delivery Coordinator for District 8 and District
11. Provided technical advice on geometric standards and procedural advice to the districts in the development of transportation projects that are high quality, cost effective, and within programmed allocations and established schedules.
Ensured the uniform application of geometric design standards, procedures, guidelines and practices. Assisted with the revisions and updates to the Highway Design Manual (HDM) and the Project Development Procedures Manual (PDPM).
Provided independent reviews and comments on project documents prepared Luis Betancourt has over 35 years
of executive, management and
technical experience in the areas
of transportation/geometrics and
program/project management. During
his career, he has led multi-functional
teams and successfully helped to
delivered high-profile, state of the art
complex transportation projects. Luis
helped in the delivery of all capital
projects in Caltrans District 8 and
District 11. He oversaw the delivery
of in-house and locally funded capital
projects. His proactive management
approach, communication and
problem-solving skills, ability to build
consensus and strong leadership skills
has helped District 8 and District 11
successfully meet its project delivery
commitments.
Professional Registrations +
Certifications
• Professional Engineer (Civil), CA
C43806
Education + Training
• Bachelor of Science, Civil
Engineering, California State
University, Chico. 1985
Luis Betancourt, PE
QA/QC Manager
SPECIALTY EXPERIENCE
• Interchange Design
• Highway Design
• Intersection Design
• Bicycle Facilities
• Pedestrian Facilities
SCOPE TECHNICAL AREA EXPERTISE
• QA/QC
• Project Management
• Highway Design
• Geometric Compliance <1
years with EXP
35+
years of
experience
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xvi
by the districts including procedural, engineering, economic, environmental, policy matters and cost estimates. Approved deviations from geometric design standards, major scope changes and requests for additional funding. Assisted the districts in resolving issues and gain approval with FHWA regarding design details and standards, federal fund participation and environmental impacts. Served as the principle Caltrans HQ Project Delivery contact with FHWA. *Interstate 10 Express Lanes from Los Angeles County to Interstate 15, San Bernardino County, CA Served as the Caltrans HQ oversight engineer for geometric standards and project delivery of this 10 mile-long, $720 million project, developed and funded cooperatively by SBCTA and Caltrans. This will add two express lanes in each direction of I-10 from the Los Angeles County Line to I-15 through the cities of Montclair and Ontario. The project will also reconstruct the two outside lanes with long life pavement and add safety lighting. This project has used alternative delivery method (design-build) and innovative financing using Transportation Infrastructure Finance and Innovation Act (TIFIA) federal loan from USDOT. The project requires outside widening necessitating reconstruction of several local street interchanges. *Caltrans District 8 Division of Design, San Bernardino + Riverside Countries, CA Served as the Acting Deputy District Director for Design from May 2008 to November 2008. Developed and implemented the Division’s strategic, business and operational plans consistent with the Department’s mission, vision, goals, strategic objectives, and performance measure. Set policies and priorities for the Division’s work products. Directed and evaluated the performance of managers and established management control systems and performance targets. Represented Caltrans at local agency meetings, committees, task forces and public forums. Maintained effective working relationships with local governments, other state and federal agencies.
*Interstate 15 Express Lane from Cajalco Road to San Bernardino County; Riverside County, CA Served as the Caltrans HQ oversight engineer for geometric standards and project delivery. This 20-mile long $470 million project developed by RCTC in collaboration with Caltrans and FHWA will add two express lanes to I-15 in both directions, from Cajalco Road to State Route 60, widen bridges and add soundwalls. This design-build project will be built within the existing median and offer multiple entry and exit points to the express lanes. This project has used alternative delivery method (design-build) and innovative financing using TIFIA loan from USDOT. The project is anticipated to improve existing and future mobility along the I-15 corridor, reduce congestion and improve traffic flow. It will also expand the regional express lane network and increase travel time reliability. *State Route 58 (SR-58) New Expressway in the Community of Hinkley and Kramer Junction, San Bernardino County, CA
Served as the Caltrans HQ oversight engineer for geometric standards and project delivery. This 24-mile long $400 million new expressway project provided a vital link from Central California for the efficient movement of agricultural and dairy products to the rest of the country. This CMGC project was the final two segments of SR-58 that connected Bakersfield to Barstow as a high-speed expressway facility. The scope of work for the project included adding two lanes in each direction, separated by a wide dirt median, standard inside and outside shoulder, addition of four local street interchanges, bridges, culverts and erosion control. The project was completed in 2019 and has significantly helped in enhancing goods movement on the SR-58 corridor which carries over 40% truck traffic.
Luis Betancourt, PE – continued
QA/QC Manager
*Work performed at previous firm.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xvii
Project Experience
State Route 210/Waterman Avenue Interchange Project, San Bernardino, CA The project consists of widening SR-210 eastbound on-ramps to increase the ramps capacity, restripe the overcrossing between the ramps and modify the existing traffic signals in the City of San Bernardino. As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
City of Chino, Pine Avenue Extension to State Route 71, Chino, CA Christine is serving as Roadway Task Lead for the Pine Avenue Widening Project at the SR71 / Pine Avenue interchange in the cities of Chino and Chino Hills. The project includes widening the northbound and southbound off-ramps to increase the ramp capacities, install a traffic signal at the SR71 northbound off-ramp to Pine Avenue, and restripe the overcrossing between the SR-71 northbound and southbound off ramps in the cities of Chino and Chino Hills.
City of Seal Beach, Seal Beach Boulevard & I-405 Pavement Rehabilitation, Seal Beach, CA
The City of Seal Beach is proposing a pavement rehabilitation project at the intersection of Seal Beach Boulevard and I-405 EB Ramps / North Gate Road. The project will include pavement rehabilitation for the entire intersection and extending approximately 440 linear feet to the south. As Assistant Project Manager, Christine is responsible for ensuring the project remains on schedule and both identifying and mitigating any potential delays. Christine is also responsible for coordination efforts with the entire team, including teaming partners, and stakeholders (including Caltrans District 12). Finally, Christine is responsible for ensuring the quality and timing of each deliverable, including the Preliminary Environmental Study (PES) and CE /CE, the geotechnical report, the topographic survey, right-of-way certification, utility research, PS&E documents, and any permits required for construction.
Caltrans District 8, Project Management Support Services, San Bernardino, CA EXP is providing consultation, research, professional and technical services required for Program / Project Management Services on an “as-needed” basis to support Caltrans, Division of Program / Project Management (PPM), District 8. As part of the PPM team, Christine assists with providing services to Caltrans including, but not limited to, integration management; scope management; time management; cost management; quality management; resource management; communication management; risk Christine Brown, PE
Roadway/Traffic Design
*Work performed at previous firm.
8+
years of
experience
SPECIALTY EXPERIENCE
• program/project
management
• roadway design
• complete streets
projects
• ADA curb ramps and
access paths
• bicycle facilities
SCOPE TECHNICAL AREA EXPERTISE
• intersection improvements
• grading
• roadway design
• pedestrian facilities
Christine is a California Professional
Engineer with over 8 years of hands-on
civil engineering experience in the design
and management of public improvement
projects throughout Southern California.
Her expertise includes project and
program management, geometric design
and corridor modeling of trail, roadway,
and transit corridors including grading,
drainage, and wet utilities; intersection
improvements including ADA curb ramps
and access paths; Complete Streets
projects; Safe Routes to Schools projects;
and traffic analysis.
Professional Registrations
• Professional Engineer (Civil): CA
92510
• CBPELSG QSD: 92510
Education + Training
• B.S., Civil Engineering, California
Polytechnic University, Pomona
2+
years with EXP
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xviii
Christine Brown, PE – continued
Roadway/Traffic Design
*Work performed at previous firm.
management; project scheduling; project coordination; PM developments and project resource estimating services.
SBCTA, I-215 Bi-County Landscaping PA&ED and PS&E, San Bernardino County, CA SBCTA is proposing landscape improvements to I-215 in order to provide a cohesive corridor between the counties of San Bernardino and Riverside. The project will require significant coordination with all stakeholders including Caltrans District 8, and the cities of Colton, San Bernardino, and Grand Terrace in order to obtain approval of the landscape design and environmental document. As project engineer, Christine is responsible for assisting with the design and plan production, as well as the preparation and approval of the Project Report.
City of Temecula, Santa Gertrudis Creek Phase II, Margarita Under-Crossing, Temecula, CA The City of Temecula is proposing to construct an undercrossing for pedestrian / bicycle use along the Santa Gertrudis Creek trail at Margarita Road. The undercrossing will provide continuous, safe passage under Margarita Road, connecting schools and residential areas. Christine is assisting with the development and ongoing management of the project schedule along with liaising between the various team members and subconsultants. As Roadway / Trail Task Lead, Christine is also responsible for the design of the undercrossing including geometric layout, grading, drainage, bicycle lane improvements, and ADA modifications. Christine will also be developing the construction cost estimate and technical specifications for the project.
County of San Bernardino, Phelan Road Widening Project, San Bernardino, CA Christine is serving as the QA/QC Lead for the Project Approval and Environmental Document phase of the Phelan Road Widening project. The purpose of the project is to widen 12.1 miles of Phelan Road from 2 lanes to 4 lanes with a painted median to accommodate for the increased population and resulting traffic in the region. The project will also re-align Phelan Road at State Route 138 to eliminate the existing skewed intersection which will ultimately be approved through Caltrans District 8 Oversight.
City of Downey, Lakewood Boulevard and Imperial Highway Intersection Improvements, Downey, CA The City of Downey is looking to improve traffic circulation and mobility within the I-605 Freeway corridor by minimizing congestion through added capacity and improved operation of the Lakewood Boulevard and Imperial Highway intersection.
As project engineer, Christine is responsible for the design of the roadway widening and civil improvements including the geometric layout, grading, drainage, ADA curb ramp upgrades, and private property improvements. Christine is also assisting with the development of the technical specifications and cost estimate.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xix
Jose is a civil engineering designer with
advance skills in design of infrastructure
projects. He is extremely knowledgeable
in communicating plans and designs
through electronic media with a focus
on three-dimensional road, utilities and
grading designs. Jose’s experience includes
a variety of project types and scales for
a range of clients. He has performed as
a lead CAD Designer on large projects
coordinating the efforts of designers
and draftsmen into finished products.
He has also provided individual services
on small and large projects alike where
his responsibilities ranged from design
through plan production. Jose is a native
Spanish speaker, and he is perfectly fluent
in English and Spanish communications.
Education + Training
• Associate of Science, Architectural
Design, Westwood College of
Technology, California 20031
• Associates of Science, Construction
Management, California 2011
Jose Carrillo
Roadway/Traffic Design
SPECIALTY EXPERIENCE
• design infrastructure
• civil engineering
• CAD design
• utilities and grade
designs
SCOPE TECHNICAL AREA EXPERTISE
• roadway design
• traffic design
1.5 years with EXP
15+
years of
experience
*Work performed at previous firm.
Project Experience
State Route 210/Waterman Avenue Interchange Project, San Bernardino, CA The project consists of widening SR-210 eastbound on-ramps to increase the ramps capacity, restripe the overcrossing between the ramps and modify the existing traffic signals in the City of San Bernardino. As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
City of Chino, SR-71/Pine Ave. Interchange, Chino, CA
Roadway Designer. Jose is serving as roadway designer and assistant project manager for Pine Avenue off-ramps widening, coordinating design and plan gathering with sub-consultants and responsible for submittal coordination with Caltrans and City of Chino. The project would accommodate future increases of traffic and extension of Pine Avenue to the east.
City of Seal Beach, Seal Beach Boulevard & I-405 Pavement Rehabilitation, Seal Beach, CA
The City of Seal Beach is proposing a pavement rehabilitation project at the intersection of Seal Beach Boulevard and I-405 EB Ramps / North Gate Road.
The project will include pavement rehabilitation for the entire intersection and extending approximately 440 linear feet to the south. As Assistant Project Manager, Christine is responsible for ensuring the project remains on schedule and both identifying and mitigating any potential delays. Christine is also responsible for coordination efforts with the entire team, including teaming partners, and stakeholders (including Caltrans District 12). Finally, Christine is responsible for ensuring the quality and timing of each deliverable, including the Preliminary Environmental Study (PES) and CE /CE, the geotechnical report, the topographic survey, right-of-way certification, utility research, PS&E documents, and any permits required for construction.
County of San Bernardino, Phelan Road Widening, San Bernardino, CA Roadway Designer. Jose is serving as roadway designer for the twelve-mile stretch of roadway widening of Phelan Road from SR-138 to Los Banos Ave. The project is currently under environmental process and geometrics approval by the County of San Bernardino.
*County of Riverside, I-10/Cherry Valley Blvd. Interchange, Calimesa, CA Served as primary designer for Cherry Valley Boulevard road widening and widening of I-10 on-ramps and off-ramps, responsible for coordinating Caltrans City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xx
Jose Carillo – continued
Roadway/Traffic Design
*Work performed at previous firm.
submittals, coordinate utility relocations. Project would accommodate future increase of traffic due to commercial land development project.
*City of Palm Springs, Highway Safety Improvements, Palm Springs, CA The project proposed to improve seventeen (17) signalized intersections with the latest in traffic safety equipment, Mr.
Carrillo’s role as primary designer was to re-design the existing curb ramps at all corners and bring them up to current Americans with Disability Act standards (ADA) as well as coordinate traffic signal modifications and utility relocations. *City of Lake Elsinore, Palomar Street Multi-Use Trail, Lake Elsinore, CA Project aimed to create a multi-use, pedestrian friendly trail that will serve as a key linkage between the City of Wildomar and the Murrieta Creek Trail by widening the existing roadway and placing a new 12’ foot Class 1 Bike Lane for bicyclist and pedestrians to share. Mr. Carrillo served as the primary designer for the roadway widening improvements and placement of bicycle trail.
*County of Riverside, Avenue 48 Reconstruction, Coachella, CA Mr. Carrillo served as the primary designer of the reconstruction design of Avenue 48 which consist of widening the roadway, construction of new curb and gutter, sidewalk, and curb ramps, adding a raised median, adjusting and relocation of utilities. Project also involved coordination with two approving agencies considering the project lays between the jurisdictional boundaries of County of Riverside and City of Coachella. *Los Angeles World Airports, Airport Modernization, Los Angeles, CA Design domestic and fire water transmission lines, power and communication duct banks, assisted with the relocation and abandonment of existing utilities for $5.4 billion LAX Tom Bradley International Terminal expansions, Crossfield and Taxilane “S” . Coordinated with sub consultants for gathering of plans and plan submittal to client and approving agencies. Permit processing with city of Los Angeles permit agency.
*U.S. Department of the Navy, Site Preparation Operable Unit 11, Naval Air Station North Island, Coronado, CA Assistant designer and drafter of on-site civil improvements, erosion control, and Strom Water Pollution Prevention Plans. *El Segundo Energy Center, LLC, Water Pollution Control, El Segundo, CA Design and drafted Storm Water Pollution Prevention Plans, underground utility abandonment and demolition plans, coordinated with contractor for on-site construction changes and reflect changes on plans.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxi
Mitsuru Tanaka has over 23 years of experience in transportation planning and traffic engineering projects for various state transportation agencies including DDOT, VDOT, MdSHA, MdTA, MTA, DelDOT, PennDOT, NJDOT, GDOT, Caltrans, and FHWA. His areas of expertise include travel demand forecasting, capacity/ level of service analysis, traffic safety analysis, traffic impact analysis, traffic signal design, ITS design, signing and pavement marking design, roadway lighting design, and developing Transportation Management Plan (TMP), Maintenance of Traffic (MOT) plans and detour plans. He has been deeply familiar with Highway Capacity Manual (HCM), Manual on Uniform Traffic Control Devices (MUTCD), Highway Safety Manual (HSM), the AASHTO Greenbook, ITE Traffic Engineering Handbook, ITE Trip Generation Manual, ANSI/IESNA RP-8-00, and local and state guidelines for traffic engineering designs and studies. Mitsuru has experience with the following software packages: CUBE Voyager, Highway Capacity Software (HCS), Synchro/SimTraffic, SIDRA, VISSIM, CORSIM, MicroStation, AutoCAD, Visual, and AGI32. Mitsuru has managed more than several small to mid-sized traffic engineering study and design projects for enhancing multi-modal transportation safety and operations in his career.
Project Experience
State Route 210/Waterman Avenue Interchange Project, San Bernardino, CA The project consists of widening SR-210 eastbound on-ramps to increase the ramps capacity, restripe the overcrossing between the ramps and modify the existing traffic signals in the City of San Bernardino. As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
Euclid/Pine Avenue Intersection Improvement Project, Chino, CA/Caltrans District 8
The project consists of adding left and right turn lanes at the intersections including modifying traffic signal, adding sidewalk, curb ramps, bike lanes and safety lighting. . As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
City of Chino, Euclid Avenue Restriping Project, Chino, CA EXP is providing design services for Euclid Avenue (SR-83) Restriping Project between Pine and Bickmore Avenue. EXP’s tasks include preparing a Traffic Report and preparing the PS&E package for the project. The scope of work for the project consists of shifting lanes to the west by restriping to create room to add a second northbound through lane. A 14-foot continuous two-way left-turn lane is proposed between north and southbound lanes. The addition of a second Professional Registrations +
Certifications
• Professional Engineer (PE):
• DC #PE922223,
• VA #0402053361,
• MD #51273,
• DE #26195,
• WV #24605,
• GA #PE046761,
• FL #PE91047,
• IL #062073065,
• WI #48379-6,
• OR #66717PE
• Professional Traffic Operations
Engineer (PTOE) #1024
• Professional Transportation Planner
(PTP) #271
Education + Training
• M.S., Civil Engineering, University of
Delaware, 1998
• B.S., Civil Engineering, Hokkaido
University, Japan, 1994
Mitsuru Tanaka, PE
Traffic Operations Analysis Report
SCOPE TECHNICAL AREA EXPERTISE
• travel demand forecasting
• traffic impact analysis
• traffic signal design
• ITS design
• signing and pavement marking
design
• roadway lighting design
4 years with EXP
23+
years of
experience
SPECIALTY EXPERIENCE
• transportation planning
• traffic engineering
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxii
northbound through lane is expected to significantly increase the capacity for this movement as there is currently only one northbound lane. The proposed improvements will help reduce delay and improve overall level of service on the corridor.
Pine Avenue Extension to SR-71 Widening, Chino, CA
Mitsuru is responsible for designing electrical plans at a diamond-shaped freeway interchange. The project included widening the existing off-ramps and traffic signal and electrical system designs at the interchange. There are two traffic signals to be designed and one of them is a new traffic signal for accommodating the expected traffic volume increase due to the roadway extension into the City of Chino. A traffic study including the signal warrant analysis was conducted in advance of developing the electrical plans for justifying the new signal, determining the optimized signal phase and timing, and analyzing the existing and future traffic operations at the interchange. The electrical plans included the modification designs of the existing ramp metering system and highway lighting system as well as the existing and new traffic signal systems at the interchange. In addition, VISSIM traffic simulation models were developed for several scenarios including adjacent two interchanges along SR71 for assessing the traffic impacts to the surrounding area.
Happy Valley Road Traffic Study (Walker County Traffic Engineering IDIQ), Walker County, GA Role: Lead Traffic Engineer. Dates: 2021-Ongoing. Value: $20K for Study. Contract Type: IDIQ Task Order. Description: Mitsuru is a lead traffic engineer responsible for the traffic study of investigating feasible alternatives of transportation facility improvements in this project. The study area is over a 2.5-mile stretch including 29 intersections located at northern end of Walker County which has a state border line with Tennessee within half a mile. There are 4 public schools, 1 high school, 1 middle school and 2 elementary schools, and several developments are currently planned to be built along Happy Valley Road within a few years in the study area. The County plans to install new sidewalks along Happy Valley Road for the school students, at the same time requested to investigate if any other highway and intersection improvements are necessary to accommodate the traffic from/to the planned developments. The future traffic volumes were projected based on the information of the planned developments, background growth, and existing traffic patterns in the area. Synchro/SimTraffic software was utilized for the level of service (LOS) analysis. As the conclusion, three roundabouts and additional turn lanes at more than several intersections were recommended. The analysis results and recommendations were presented to the local residents and the County staff.
Mitsuru Tanaka, PE – continued
Traffic Operations Analysis Report
*Work performed at previous firm.
APPENDIX A | xxiii
Ben is a Professional Engineer with more than 15 years of experience in transportation engineering. He served as project manager and lead engineer for traffic and transportation projects in California and Canada. His specialties include active transportation analysis, traffic network simulation and modeling, traffic impact studies, traffic signal operation, construction traffic management and project management. He possesses working knowledge of software such as Synchro, SimTraffic, HCS, VISSIM, Aimsun, Manifold, TransCAD, AutoCAD.
Ben’s working experience also includes traffic demand forecasts, Environmental Assessments (EA), traffic safety, and construction staging.
Project Experience
State Route 210/Waterman Avenue Interchange Project, San Bernardino, CA The project consists of widening SR-210 eastbound on-ramps to increase the ramps capacity, restripe the overcrossing between the ramps and modify the existing traffic signals in the City of San Bernardino. As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
Euclid/Pine Avenue Intersection Improvement Project, Chino, CA/Caltrans District 8
The project consists of adding left and right turn lanes at the intersections including modifying traffic signal, adding sidewalk, curb ramps, bike lanes and safety lighting. . As the prime consultant, the EXP team is responsible for the Project Approval/Environmental Document and PS&E phases of the project.
City of Chino, Euclid Avenue Restriping Project, Chino, CA EXP is providing design services for Euclid Avenue (SR-83) Restriping Project between Pine and Bickmore Avenue. EXP’s tasks include preparing a Traffic Report and preparing the PS&E package for the project. The scope of work for the project consists of shifting lanes to the west by restriping to create room to add a second northbound through lane. A 14-foot continuous two-way left-turn lane is proposed between north and southbound lanes. The addition of a second northbound through lane is expected to significantly increase the capacity for this movement as there is currently only one northbound lane. The proposed improvements will help reduce delay and improve overall level of service on the corridor.
Professional Registrations +
Certifications
• Professional Engineer (Civil), NV
• Professional Traffic Operations
Engineer (PTOE)
• P . Eng
Education + Training
• Master of Applied Science,
Transportation Engineering,
University of Waterloo (2008)
• Master of Applied Science, Highway
Engineering, Sharif University
(1998)
• Bachelor of Civil Engineering, K.N.T
University (1992)
Affiliations + Memberships
• WTS membership
Ben Hashemloo, PE
Traffic Operations Analysis Report
SCOPE TECHNICAL AREA EXPERTISE
• active transportation study
• data collection planning
• inspection services for traffic
• signal & street improvements
• preliminary studies & research
• traffic impact study
• transportation network
• simulation
• traffic signal optimization
4 years with EXP
15+
years of
experience
SPECIALTY EXPERIENCE
• project managment
• transportation analysis
• simulation + modeling
• traffic impact studies
• signal operation
• construction traffic
management
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxiv
Fruitvale and Allendale Intersection Improvement, City of Saratoga, CA Project Manager to study existing and proposed design layout for the intersection of Fruitvale Avenue and Allendale Avenue, provide traffic signal design, control stripping and signing plans, and prepare specifications and cost estimates. The presence of a middle school adjacent to the intersection has raised safety concerns for students crossing the intersection.
The intersection geometry was improved and signal plans, pavement marking, and signing were updated.
SBCTA I-215 Bi-County Landscaping PA&ED and PA&E, San Bernardino County, CA Traffic lead to analyze traffic condition and prepare transportation management plans during landscape construction. This 5.1 long project is located from the San Bernardino County and Riverside County line to Orange Show Road in the City of San Bernardino and will provide a themed landscape transition along the I-215. The transportation management plan will include proposed lane/shoulder closure and required plan to protect the safety of road users and construction crew.
On-Call Engineering Services, Seal Beach, CA.
Traffic + Transportation Engineer. EXP is providing engineering services that include plans, technical specifications and estimates, bid support, construction management, survey, geotechnical, community outreach, public/private development plans, processing required permits and agreements, hydrology and hydraulic analysis, water and sewers studies, National Pollutant Discharge Elimination System (NPDES), Water Quality Management Plan (WQMP), Storm Water Pollution Prevention Plans (SWPPP), Grant Writing and Coastal Commissioning coordination.
SR-1 – Traffic Signal Upgrades, and Pavement Rehabilitation Newport Beach, Huntington Beach, Seal Beach, CA.
Traffic engineer to upgrade the traffic signals located on State Route (SR) 1 between Crystal Heights Drive and First Street, in the cities of Newport Beach, Huntington Beach, and Seal Beach in Orange County. This project would improve 20 intersections in the study area. The proposed improvements for this location are to remove and replace the existing traffic signals and equipment due to age and serviceability with current Caltrans standard traffic signals and equipment, upgrade the existing curb ramps to the current American with Disability Act (ADA) standard, relocate/ adjust the existing drainage facility due to ADA curb ramp improvements, trim the existing median island, and remove the existing pedestrian push button on the median island.
Sidewalk/Pedestrian Signal Improvement, City of Pittsburg, CA.
Project Manager. Designed new traffic signal and controller at the intersection of Range Road and West Leland Road in the City of Pittsburg in conjunction with the City’s project to widen sidewalks to encourage active transportation and enhance pedestrian safety. Layouts were developed, and specification and cost estimates were prepared for construction bid support.
Ben Hashemloo, PE – continued
Traffic Operations Analysis Report
*Work performed at previous firm.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxv
Caltrans, SR-1 Project: Traffic Signal Upgrades and Pavement Rehabilitation, Newport Beach, Huntington Beach, Seal Beach, CA
The traffic signal and pavement rehabilitation project is located on State Route (SR) 1 between Newport Beach and Seal Beach. This project would improve 20 intersections for 25 miles of roadway and rehab the pavement between Warner Ave. and County Line. Portia was the lead engineer responsible for the hydrology and hydraulics analysis, drainage report, NPDES compliance, and plan preparation. Tasks include coordinating with roadway and signal designers to ensure drainage needs are implemented.
San Bernardino County, Phelan Road Widening, San Bernardino County, CA Portia is serving as Hydrology/Hydraulics/Water Quality Lead. EXP is providing preliminary engineering and environmental consulting services for the Phelan Road Widening Project. Phelan Road is currently a two-lane road that serves the communities of Phelan and Hesperia and is often a thoroughfare and diversion route for those experiencing closures or traffic congestion on nearby Interstate 15 (I-15). The project proposes to widen approximately 12.1 miles of Phelan Road from two (2) lanes to a five (5) lane major highway designation with the center serving as one (1) continuous left turn lane.
City of Hesperia, Peach Avenue Improvement, Hesperia, CA The City of Hesperia proposes to realign Peach Avenue between Centennial Street and Hinton Street on Peach Avenue where it crosses the Antelope Valley Wash. The project consists of realigning and raising the roadway profile over the Antelope Valley Wash with reinforced concrete boxes (RCBs) culvert, with new asphalt concrete pavement. Portia was responsible for the hydraulic alternative analysis and design of new RCBs. Design include channel realignment, grading and structural details for the RCBs to accommodate the new roadway.
City of Temecula, Diaz Road Improvements, Temecula, CA
The project proposes to improve Diaz Road to a major arterial road between Cherry Street and Rancho California Road. Design elements includes roadway widening and extension, raised median, landscaping, curb and gutter, sidewalk and trail realignment, drainage facilities, and treatment BMPs. Portia is responsible for the drainage analysis to comply with the City’s and Riverside County Flood Control District design criteria, WQMPand PS&E.
City of Temecula, Santa Gertrudis Creek, Phase II, Margarita Under Crossing, Temecula, CA
Portia serves as the drainage lead and the project goal is to construct an under crossing for pedestrian/bicycle use at Margarita Road. The 1000’ multi-use trail along Santa Gertrudis Creek crosses Margarita Road atgrade under the existing bridge. The under crossing will Portia Gonzalez, PE, QSD/QSP
Stormwater & Drainage Design
SPECIALTY EXPERIENCE
• hydrology
• hydraulics
• pavement drainage
design
• flood control facilities
• stormwater permitting
SCOPE TECHNICAL AREA EXPERTISE
• pavement hydraulics
• hydrology
• hydraulics
• stormwater permitting 4+
years with EXP
31+
years of
experience
*Work performed at previous firm.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
Portia brings more than 31 years of experience.
She has served as project manager for various
transportation projects in California, Arizona
and Nevada. Her expertise includes project
management, drainage design, hydrologic
and hydraulic modeling, storm water
management, 2D modeling, river modeling,
floodplain delineation studies, storm drain
master planning, detention basin design,
bridge scour, roadway drainage and design,
water resource planning, sediment transport
and water distribution.
Professional Registrations
• Professional Engineer (Civil): CA
52302
• Qualified SWPPP Developer (QSD
52302)
• Construction General Permit Qualified
SWPPP Practitioner (QSP)
Education + Training
• M.S., Civil Engineering, Water
Resources, California State University,
2010
• B.S., Civil Engineering, California State
University, 1991
APPENDIX A | xxvi
Portia Gonzalez, PE, QSD/QSP – continued
Stormwater & Drainage Design
*Work performed at previous firm.
provide continuous, safe passage under Margarita Road connecting schools and residential areas.
I-40 Regrade Median Cross Slope Barstow, CA, USA
The I-40 Regrade Project is to re-grade the existing median cross slope within the clear recovery zone (CRZ) to 10:1 or flatter to reduce the severity and the number of run-off-the road accidents in the median on Interstate 40 from 1.4 miles east of Fort Cady Road (PM R25.0) to Crucero Road (PM R50.0) near Barstow, in San Bernardino County. This project is multi-phased that covers both PA/ED and PS&E phase.
Portia is responsible for the drainage analysis and design of over 25 culverts that would be extended to accommodate the proposed fill in the median. Other tasks include Caltrans coordination and stormwater coordination. Cost: $28.5M │ Length of time spent on project: 08/2019 – Current
City of Anaheim, Katella Smart Street - Jean Street to Humor Street, CA, USA Project Manager for a corridor improvement project in the City of Anaheim. Project elements include pavement rehabilitation, new storm drain trunk line, signing and striping, utility relocations, intersection improvements, traffic signal, ADA ramps, and bus turn- outs.
*SANBAG, PA/ED I-10 Express Lane Project, Project Report/Environmental Document, Montclair to Redlands, CA, USA
The I-10 Express Lanes Alternative proposes to construct two express lanes in each direction from the Los Angeles County Line in Montclair to Ford Street in Redlands, a distance of 33-miles, along with additional auxiliary lanes at selected locations. The proposed project will consist of the widening of existing roadbeds and undercrossings, replacements for six overcrossings, the widening of 50 bridges, the realignment of on-/off-ramps, auxiliary lanes, and drainage improvements. The total project length is approximately 35 miles including 2 miles of transitional signage and striping west of the Los Angeles/San Bernardino County Line. Within these limits are three freeway-to-freeway interchanges (I-15, I-215, and I-210), 30 local interchanges, and more than 50 bridge structures that will be affected by this project. The scope of services to be provided includes the necessary tasks and activities required to complete the PA/ED process, including project management, engineering, HOV and Express Lanes alignment assessment, access/egress planning, traffic forecasts, an HOV report, a PR, Geometric Approval Drawings (GADs), fact sheets, and environmental technical studies.
Drainage Engineer responsible for the PA/ED Phase Drainage Report and Floodplain Report to support the construction of a 26-mile- long HOV lane along I-10. A conceptual drainage plan and hydraulic analysis were prepared to determine onsite and offsite drainage and water quality requirements. As part of this project, I-10 is proposed to be widened at the Santa Ana River crossing. A Preliminary Bridge Hydraulics report was performed to determine whether the proposed pier extensions will impact the river’s 100-year design flows.
*Caltrans District 8 PM On-Call, San Bernardino, CA, USA Provided Project Management (PM) services for District 8 mainly in the I-15 Corridor.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxvii
Christina Agustin brings her education and skills in water resources engineering to perform detailed hydrology and hydraulic analysis for stormwater design and management for clients in Southern California. Her experiences in the public and non- profit sector bring knowledge of stormwater management for water quality and flood control, and the integrated use of public education and outreach. Her technical skills include working with the programs: Flow-Master, StormCAD, HEC-RAS, MS Excel.
Project Experience
Caltrans District 12, SR-91 Improvement Project Segment 1 PS&E, Orange County, CA, USA
Conduct hydrology and hydraulic assessment for drainage analysis of existing and proposed drainage systems. The State Route 91 (SR-91) Segment 1 Improvement Project from Lakeview Ave to State Route 55 (SR-55) proposes to improve traffic operations by constructing a new drop ramp directly from Lakeview Ave to the SR-55 Connector and relocating the SR-91/SR-55 diverge east of Lakeview Ave. The project also combines the Lakeview Ave WB loop and WB slip on-ramps as a single tight diamond on-ramp to SR-91 (WB SR-91 on-ramp)
City of Temecula, Diaz Road Improvements WQMP, PS&E, Temecula, CA, USA
Provide support for drainage analysis. Project design proposes road widening and extension to improve traffic flow, design also includes a raised median, landscaping, curb and gutter, sidewalk and trail realignment, and drainage facilities. Drainage analysis design to comply with the design criteria set forth by City of Temecula and Riverside county Flood Control District.
*City of Yorba Linda, Public Works Department – Engineering Division, Yorba Linda, CA, USA
Assisted in the preparation and finalization of right-of-entry exhibits for the Road Widening and Street Improvement of Bastanchury Road RFP supporting documents.
Reviewed and assisted in the issuance of transportation and encroachment permits.
Conducted annual BMP monitoring at commercial sites.
*City of Encinitas, Public Works Department – Stormwater Division, Encinitas, CA, USA
Updated City’s geodatabase by digitizing structural BMP features according to As- Built plans. Received and reviewed BMP self-inspection submittals and assisted in the residential and commercial BMP monitoring and reporting.
Professional Registration +
Certifications
• Engineer in Training, 150949, CA
Education + Training
• M.S, Civil Engineering - Water
Resources, California State
University - Fullerton, 2022
• B.S., Environmental Engineering,
California Polytechnic State
University – San Luis Obispo, 2013
Christina Agustin, EIT
Stormwater & Drainage Design
SPECIALTY EXPERIENCE
• flood control
• hydrology analysis
• hydraulic analysis
• stormwater design &
management
SCOPE TECHNICAL AREA EXPERTISE
• pavement hydraulics
• hydraulics
• hydrology
>1
years with EXP
5+
years of
experience
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxviii
Christina Agustin, EIT – continued
Stormwater & Drainage Design
*Work performed at previous firm.
*San Elijo Lagoon Conservancy, Water Quality and Hydrology Data Collection, Encinitas, CA, USA Build upon water quality dataset to create baseline data. Measured weekly surface water parameters: dissolved oxygen, salinity, and temperature of San Elijo Lagoon, a coastal wetland. Conducted a hydrologic data analysis utilizing rain gauge data to illustrate changes in streamflow, rainfall accumulation, and water depth during 2015-2016 wet season. *San Diego Coastkeeper, Water Quality Data Collection, San Diego, CA, USA Monitored and collected surface water parameters and samples of local creeks throughout San Diego County on a monthly basis.
Recorded parameters: temperature, pH, conductivity, and dissolved oxygen level.
Adhered to proper protocol to record data that accurately reflected the physical and biological conditions of the waterway. And adhered to chain of custody of all datasheets, water samples, and data monitoring devices.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxix
Shubhee has 4+ years of civil and environmental engineering experience in the areas of hydrology, hydraulics and water resources engineering and planning. Her experience includes hydrologic and hydraulic modeling, storm water management, 2D modeling, river modeling, culver and bridge design, drainage design, flood control design, water resources modelling and planning, water demand and supply imbalances with climate change, water data analysis and visualization, quality assurance/quality control (QA/ QC) and client correspondence. Shubhee has held positions ranging from Graduate Intern to Water Resources Engineer and Planner. She has worked on various water resources projects, including the California American Water Comprehensive Planning Study, American River Basin Study, Integrated Water Resources Planning for the City of Roseville, Shasta Dam Raise Environmental Impact Study Report, Yuba Water Authority Annual Groundwater Monitoring , Stormwater Discharge Sampling for the City of Sacramento, Water Quality Modelling for Salmon. Shubhee has worked with a variety of agencies, including U.S. Department of the Interior, Bureau of Reclamation (Reclamation), California American Water, American River Water Agency, El Dorado County, City of Hesperia, City of Roseville, City of Yuba, City of Sacramento, Placer County Water Authority (PCWA), Regional Water Authority (RWA). Shubhee is experienced in water resources modelling, integrated resources planning and design.
She brings working knowledge of software such as FlowMaster, HydroCalc, Civil 3D, AutoCAD, InfoWater and InfoSewer, HEC-RAS, HEC HMS, ArcGIS, CalSim2 and CalSim3, and SALMOD. She is also knowledgeable in the required frequencies of stormwater quality and required stormwater permits and planning. Shubhee understands environmental considerations, including storm water pollution prevention plan compliance.
Project Experience
City of Chino, SR-71/Pine Avenue Interchange Ramp Widening, Caltrans, Chino, CA
This project is located in the cities of Chino and Chino Hills in western San Bernardino County. The SR-71/Pine Avenue Interchange Ramp Widening Project proposes to improve Northbound and Southbound off-ramp , install new traffic, signal at the intersection of SR-71 northbound off-ramp and Pine Avenue, construct retaining walls with concrete barrier on top at both off-ramps to allow for roadway widening, restripe Pine Avenue bridge to provide two through lanes in each direction Reconstruct existing curb ramps to current ADA standards, add bike lane, add sidewalk on both sides of Pine Avenue east of northbound off-ramps. Shubhee assisted in project management of the project and acted as the project engineer for designing the proposed improvements. She also performed hydrology and hydraulic analysis using Civil 3d, Autoturn, ArcGIS, Google Earth and AutoCAD and was responsible for design, stormwater analysis and BMPs for the project.
Education + Training
• MS, Civil and Environmental
Engineering, University of
California, Irvine, 2018
• BS, Civil Engineering, Barkatullah
University, Bhopal, 2015
Affiliations + Memberships
• AWRA
• ASCE
Shubhee Saxena
Construction Staging/Traffic Handling
SPECIALTY EXPERIENCE
• hydrology
• hydraulics
• pavement drainage
design
• flood control facilities
• stormwater permitting
SCOPE TECHNICAL AREA EXPERTISE
• pavement hydraulics
• hydraulics
• hydrology
• water resources planning +
management
• low impact development +
urban runoff management
• stormwater permitting
4+
years with EXP
4+
years of
experience
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxx
Peach Avenue Street Improvements, City of Hesperia, San Bernardino County CA Project Engineer. Water Resources Engineer. The City of Hesperia is focusing on realigning Peach Avenue between Centennial Street and Hinton Street on Peach Avenue where it crosses the Antelope Valley Wash. The project consists of realigning and raising the roadway profile over the Antelope Valley Wash with reinforced concrete boxes (RCBs) culvert, with new asphalt concrete pavement.
It also includes golf course and irrigation modifications. The project would also improve public safety and mobility by constructing RCBs culvert spanning over the Antelope Valley Wash, replacing the existing low water crossing and eliminating flood-related hazards during inclement weather events. The project is anticipated to be constructed in spring 2021 under the CDBG Program fiscal year 2020-21. Shubhee is the water resources engineer and performed hydrology and hydraulic delineation and analysis using GIS tools.
She is responsible for hydraulic design and modeling, storm water management, 2D modeling, river modeling, culver and bridge design, drainage design, flood control design, quality assurance/quality control (QA/QC) using San Bernardino County Flood Control District hydrology requirements.
OCTA, The State Route 91 (SR-91) Segment 1 Improvement Project from Lakeview Avenue to State Route 55 (SR-55), Anaheim CA, USA
The project proposes to improve traffic operations along this segment of SR-91 by constructing a new drop ramp (SB SR-55 on- ramp) directly from Lakeview Avenue to the SR-55 Connector and relocating the SR-91/SR-55 diverge east of Lakeview Avenue.
Additionally, the project would combine the Lakeview Avenue WB loop and WB slip on-ramps as a single tight diamond on-ramp to SR-91 (WB SR-91 on-ramp). Lakeview Avenue between Santa Ana Canyon Road and Riverdale Avenue would also be reconstructed along with replacement of the overcrossing structure. The project requires drainage improvements in the whole segment along with the roadway improvements. Shubhee is responsible for various drainage tasks as the drainage engineer and performs hydraulic analysis for drainage plans and profiles for the project.
Diaz Road Expansion, Temecula, Riverside County CA
The Diaz Road Expansion Project proposes to improve Diaz Road as necessary to meet the classification requirements of Major Arterial (4 Lanes Divided), City Standard No. 101, approximately between Cherry Street and Rancho California Road. The approximate
2.2-mile segment will be improved on its current horizontal alignment and as depicted in the City’s General Plan. Design elements includes roadway widening and extension, raised median, landscaping, curb and gutter, sidewalk and trail realignment, drainage facilities, and treatment BMPs. Shubhee performed hydrology and hydraulic analysis using ArcGIS, Google Earth and AutoCAD and is responsible for design, stormwater analysis and BMPs for the project.
Shubhee Saxena– continued
Construction Staging/Traffic Handling
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxi
Parakh has served as engineer for drainage and transportation projects in California.
Parakh Jaiswal specializes in hydrology and water Resources. She is well versed with hydrology, groundwater hydrology, flow in unsaturated porous media, watershed modelling, hydrologic computational modelling, wavelets in hydrology, and merging models and data. She has working knowledge of software such as ArcGIS, SWMM, PCSWMM, Sewer GEMS, HEC-HMS, HEC-RAS, MIKE-SHE, MicroStation, FlowMaster, MS Word, MS Excel.
Project Experience
City of Chino, State Route 71/Pine Avenue Interchange, Chino CA The project proposes to widen the Northbound and Southbound ramps to SR-71/ Pine Avenue intersection, install new traffic signal at the intersection, construct retaining walls with concrete barrier on top at both off-ramps to allow for roadway widening, restripe Pine Avenue bridge to provide two through lanes in each direction, reconstruct existing curb ramps to current ADA standards, add bike lane, add sidewalk on both sides of Pine Avenue east of northbound off-ramps. Parakh is responsible for the drainage analysis, preparing SWDR, stage construction, pavement delineation, striping and traffic management plans. She is also responsible for communicating with Caltrans for SWDR and drainage report for the project.
SBCTA, SR-210 /Waterman Interchange Project, San Bernardino, CA The project includes roadway and structural engineering, traffic analysis, drainage, environmental, geotechnical, surveying, and utility coordination. The purpose of the project is to improve traffic operations and local circulation at the SR210 / Waterman Avenue interchange. The eastbound on-ramp will be widened from one lane to two lanes; additionally, the intersection of Waterman Avenue and East 30th Street will be restriped to allow for two left-turn lanes in the northbound direction, while the intersection of Waterman Avenue and the eastbound ramps will be widened to allow for two left-turn lanes in the southbound direction. This project requires approval from Caltrans District 8 Oversight. Parakh is responsible for the drainage plans, drainage report and Stormwater data report.
City of Rialto, Street Overlay & Reconstruction Project This project is to provide engineering services for the City’s 2020/2021 Street Overlay & Reconstruction Project. The scope of work includes pavement rehabilitation in various degrees, drainage analysis and design, utility identification and coordination, new ADA curb ramps, repair or reconstruction of damaged or deficient PCC curb ramps, curb, gutter, sidewalk, driveways approaches, and cross gutters. Parakh is the drainage and stormwater engineer and is responsible for the hydrology and hydraulic analysis for multiple locations throughout the City.
Professional Registration +
Certifications
• Engineer in Training, Civil, 170158,
CA
Education + Training
• MS, Civil Engineering, University of
California, Irvine, 2019
• BTech, Civil Engineering, Galgotias
College of Engineering and
Technology, India, 2016
Parakh Jaiswal, EIT
Construction Staging/Traffic Handling
SPECIALTY EXPERIENCE
• hydrology
• hydraulics
• pavement drainage
design
• flood control facilities
• stormwater permitting
SCOPE TECHNICAL AREA EXPERTISE
• pavement hydraulics
• hydraulics
• hydrology
• water resources planning +
management
• low impact development +
urban runoff management
• stormwater permitting
4+
years with EXP
4+
years of
experience
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxii
Parakh Jaiswal, EIT – continued
Construction Staging/Traffic Handling
*Work performed at previous firm.
SBCTA I-215 Bi-County Landscaping PA&ED and PA&E, San Bernardino County, CA Parakh is serving as an engineer for the I-215 Bi-County Landscape project and is responsible for PA/ED phase Storm Water Drainage Report. This 5.1 long project will provide a themed landscape transition along the I-215 between the San Bernardino County and Riverside County line and Orange Show Road in the City of San Bernardino. The project will require significant coordination with Caltrans District 8 as well the stakeholder cities of Colton, San Bernardino, and Grand Terrace in order to build consensus and ultimately gain approval of the landscape design and environmental document.
Caltrans 12A1756 SR-1 Project: EA 0P5900: Traffic Signal Upgrades, Newport Beach, Huntington Beach, Seal Beach, CA and EA 0P6800: Pavement Rehabilitation, Huntington Beach to County Line, CA Parakh’s responsibility is to prepare the drainage basemaps for the project as well as the Storm Water Drainage Report. Traffic Signal Upgrades: Upgrade Traffic Signal project located on State Route (SR) 1 between Crystal Heights Drive (PM 13.0) and First Street (Post Mile [PM] 33.6), in the cities of Newport Beach, Huntington Beach, and Seal Beach in Orange County (EA 0P6800). The proposed improvements for this location are to remove and replace the existing traffic signals and equipment due to age and serviceability with current Caltrans standard traffic signals and equipment, upgrade the existing curb ramps to the current American with Disability Act (ADA) standard, relocate/adjust the existing drainage facility due to ADA curb ramp improvements, trim the existing median island, and remove the existing pedestrian push button on the median island.
Pavement Rehabilitation: The proposed improvements include a cold-plane and overlay of the existing pavement on SR 1, removing and replacing the existing traffic signal loops detectors within the project limits, upgrading the existing curb ramps to current ADA standards, and restriping the overlay area to the pre-project condition by incorporating current Caltrans striping and delineator standards.
I-40 Regrade Median Cross Slope, Barstow, CA
Parakh is responsible for the drainage analysis of over 15 culverts that would be extended to accommodate the proposed fill in the median. The I-40 Regrade Project is to re-grade the existing median cross slope within the clear recovery zone (CRZ) to 10:1 or flatter to reduce the severity and the number of run-off-the road accidents in the median on Interstate 40 from 1.4 miles east of Fort Cady Road (PM R25.0) to Crucero Road (PM R50.0) near Barstow, in San Bernardino County. This project is multi-phased that covers both PA/ED and PS&E phase.
Diaz Road Expansion, Temecula, CA
The Diaz Road Expansion Project proposes to improve Diaz Road as necessary to meet the classification requirements of Major Arterial (4 Lanes Divided), City Standard No. 101, approximately between Cherry Street and Rancho California Road. The approximate
2.2 mile segment will be improved on its current horizontal alignment and as depicted in the City’s General Plan. Parakh is responsible for the hydrology, stormwater analysis and BMPs for the project.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxiii
Hashmi Quazi, PhD, PE, GE
Principal-in-Charge / Project Director
Dr. Quazi has over 35 years of overall experience and 34 years with Converse Consultants providing geotechnical engineering services and has earned a reputation for providing quality work in an honest and ethical manner, on time and within budget. Dr.
Quazi provides quality control, budget oversight, and technical assistance on various types of projects, including interchanges, streets, bridges, grade separation and other related projects.
Relevant Experience
SR-71 & Pine Avenue Widening, Chino, CA. Principal in
Charge. Provided technical oversight and budget control for design phase services . The project consisted of widening the SR-71 north bound and south bound off-ramp by adding a 12-foot-wide lane for a distance of 600 feet to the ramp termini to accommodate the proposed lanes each, modify existing traffic signal at the intersection of SR -71 southbound off-ramp and Pine Avenue to accommodate the new lane configuration, restripe Pine Avenue bridge to provide two through lanes in each direction, one westbound left-turn lane, two eastbound left-turn lanes and five-foot outside shoulders, connect riser at north bound off ramp to existing 42” pipe culvert and all curb ramps will be reconstructed to meet ADA standards per Caltrans Standard Plan.
I-10/Jackson Street Interchange Improvements, Indio, CA. Principal in Charge. Provided technical oversight and budget control for design phase services . The project was located at Jackson Street near the Interstate 10 freeway crossing in the City of Indio. The southern bridge, which spans across the Whitewater River channel to the south of the freeway, is 552 feet long and 47 feet wide, and begins at the intersection of Jackson Street and 43rd Avenue. The improvements consisted of reconfiguring the existing interchanges and widening or reconstructing the bridges that cross the Whitewater River channel. In addition, the project included lane additions, realignments, ramp and bridge widening, sidewalk, parkway and traffic signal improvements.
I-10/Cherry Valley Interchange Improvements, Calimesa, CA. Principal in Charge. Provided technical oversight and budget control for geotechnical investigation for the project. The project involved the evaluation of 4 alternatives to making modifications to the Cherry Valley Boulevard Overcrossing (OC) which is a four-span concrete girder bridge constructed in 1965. It is 273 feet long, 47 feet wide, and crosses six lanes of traffic over I-10 in Calimesa, California.
Magnolia Avenue Bridge Widening, Corona, CA. Principal in Charge. Provided technical oversight and budget control for geotechnical investigation for the project. The project consisted of widening the Magnolia Avenue Bridge over the Temescal Wash and street widening between El Camino Avenue and 1,000 feet east of All -American Way. The proposed widening consisted of an additional lane in each direction for a total of three 12-foot lanes in each direction, a 12-foot striped median, 8-foot outside shoulders in both directions, 5-foot sidewalks on the north and south sides of the bridge.
I-15 & SR -91 Express Lane Connector , Corona, CA. Principal in Charge. Provided technical oversight and budget control for the design phase for the project. T he project consisted of the design and construction of express lane infrastructure. This included new south-to-west/east-to- north Express Lanes connector between I-15 Express Lanes and SR-91 Express Lanes; widening of eastbound SR-91; extension of the SR -91 eastbound Express Lane to approximately ½ -mile east of the I-15/SR-91 interchange; a 90-ft long, 8 to 10-ft high masonry sound wall; and Detention basin/swales located on the northwest quadrant of I-15 and SR-91 freeway interchange.
EDUCATION
Ph.D., Civil Engineering, University of
Arizona, 1987
M.S., Civil Engineering, Arizona State
University, 1982
B.S., Bangladesh Engineering
University, 1978
REGISTRATIONS/CERTIFICATIONS
California, Civil Engineer, #46651
California, Geotechnical Engineer,
#2517
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxiv
ERIC TURNER
Director of Environmental Services
A certified DBE, SBE & WBE firm 30900 Rancho Viejo Road, Suite 100 San Juan Capistrano, CA 92675
949.489.2700 | vcsenvironmental.com
ErEric has worked with interdisciplinary teams in support of transportation, infrastructure, port, coastal, commercial, and residential projects in the Southern California area since 2010. He has also provided technical support for various port, coastal, rail, and roadway projects in Northern California, Georgia, Maryland, Washington, and Virginia. Prior to his consulting career, Eric worked for the City of San Diego Environmental Services Department.
Responsibilities include preparing and processing environmental documents in compliance with the California Environmental Quality Act (CEQA), the National Environmental Policy Act (NEPA) and Caltrans’ Standard Environmental Reference (SER); preparing and p rocessing regulatory permits with the US Army Corps of Engineers (USACE), Regional Water Quality Control Board (RWQCB), California Department of Fish and Wildlife (CDFW) and United States Fish and Wildlife (USFWS); and mitigation compliance. Eric appreciates the importance of fine project details and how they fit within the larger context of project goals, having managed projects through all phases: scoping, environmental review, permitting, construction and close-out. His primary strength is his ability to foresee potential obstacles early in the project scoping phase and identify appropriate actions to take in advance to maintain project schedules and budgets.
SELECT PROJECTS – VCS ENVIRONMENTAL
SSAANN JJAACCIINNTTOO RREESSIIDDEENNTTIIAALL DDEEVVEELLOOPPMMEENNTT PPRROOJJEECCTT TTTTMM 3388220022 || SSAANN JJAACCIINNTTOO,, CCAA
The Project proposed developing an approximately 33.8-acre vacant site with up to 181 single-family residential homes and associated infrastructure. Eric was the environmental project manager and primary author of the Initial Study/Mitigated Negative Declaration, with technical studies for air quality/greenhouse gas, biological resources, cultural resources, hazardous materials, and transportation.
The draft IS/MND is scheduled for public review and certification in Q1 of 2023.
SSEEAALL BBEEAACCHH BBOOUULLEEVVAARRDD AATT NNOORRTTHH GGAATTEE RROOAADD IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTT || SSEEAALL
BBEEAACCHH,, CCAA
The City of Seal Beach in cooperation with the California Department of Transportation (Caltrans) District 12, jointly plan to rehabilitate Seal Beach Blvd. with mill and overlay of AC pavement repair. Eric was the environmental project manager responsible for oversight of the Preliminary Environmental Study (PES) in support of a NEPA categorical exclusion (CE). The PES was prepared in conformance with Caltrans’ Local Assistance Procedures Manual (LAPM) and Standard Environmental Reference (SER). Approval of the PES and NEPA CE is scheduled for Q1 of 2023.
II--221155 UUNNIIVVEERRSSIITTYY IINNTTEERRCCHHAANNGGEE || SSAANN BBEERRNNAARRDDIINNOO,, CCAA Environmental oversight for SBCTA. This project will reconstruct the I -215 and University Avenue Interchange to create the first Diverging Diamond Interchange (DDI) design implemented in California. As part of the Project Delivery Team (PDT),
YEARS OF EXPERIENCE
13 YEARS WITH VCS
7 EDUCATION
Master of Urban & Regional
Planning, emphasis in
Environmental Planning &
Policy, Cal Poly Pomona, CA
2010
B.A., History, Minor in
Psychology, University of
California, San Diego, CA,
2001
PROFESSIONAL AFFILIATIONS
Association of Environmental
Professionals
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxv
ERIC TURNER
Director of Environmental Services VVCCSS EEnnvviirroonnmmeennttaall
A certified DBE, SBE & WBE firm 30900 Rancho Viejo Road, Suite 100 San Juan Capistrano, CA 92675
949.489.2700 | vcsenvironmental.com
Eric provided oversight and peer review over the scoping and production of technical studies including a Natural Environmental Study/Minimal impacts (NESMI), Phase I Initial Site Assessment (ISA), Historical Resources Evaluation Report (HRER), Archaeological Survey Report (ASR), Historic Property Survey Report (HPSR) and Visual Impact Assessment (VIA) technic al memo during the project’s PA&ED phase. Eric was also tasked with integrating the project’s environmental commitments into the Plan Specifications and Estimates ( PS&E) package and with coordinating technical updates for the revalidation and environmental certification.
II--1100 EEAASSTTBBOOUUNNDD TTRRUUCCKK CCLLIIMMBBIINNGG LLAANNEE EEXXTTEENNSSIIOONN || SSAANN BBEERRNNAARRDDIINNOO,, CCAA Environmental oversight for SBCTA. This project will add a truck climbing lane from west of the 16th Street Bridge in the City of Yucaipa to just east of the County Line Road Bridge at the San Bernardino County and Riverside County line to slow moving trucks that are climbing the steep grade along the project from the general traffic lanes . As part of the Project Description Team ( PDT), Eric provided early oversight on scoping of the technical studies including a Natural Environmental Study/Minimal Impacts ( NESMI), Phase I Initial Site Assessment ( ISA) and New Source Review ( NSR) during the project’s Project Approval & Environmental Documentation (PA&ED) phase. Eric is currently assisting the team in permit ting strategy, application review, and mitigation coordination in support of the 404, 401 and 1602 permits to cover impacts to Oak Glen Creek.
FFIIVVEE BBRRIIDDGGEESS SSEEIISSMMIICC RREETTRROOFFIITT || CCOOLLTTOONN,, CCAA Project Manager. These projects entailed the seismic retrofit of three railroad overpass bridges and two pedestrian bridges for the City of Colton. Eric worked closely with the engineer and reviewed the technical plans to draft the project descriptions. Caltrans provided local assistance on these projects and made final determinations on the required technical studies including five topic areas: Natural Environment Study Minimal Impacts ( NESMI), Cultural Resources, Initial Site Assessment (ISA), Air Quality Checklist and Noise. Eric processed the bridges under five separate Categorical Exemptions/Categorical Exclusions for CEQA/NEPA compliance under Caltrans review.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxvi
JOEL MARTINEZ
Project Coordinator I | Environmental Analyst
A certified DBE, SBE & WBE firm 30900 Rancho Viejo Road, Suite 100 San Juan Capistrano, CA 92675
949.489.2700 | vcsenvironmental.com
Joel is a Project Coordinator at VCS Environmental (VCS). Joel received his Master’s in Environmental Studies from California State University , Fullerton in 2022 and has additional educational background in Environmental Analysis. Joel previously interned for the City of Chino and Orange County Sanitation District. He was involved in water conservation outreach and education, monitoring commercial/ residential waste practices, and implementing waste reduction practices for the public. He is responsible for CEQA/NEPA and regulatory permitting documents, as well as coordinating with VCS Project Managers to ensure that project deadlines are met.
SELECT PROJECTS
SSHHAADDYY VVIIEEWW RREESSIIDDEENNTTIIAALL || CCHHIINNOO HHIILLLLSS,, CCAA The project proposes the development of a single-family residential subdivision.
The proposed subdivision would consist of 159 single -family residential homes, a community recreation center, private interior streets, debris basins, utility infrastructure, and other associated improvements. Joel researched and coordinated with multiple mitigation banks for necessary information needed for California Department of Fish and Wildlife ( CDFW) and Regional Water Quality Control Board (RWQCB) permits.
II--1100 EEAASSTTBBOOUUNNDD TTRRUUCCKK CCLLIIMMBBIINNGG LLAANNEE EEXXTTEENNSSIIOONN || SSAANN BBEERRNNAARRDDIINNOO,, CCAA This project will add a truck climbing lane from west of the 16th Street Bridge in the City of Yucaipa to just east of the County Line Road Bridge at the San Bernardino County and Riverside County line to slow moving trucks that are climbing the steep grad e along the project from the general traffic lanes. Joel researched and coordinated with multiple mitigation banks for necessary information needed for California Department of Fish and Wildlife ( CDFW) and Regional Water Quality Control Board (RWQCB) permits.
SSHHOOEEMMAAKKEERR BBRRIIDDGGEE RREEPPLLAACCEEMMEENNTT || LLOONNGG BBEEAACCHH,, CCAA This project is proposing to replace the Shoemaker Bridge (Wes t Shoreline Drive) in the City of Long Beach, California. Joel is assisting by reviewing and researching necessary information from technical documents relating to the project ; as well as, preparing environmental documents for agency compliance (e.g. Caltrans, U.S.
Fish and Wildlife Services (USFWS)).
DDIIAAMMOONNDD SSPPEECCIIFFIICC PPLLAANN,, DDIIAAMMOONNDD IINNDDOOOORR SSPPOORRTTSS CCEENNTTEERR || LLAAKKEE EELLSSIINNOORREE,, CCAA
The Diamond Indoor Sports Center is a proposed 520,000 square foot commercial sports facility to be developed on 23.12 acres of vacant land located in the Back Basin of Lake Elsinore. Joel is assisting by researching and preparing document s such as the Conservation Easement for the project; as well as coordinating with multiple mitigation banks for necessary information needed for California Department of Fish and Wildlife (CDFW) and Regional Water Quality Control Board (RWQCB) permits.
YEARS OF EXPERIENCE
1 YEARS WITH VCS
>1
EDUCATION
M.S., Environmental Studies,
California State University,
Fullerton
B.A., Communications,
California State University,
Fullerton
AFFILIATIONS
Association of Environmental
Professionals (AEP)
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxvii
JOEL MARTINEZ
Project Coordinator I | Environmental Analyst VVCCSS EEnnvviirroonnmmeennttaall
A certified DBE, SBE & WBE firm 30900 Rancho Viejo Road, Suite 100 San Juan Capistrano, CA 92675
949.489.2700 | vcsenvironmental.com
SSEEAALL BBEEAACCHH || SSEEAALL BBEEAACCHH,, CCAA
This project proposes to rehabilitate Seal Beach Blvd., located at N Gate Rd & Seal Beach Blvd, Seal Beach, CA 90740 in Orange County. Joel assisted by preparing the Caltrans Preliminary Environmental Study (PES) on behalf of the City of Seal Beach.
This Caltrans PES will be used in support of the City project which is f ederally funded.
JJUURRUUPPAA VVAALLLLEEYY GGRRAADDEE SSEEPPAARRAATTIIOONN PPRROOJJEECCTT || JJUURRUUPPAA VVAALLLLEEYY,, CCAA The project included the construction of a new grade separation to replace a previously existing Union Pacific Railroad at-grade crossing located on Jurupa Road in the City of Jurupa Valley. To the east, the project is lined by retail, commercial and light industrial land uses. To the west, residential along with some commercial uses line the project. Joe l assisted with updates to the Biological technical report for the project, by assisting staff with on-site Least Bell’s Vireo (LBV) bird surveys.
AANNAAHHEEIIMM PPUUBBLLIICC UUTTIILLIITTIIEESS || AANNAAHHEEIIMM,, CCAA VCS Environmental is tasked with environmental compliance with NEPA in support of this undergrounding electrical utilities project, which will replace overhead power lines with underground facilities to reduce the risk of fire hazards within Tier 1, Tier 2 and Tier 3 fire hazard zones. Joel is assisting with the FEMA (NEPA Lead Agency) environmental checklist and compliance documentation for approval of a NEPA Categorical Exclusion (CE). This NEPA CE will be used in support of the City project which is funded by a NEPA Grant.
PPIICCOO RRIIVVEERRAA RREEGGIIOONNAALL BBIIKKEEWWAAYY PPRROOJJEECCTT ((CCIIPP NNOO.. 2211228800)) [[AATTPPLL--55335511 ((003322))]] ||
PPIICCOO RRIIVVEERRAA,, CCAA
VCS prepared the CEQA Initial Study/Mitigated Negative Declaration and Addendum. The project involved the construction of a Class IV Bikeway and associated water quality and road improvements to Mines Avenue from Paramount Boulevard to the San Gabriel River, construction of a bicycle/ pedestrian bridge over the San Gabriel River, reconstruction and restriping of the Class I Bikeway and Class II Bikeway along Dunlap Crossing Road. Joel is assisting with the preparation of the environmental portion of the 408 Permit including the preparation of the U.S. Army Corps of Engineers required NEPA Environmental Assessment. Joel reviewed and researched necessary information from technical documents relating to the project to complete the Environmental Assessment required for submission.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxviii
KIM S. RHODES, PLA 3867
Senior Landscape Architect
Kim Rhodes is an award-winning, California registered landscape architect, client manager and vice president with DEA. For the past 37 years, she has been responsible for landscape architectural design and management on numerous projects, including design and planning for highway/ roadway/ interchange design, corridor master plans, structure aesthetics, gateways, parks, multi-modal trails, interpretive signage, streetscapes, sports facilities, schools and universities, commercial, residential, and industrial developments. She has significant experience serving as a contract manager on numerous Caltrans District 8 contracts providing management and design services for corridor master plans, visual impact assessments, project reports, PS&E’s and highway aesthetics.
On-Call Landscape Architecture Support Services, Contract #08A2939 for Caltrans District 8, Riverside and San Bernardino Counties, California DEA is currently providing landscape architectural services under this $1 million, five-year contract with Caltrans District 8. DEA landscape architects and graphic designers provide an array of services including the preparation of Project Reports (PR’s) and PS&E’s for worker safety, erosion control and planting/irrigation improvements. As part of her contract management duties, she is responsible for the dissemination of project specific data and budgeting within the Caltrans WBS structure. As project manager, Kim is the primary point of contact between project subconsultants, internal staff, and works closely with them to ensure compliance with the project criteria.
I-215 Bi-County Parkway Gap Closure, San Bernardino, Colton, Grand Terrace and Riverside County, California
This $5.5 million dollar project includes the development of a supplemental Project Report, Visual Impact Assessment, and final plans, specifications and estimates for over five miles of planting and irrigation on the I-215 corridor from Orange Show Road to the County line. The goal includes a design that provides a distinctive, cohesive corridor between San Bernardino and Riverside Counties. Kim is serving as the project manager.
I-15 Railroad Canyon Interchange, Lake Elsinore, California The project required coordination between Caltrans District 8, the City of Lake Elsinore and the Riverside County Transportation Commission. DEA prepared the PS&E’s for planting, erosion control and irrigation. DEA landscape architects are also working on the structure aesthetics that will include the development of thematic art.
SR-73 Transportation Corridor Enhancement Master Plan, Aliso Viejo, California As project manager, Kim worked with the City of Aliso Viejo on the development of the SR 73 Transportation Corridor Enhancement Master Plan. This document focused on data collection and multi-agency coordination, an “art in public places” program, plant palette development, preparation of maintenance guidelines, and a comprehensive corridor enhancement master plan. The plan addressed study characterizations, visioning, inventories, analysis, corridor schematics, landscape treatments, gateway elements, intersection sequencing, goals and objectives, a 10-year capital improvement program and funding options.
I-15 / Limonite Avenue Interchange, Eastvale and Jurupa Valley, California The I-15 / Limonite Avenue interchange project included close coordination with the City of Eastvale, the City of Jurupa Valley and Riverside County. The project involved improvements to the ‘level of service’ provided to the traveling public including on and off ramp capacity, bridge improvements and highway widening. The design consisted of inert materials such as decomposed granite and rock cobble in addition to low water use trees and shrubs such as Palo Verde, Texas Ranger, Toyon, and Coffeeberry. The soundwall was planted with vines and the bioswales include grasses such as Elk Blue Rush and Deer Grass.
Education: BS, Landscape
Architecture, 1985, California State
Polytechnic University, Pomona
Registration: Registered Landscape
Architect, California, (3867), 1993
Areas of Expertise:
• Management
• Corridor Master Planning
• Design
• Structure Aesthetics /
Transportation Art
Relevance to this RFP:
• Caltrans experience
• SBCTA experience
• Current and similar project type
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xxxix
CL Surveying and Mapping, Inc.
400 East Rincon Street, Suite 202
Corona, CA 92879
(p) 909.484.4200 (f)909.484.4229
DBE MBE SBE
Daniel Calvillo, PLS 8294 – Survey Project Manager
Education: Engineering Technology Construction, California State Polytechnic University Pomona
Experience: Mr. Calvillo is one of two founding owners of CL Surveying and Mapping (founded in 2007) and has over 24 years of experience in the Land Surveying Industry. As the Director of Field Operations of CL Surveying and Mapping, he manages a talented staff of professionals on projects of varying magnitude and complexity, ranging from Major Transportation Improvements, Street Improvements, Bridge Widening Projects, Grade Separations, etc. In addition, Mr. Calvillo has extensive knowledge of field surveying related applications. He brings a high degree of technical expertise to field operations and is a key role in structuring field procedures that have resulted in completing projects in a timely and cost-efficient manner.
Mt. Vernon Viaduct Replacement Project (San Bernardino, CA) 2020 -Present - Owner: SBCTA CL Surveying and Mapping is working together with the Traylor-Granite JV(General Contractor) to reconstruct the Mt Vernon Avenue Bridge which has been an iconic structure and serving as a vital link for residents, visitors, students and businesses since 1934. CL Survey has been contracted to supply survey support services to assist in the construction of the bridge, the construction of shoofly tracks, realignment of existing tracks through the BNSF Rail yard, utility relocation and Retaining Walls. This project spans existing BNSF Rail yards and Metrolink tracks.
The new structure is anticipated to open in 2024.
Alabama/ I-10 Improvements Project (Redlands, CA) 2022 -Present – Owner: SBCTA The San Bernardino County Transportation Authority (SBCTA), the City of Redlands, and the County of San Bernardino are improving the I-10 at Alabama Street Interchange between Orange Tree Lane and Industrial Park Avenue. The project will Reduce congestion, improve safety, and improve traffic operations along Alabama Street between Orange Tree Lane and Industrial Park Avenue. Widen Alabama Street in both the southbound and northbound directions to accommodate turn pockets onto I-10. And provide Americans with Disabilities Act (ADA) compliant curb ramps, pedestrian push buttons and signals, and detectable warning surfaces at intersections where crosswalks are included. CL Surveying and Mapping will be working with Anser Advisory through the Construction Management contract to provide construction staking support services on an as-needed basis throughout construction.
Caltrans District’s 5, 6, 7, & 8 On-Call Surveying Services ( Los Angeles, Santa Cruz, Riverside and San Bernardino Counties ) - CL Surveying and Mapping served on multiple survey team s providing a wide range of Design and Construction Survey support services directly through Caltrans. Design Survey services included topographic surveys to assist in the design of future Caltrans construction projects. Construction Survey services consisting of construction staking for a variety of Caltrans construction projects. During the extent of this contract, CL Surveying and Mapping performed work on the following Contracts: 08A2427, 08A3230, 07A4679, 06A2641, and 07A5357.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xl
CL Surveying and Mapping, Inc.
400 East Rincon Street, Suite 202
Corona, CA 92879
(p) 909.484.4200 (f)909.484.4229
DBE MBE SBE
Stoddard Wells Road Widening (Apple Valley, CA) 2020 to 2021 - CL Surveying and Mapping was contracted to perform a Topographic Survey and Right of Way Mapping to assist in the Road Widening of approximately 2 miles of Stoddard Wells Road in the Towne of Apple Valley. This specific project consisted of level runs, GPS Surveys to match the California Coordinate System, Mobile LIDAR mapping, conventional topography, boundary establishment that consisted of a combination of record maps and Sectionalized Land of the Public Land Survey System(PLSS).
Mt. Vernon Storm Drain Topographic Survey (San Bernardino, CA) 2021 -2021 - Owner: SBDPW CL Surveying and Mapping is working together with the Onward Engineering for the design of the Mt. Vernon Storm Drain. This project will add a new RCP Storm Drain Pipe that connects at 16th Street and Mt. Vernon up to Cajon Boulevard at Highland Avenue. We provided the design topographic survey and right of way mapping for the new construction of the storm drain line on the affected streets.
Strengths That This Team Member Brings to the Team:
• Currently performing work on existing SBCTA Projects
• Performed mobile mapping and topographic survey work through Caltrans District 8 On - Call on the specific segments included on this Phase 2 SR-395 project. • Have worked on multiple major transportation projects including the I -15/I-215 Devore Interchange, SR91 Improvements in Corona and the Mid Coast Transit Corridor in San Diego
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
APPENDIX A | xli
“I thoroughly enjoyed working with Mike Mays on the Palmdale project. His knowledge of utilities and coordination with each utility company helped bring our project to the finish line.” - Alicia Cannon, PE, Project Manager, Jacobs
EEPPIICC LLAANNDD SSOOLLUUTTIIOONNSS,, IINNCC..
YYEEAARRSS OOFF EEXXPPEERRIIEENNCCEE
17 years (1 year with EPIC)
EEDDUUCCAATTIIOONN
B.S., Civil Engineering, California State
Polytechnic University, Pomona
AASSSSOOCCIIAATTIIOONNSS
Member, American Society of Civil
Engineers (ASCE)
Member, Business Development
Association of the Inland Empire
(BDAIE)
CCEERRTTIIFFIICCAATTEESS && CCOOUURRSSEEWWOORRKK
Introduction to Practical Railway
Engineering, American Railway
Engineering and Maintenance-of-Way
Association (AREMA)
Utility Process for Local Agencies,
Caltrans
Fundamentals of Inspection Practice,
Caltrans
Roadway Worker Safety Training
Certificate, SCRRA
Contractor Orientation, BNSF Railway
Contractor Orientation, Union Pacific
Railroad
MMIICCHHAAEELL MMAAYYSS
UTILIT Y SERVICES MANAGER
Michael “Mike” Mays is the Utility Services Manager for Epic Land Solutions ’ stand-alone Utility Services department which provides utility research, cost estimating, utility relocation coordination, and Caltrans Right of Way Certification services for publ ic agenc ies. Mike has 17 years of experience planning, designing, and overseeing utility relocations and is very familiar working within agencies’ procedures and protocols for protecting and relocating utility facilities, particularly for grade separation and highway projects. He has performed wet utility design and managed all aspects of utility coordination work, including preliminary and final report of investigation, determination of relocation liability, preliminary engineering, acquisition of required railroad encroachment permits, Right of Way certification, drafting utility agreements and legal notifications, plans, specifications, estimates, quantities, bid support, and construction support . Mike also understands the requirements of Caltrans LAPM and has developed relationships with key staff at Caltrans.
NNOOTTAABBLLEE EEXXPPEERRIIEENNCCEE
SSRR--221100 WWaatteerrmmaann AAvveennuuee ((SSRR--1188)) IInntteerrcchhaannggee PPrroojjeecctt,, SSaann BBeerrnnaarrddiinnoo CCoouunnttyy TTrraannssppoorrttaattiioonn AAuutthhoorriittyy ((SSBBCCTTAA)),, SSaann BBeerrnnaarrddiinnoo,, CCAA:: The project is designed to improve traffic operations and local circulation at the SR-210 Waterman Avenue intersection with East 30th Street and the eastbound SR -210 entrance ramp.
Utility coordination tasks recently kicked off for this project. To date, M ike has identified utility purveyors in the project area and sent out Facility Map Requests (FMRs) for the utility companies to provide as-built maps and facility maps.
PPSS&&EE II--1100 MMtt.. VVeerrnnoonn IInntteerrcchhaannggee IImmpprroovveemmeennttss PPrroojjeecctt,, CCiittyy ooff CCoollttoonn,, CCAA:: This project replaces the existing bri dge over I -10 and Mount Vernon Avenue and constructs local circulation improvements. In coordination with the EPIC right of way team and the prime design engineer, Mike is performing full utility relocation coordination for up to ten (10) facilities in con flict with the proposed improvements. Utility tasks support 35% level design, potholing coordination, 65% design plans, 100% plans, and Caltrans Utility Certification.
PPAA&&EEDD SSRR--6600 aatt RReeddllaannddss BBoouulleevvaarrdd IInntteerrcchhaannggee IImmpprroovveemmeennttss,, CCiittyy ooff MMoorreennoo VVaalllleeyy,, CCAA:: Up to ten (10) utility purveyors have facilities in the project location that are potentially in conflict with the proposed design. As the subconsultant to the design engineer, Mike is overseeing utility research, potholing investigations, and seeks to identify potentially prohibitive utility facility relocations and coordinate the utility clearance process for on-time project certification.
SSRR--7711 PPiinnee AAvveennuuee OOffff--RRaammpp IImmpprroovveemmeennttss CCiittyy ooff CChhiinnoo,, CCAA:: This project widens the SR-71 northbound and southbound off ramps to increase the ramps capacity. EPIC provided utility relocation coordination for two (2) utility conflicts.
Mike produced a pothole plan and provided a pothole investigation estimate, as- builts and facility verification for 10 utility companies.
City of Fontana | RFP For Design Services | SP-81-DE-23 | Citrus Avenue Widening at SR-210 Project
14 16498.00150\32126437.1
EXHIBIT B
Schedule of Charges/Payments
Consultant will invoice City on a monthly cycle. Consultant will include with each invoice a detailed progress report that indicates the amount of budget spent on each task. Consultant will inform City regarding any out-of-scope work being performed by Consultant. This is a time-and-materials contract.
FIRM: EXP U.S. Services Inc.
ROLE:PRIME CONSULTANT 3/31/2023
TASK Syed Raxa Luis Bentancourt Christine Brown Portia Gonzalez Mitsuru Tanaka Jose Carrillo Jasreen Brar Ben Hashemloo Parakh Jaiswal NO. Project Manager QC Reviewer Project Engineer Drainage Engineer Traffic Engineer Engineer/Designer Engineer/Designer Engineer/Designer Engineer/Designer $380.26 $153.76 $163.39 $373.31 $225.11 $155.76 $118.27 $215.27 $126.24
1.1 Project Management 30 10 40 $12,945.35 $12,945.35
1.2 Coordination and Meetings 20 20 $7,605.14 $7,605.14 SUBTOTAL 50 10 0 0 0 0 0 0 0 60 $20,550.49 $0.00 $0.00 $0.00 $0.00 $0.00 $20,550.49
2.1 Research and Data Collection 1 4 5 $786.44 $786.44
2.2 Utility Research and Coorrdination 2 2 $326.78 $20,926.00 $21,252.78
2.3 Geotechnical Report 4 4 $653.56 $26,940.00 $27,593.56
2.4 Surveying and Mapping 4 4 $653.56 $12,700.00 $13,353.56
2.5 Utility Potholing 4 4 $653.56 $6,764.00 $7,417.56
SUBTOTAL 0 0 15 0 0 4 0 0 0 19 $3,073.89 $0.00 $0.00 $26,940.00 $27,690.00 $12,700.00 $70,403.89
3.1 Categorical Exemption 2 2 $326.78 $18,886.00 $4,260.00 $23,472.78 SUBTOTAL 0 0 2 0 0 0 0 0 0 2 $326.78 $18,886.00 $0.00 $4,260.00 $0.00 $0.00 $23,472.78
4.1 Traffic Operations Analysis Report 40 40 $8,610.76 $8,610.76
4.2 Storm Water Data Report 2 40 42 $5,796.21 $5,796.21
4.3 Drainage Report 2 40 42 $5,796.21 $5,796.21
4.4 Traffic Management Plan 4 4 $653.56 $653.56
4.5 Street Improvement Plans 4 220 224 $34,921.29 $34,921.29
4.6 Traffic Signal Imrpovement Plans 2 16 100 118 $15,756.02 $15,756.02
4.7 Storm Drain Imprvoement Plans 2 50 52 $8,114.90 $8,114.90
4.8 Signing and striping Plans 2 40 42 $5,057.77 $5,057.77
4.9 Landscape and Irrigation Plan 2 2 $326.78 $20,987.32 $21,314.10
4.10 Estimate of Probable Construction Cost 2 12 14 $2,195.93 $2,195.93
4.11 Technical Specifications 40 40 $6,535.56 $6,535.56 SUBTOTAL 0 0 58 4 16 282 140 40 80 620 $93,764.98 $0.00 $20,987.32 $0.00 $0.00 $0.00 $114,752.30
5.1 Caltrans Encroachment Permit 100 100 $16,338.91 $16,338.91 SUBTOTAL 0 0 100 0 0 0 0 0 0 100 $16,338.91 $0.00 $0.00 $0.00 $0.00 $0.00 $16,338.91
6.1 Bid Support 4 4 $653.56 $653.56
6.2 Construction Engineering 12 12 $1,960.67 $1,960.67
6.3 As-Built Drawings 2 8 10 $1,572.88 $1,572.88
SUBTOTAL 0 0 18 0 0 8 0 0 0 26 $4,187.10 $0.00 $0.00 $0.00 $0.00 $0.00 $4,187.10 SUBTOTAL HOURS : 50 10 193 4 16 294 140 40 80 827
SUBTOTAL LABOR : $19,012.86 $1,537.64 $31,534.10 $1,493.23 $3,601.76 $45,794.15 $16,558.48 $8,610.76 $10,099.19 $138,242.15 $18,886.00 $20,987.32 $31,200.00 $27,690.00 $12,700.00 $249,705.47 ODC'S : $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL : $138,242.15 $18,886.00 $20,987.32 $31,200.00 $27,690.00 $12,700.00 $249,705.47 TASK 2 - DATA COLLECTION
EXP U.S. Services Inc. - Detailed Labor and Fee Breakdown Citrus Widening at SR-210 Project
TASK DESCRIPTIONS TOTAL FEE PRIME
CONSULTANT TASK TOTAL
Sub-Consultants
Converse Epic Land Solutions Cl SurveyingDEA
Total Hours
Prime
Consultant
City of Fontana
ENVIRONMENTAL SERVICES AND FINAL ENGINEERING DESIGN SUBTOTALS TASK 3 - ENVIRONMENTAL
TASK 4 - ENGINEERING
TASK 5 - PERMIT
TASK 6 - BBIDDING AND CONSTRUCTION ENGINEERING
TASK 1 - PROJECT MANAGEMENT
VCS