STAGE RED INTERIOR REMODEL

8463 Sierra Avenue Fontana, CA 92335
DE-24-25-SB

SUBMISSION DEADLINE:

SEPTEMBER 18, 2023
2:00 PM

BID MUST BE SUBMITTED ELECTRONICALLY
Hard Copies will NOT be accepted as a viable bid.

TABLE OF CONTENTS
DE-24-25-SB

ITEM PAGE

i

NOTICE INVITING SEALED BIDS 1

INSTRUCTIONS TO BIDDERS 2
➢ Availability of Contract Documents
➢ Examination of Contract Documents
➢ Interpretation of Contract Documents
➢ Inspection of Site; Pre-Bid Conference and Site Walk
➢ Addenda
➢ Completion of Bid Forms
➢ Modification of Bids
➢ Designation of Subcontractors (Entered Online)
➢ Licensing Requirements
➢ Signing of Bids
➢ Submission of Sealed Bids (Electronic Bid Only)
➢ Delivery and Opening of Bids
➢ Withdrawal of Bid
➢ Basis of Award; Balanced Bids
➢ Disqualification of Bidders; Interest In More Than One Bid ➢ Insurance Requirements
➢ Award Process
➢ Filing of Bid Protests
➢ Workers Compensation
➢ Substitution of Security
➢ Prevailing Wages
➢ Debarment of Contractors and Subcontractors
➢ Performance Bond and Payment (Labor and Materials) Bond Requirements

➢ Sales and Other Applicable Taxes, Permits, Licenses and Fees ➢ Iran Contracting Act of 2010

➢ Execution of Contract

BID FORMS 9
➢ Information Required of Bidders (Submit Online)
➢ Bid Form (Submit Online)
➢ Contractor’s Certificate Regarding Workers’ Compensation (Submit Online)

➢ Non-Collusion Declaration (Submit Online)
➢ Payment Bond (Labor and Materials), If Bid Amount is Over $25,000

TABLE OF CONTENTS
DE-24-25-SB

ITEM PAGE

ii

CONTRACT 15
➢ Article 1. Scope of Work
➢ Article 2. Time for Completion
➢ Article 3. Contract Price
➢ Article 4. Payments
➢ Article 5. Payments Withheld and Backcharges
➢ Article 6. Changes and Extra Work
➢ Article 7. Liquidated Damages
➢ Article 8. Component Parts of The Contract
➢ Article 9. Provisions Required By Law
➢ Article 10. Indemnification
➢ Article 11. Prevailing Wages
➢ EXHIBIT “A” – Change Order Form

GENERAL CONDITIONS 28
Article 1.- Definitions
Article 2. - Contract Documents
Article 3. - Detail Drawings And Instructions
Article 4. – Substitutions
Article 5. – Materials
Article 6. - Contractor’s Supervision
Article 7. – Workers
Article 8. – Subcontractors
Article 9. - Permits And Licenses
Article 10. - Diversion of Recyclable Waste Materials
Article 11. - Removal of Hazardous Materials
Article 12. - Sanitary Facilities
Article 13. - Air Pollution Control
Article 14. - Fire Protection
Article 15. - Cleaning Up
Article 16. - Excessive Noise
Article 17. - Protection Of Work And Property
Article 18. - Contractors Means And Methods
Article 19. - Authorized Representatives
Article 20. - Hours of Work
Article 21. - Prevailing Rates of Wages
Article 22. - Non-discrimination/Equal Employment Opportunity Article 23. - Labor/Employment Safety
Article 24. - Workers’ Compensation Insurance

TABLE OF CONTENTS
DE-24-25-SB

ITEM PAGE

iii

Article 25. - Employer’s Liability Insurance
Article 26. - Commercial General Liability Insurance
Article 27. - Automobile Liability Insurance
Article 28. - Form And Proof of Carriage Of Insurance
Article 29. - Time For Completion And Liquidated Damages Article 30. - Cost Breakdown And Periodic Estimates
Article 31. - City’s Right To Terminate Contract
Article 32. - Warranty And Guarantee
Article 33. - Notice And Service Thereof
Article 34. – Integration

OTHER DOCUMENTS

STAGE RED CONSTRUCTION PLANS (BID PLAN SET) Attachment
STAGE RED CONSTRUCTION CALC SET (BID PLAN SET) Attachment FURNISHINGS AND FINISHES LISTS Attachment

1 CITY OF FONTANA

NOTICE INVITING SEALED BIDS

NOTICE IS HEREBY GIVEN that sealed bids will be received only by submitting electronically atww.fontanapurchasing.org, for STAGE RED Interior Remodel DE-24-25-SB no later than SEPTEMBER 18, 2023, 2:00 PM, at which time or thereafter said Bids will be electronically opened and available online. Bids received after this time will not be able to submit electronically. Bids shall be valid for 90 calendar days after the Bid opening date.

DESCRIPTION OF WORK:

The work is described as follows: Demolition, construction of two new Balconies, three New Bars, New Raised Platform, and New Walls, Ceilings, Installation of new Lighting, Flooring, Foodservice Equipment, Audio/Visual Equipment, and Finishes, including allNew Structural, Mechanical, Plumbing & Electrical scope. All improvements noted, as identified on the attached construction plans, dated 8.01.23 consisting of 113 pages, prepared by Ideation Group, Inc (“Construction Plans”). Contractor shall be responsible for demolition, construction, and installation of all improvements specifically identified on or implied by Construction Plans, unless specifically noted on the Construction Plans to be performed by others. The City is contracting a company/consultant to provide the furnishings, furniture and lighting required for Stage RED. Please review plans to identify what is the contractor’s responsibility. Refer to attachments for information on the furnishings, fixtures and finishes that will be provided.

Bid must be submitted electronically for the exact item(s) requested in the bid specifications. Copies of plans, specifications, and contract documents are available from the City’s Purchasing website www.fontanapurchasing.org.

An OPTIONAL Pre-Bid jobsite walk will be held at 8463 Sierra Avenue, Fontana, CA on September 31, 2023 PROMPTLY at 1:00 PM. The walk will start at 1:00 PM, beginning with a brief presentation, then will continue with a site walk until 4:00 pm.

Each Bid submitted electronically shall be accompanied by the bid forms, non-collusion declaration, and all additional documentation required by the Instructions to Bidders. The successful Bidder will be required to furnish the City with a Payment (Labor and Materials) Bond equal to 100% of the successful Bid, prior to execution of the Contract. The bond we need to be secured from a surety that meets all of the State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and is admitted by the State of California. The cost of said bonds shall be included in the Bid amount. Pursuant to Public Contract Code Section 22300, the successful Bidder may substitute certain securities for funds withheld by City to ensure his performance under the Contract.

Each Bidder shall be a licensed contractor pursuant to the Business and Professions Code and shall be licensed in the following appropriate classification(s) of contractor’s license(s), for the work Bid upon, and must maintain the license(s) throughout the duration of the Contract. At the time of submitting a bid, the prime contractor and subcontractor shall possess a Class "B" contractor’s license or a Class “C” specialty license sufficient to perform the work.

Pursuant to Public Contract Code Section 3400(b), if the City should make findings designating certain materials, products, things, or services by specific brand or trade name, such findings and the materials, products, things, or services and their specific brand or trade names will be set forth in the Special Conditions.

2 The City shall award the Contract for the Project to the lowest responsive, responsible Bidder on the basis of the base Bid alone by the City. The City reserves the right to reject any or all Bids or to waive any irregularities or informalities in any Bids or in the Bidding process.

INSTRUCTIONS TO BIDDERS
3 INSTRUCTIONS TO BIDDERS

1. AVAILABILITY OF CONTRACT DOCUMENTS
Bids must be submitted to the City on the Bid Forms which are a part of the Bid Package for the Project. Contract Documents may be obtained from the Purchasing website www.fontanapurchasing.org.

2. EXAMINATION OF CONTRACT DOCUMENTS
Bidders shall be solely responsible for examining the Project Site and the Contract Documents, including any Addenda issued during the Bidding period, and for informing itself with respect to local labor availability, laws and codes, local permit requirements, wage scales, local tax structure, contractors’ licensing requirements, availability of required insurance, and other factors that could affect the Work. Bidders are responsible for consulting the standards referenced in the Contract. Failure of Bidder to so examine and inform itself shall be at its sole risk, and no relief for error or omission will be given except as required under State law.

3. INTERPRETATION OF CONTRACT DOCUMENTS
Discrepancies in, and/or omissions from the Plans, Specifications or other Contract Documents or questions as to their meaning shall be immediately brought to the attention of the City by submission of a written request for an interpretation or correction by using the online bid system at www.fontanapurchasing.org, NO LATER THAN 7 Days prior to the bid closing date.

Any interpretation of the Contract Documents will be made only by Addenda duly issued electronically to each person registered on the prospective bidder’s list. The City will not be responsible for any explanations or interpretations provided in any other manner. No person is authorized to make any oral interpretation of any provision in the Contract Documents to any Bidder, and no Bidder should rely on any such oral interpretation.

Bids shall include complete compensation for all items that are noted in the Contract Documents and are the responsibility of the Contractor.

4. INSPECTION OF SITE; PRE-BID CONFERENCE AND SITE WALK Each prospective Bidder is responsible for fully acquainting itself with the conditions of the Project Site (which may include more than one site), as well as those relating to the construction and labor of the Project, to fully understand the facilities, difficulties and restrictions which may impact the cost or effort required to complete the Project. To this end, a Pre-Bid Conference and Site Walk will be held on the date(s) and time(s) indicated in the Notice Inviting Bids.

5. ADDENDA
The City reserves the right to revise the Contract Documents prior to the Bid opening date.

Revisions, if any, shall be made by Addenda. All Addenda issued by the City shall be included in the Bid and made part of the Contract Documents. Pursuant to Public Contract Code Section 4104.5, if the City issues an Addendum which includes material changes to the Project less than 72 hours prior to the deadline for submission of Bids, the City will extend the deadline for submission of Bids. The City may determine, in its sole discretion, whether an Addendum warrants postponement of the Bid submission date. Each prospective Bidder shall provide City a name and email address to which Addenda may be sent, as well as a telephone number by which

INSTRUCTIONS TO BIDDERS
4 the City can contact the Bidder. Copies of Addenda will be available on the City’s Purchasing website www.fontanapurchasing.org. Please Note: Bidders are responsible for ensuring that they have received any and all Addenda. To this end, each Bidder should contact the City’s Purchasing website www.fontanapurchasing.org to verify that he has received all Addenda issued, if any, prior to the Bid opening.

6. COMPLETION OF BID FORMS
Bids shall only be prepared using copies of the Bid Forms which are included in the Contract Documents. The use of substitute Bid forms other than clear and correct photocopies of those provided by the City will not be permitted. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable) and initial all interlineations, alterations, or erasures to the Bid Forms. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms nor make substitutions thereon. USE OF BLACK OR BLUE INK, INDELIBLE PENCIL, ELECTRONICALLY OR TYPED IS REQUIRED. Deviations in the Bid form may result in the Bid being deemed non-responsive.

7. MODIFICATIONS OF BIDS
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents. Unauthorized additions, modifications, revisions, conditions, limitations, exclusions or provisions attached to a Bid may render it non-responsive and may cause its rejection.

Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms, nor make substitutions thereon. Oral, telephonic and electronic modifications will not be considered, unless the Notice Inviting Bids authorizes the submission of electronic Bids and modifications thereto and such modifications are made in accordance with the Notice Inviting Bids.

8. DESIGNATION OF SUBCONTRACTORS (Entered Online)
In compliance with the Subletting and Subcontracting Fair Practices Act of the Public Contract Code of the State of California, each Bidder shall set forth below: (a) the name and the location of the place of business and (b) the portion of the work which will be done by each subcontractor who will perform work or labor or render service to the Contractor in or about the construction of the work in an amount in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Amount. Notwithstanding the foregoing, if the work involves streets and highways, then the Contractor shall list each subcontractor who will perform work or labor or render service to Contractor in or about the work in an amount in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Amount or $10,000, whichever is greater. No additional time shall be granted to provide the below requested information.

If no subcontractor is specified, for a portion of the work, or if more than one subcontractor is specified for the same portion of Work, to be performed under the Contract in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Amount or $10,000, whichever is greater if the work involves streets or highways, then the Contractor shall be deemed to have agreed that it is fully qualified to perform that Work, and that it shall perform that portion itself.

9. LICENSING REQUIREMENTS
Pursuant to Section 7028.15 of the Business and Professions Code and Section 3300 of the Public Contract Code, all Bidders must possess proper licenses for performance of this Contract.

Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Section 7028.5 of the Business and Professions Code, the City shall consider any Bid

INSTRUCTIONS TO BIDDERS
5 submitted by a contractor not currently licensed in accordance with state law and pursuant to the requirements found in the Contract Documents to be nonresponsive, and the City shall reject the Bid. The City shall have the right to request, and Bidders shall provide within five (5) calendar days, evidence satisfactory to the City of all valid license(s) currently held by that Bidder and each of the Bidder’s subcontractors, before awarding the Contract. Please also note that, pursuant to Public Contract Code Section 20676, sellers of "mined material" must be on an approved list of sellers published pursuant to Public Resources Code Section 2717(b) in order to supply mined material for this Contract.

10. SIGNING OF BIDS
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.

If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of Bidder assumed under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.

11. SUBMISSION OF SEALED BIDS
Once the Bid and supporting documents have been completed and signed as set forth herein, they shall be submitted electronically.

Only where expressly permitted in the Notice Inviting Bids, may Bidders submit their Bids via electronic transmission pursuant to Public Contract Code Sections 1600 and 1601. The acceptable method(s) of electronic transmission shall be stated in the Notice Inviting Bids.

12. DELIVERY AND OPENING OF BIDS
Bids are to be submitted electronically. Electronic Bid System will close exactly at the time set forth in the Notice Inviting Bid. All applicable forms required to be completed per the bid documents, shall be submitted electronically prior to the due date and time. Hard copies will not be accepted as a viable bid. It is the Bidder’s sole responsibility to ensure that its Bid is received as specified. Bids may be submitted earlier than the dates(s) and time(s) indicated.

Bids will be available at the date and time stated in the Notice Inviting Bids and the amount of each Bid will be available online and recorded. The City may in its sole discretion, elect to postpone the opening of the submitted Bids. City reserves the right to reject any or all Bids and to waive any informality or irregularity in any Bid. In the event of a discrepancy between the written amount of the Bid Amount and the numerical amount of the Bid Amount, the written amount shall govern.

INSTRUCTIONS TO BIDDERS
6 13. WITHDRAWAL OF BID
Prior to Bid opening, a Bid may be withdrawn by the Bidder only by using the City’s electronic bidding system.

14. BASIS OF AWARD; BALANCED BIDS
The City shall award the Contract to the lowest responsive, responsible Bidder submitting a responsive Bid. The City may reject any Bid which, in its opinion when compared to other Bids received or to the City’s internal estimates, does not accurately reflects the cost to perform the Work. The City may reject as non-responsive any Bid which unevenly weights or allocates costs, including but not limited to overhead and profit to one or more particular Bid items.

15. DISQUALIFICATION OF BIDDERS; INTEREST IN MORE THAN ONE BID No Bidder shall be allowed to make, submit or be interested in more than one Bid. However, a person, firm, corporation or other entity that has submitted a subproposal to a Bidder, or that has quoted prices of materials to a Bidder, is not thereby disqualified from submitting a subproposal or quoting prices to other Bidders submitting a Bid to the City. No person, firm, corporation, or other entity may submit subproposal to a Bidder, or quote prices of materials to a Bidder, when also submitting a prime Bid on the same Project.

16. INSURANCE REQUIREMENTS
The successful Bidder shall procure the insurance in the form and in the amount specified in the Contract Documents.

17. AWARD PROCESS
Once all Bids are electronically opened and reviewed to determine the lowest responsive and responsible Bidder, the City will award the contract. The apparent successful Bidder should begin to prepare the following documents: (1) the Payment (Labor and Materials) Bond; and (2) the required insurance certificates and endorsements. Once the City notifies the Bidder of the award, the Bidder will have ten (10) consecutive calendar days from the date of this notification letter to execute the Contract and supply the City with all of the required documents and certifications. Regardless whether the Bidder supplies the required documents and certifications in a timely manner, the Contract time will begin to run ten (10) calendar days from the date of the notification. Once the City receives all of the properly drafted and executed documents and certifications from the Bidder, the City shall issue a Notice to Proceed to that Bidder.

18. FILING OF BID PROTESTS
Bidders may file a “protest” of a Bid with the City’s Purchasing Officer. In order for a Bidder’s protest to be considered valid, the protest must:

A. Be filed in writing within five (5) calendar days after the Bid opening date; B. Clearly identify the specific irregularity or accusation; C. Clearly identify the specific City staff determination or recommendation being protested;

INSTRUCTIONS TO BIDDERS
7 D. Specify, in detail, the grounds of the protest and the facts supp orting the protest; and
E. Include all relevant, supporting documentation with the protest at time of filing.

If the protest does not comply with each of these requirements, it will be rejected as invalid.

If the protest is valid, the City’s Purchasing Officer, or other designated City staff member, shall review the basis of the protest and all relevant information. The Purchasing Officer will provide a written decision to the protestor. The protestor may then appeal the decision of the City Manager.

19. WORKERS COMPENSATION
Each Bidder shall submit the Contractor’s Certificate Regarding Workers’ Compensation form.

20. SUBSTITUTION OF SECURITY
The Contract Documents call for monthly progress payments based upon the percentage of the work completed. The City will retain five percent (5%) of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidder, the City will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.

21. PREVAILING WAGES
This is project is a public work in the State of California, funded in whole or in part with public funds. Therefore, the higher of the two applicable prevailing wage rates, federal or state, will be enforced. The Contractor’s duty to pay State prevailing wages can be found under Labor Code Section 1770 et seq. Labor Code Sections 1775 and 1777.7 outline the penalties for failure to pay prevailing wages and to employ apprentices, including forfeitures and debarment. The State Wage Decision is also available online at http://www.dir.ca.gov/dlsr/.

Apprenticeship Program: Attention is directed to Sections 1777.5, 1777.6 and 1777.7 of the California Labor Code and Title 8, California Administrative code, Section 200 et seq. to ensure compliance and complete understanding of the law regarding apprentices.

22. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Section 1777.1 or Section 1777.7 of the Labor Code and the Federal “Excluded Parties List System”. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to the City. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the Project.

INSTRUCTIONS TO BIDDERS
8 23. PERFORMANCE BOND AND PAYMENT (LABOR AND MATERIALS) BOND

REQUIREMENTS
Within the time specified in the Contract Documents, the Bidder to whom a Contract is awarded shall deliver to the City four identical counterparts of the Performance Bond and Payment (Labor and Materials) Bond, each in an amount equal to one hundred percent (100%) of the Total Bid Amount and in the form supplied by the City and included in the Contract Documents. Failure to do so may, in the sole discretion of City, result in the forfeiture of the Bid Guarantee. The surety supplying the bond must be an admitted surety insurer, as defined in Code of Civil Procedure Section 995.120, authorized to do business as such in the State of California and satisfactory to the City.

24. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES Contractor and its subcontractors performing work under this Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the work will be located, unless otherwise expressly provided by the Contract Documents.

25. IRAN CONTRACTING ACT OF 2010
In accordance with Public Contract Code Section 2200 et seq., the City requires that any person that submits a bid or proposal or otherwise proposes to enter into or renew a contract with the City with respect to goods or services of one million dollars ($1,000,000) or more, certify at the time the bid is submitted or the contract is renewed, that the person is not identified on a list created pursuant to subdivision (b) of Public Contract Code Section 2203 as a person engaging in investment activities in Iran described in subdivision (a) of Public Contract Code Section 2202.5, or as a person described in subdivision (b) of Public Contract Code Section 2202.5, as applicable.

26. EXECUTION OF CONTRACT
As required herein the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. The City may require appropriate evidence that the persons executing the Contract are duly empowered to do so.

END OF INSTRUCTIONS TO BIDDERS

SUBMIT ONLINE

INFORMATION REQUIRED OF BIDDER
9 INFORMATION REQUIRED OF BIDDER

A. INFORMATION ABOUT BIDDER
BIDDER certifies that the following information is true and correct:

Bidder's Name:

Business Address:

Telephone: Fax:

Email Address:

State Contractor's License No. and Class:

Original Date Issued: Expiration Date:

DIR No.: Expiration Date:

What type of work does the Bidder normally perform with its own forces? __________________________________________________________ _________________________________________________________ _________________________________________________________ _________________________________________________________ Name of Bonding Company and Name and Address of Agent:
_________________________________________________________ _________________________________________________________

SUBMIT ONLINE

BID FORM
10 BID FORM

TOTAL BID AMOUNT (BASED ON PLANS): The costs for any Work shown or required in the Contract Documents, but not specifically identified as a line item are to be included in the related line items and no additional compensation shall be due to Contractor for the performance of the Work.

NO.

ITEM DESCRIPTION

UNIT OF
MEASURE QTY.

1. The contractor shall
construct the proposed
project in accordance with
the plans and specifications.

LS 1

$
Total Bid Amount in Numbers

Total Bid Amount in Written Form

Number of Days to Complete the Project (70 Working Days)

The undersigned agrees that this Bid Form constitutes a firm offer to the City which cannot be withdrawn for the number of calendar days indicated in the Notice Inviting Bids from and after the Bid opening, or until a Contract for the Work is fully executed by the City and a third party, whichever is earlier.

1. Upload the Bid Form.

2. Upload the Information Required of Bidder Form.

3. Upload the fully executed Non-Collusion Declaration Form.

4. Upload the completed Contractor’s Certificate Regarding Workers’ Compensation Form.

5. List Subcontractors online.

I hereby certify under penalty of perjury under the laws of the State of California, which all of the information submitted in connection with this Bid and all of the representations made herein are true and correct.

SUBMIT ONLINE
CONTRACTOR’S CERTIFICATE REGARDING
WORKERS’ COMPENSATION
11 SDPUB\SAKINS\347250.2
CONTRACTOR’S CERTIFICATE REGARDING
WORKERS’ COMPENSATION

I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Contract.

Name of Bidder
Signature
Name and Title
Dated

SUBMIT ONLINE

NON-COLLUSION DECLARATION
12 NON-COLLUSION DECLARATION

The undersigned declares:

I am the ______________________________ of _________________________ ___________________________________________, the party making the foregoing bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. T he bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, join t venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on ______________________[date], at ___________________________________[city], _____[state].

__________________________________
(Signature)
__________________________________
(Print Name)
__________________________________
(Title)

PAYMENT BOND (LABOR AND MATERIALS)
13 SDPUB\SAKINS\347250.2

PAYMENT BOND (LABOR AND MATERIALS)

KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Fontana (hereinafter designated as the “City”), by action taken or a resolution passed ___________ , 20____ has awarded to ________________ hereinafter designated as the “Principal,” a contract for the work described as follows:
____________________________________________________________________________ (the “Project”); and
WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.

NOW THEREFORE, we, the Principal and __________________________ as Surety, are held and firmly bound unto the City in the penal sum of ______________ Dollars ($___________) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Section 3181 of the Civil Code, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 18663 of the Revenue and Taxation Code, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.

This bond shall inure to the benefit of any of the persons named in Section 3181 of the Civil Code so as to give a right of action to such persons or their assigns in any suit brought upon this bond.

It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the contract, agreement or bond, nor by any

PAYMENT BOND (LABOR AND MATERIALS)
14 SDPUB\SAKINS\347250.2
conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Section 3110 or 3112 of the Civil Code, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned.

IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed unoriginal thereof, have been duly executed by the Principal and Surety above named, on the _____ day of ______________________ 20______ the name and corporate seal of each corporate party being hereto affixed and these presents duly signed b its undersigned representative pursuant to authority of its governing body. (Corporate Seal of Principal,
if corporation)

Principal (Property Name of Contractor)
By:
(Signature of Contractor)
(Seal of Surety)
Surety
By:

Attorney in Fact
(Attached Attorney-In-Fact
Certificate and Required
Acknowledgements)

*Note: Appropriate Notarial Acknowledgments of Execution by Contractor and +surety and a power of Attorney MUST BE ATTACHED.

PAYMENT BOND (LABOR AND MATERIALS)
15 SDPUB\SAKINS\347250.2

CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT

State of California }
} ss.

County of __________________________ }
On before me,

personally appeared
Here Insert Name and Title of the Officer
Name(s) of Signer(s)

who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Place Notary Seal Above Signature of Notary Public
_______________________________________________________

OPTIONAL
_____________________________________________________________

Though the information below is not required by law, it may prove valuable to persons relying on the doc ument and could prevent fraudulent removal and reattachment of this form to another document.

Description of Attached Document

Title of Type of Document:

Document Date:

Number of Pages:

Signer(s) Other Than Named Above:

Capacity(ies) Claimed by Signer(s)

Signer’s Name: Signer’s Name:
 Individual  Individual
 Corporate Officer Title(s):  Corporate Officer Title(s):
 Partner -  Limited  General  Partner -  Limited  General  Attorney in Fact Right Thumbprint of Signer
Top of thumb here
 Attorney in Fact Right Thumbprint of Signer
Top of thumb here  Trustee  Trustee
 Guardian or Conservator  Guardian or Conservator
 Other:  Other:

Signer is Representing: Signer is Representing:

.

CONTRACT
16 SDPUB\SAKINS\347250.2

CONTRACT
THIS CONTRACT is made this _____ day of _________, 20 23, in the County of San Bernardino, State of California, by and between the City of Fontana, hereinafter called City, and ______________________________, hereinafter called Contractor. The City and the Contractor for the considerations stated herein agree as follows:

ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated the Contract and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5 below for the following Project:

STAGE RED INTERIOR REMODEL, DE-24-25-SB
The Contractor and its surety shall be liable to the City for any damages arising as a result of the Contractor’s failure to comply with this obligation.

ARTICLE 2. TIME FOR COMPLETION.

2.1 The Work shall be commenced on the date stated in the City’s Notice to Proceed.

The Contractor shall complete all Work required by the Contract Documents within seventy (70) working days from the commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.

Contract shall use the City’s general Project performance schedule shown below as a reference point when developing their project schedule:
• Bid opening date of September 18.
• Notice to Proceed (NTP) issued by September 28th.
o Contract will go to City Council for award in September. • Construction begins on or before October 15th.
• Construction completion on or before January 20th.

2.2 Contractor shall coordinate the Work with the other work being performed on the Project, in accordance with those schedules as may be issue d from time to time during the performance of the Work, and any other scheduling requirements listed in this Agreement, so as not to delay, impede, obstruct, hinder or interfere with the commencement, progress or completion of the whole or any part of the Work or other work on the Project.

2.3 The Contractor shall participate and cooperate with the City in the development of schedules and other efforts to achieve timely completion of the Work providing

CONTRACT
17 SDPUB\SAKINS\347250.2
information for the scheduling of the times and sequenc e of operations required for its Work (“Contractor Schedule”) to meet City’s overall master project schedule requirements (“Master Schedule”). The Contractor shall continuously monitor the Master Schedule so as to be fully familiar with the timing, phasin g and sequence of operations of the Work and of other work on the Project, and shall execute the Work in accordance with the requirements of the Master Schedule including any revisions thereto. The Contractor shall notify the City within 48 hours of any slippage in the Contractor Schedule and shall submit a detailed recovery plan to the City for approval within five (5) calendar days of such notice.

2.4 Should the progress of the Work or of the Project be delayed disrupted, hindered, obstructed, or interfered with by any fault or neglect or act or failure to act of the Contractor or any of its officers, agents, servants, employees, subcontractors or suppliers so as to cause any additional cost, expense, liabi lity or damage to the City or any consultants retained by the City for the Project, including legal fees and disbursements incurred by the City or the consultants retained by the City for the Project, (whether incurred in defending claims arising from such delay or in seeking reimbursement and indemnity from the Contractor and its surety hereunder or otherwise) or any damages or additional costs or expenses for which the City or the consultants retained by the City for the Project, may or shall become liable, the Contractor and its surety s hall and does hereby agree to compensate the City or the consultants retained by the City for the Project,, for and indemnify them against all such costs, expenses, damages and liability.

2.5 The City, in its sole discretion, may direct the Contractor to w ork overtime and, if so directed, the Contractor shall work said overtime and, provided that the Contractor is not in default under any of the terms or provisions of this Agreement or of any of the other Contract Documents, the City will pay the Contractor for such actual additional wages paid, if any, at the prevailing wage rates plus taxes imposed by law on such additional wages, plus workers' compensation insurance, liability insurance and levies on such additional wages if required to be paid by the Contractor.

2.6 If, however, the progress of the Work or of the Project is delayed by any fault or neglect or act or failure to act of the Contractor or any of its officers, agents, servants, employees, subcontractors or suppliers, then the Contractor shall, in addition to all of the other obligations imposed by this Agreement upon the Contractor in such case, and at its own cost and expense, work such overtime as may be necessary to make up for all time lost in the completion of the Work and of the Project due to such delay. Should the Contractor fail to make up for the time lost by reason of such delay, the City shall have the right to cause other contractors to work overtime and to take whatever other action it deems necessary to avoid delay in the completion of the Work and of the Project, and the cost and expense of such overtime and/or such other action shall be borne solely by the Contractor.

CONTRACT
18 SDPUB\SAKINS\347250.2
ARTICLE 3. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of ____________________________________________________________ Dollars ($_________________________________). Payment shall be made as set forth in the General Conditions.

CONTRACT
19 SDPUB\SAKINS\347250.2
ARTICLE 4. PAYMENTS

4.1 The City shall make progress payments following receipt of undisputed and properly submitted payment requests. Contractor shall be paid a sum equal to ninety-five percent (95%) of the value of Work performed up to the last day of the previous month, less the aggregate of previous payments.

4.2 The Contractor shall, after the full completion of The Work, submit a final payment application. All prior progress estimates shall be subject to corr ection in the final estimate and payment.

4.3 Unless otherwise required by law, the final payment of ten percent (10%) of the value of the Work, if unencumbered, shall be paid no later than sixty (60) Days after the date of recordation of the Notice of Completion.

4.4 Acceptance by Contractor of the final payment shall constitute a waiver of all claims against the City arising from this Contract.

4.5 Payments to the Contractor shall not be construed to be an acceptance of any defective work or improper materials, or to relieve the Contractor of its obligations under the Contract Documents.

4.6 The Contractor shall submit with each payment request the Contractor’s conditional waiver of lien for the entire amount covered by such payment request, as well as a valid unconditional waiver of lien from the Contractor and all subcontractors and materialmen for all work and materials included in any prior invoices. Waivers of lien shall be in the forms prescribed by California Civil Code Section 3262. Prior to final payment by the City, the Contractor shall submit a final waiver of lien for the Contractor’s work, together with releases of lien from any subcontractor or materialmen.

ARTICLE 5. PAYMENTS WITHHELD AND BACKCHARGES In addition to amounts which the City may retain under other provisions of the Contract Documents the City may withhold payments due to Contractor as may be necessary to cover:
a. Stop Notice Claims.
b. Defective work not remedied.
c. Failure of Contractor to make proper payments to its subcontractors or suppliers. d. Completion of the Contract if there exists a reasonable doubt that the work can be completed for balance then unpaid.
e. Damage to another contractor or third party.
f. Amounts which may be due the City for claims against Contractor.

CONTRACT
20 SDPUB\SAKINS\347250.2
g. Failure of Contractor to keep the record (“as-built”) drawings up to date. h. Failure to provide updates on the construction schedule. i. Site clean up.
j. Failure of the Contractor to comply with requirements of the Contract Documents. k. Liquated damages.
l. Legally permitted penalties.

Upon completion of the Contract, the City will reduce the final Contract amount to reflect costs charged to the Contractor, backcharges or payments withheld pursuant to the Contract Documents.

ARTICLE 6. CHANGES AND EXTRA WORK

6.1 The City, without invalidating the Contract, may order changes in the Work consisting of additions, deletions or other revisions, the Contract amount and Contract time being adjusted accordingly. All such changes in the Work shall be authorized by Change Order, in the form attached hereto and incorporated herein as Exhibit “A,” and shall be performed under the applicable conditions of the Contract Documents. A Change Order signed by the Contractor indicates the Contractor's agreement therewith, including any adjustment in the Contract amount or the Contract time, and the full and final settlement of all costs (direct, indirect and overhead) related to the Work authorized by the Change Order.

6.2 All claims for additional compensation to the Contractor sha ll be presented in writing before the expense is incurred and will be adjusted as provided herein. No work shall be allowed to lag pending such adjustment, but shall be promptly executed as directed, even if a dispute arises. No claim will be considered after the work in question has been done unless a written contract change order has been issued or a timely written notice of claim has been made by Contractor.

Contractor shall not be entitled to claim or bring suit for damages, whether for loss of profits or otherwise, on account of any decrease or omission of any item or portion of Work to be done. Whenever any change is made as provided for herein, such change shall be considered and treated as though originally included in the Contract, and shall be subject to all terms, conditions and provisions of the original Contract.

6.3 Owner Initiated Change. The Contractor must submit a complete cost proposal, including any change in the Contract time, within seven (7) Days after receipt of a scope of a propo sed change order, unless the City requests that proposals be submitted in less than seven (7) Days.

CONTRACT
21 SDPUB\SAKINS\347250.2

6.4 Contractor Initiated Change. The Contractor must give written notice of a proposed change order required for compliance with the Contract Documents within seven (7) Days of discovery of the facts giving rise to the proposed change order.

6.5 Whenever possible, any changes to the Contract amount shall be in a lump sum mutually agreed to by the Contractor and the City.

6.6 Price quotations from the Contractor shall be accompanied by sufficiently detailed supporting documentation to permit verification by the City.

6.7 If the Contractor fails to submit the cost proposal within the seven (7) Day period (or as requested), the City has the right to order the Contractor in writing to commence the work immediately on a force account basis and/or issue a lump sum change to the contract price in accordance with the City’s estimate of cost. If the change is issued based on the City estimate, the Contractor will waive its right to dispute the action unless within fifteen (15) Days following completion of the added/deleted work, the Contractor presents written proof that the City’s estimate was in error.

6.8 Estimates for lump sum quotations and accounting for cost-plus-percentage work shall be limited to direct expenditures necessitated specifically by the subject extra work, and shall be segregated as follows:
(a) Labor. The costs of labor will be the actual cost for wages prevailing locally for each craft or type of worker at the time the extra work is done, plus employer payments of payroll taxes and insurance, health and welfare, pension, vacation, apprenticeship funds, and other direct costs resulting from Federal, State or local laws, as well as assessment or b enefits required by lawful collective bargaining agreements. The use of a labor classification which would increase the extra work cost will not be permitted unless the contractor establishes the necessity for such additional costs. Labor costs for equip ment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. (b) Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available in the quantities involved, plus sales tax, freight and delivery. Materials cost shall be based upon supplier or manufacturer’s invoice. If invoices or other satisfactory evidence of cost are not furnished within fifteen (15) Days of delivery, then the City shall determine the materials cost, at its sole discretion.
(c) Tool and Equipment Use. No payment will be made for the use of small tools, tools which have a replacement value of $1,000 or less. Regardless of ownership, the rates to be used in dete rmining equipment use costs shall not exceed listed rates prevailing locally at equipment rental agencies, or distributors, at the time the work is performed.

CONTRACT
22 SDPUB\SAKINS\347250.2
(d) Overhead, Profit and Other Charges. The mark-up for overhead (including supervision) and pro fit on work added to the Contract shall be according to the following:
i. “Net Cost” is defined as consisting of costs of labor, materials and tools and equipment only excluding overhead and profit. The costs of applicable insurance and bond premium will be reimbursed to the Contractor and subcontractors at cost only, without mark-up.
ii. For Work performed by the Contractor’s forces the added cost for overhead and profit shall not exceed fifteen (15%) percent of the Net Cost of the Work. iii. For Work per formed by a subcontractor, the added cost for overhead and profit shall not exceed fifteen (15%) percent of the Net Cost of the Work to which the Contractor may add five (5%) percent of the subcontractor’s Net Cost. iv. For Work performed by a sub-subcontractor the added cost for overhead and profit shall not exceed fifteen (15 %) percent of the Net Cost for Work to which the subcontractor and general contractor may each add an additional five (5 %) percent of the Net Cost of the lower tier subcontractor.
v. No additional mark up will be allowed for lower tier subcontractors, and in no case shall the added cost for overhead and profit payable by City exceed twenty -five (25%) percent of the Net Cost as defined herein.

6.9 For added or deducted Work by subcontractors, the Contractor shall furnish to the City the subcontractor’s signed detailed estimate of the cost of labor, material and equipment, including the subcontractor markup for overhead and profit. The same requirement shall apply to sub-subcontractors.

6.10 For added or deducted work furnished by a vendor or supplier, the Contractor shall furnish to the City a detailed estimate or quotation of the cost to the Contractor, signed by such vendor or supplier.

6.11 Any change in The Work involving both additions and deletions shall indicate a net total cost, including subcontracts and materials. Allowance for overhead and profit, as specified herein, shall be applied if the net total cost is an extra; overhead and profit allowances shall not be applied if t he net total cost is a credit. The estimated cost of deductions shall be based on labor and material prices on the date the Contract was executed.

6.12 Contractor shall not reserve a right to assert impact costs, extended job site costs, extended overhead, constructive acceleration and/or actual acceleration beyond what is stated in the change order for work. No claims shall be allowed for impact, extended overhead costs, constructive acceleration and/or actual acceleration due to a multiplicity

CONTRACT
23 SDPUB\SAKINS\347250.2
of changes and/or clarifications. The Contractor may not change or modify the City’s change order form in an attempt to reserve additional rights.

6.13 If the City disagrees with the proposal submitted by Contractor, it will notify the Contractor and the City will provide its opinion of the appropriate price and/or time extension. If the Contractor agrees with the City, a change order will be issued by the City. If no agreement can be reached, the City shall have the right to issue a unilateral change order setting forth its determination of the reasonable additions or savings in costs and time attributable to the extra or deleted work. Such determination shall become final and binding if the Contractor fails to submit a claim in writing to the City within fifteen (15) Days of the issuance of the unilateral change order, disputing the terms of the unilateral change order.

6.14 No dispute, disagreement or failure of the parties to reach agreement on the terms of the change order shall relieve the Contractor from the obligation to proceed with performance of the work, including extra work, promptly and expeditiously.

6.15 Any alterations, extensions of time, extra work or any other changes may be made without securing consent of the Contractor’s surety or sureties.

ARTICLE 7. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is agreed that the Contractor will pay the City the sum of $1,500.00 for each and every calendar day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the Contractor agrees the City may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article does not exclude recovery of other damages specified in the Contract Documents.

ARTICLE 8. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the following:

Notice Inviting Bids
Instructions to Bidders
Contractor's Bid Forms
Contractor’s Certificate Regarding Workers’ Compensation Designation of Subcontractors
Information Required of Bidders
Non-Collusion Declaration form
Contract
Payment (Labor and Materials) Bond
General Conditions
California Building Codes as defined in the General Conditions Addenda
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract

CONTRACT
24 SDPUB\SAKINS\347250.2
The Contactor shall complete the Work in strict accordance with all of the Contract Documents.

All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.

ARTICLE 9. PROVISIONS REQUIRED BY LAW. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, includi ng, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Project.

ARTICLE 10. INDEMNIFICATION.

10.1 To the fullest extent permitted by law, the Contractor shall defend, indem nify and hold harmless the City and their respective officials, officers, agents, employees, and representatives (“indemnitees”) from any and all claims, demands, causes of action, costs, expenses, liabilities, losses, damages (including without limitation the payment of all consequential damages and attorneys fees and other related costs and expenses) or injuries, in law or equity, regardless of whether the allegations are false, fraudulent, or groundless, to tangible property or persons (including wrongful death) arising out of or resulting from the performance of the Work or this Agreement (including claims made by subcontractors for nonpayment), to the extent that the acts, omissions or willful misconduct are attributable to the Contractor or anyone employed directly or indirectly by any of them. Contractor shall defend, at Contractor’s own cost, expense and risk, with legal counsel of indemnitee’s choosing, any and all such aforesaid suits, actions or other legal proceedings of every kind that may be brought or institu ted against the City and their respective officials, officers, agents, employees and representatives. To the extent of its liability, Contractor shall pay and satisfy any judgment, award or decree that may be rendered against the City and their respective officials, officers, agents, employees, and representatives, in any such suit, action or other legal proceeding. Contractor shall reimburse the City and their respective officials, officers, agents, employees, and representatives for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. The only limitations on this provision shall be those imposed by Civil Code Section 2782.

10.2 Nothing contained in the preceding section shal l be deemed to obligate the Contractor to indemnify the City or any of the other indemnitees, against liability for damages or any other loss, damage or expense sustained, suffered or incurred on account of death or bodily injury to active persons or injury to property caused by the sole negligence or willful misconduct of the City or any of the other indemnitees set forth above. Therefore, if it is determined by legal proceedings or agreement, that the Contractor has no direct contributory or incidental negligence

CONTRACT
25 SDPUB\SAKINS\347250.2
or other obligation to the City or the other indemnitees, and the Contractor is in no way a proper party to a particular claim, then the Contractor shall not be obligated to hold the City or any indemnitees harmless with respect to said claim. However, until such determination is made by legal proceedings or agreement, or if the Contractor is found to have any degree of direct or contributory negligence or if it is determined that the Contractor is in any way or to any degree a proper party to said claim, then the Contractor’s obligations under all of the terms and provisions of the preceding section shall remain in full force and effect.

10.3 Nothing in this provision, or elsewhere in the Contract Documents, shall be deemed to relieve the Contractor of its duty to defend the City or any indemnitee, as specified under this Article, pending a determination of the respective liabilities of the City or any indemnitee, by legal proceeding or agreement.

10.4 In furtherance to, but not in limitation of the indemnity provisions in this Agreement, Contractor hereby expressly and specifically agrees that its obligation to indemnify, defend and hold harmless as provided in this Agreement shall not in any way be affected or diminished by any sta tutory or constitutional immunity it enjoys from suits by its own employees or from limitations of liability or recovery under workers’ compensation laws.

ARTICLE 11. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in accordance wit h the Labor Code which such rates shall be made available online at http//www.dir.ca.gov/dlsr and which must be posted at the job site.

CONTRACT
26 SDPUB\SAKINS\347250.2
IN WITNESS WHEREOF, this Contract has been duly executed by the above - named parties, on the day and year above written.

CITY OF FONTANA
By:

City Manager
[INSERT CONTRACTOR'S NAME]
By:
[INSERT NAME]
[INSERT TITLE]
Attest:

By:

City Clerk
Attest: 1
By:
[INSERT NAME]
[INSERT TITLE]
Approved as to form:

Best Best & Krieger LLP
City Attorney

By: _____________________________
Department Head

IN COMPLIANCE WITH CONTRACT INSURANCE REQUIREMENTS
By: _____________________________
Director of Human Resources/
Risk Management

IN COMPLIANCE WITH PURCHASING AND CONTRACT ADMINISTRATION POLICIES/PROCEDURES

Chief Financial Officer

Purchasing Office

1 Attestation of Contractor’s signature must be obtained when required by the by -laws, articles of incorporation or other laws, rules or regulations applicable to Contractor’s business entity.

EXHIBIT “A” - CHANGE ORDER FORM
27 SDPUB\SAKINS\347254.2
EXHIBIT “A” CHANGE ORDER FORM

TRACKING INFORMATION
Bid/Contract Number: Change Order Number:

Project Description:

Contractor: PO Number:

For Housing Authority Only
Property Address:

Owner Name:

CONTRACT INFORMATION

Original Contract Amount Original Completion Time
$

Cumulative Contract Amount Cumulative Completion Time $

Current Change Amount (+/-): Current Days (+/-)
$

New Contract Amount New Completion Time
$

Total % Over Contract:

INITIATING PARTY (Party responsible for initiating the change order request) City Initiated Contractor Initiated

Change in Scope Unforeseen Conditions Balancing

EXHIBIT “A” - CHANGE ORDER FORM
28 SDPUB\SAKINS\347250.2

CONTRACT CHANGE ORDER FORM

REASON(S) FOR THE CHANGE ORDER
ADJUSTMENT JUSTIFICATION: Attach complete itemized cost breakdown of all labor and material showing actual quantities, hours, unit prices, wage rates, required for the change, and the effect upon the time for performance of the work of such change order. Contractor’s form may be attached) Detailed Justification (Required):

Execution of this change order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in Contract, law or equity, arising out of or related to the subject of the change order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages.

Contractor: ___________________________________ Date: ____________

CITY OF FONTANA:

Project Manager: ______________________________ Date: ____________

Engineering Manager: __________________________ Date: ____________

Department Head: _____________________________ Date: ____________ (Required $25,000 and less)

Deputy City Manager: __________________________ Date: ____________ (Required $50,000 and less)

City Manager: ________________________________ Date: ____________ (Required Over $50,000)

Review of Analysis:

Purchasing Office: ____________________________ Date: ____________

Finance Department: ___________________________ Date: ____________ Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-29-

GENERAL CONDITIONS

ARTICLE 1. DEFINITIONS
a. Acceptable, Acceptance or words of similar import shall be understood to be the acceptance of the City.
b. Act of God an Act of God is an earthquake of magnitude 3.5 on the Richter scale and tidal waves.
c. Approval means written authorization by the City.
d. California Building Codes shall mean the following, as such may be modified by the City of Fontana Municipal Code:
2022 California Building Code
2022 California Electrical Code
2022 California Plumbing Code
2022 California Mechanical Code
e. Contract Documents includes all documents as stated in the Contract. f. City and Contractor are those stated in the Contract. The terms City and Owner may be used interchangeably.
g. Day shall mean calendar day unless otherwise specifically designated. h. Engineer shall mean the General Manager, or his or her designee, for the City of Fontana, acting either directly or through properly authorized agents, such as agents acting within the scope of the particular duties entrusted to them. Also sometimes referred to as the “City’s Representative” or “Representative” in the Contract Documents. i. Equal, Equivalent, Satisfactory, Directed, Designated, Selected, As Required and similar words shall mean the written approval, selection, satisfaction, direction, or similar action of the Engineer and/or City.
j. Force Majeure shall mean (i) riots, civil disturbances, insurrection or acts of public enemy, but only occurring at or in the immediate vicinity of the Site or if directly disrupting or delaying the supply chain of materials to the Project; (ii) war if declared by the United States Congress but only if directly disrupting or delaying the supply chain of labor or materials to the Project; (iii) a court administrative or other governmental order directing that the construction of the Project be stopped (except where due to failure to obtain or comply with any authorizations of governmental authorities; (iv) strikes or labor disputes, but only if directly disrupting or delaying the supply chain of labor or materials to the Project and only if not precipitated by Contractor's or a Subcontractor's actual violation of the Union Requirement; (v) casualty at the Site resulting in direct physical damage to the Work not the result, in whole or in part, of the actions or omissions of Contractor or Subcontractors; (vi) acts of terrorism directed at Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-30-

the Project or resulting in direct physical damage to the Project or directly disrupting or delaying the supply chain of labor or materials to the Project; (vii) Delays caused, other than by Contractor's negligence or breach of the Contract Documents, by conflicts in the coordination of Contractor's Work with the work of other contractors; (viii) delay in the issuance of permits or approvals by governmental authorities to the extent caused solely by circumstances within the control and responsibility of City; or (viii) Acts of God. k. Indicated, Shown, Detailed, Noted, Scheduled or words of similar meaning shall mean that reference is made to the drawings, unless otherwise noted. It shall be understood that the direction, designation, selection, or similar import of the Engineer and/or City is intended, unless stated otherwise.
l. Install means the complete installation of any item, equipment or material. m. Material shall include machinery, equipment, manufactured articles, or construction such as form work, fasteners, etc., and any other classes of material to be furnished in connection with the Contract. All materials shall be new unless specified otherwise. n. Perform shall mean that the Contractor, at Contractor’s expense, shall take all actions necessary to complete The Work, including furnishing of necessary labor, tools, and equipment, and providing and installing Materials that are indicated, specified, or required to complete such performance.
o. Project is The Work planned by City as provided in the Contract Documents. p. Provide shall include provide complete in place, that is furnish, install, test and make ready for use.
q. Recyclable Waste Materials shall mean materials removed from the Project site which are required to be diverted to a recycling center rather than an area landfill. Recyclable Waste Materials include asphalt, concrete, brick, concrete block, and rock. r. Specifications means that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards and workmanship for the work. The Work shall be done in accordance with the California Building Codes, as defined herein, including all current supplements, Addenda, and revisions thereof which are incorporated herein. In any conflict the contract documents will be interpreted as set forth below. s. The Work means the entire improvement planned by the City pursuant to the Contract Documents.
t. Work means labor, equipment and materials incorporated in, or to be incorporated in the construction covered by the Contract Documents.

ARTICLE 2. CONTRACT DOCUMENTS
a. Contract Documents. The Contract Documents are complementary, and what is called for by one shall be as binding as if called for by all. b. Interpretations. The Contract Documents are intended to be fully cooperative and to be complementary. If Contractor observes that any documents are in conflict, the Contractor shall Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-31-

promptly notify the Purchasing in writing. In case of conflicts between the Contract Documents, the order of precedence shall be as follows:

1. Change Orders or Work Change Directives

2. Addenda

3. Contract

4. General Conditions

5. Instructions to Bidders

6. Notice Inviting Bids

7. Contractor’s Bid Forms

8. California Building Codes

9. Reference Documents

c. Conflicts in Contract Documents. Notwithstanding the orders of precedence established above, in the event of conflicts, the more stringent requirement and higher standard shall always apply.
d. Organization of Contract Documents. Organization of the Contract Documents into divisions, sections, and articles, and arrangement of drawings shall not control the Contractor in dividing The Work among subcontractors or in establishing the extent of Work to be performed by any trade.

ARTICLE 3. DETAIL DRAWINGS AND INSTRUCTIONS
a. Examination of Contract Documents. Before commencing any portion of The Work, Contractor shall again carefully examine all applicable Contract Documents, the Project site and other information given to Contractor as to materials and methods of construction and other Project requirements. Contractor shall immediately notify the Engineer of any potential error, inconsistency, ambiguity, conflict or lack of detail or explanation. If Contractor performs, permits, or causes the performance of any Work which is in error, inconsistent or ambiguous, or not sufficiently detailed or explained, Contractor shall bear any and all resulting costs, including, without limitation, the cost of correction. In no case shall the Contractor or any subcontractor proceed with Work if uncertain as to the applicable requirements. b. Additional Instructions. After notification of any error, inconsistency, ambiguity, conflict or lack of detail or explanation, the Engineer will provide any required additional instructions, by means of drawings or other written direction, necessary for proper execution of Work within a reasonable time from the receipt of such notification.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-32-

c. Quality of Parts, Construction and Finish. All parts of The Work shall be of the best quality of their respective kinds and the Contractor must use all diligence to inform itself fully as to the required construction and finish. In no case shall Contractor proceed with The Work without obtaining first from the Engineer such Approval may be necessary for the proper performance of Work.
d. Contractor’s Variation from Contract Document Requirements. If it is found that the Contractor has varied from the requirements of the Contract Documents including the requirement to comply with all applicable laws, ordinances, rules and regulations, the Engineer may at any time, before or after completion of the Work, order the improper Work removed, remade or replaced by the Contractor at the Contractor’s expense.

ARTICLE 4. SUBSTITUTIONS
a. Pursuant to Public Contract Code Section 3400(b) the City may make a finding that is described in the invitation for Bids that designates certain products, things, or services by specific brand or trade name.
b. Unless specifically designated in the Contract Documents, whenever any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such Specifications shall be deemed to be used for the purpose of facilitating the description of the material, process or article desired and shall be deemed to be followed by the words “or equal.” Contractor may, unless otherwise stated, offer for substitution any material, process or article which shall be substantially equal or better in every respect to that so indicated or specified in the Contract Documents. However, the City may have adopted certain uniform standards for certain materials, processes and articles. c. Contractor shall submit requests, together with substantiating data, for substitution of any “or equal” material, process or article no later than thirty-five (35) days after award of the Contract. To facilitate the construction schedule and sequencing, some requests may need to be submitted before thirty-five (35) days after award of Contract. Provisions regarding submission of “or equal” requests shall not in any way authorize an extension of time for performance of this Contract. If a proposed “or equal” substitution request is rejected, Contractor shall be responsible for providing the specified material, process or article. The burden of proof as to the equality of any material, process or article shall rest with the Contractor. The City has the complete and sole discretion to determine if a material, process or article is an “or equal” material, process or article that may be substituted.
d. Data required to substantiate requests for substitutions of an “or equal” material, process or article data shall include a signed affidavit from the Contractor stating that, and describing how, the substituted “or equal” material, process or article is equivalent to that specified in every way except as listed on the affidavit. Substantiating data shall include any and all illustrations, specifications, and other relevant data including catalog information which describes the requested substituted “or equal” material, process or article, and substantiates that it is an “or equal” to the material, process or article. The substantiating data must also include information regarding the durability and lifecycle cost of the requested substituted “or equal” material, process or article. Failure to submit all the required substantiating data, including the signed affidavit, to the City in a timely fashion will result in the rejection of the proposed substitution.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-33-

e. The Contractor shall be responsible for and shall, therefore, bear all costs related to a substituted “or equal” material, process or article for those substitution requests submitted to the Engineer following Contract award if the timelines set forth herein permit the submission of substitution requests after Contract award. Such substitution request costs may include City staff time, independent consultants, any tests or inspections made necessary by the substitution request, in the sole discretion of the City, and the increased cost, if any, of the proposed “or equal” material. If the timeline set forth herein, permits a substitution request to be made prior to Contract award, the City, in its sole discretion, may require the Bidder to submit a deposit or payment for the estimated reasonable costs which may be incurred by the City staff and independent consultants in evaluating the substitution request, as a condition of reviewing the substitution request.
f. Contractor is directed to the Special Conditions (if any) to review any findings made pursuant to Public Contract Code section 3400.

ARTICLE 5. MATERIALS
a. Except as otherwise specifically stated in the Contract Documents, Contractor shall provide and pay for all materials, labor, tools, equipment, water, lights, power, transportation, superintendence, temporary constructions of every nature, and all other services and facilities of every nature whatsoever necessary to execute and complete this Contract within specified time. b. Unless otherwise specified, all materials shall be new and the best of their respective kinds and grades as noted and/or specified, and workmanship shall be of good quality. c. Materials shall be furnished in ample quantities and at such times as to ensure uninterrupted progress of The Work and shall be stored properly and protected as required by the Contract Documents. Contractor shall be entirely responsible for damage or loss by weather or other causes to materials or Work.
d. No materials, supplies, or equipment for Work under this Contract shall be purchased subject to any chattel mortgage or under a conditional sale or other agreement by which an interest therein or in any part thereof is retained by the seller or supplier. Contractor warrants good title to all material, supplies, and equipment installed or incorporated in the work and agrees upon completion of all work to deliver the Project, to the City free from any claims, liens, or charges.
e. Materials shall be stored on the Project site in such manner so as not to interfere with any operations of the City or any independent contractor.

ARTICLE 6. CONTRACTOR’S SUPERVISION
Contractor shall continuously keep at the Project site, a competent and experienced full-time Project superintendent approved by the City. Superintendent must be able to proficiently speak, read and write in English. Any change in Project Superintendent must be approved in writing by the City prior to personnel being changed. Contractor shall continuously provide efficient supervision of the Project.

ARTICLE 7. WORKERS
Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-34-

a. Contractor shall at all times enforce strict discipline and good order among its employees.

Contractor shall not employ on the Project any unfit person or any one not skilled in the Work assigned to him or her.
b. Any person in the employ of the Contractor whom the City may deem incompetent or unfit shall be dismissed from The Work and shall not be employed on this Project except with the written Approval of the City.

ARTICLE 8. SUBCONTRACTORS
a. Contractor agrees to bind every subcontractor to the terms of the Contract Documents as far as such terms are applicable to subcontractor’s portion of The Work. Contractor shall be as fully responsible to the City for the acts and omissions of its subcontractors and of persons either directly or indirectly employed by its subcontractors, as Contractor is for acts and omissions of persons directly employed by Contractor. Nothing contained in these Contract Documents shall create any contractual relationship between any subcontractor and the City. b. The City reserves the right to Approve all subcontractors. The City’s Approval of any subcontractor under this Contract shall not in any way relieve Contractor of its obligations in the Contract Documents.
c. Prior to substituting any subcontractor listed in the Bid Forms, Contractor must comply with the requirements of the Subletting and Subcontracting Fair Practices Act pursuant to California Public Contract Code section 4100 et seq.

ARTICLE 9. PERMITS AND LICENSES
Permits and licenses necessary for prosecution of The Work shall be secured and paid for by Contractor, unless otherwise specified in the Contract Documents. a. Contractor shall obtain and pay for all other permits and licenses required for The Work, including excavation permit and for plumbing, mechanical and electrical work and for operations in or over public streets or right of way under jurisdiction of public agencies other than the City. b. The Contractor shall arrange and pay for all off-site inspection of the Work related to permits and licenses, including certification, required by the specifications, drawings, or by governing authorities, except for such off-site inspections delineated as the City's responsibility pursuant to the Contract Documents.
c. Before Acceptance of the Project, the Contractor shall submit all licenses, permits, certificates of inspection and required approvals to the City.

ARTICLE 10. DIVERSION OF RECYCLABLE WASTE MATERIALS
In compliance with the applicable City’s waste reduction and recycling efforts, Contractor shall divert all Recyclable Waste Materials to appropriate recycling centers. Contractor will be required to submit weight tickets and written proof of diversion with its monthly progress payment requests. Contractor shall complete and execute any certification forms required by City or other applicable agencies to document Contractor’s compliance with these diversion requirements. All costs incurred for these waste diversion efforts shall be the responsibility of the Contractor.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-35-

ARTICLE 11. REMOVAL OF HAZARDOUS MATERIALS
Should Contractor encounter material reasonably believed to be polychlorinated biphenyl (PCB) or other toxic wastes and hazardous materials which have not been rendered harmless at the Project site, the Contractor shall immediately stop work at the affected Project site and shall report the condition to the City in writing. The City shall contract for any services required to directly remove and/or abate PCBs and other toxic wastes and hazardous materials, if required by the Project site(s), and shall not require the Contractor to subcontract for such services. The Work in the affected area shall not thereafter be resumed except by written agreement of the City and Contractor.

ARTICLE 12. SANITARY FACILITIES
Contractor shall provide sanitary temporary toilet buildings for the use of all workers. All toilets shall comply with local codes and ordinances. Toilets shall be kept supplied with toilet paper and shall have workable door fasteners. Toilets shall be serviced no less than once weekly and shall be present in a quantity of not less than 1 per 20 workers as required by CAL-OSHA regulation. The toilets shall be maintained in a sanitary condition at all times. Use of toilet facilities in The Work under construction shall not be permitted. Any other Sanitary Facilities required by CAL-OSHA shall be the responsibility of the Contractor.

ARTICLE 13. AIR POLLUTION CONTROL
Contractor shall comply with all air pollution control rules, regulations, ordinances and statutes.

All containers of paint, thinner, curing compound, solvent or liquid asphalt shall be labeled to indicate that the contents fully comply with the applicable material requirements.

ARTICLE 14. FIRE PROTECTION
a. Contractor is responsible for providing and maintaining fire extinguishers, fire protection, fire watch and other necessary fire protection devices as may be required by the applicable regulatory agencies, the Contract Documents, and/or the City.

b. Contractor shall provide fire watch and be responsible for all fire prevention in connection with The Work. Open fires will not be permitted on or about the Project site.

c. The Contractor shall make chemical fire extinguishers available at the location where the Contractor performs any torch cutting or welding operations. Contractor shall provide the E ngineer with notice prior to undertaking any torch cutting and welding operations. Contractor, if performing cutting or welding operations, shall undertake all appropriate safety measures including but not limited to a fire watch, fire extinguishers, fire blankets and shall be responsible for any damage caused by its operations.

ARTICLE 15. CLEANING UP
a. Contractor at all times shall keep premises free from debris such as waste, rubbish, and excess materials and equipment. Contractor shall not store debris under, in, or about the premises. Upon completion of Work, Contractor shall clean the interior and exterior Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-36-

of the building or improvement including fixtures, equipment, walls, floors, ceilings, roofs, window sills and ledges, horizontal projections, and any areas where debris has collected so surfaces are free from foreign material or discoloration. Contractor shall clean and polish all glass, plumbing fixtures, and finish hardware and similar finish surfaces and equipment. Contractor shall also clean all bui ldings, asphalt and concrete areas to the degree necessary to remove oil, grease, fuel, or other stains caused by Contractor operations or equipment.

b. Contractor shall fully clean up those areas of the Site where it has been working at the completion of the Work. If the Contractor fails to immediately clean up as required, the City may do so and the cost of such clean up shall be charged back to the Contractor.

c. Contractor is responsible for its own bulk trash (e.g., boxes, crates, lumber, etc.) removal from the Project Site. Contractor is responsible for the cost of dumpsters generated by its own rubbish and surplus material. The placement of Contractor’s dumpster(s) shall be coordinated with, and subject to approval of, the Engineer prior to delivery. The disposal of construction debris within the Project Site will not be permitted.

d. Contractor shall store volatile or hazardous waste materials in properly labeled, covered containers and remove from the Project Site daily. Contractor shall also prevent accumulation of wastes that create hazardous conditions and provide adequate ventilation during use of volatile or noxious substances.

e. Contractor shall provide cleaning materials only as recommended by manufacturer of the surface to be cleaned and shall use cleaning materials only on surfaces as recommended by cleaning material manufacturer and in accordance with instructions.

f. Contractor shall conduct cleaning and disposal operations in accordance with all applicable legal requirements and shall not burn or bury rubbish and waste materials on the Project Site. Contractor shall not dispose of any wastes including mineral spirits, oil, paint, drywall mud, paint thinners, or grout in storm or sanitary drains.

g. Contractor shall be respons ible for cleaning up during and after installation of its materials and shall leave areas broom clean or better. Contractor’s Work, lunch, and parking areas will be left neat and in an orderly manner on a daily basis. After every work shift, facilities must be cleaned in a manner acceptable to the Engineer.

h. Contractor shall, within twenty -four (24) hours from the request of the Engineer, remove excess debris from the Work and/or Project site or Engineer shall undertake such removal work at the expense of the Contractor.

ARTICLE 16. EXCESSIVE NOISE
Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-37-

a. The Contractor shall use only such equipment on the work and in such state of repair so that the emission of sound therefrom is within the noise tolerance level of that equipment as established by CAL-OSHA.
b. The Contractor shall comply with the most res trictive of the following: (1) local sound control and noise level rules, regulations and ordinances and (2) the requirements contained in these Contract Documents, including hours of operation requirements. No internal combustion engine shall be operated on the Project without a muffler of the type recommended by the manufacturer. Should any muffler or other control device sustain damage or be determined to be ineffective or defective, the Contractor shall promptly remove the equipment and shall not return said equipment to the job until the device is repaired or replaced. Said noise and vibration level requirements shall apply to all equipment on the job or related to the job, including but not limited to, trucks, transit mixers or transit equipment that may or may not be owned by the Contractor.

ARTICLE 17. PROTECTION OF WORK AND PROPERTY
a. The Contractor shall be responsible for all damages to persons or property that occurs as a result of The Work. Contractor shall be responsible for the proper care and protection of all materials delivered and Work performed until completion and final Acceptance by the City. All Work shall be solely at the Contractor’s risk.

Contractor shall adequately protect adjacent property from settlement or loss of lateral support as nece ssary. Contractor shall comply with all applicable safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the Project site where Work is being performed. Contractor shall erect and properly maintain at all times, as required by field conditions and progress of work, all necessary safeguards, signs, barriers, lights, and watchmen for protection of workers and the public, and shall post danger signs warning against hazards created in the course of construction.
b. In an emergency affecting safety of life or of work or of adjoining property, Contractor, without special instruction or authorization from the Engineer, is hereby permitted to act to prevent such threatened loss or injury; and Contractor shall so act, without appeal, if so authorized or instructed by the Engineer or the City. Any compensation claimed by Contractor on account of emergency work shall be determined by and agreed upon by the City and the Contractor. c. Contractor shall provide such heat, covering, and enclosures as are necessary to protect all Work, materials, equipment, appliances, and tools against damage by weather conditions.
d. Contractor shall take adequate precautions to protect existing sidewalks, curbs, pavements, utilities, and other a djoining property and structures, and to avoid Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-38-

damage thereto, and Contractor shall repair any damage thereto caused by The Work operations. Contractor shall:
1) Enclose the working area with a substantial barricade, and arrange work to cause minimum amount of inconvenience and danger to the public. 2) Provide substantial barricades around any shrubs or trees indicated to be preserved.
3) Deliver materials to the Project site over a route designated by the Engineer. 4) Provide any and all dust control required and follow the Applicable air quality regulations as appropriate. If the Contractor does not comply, the City shall have the immediate authority to provide dust control and deduct the cost from payments to the Contractor.
5) Confine Contractor’s appa ratus, the storage of materials, and the operations of its workers to limits required by law, ordinances, permits, or directions of the Engineer. Contractor shall not unreasonably encumber the Project site with its materials.
6) Take care to prevent dis turbing or covering any survey markers, monuments, or other devices marking property boundaries or corners. If such markers are disturbed by accident, they shall be replaced by an approved civil engineer or land surveyor, at no cost to the City. 7) Ensure that existing facilities, fences and other structures are all adequately protected and that, upon completion of all Work, all facilities that may have been damaged are restored to a condition acceptable to the City. 8) Preserve and protect from injury all buildings, pole lines and all direction, warning and mileage signs that have been placed within the right-of-way. 9) At the completion of work each day, leave the Project site in a clean, safe condition.
10) Comply with any stage construction and traffi c handling plans. Access to residences and businesses shall be maintained at all times.

These precautionary measures will apply continuously and not be limited to normal working hours. Full compensation for the Work involved in the preservation of life, safety and property as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made therefor. e. Should damage to persons or property occur as a result of The Work, Co ntractor shall be responsible for proper investigation, documentation, including video or Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-39-

photography, to adequately memorialize and make a record of what transpired.

The City shall be entitled to inspect and copy any such documentation, video, or photographs.

ARTICLE 18. CONTRACTORS MEANS AND METHODS
Contractor is solely responsible for the means and methods utilized to Perform The Work. In no case shall the Contractor’s means and methods deviate from commonly used industry standards.

ARTICLE 19. AUTHORIZED REPRESENTATIVES
The City shall designate representatives, who shall have the right to be present at the Project site at all times. The City may designate an inspector who shall have the right to observe all of the Contractor’s Work. The inspector is not authorized to make changes in the Contract Documents.

The inspector shall not be responsible for the Contractor’s failure to carry out The Work in accordance with the Contract Documents. Contractor shall provide safe and proper facilities for such access.

ARTICLE 20. HOURS OF WORK
a. Eight (8) hours of work shall constitute a legal day’s work. The Contractor and each subcontractor shall forfeit, as penalty to the City, twenty-five dollars ($25) for each worker employed in the execution of Work by the Contractor or any subcontractor for each day during which such worker is required or permitted to work more than eight (8) hours in any one day and forty (40) hours in any week in violation of the provisions of the Labor Code, and in particular, Section 1810 to Section 1815, except as provided in Labor Code Section 1815. b. Work shall be accomplished on a regularly scheduled eight (8) hour per day work shift basis, Monday through Friday, between the hours of 7:00 a.m. and 5:00 p.m. c. It shall be unlawful for any person to operate, permit, use, or cause to operate any of the following at the Project site, other than between the hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, with no Work allowed on City -observed holidays, unless otherwise Approved by the Engineer:
1) Powered Vehicles
2) Construction Equipment
3) Loading and Unloading Vehicles
4) Domestic Power Tool.

ARTICLE 21. PREVAILING RATES OF WAGES
Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-40-

This contract will be funded in whole or in part with federal housing and community development funds. The Federal Labor Standards Provisions, including prevailing wage requirements of the Davis-Bacon and Related Acts will be enforced. A copy of the Federal Wage Decision applicable to this project is included in the Bid Document.

This is project is a public work in the State of California, funded in whole or in part with public funds. Therefore, the higher of the two applicable prevailing wage rates, federal or state, will be enforced. The Contractor’s duty to pay State prevailing wages can be found under Labor Code Section 1770 et seq. Labor Code Sections 1775 and 1777.7 outline the penalties for failure to pay prevailing wages and to employ apprentices, including forfeitures and debarment. The State Wage Decision is on file at the City Clerk’s office, and is also available online at http://www.dir.ca.gov/dlsr/.

At the time of submitting a bid, the prime contractor and subcontractor shall possess a Class "B" contractor’s license or a Class “C” specialty license sufficient to perform the work.

ARTICLE 22. NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY Pursuant to Labor Code Section 1735 and other applicable provisions of law, the Contractor and its subcontractors shall not discriminate against any employee or applicant for employment because of race, color, religion, sex, national origin, age, political affiliation, marital status, or handicap on this Project. The Contractor will take affirmative action to insure that employees are treated during employment or training without regard to their race, color, religion, sex, national origin, age, political affiliation, marital status, or handicap.

ARTICLE 23. LABOR/EMPLOYMENT SAFETY
The Contractor shall maintain emergency first aid treatment for his employees which complies with the Federal Occupational Safety and Health Act of 1970 (29 U.S.C. § 651 et seq.), and California Code of Regulations, Title 8, Industrial Relations Division 1, Department of Industrial Relations, Chapter 4.

ARTICLE 24. WORKERS’ COMPENSATION INSURANCE
The Contractor shall Provide, during the life of this Contract, workers’ compensation insurance for all of the employees engaged in Work under this Contract, on or at the Project site, and, in case any of sublet Work, the Contractor shall require the subcontractor similarly to provide workers’ compensation insurance for all the latter’s employees as prescribed by State law. Any class of employee or employees not covered by a subcontractor’s insurance shall be covered by the Contractor’s insurance. In case any class of employees engaged in work under this Contract, on or at the Project site, is not protected under the Workers’ Compensation Statutes, the Contractor shall provide or shall cause a subcontractor to provide, adequate insurance coverage for the protection of such employees not otherwise protected. The Contractor is required to secure payment of compensation to his employees in accordance with the provisions of Section 3700 of the Labor Code. The Contractor shall file with the City certificates of his insurance protecting workers. Company or companies providing insurance coverage shall be acceptable to the City, if in the form and coverage as set forth in the Contract Documents.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-41-

ARTICLE 25. EMPLOYER’S LIABILITY INSURANCE
Contractor shall provide during the life of this Contract, Employer’s Liability Insurance, including Occupational Disease, in the amount of, at least, one million dollars ($1,000,000.00) per person per accident. Contractor shall provide City with a certificate of Employer’s Liability Insurance. Such insurance shall comply with the provisions of the Contract Documents. The policy shall be endorsed, if applicable, to provide a Borrowed Servant/Alternate Employer Endorsement and contain a Waiver of Subrogation in favor of the City.

ARTICLE 26. COMMERCIAL GENERAL LIABILITY INSURANCE
a. Contractor shall procure and maintain during the life of this Contract and for such other period as may be required herein, at its sole expense, Commercial General Liability insurance coverage, including but not limited to, premises liability, contractual liability, products/completed operations if applicable, personal and advertising injury – which may arise from or out of Contractor’s operations, use, and management of the Project site, or the performance of its obligations hereunder. Policy limits shall not be less than $1,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit. b. Such policy shall comply with all the requirements of this Article. The limits set forth herein shall apply separately to each insured against whom claims are made or suits are brought, except with respect to the limits of liability. Further the limits set forth herein shall not be construed to relieve the Contractor from liability in excess of such coverage, nor shall it limit Contractor’s indemnification obligations to the City, and shall not preclude the City from taking such other actions available to the City under other provisions of the Contract Documents or law. c. Contractor shall make certain that any and all subcontractors hired by Contractor are insured in accordance with this Contract. If any subcontractor’s coverage does not comply with the foregoing provisions, Contractor shall indemnify and hold the City harmless from any damage, loss, cost, or expense, including attorneys’ fees, incurred by the City as a result thereof.
d. All general liability policies provided pursuant to the provisions of this Article shall comply with the provisions of the Contract Documents.
e. All general liability policies shall be written to apply to all bodily injury, including death, property damage, personal injury, owned and non -owned eq uipment, blanket contractual liability, completed operations liability, explosion, collapse, under-ground excavation, removal of lateral support, and other covered loss, however occasioned, occurring during the policy term, and shall specifically insure the performance by Contractor of that part of the indemnification contained in these Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-42-

General Conditions, relating to liability for injury to or death of persons and damage to property. If the coverage contains one or more aggregate limits, a minimum of 50% of any such aggregate limit must remain available at all times; if over 50% of any aggregate limit has been paid or reserved, the City may require additional coverage to be purchased by Contractor to restore the required limits. Contractor may combine primary, umbrella, and as broad as possible excess liability coverage to achieve the total limits indicated above. Any umbrella or excess liability policy shall include the additional insured endorsement described in the Contract Documents.

ARTICLE 27. AUTOMOBILE LIABILITY INSURANCE
Contractor shall take out and maintain at all times during the term of this Contract Automobile Liability Insurance in the amount of, at least, one million dollars ($1,000,000). Such insurance shall provide coverage for bodily injury and property damage including coverage for non-owned and hired vehicles, in a form and with insurance companies acceptable to the City. Such insurance shall comply with the provisions of Article 30 below.

ARTICLE 28. FORM AND PROOF OF CARRIAGE OF INSURANCE
a. Any insurance c arrier providing insurance coverage required by the Contract Documents shall be admitted to and authorized to do business in the State of California unless waived, in writing, by the City Risk Manager. Carrier(s) shall have an A.M. Best rating of not less than an A:VIII. Insurance deductibles or self-insured retentions must be declared by the Contractor, and such deductibles and retentions shall have the prior written consent from the City. At the election of the City the Contractor shall either 1) reduc e or eliminate such deductibles or self - insured retentions, or 2) procure a bond which guarantees payment of losses and related investigations, claims administration, and defense costs and expenses. b. Contractor shall cause its insurance carrier(s) to f urnish the City with either 1) a properly executed original Certificates(s) of Insurance and certified original copies of Endorsements effecting coverage as required herein, or 2) if requested to do so in writing by the City Risk Manager, provide original Certified copies of policies including all Endorsements and all attachments thereto, showing such insurance is in full force and effect. The City, its Director’s and officers, employees, agents or representatives are named as Additional Insureds and Provi de a Waiver of Subrogation in favor of those parties. Further, said Certificates(s) and policies of insurance shall contain the covenant of the insurance carrier(s) that shall provide no less than thirty (30) days written notice be given to the City prior to any material modification or cancellation of such insurance. In the event of a material modification or cancellation of coverage, the City may terminate or Stop Work pursuant to the Contract Documents, unless the City receives, prior to such effective date, another properly executed original Certificate of Insurance and original copies of endorsements or certified original policies, including all endorsements and attachments thereto evidencing coverage’s set forth herein and Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-43-

the insurance required herein is in full force and effect. Contractor shall not take possession, or use the Project site, or commence operations under this Agreement until the City has been furnished original Certificate(s) of Insurance and certified original copies of Endorsements or policies of insurance including all Endorsements and any and all other attachments as required in this Section. The original Endorsements for each policy and the Certificate of Insurance shall be signed by an individual authorized by the insurance carrier to do so on its behalf. c. It is understood and agreed to by the parties hereto and the insurance company(s), that the Certificate(s) of Insurance and policies shall so covenant and shall be construed as primary, and the City’s insurance and/or deduct ibles and/or self - insured retentions or self-insured programs shall not be construed as contributory. d. The City reserves the right to adjust the monetary limits of insurance coverage’s during the term of this Contract including any extension thereof -if i n the City’s reasonable judgment, the amount or type of insurance carried by the Contractor becomes inadequate.
e. Contractor shall pass down the insurance obligations contained herein to all tiers of sub-contractors working under this Contract.

ARTICLE 29. TIME FOR COMPLETION AND LIQUIDATED DAMAGES
a. Time for Completion/Liquidated Damages. Work shall be commenced within ten (10) days of the date stated in the City’s Notice to Proceed and shall be completed by Contractor in the time specified in the Contract Document s. The City is under no obligation to consider early completion of the Project; and the Contract completion date shall not be amended by the City’s receipt or acceptance of the Contractor’s proposed earlier completion date. Furthermore, Contractor shall not, under any circumstances, receive additional compensation from the City (including but not limited to indirect, general, administrative or other forms of overhead costs) for the period between the time of earlier completion proposed by the Contractor and the Contract completion date. If The Work is not completed as stated in the Contract Documents, it is understood that the City will suffer damage. In accordance with Government Code section 53069.85, being impractical and infeasible to determine the amount of actual damage, it is agreed that Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum stipulated in the Contract for each day of delay until The Work is fully completed. Contractor and its surety shall be liable for any liquidated damages.

Any money due or to become due the Contractor may be retained to cover liquidated damages.
b. Inclement Weather. Contractor shall abide the Engineer’s determination of what constitutes inclement weather. Time extension s for inclement weather shall only Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-44-

be granted when the Work stopped during inclement weather is on the critical path of the Contractor Schedule.
c. Extension of Time. Contractor shall not be charged liquidated damages because of any delays in completion of The Work due to unforeseeable causes beyond the control and without the fault or negligence of Contractor (or its subcontractors or suppliers). Contractor shall within five (5) Days of identifying any such delay notify the City in writing of causes of delay. The City shall ascertain the facts and extent of delay and grant extension of time for completing The Work when, in its judgment, the facts justify such an extension. Time extensions to the Project shall be requested by the Contractor as they occur and without delay. No delay claims shall be permitted unless the event or occurrence delays the completion of the Project beyond the Contract completion date.
d. No Damages for Reasonable Delay. The City’s liability to Contractor for delays for which the City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall the City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs. Damages caused by unreasonable City delay, including delays caused by items that are the responsibility of the City pursuant to Government Code section 4215, shall be based on actual costs only, no proportions or formulas shall be used to calculate any delay damages.

ARTICLE 30. COST BREAKDOWN AND PERIODIC ESTIMATES
Contractor shall furnish on forms Approved by the City:
a. Within ten (10) Days of award of the Contract a detailed estimate giving a complete breakdown of the Contract price;
b. A itemized estimate of Work done for the purpose of making progress payments.

In order for the City to consider and evaluate each progress payment application, the Contractor shall submit a detailed measurement of Work performed and a progress estimate of the value.
c. Contractor shall submit, with each of its payment requests, an adjusted list of actual quantities, verified by the Project Manager, for unit price items listed, if any, in the Bid Form.
d. Following the City’s Acceptance of the Work, the Contractor shall submit to the City a written statement of the final quantities of unit price items for inclusion in the final payment request.
e. The City shall have the right to adjust any estimate of quantity and to subsequently correct any error made in any estimate for payment.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-45-

Contractor shall certify under penalty of perjury, that all cost breakdowns and periodic estimates accurately reflect the Work on the Project.

ARTICLE 31. CITY’S RIGHT TO TERMINATE CONTRACT
a. Termination for Cause: The City may, without prejudice to any other right or remedy, serve written notice upon Contractor of its intention to terminate this Contract if the Contractor:
(i) refuses or fails to prosecute The Work or any part thereof with such diligence as will ensure its completion within the time required; (ii) fails to complete The Work within the required time; (iii) should file a bankruptcy petition or be adjudged a bankrupt; (iv) should make a general assignment for the benefit of its creditors; (v) should have a receiver appointed; (vi) should persistently or repeatedly refuse or fail to supply enough properly skilled workers or proper materials to complete the work; (vii) should fail to make prompt payment to subcontractors or for material or labor; (viii) persistently disregard laws, ordinances, other requirements or instructions of the City; or (ix) should violate any of the provisions of the Contract Documents.

The notice of intent to terminate shall contain the reasons for such intention to terminate. Unless within ten (10) Days after the service of such notice, such condition shall cease or satisfactory arrangements (acceptable to the City) for the required correction are made, this Contract shall be terminated. In such case, Contractor shall not be entitled to receive any further payment until the Project has been finished. The City may take over and complete The Work by any method it may deem appropriate. Contractor and its surety shall be liable to the City for any excess costs or other damages incurred by the City to complete the Project. If the City takes over The Work, the City may, without liability for so doing, take possession of and utilize in completing The Work such materials, appliances, plant, and other property belonging to the Contractor as may be on the Project site.
b. Termination For Convenience: The City may terminate performance of The Work in whole or, in part, if the City determines that a termination is in the City's interest.

The Contractor shall terminate all or any part of The Work upon delivery to the Contractor of a Notice of Termination specifying that the termination is for the convenience of the City, the extent of termination, and the effective date of such termination.

After receipt of Notice of Termination, and except as directed by the City, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this Termination for Convenience clause, immediately proceed with the following obligations:
1) Stop Work as specified in the Notice.
2) Complete any Work specified in the Notice of Termination in a least cost/shortest time manner while still maintaining the quality called for under the Contract Documents.
3) Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the Contract Documents is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-46-

4) Terminate all subcontracts to the extent that th ey relate to the portions of The Work terminated.
5) Place no further subcontracts or orders, except as necessary to complete the remaining portion of The Work.
6) Submit to the City, within ten (10) Days from the effective date of the Notice of Terminatio n, all of the documentation called for by the Contract Documents to substantiate all costs incurred by the Contractor for labor, materials and equipment through the Effective Date of the Notice of Termination. Any documentation substantiating costs incurr ed by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the Contractor is authorized under the Contract Documents to incur, shall: (i) be submitted to and received by the C ity no later than thirty (30) Days after the Effective Date of the Notice of Termination; (ii) describe the costs incurred with particularity; and (iii) be conspicuously identified as "Termination Costs Occasioned by the City's Termination for Convenience."
7) These provisions are in addition to and not in limitation of any other rights or remedies available to the City.
c. Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease Work on the Project until such safety or liability issues are addressed to the satisfaction of the City or the Contract is terminated.

ARTICLE 32. WARRANTY AND GUARANTEE
a. Contractor warrants that all materials and equipment furnished under this Contract shall be new unless otherwise specified in the Contract Documents; and that all Work conforms to the Contract Document requirements and is free of any defect whether performed by the Contractor or any subcontractor or supplier.
b. Unless otherwise stated, all warranty periods shall begin upon the filing of the Notice of Completion. Unless otherwise stated, the warranty period shall be for one year. c. The Contractor shall remedy at its expense any damage to City-owned or controlled real or personal property.
d. Contractor shall furnish the City with all warranty and guarantee documents prior to final Acceptance of the Project by the City.
e. The City shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. The Contractor shall within ten (10) Days after being notified commence and perform with due diligence all necessary Work. If the Contractor fails to promptly remedy any defect, or damage; the county shall have the right to replace, repair, or otherwise remedy the defect, or damage at the Contractor’s expense.

Section 3 Clause
Federal Contract Provision
24 CFR Part 135

-47-

f. In the event of any emergency constituting an immediate hazard to health, safety, property, or licensees, when caused by Work of the Contractor not in accordance with the Contract requirements, the City may undertake at Contractor’s expense, and without prior notice, all Work necessary to correct such condition.
g. With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for Work performed and Materials furnished under this Contract, the Contractor shall:
1) Obtain for City all warranties that would be given in normal commercial practice;
2) Require all warranties to be executed, in writing, for the benefit of the City; and
3) Enforce all warranties for the benefit of the City, unless otherwise directed in writing by the City.

This Article shall not limit the City’s rights under this Contract or with respect to latent defects, gross mistakes, or fraud. The City specifically reserves all rights related to defective work, including but not limited to the defect claims pursuant to California Code of Civil Procedure Section 337.15.

ARTICLE 33. NOTICE AND SERVICE THEREOF
All notices shall be in writing and either served by personal delivery or mailed to the other party as designated in the Bid Forms. Written notice to the Contractor shall be addressed to Contractor’s principal place of business unless Contractor designates another address in writing for service of notice. Notice to City shall be addressed to the City as designated in the Notice Inviting Bids unless City designates another address in writing for service of notice. Notice shall be effective upon receipt or five (5) Days after being sent by first class mail, whichever is earlier.

Notice given by facsimile shall not be effective unless acknowledged in writing by the receiving party.

ARTICLE 34. INTEGRATION
a. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.
b. Contract Documents Represent Entire Contract. The Contract Documents represent the entire agreement of the City and Contract.