Nexus Project Cost 10,759,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $140,116.00
Fund Type: MSI Arterial $ 95,139.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 44,977.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - DEV FEE $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.

Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Widen Sierra Ave. from Summit
Ave. to I-15 (37603378)
Current Total Project Cost
Estimate:
$400,000.00
Total Measure I Request:
$95,139.00
(Summation of Measure I)
Comments:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 1
Nexus Project Cost 12,031,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - DEV FEE $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $1,326,367.00
Fund Type: MSI Arterial $ 900,603.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 425,764.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $16,046,098.00
Fund Type: MSI Arterial $ 10,895,300.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 5,150,798.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.

Comments:

Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Widen Sierra Ave from Foothill
Blvd to Baseline Ave. (37603281)
Current Total Project Cost
Estimate:
$21,343,063.00
Total Measure I Request:
$11,795,903.00
(Summation of Measure I)
FINAL of 2025-2029 New CPNA_.xlsx - Proj 2
Nexus Project Cost 13,826,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $413,614.00
Fund Type: MSI Arterial $ 280,844.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 132,770.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $1,430,000.00
Fund Type: MSI Arterial $ 970,970.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ 459,030.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - DEV FEE $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.

Comments:

Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Widen Foothill Blvd from Hemlock
to Almeria. (37603333)
Current Total Project Cost
Estimate:
$2,230,000.00
Total Measure I Request:
$1,251,814.00
(Summation of Measure I)
FINAL of 2025-2029 New CPNA_.xlsx - Proj 3
Nexus Project Cost 8,069,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $452,195.00
Fund Type: MSI Arterial $ 307,040.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 145,155.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $10,888,071.00
Fund Type: MSI Arterial $ 5,256,598.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 2,485,077.00 $ - $ - $ - $ - $ - $ - OTHER $ 3,146,396.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.
(Summation of Measure I)
Comments:
$13,147,629.00
Total Measure I Request:
$5,563,638.00
Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Widen Slover Ave. from Etiwanda
Ave to 800' e/o Etiwanda from 2
to 4 lanes(37603350)
Current Total Project Cost
Estimate:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 4
Nexus Project Cost 1,000,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $620,000.00
Fund Type: MSI Arterial $ 420,980.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 199,020.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - DEV FEE $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.
(Summation of Measure I)
Comments:
$620,000.00
Total Measure I Request:
$420,980.00
Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Citrus Ave. widening at SR -210
(37600039)
Current Total Project Cost
Estimate:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 5
Nexus Project Cost 4,707,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $1,918,800.00
Fund Type: MSI Arterial $ 1,302,865.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 615,935.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.
(Summation of Measure I)
Comments:

Total Project Cost is for both
Cherry Ave (Baseline Ave to So.

Highland Ave) and Walnut Ave (I-
15 to San Servaine).
$3,900,000.00
Total Measure I Request:
$1,302,865.00
Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Westgate (37600042). Widen
Cherry Ave (Baseline Ave to So.

Highland Ave 4 to 6 lanes).

Current Total Project Cost
Estimate:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 6
Nexus Project Cost 4,859,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $1,981,200.00
Fund Type: MSI Arterial $ 1,345,235.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 635,965.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.
(Summation of Measure I)
Comments:

Total Project Cost is for both
Cherry Ave (Baseline Ave to So.

Highland Ave) and Walnut Ave (I-
15 to San Servaine).
$3,900,000.00
Total Measure I Request:
$1,345,235.00
Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Westgate (37600042). Widen
Walnut Ave ( I-15 to San Sevaine
2 to 4 lanes.)
Current Total Project Cost
Estimate:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 7
Nexus Project Cost 107,590,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $100,000.00
Fund Type: MSI Arterial $ 67,900.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 32,100.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $770,000.00
Fund Type: MSI Arterial $ 522,830.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 247,170.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.
(Summation of Measure I)
Comments:
$870,000.00
Total Measure I Request:
$590,730.00
Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Intersection Widening at Santa
Ana Ave./Juniper Ave. Santa Ana
and Juniper Ave TS (37600054)
Current Total Project Cost
Estimate:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 8
Nexus Project Cost 9,708,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 67.9%
Dev. Share: 32.10%
Project Information Phase Funding PRIOR* FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FUTURE PA&ED
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $0.00
Fund Type: MSI Arterial $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $16,495,336.00
Fund Type: MSI Arterial $ 230,860.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 109,140.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 1,900,000.00 $ - $ - $ - $ - $ - $ - OTHER $ 8,116,715.00 $ - $ - $ - $ - $ - $ - OTHER $ 5,840,000.00 $ - $ - $ - $ - $ - $ - MI LOCAL ST $ 298,621.00 $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2023/2024 expenses.
(Summation of Measure I)
Comments:

This project is being funded by
multiple funding sources. Fund
622 - Strorm Drain Fund has
allocated $8,116,715 and Fund
302 -ARPA has allocated
$5,840,000 forths project.
$16,495,336.00
Total Measure I Request:
$230,860.00
Capital Project Needs Analysis
City of Fontana
Valley Arterial Sub-Program
Widen Foothill Blvd from Citrus
Ave to Maple Ave from 4 to 6
lanes. Cypress Strom Drain
(37603361)
Current Total Project Cost
Estimate:

FINAL of 2025-2029 New CPNA_.xlsx - Proj 9
Program Jurisdiction Public
Share Project Name Dev Loan? 5-Yr Advance NEXUS
Project Cost
Current Cost
Estimate
MI
Prior
MI
FY 24/25
MI
FY 25/26
MI
FY 26/27
MI
FY 27/28
MI
FY 28/29 MSI Future MI
Total
Proj 1 Valley Arterial Sub-Program City of Fontana 67.9% Widen Sierra Ave. No No 10,759,000$ 400,000$ 95,139$ -$ -$ -$ -$ -$ -$ 95,139$ Proj 2 Valley Arterial Sub-Program City of Fontana 67.9% Widen Sierra Ave f No No 12,031,000$ 21,343,063$ ########## -$ -$ -$ -$ -$ -$ ########## Proj 3 Valley Arterial Sub-Program City of Fontana 67.9% Widen Foothill Blvd No No 13,826,000$ 2,230,000$ 1,251,814$ -$ -$ -$ -$ -$ -$ 1,251,814$ Proj 4 Valley Arterial Sub-Program City of Fontana 67.9% Widen Slover Ave. No No 8,069,000$ 13,147,629$ 5,563,638$ -$ -$ -$ -$ -$ -$ 5,563,638$ Proj 5 Valley Arterial Sub-Program City of Fontana 67.9% Citrus Ave. widenin No No 1,000,000$ 620,000$ 420,980$ -$ -$ -$ -$ -$ -$ 420,980$ Proj 6 Valley Arterial Sub-Program City of Fontana 67.9% Westgate (3760004 No No 4,707,000$ 3,900,000$ 1,302,865$ -$ -$ -$ -$ -$ -$ 1,302,865$ Proj 7 Valley Arterial Sub-Program City of Fontana 67.9% Westgate (3760004 No No 4,859,000$ 3,900,000$ 1,345,235$ -$ -$ -$ -$ -$ -$ 1,345,235$ Proj 8 Valley Arterial Sub-Program City of Fontana 67.9% Intersection Widen No No 107,590,000$ 870,000$ 590,730$ -$ -$ -$ -$ -$ -$ 590,730$ Proj 9 Valley Arterial Sub-Program City of Fontana 67.9% Widen Foothill Blvd No No 9,708,000$ 16,495,336$ 230,860$ -$ -$ -$ -$ -$ -$ 230,860$ Proj 10 - Select Project Program - - Select Jurisdiction - 100.0% - Add Project Nam -Select Yes/No- -Select Yes/No- -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Proj 11 - Select Project Program - - Select Jurisdiction - 100.0% - Add Project Nam -Select Yes/No- -Select Yes/No- -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Proj 12 - Select Project Program - - Select Jurisdiction - 100.0% - Add Project Nam -Select Yes/No- -Select Yes/No- -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Proj 13 - Select Project Program - - Select Jurisdiction - 100.0% - Add Project Nam -Select Yes/No- -Select Yes/No- -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Proj 14 - Select Project Program - - Select Jurisdiction - 100.0% - Add Project Nam -Select Yes/No- -Select Yes/No- -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Proj 15 - Select Project Program - - Select Jurisdiction - 100.0% - Add Project Nam -Select Yes/No- -Select Yes/No- -$ -$ -$ -$ -$ -$ -$ -$ -$ -$

FAPD MI MAJ ST FAPD
Developer Share Vlookup Sort
AgencyList DeveloperShareList PhaseList FundList ProjectProgramList MSIFund AgencyList DeveloperShareList DevLoan/5YrAdv - Select Jurisdiction - - Select Phase - - Select Fund - - Select Project Program - AutoFill - Select Jurisdiction - 0.0% -Select Yes/No- City of Adelanto 63.5% PSR CMAQ Valley Arterial Sub-Program MSI Arterial City of Adelanto 63.5% Yes Town of Apple Valley 55.0% PA&ED DEMO Valley Freeway Interchange Program MSI InterchangeCity of Chino 35.2% No City of Chino 35.2% PS&E DEV FEE Victor Valley Major Local Highway Program MSI MLHP City of Chino Hills 13.7% City of Chino Hills 13.7% ROW DEV LOAN City of Colton 43.6% City of Colton 43.6% CONST HBP City of Fontana 32.1%
City of Fontana 32.1% LPP City of Grand Terrace 39.9%
City of Grand Terrace 39.9% MI LOCAL ST City of Hesperia 58.9% City of Hesperia 58.9% MI VFI City of Highland 46.4%
City of Highland 46.4% OTHER City of Loma Linda 38.8%
City of Loma Linda 38.8% PUC City of Montclair 18.9%
City of Montclair 18.9% PROP 1B City of Ontario 44.4%
City of Ontario 44.4% RIV COUN City of Rancho Cucamonga 28.7% City of Rancho Cucamonga 28.7% RXR City of Redlands 23.1% City of Redlands 23.1% STP City of Rialto 40.9%
City of Rialto 40.9% STIP City of San Bernardino 32.4%
City of San Bernardino 32.4% TCRP City of Upland 48.3%
City of Upland 48.3% City of Yucaipa 30.9%
City of Yucaipa 30.9% San Bernardino County - Adelanto Sphere 63.0% San Bernardino County - Adelanto Sphere 63.0% San Bernardino County - Apple Valley Sphere 57.2% San Bernardino County - Apple Valley Sphere 57.2% San Bernardino County - Chino Sphere 36.7% San Bernardino County - Chino Sphere 36.7% San Bernardino County - Colton Sphere 37.2% San Bernardino County - Colton Sphere 37.2% San Bernardino County - Devore/Glen Helen Sphere 62.2% San Bernardino County - Devore/Glen Helen Sphere 62.2% San Bernardino County - Fontana Sphere 41.7% San Bernardino County - Fontana Sphere 41.7% San Bernardino County - Hesperia Sphere 41.5% San Bernardino County - Hesperia Sphere 41.5% San Bernardino County - Loma Linda Sphere 72.3% San Bernardino County - Loma Linda Sphere 72.3% San Bernardino County - Montclair Sphere 36.6% San Bernardino County - Montclair Sphere 36.6% San Bernardino County - Redlands Donut Hole 62.0% San Bernardino County - Redlands Sphere 35.5% San Bernardino County - Redlands Sphere 35.5% San Bernardino County - Redlands Donut Hole 62.0% San Bernardino County - Rialto Sphere 37.6% San Bernardino County - Rialto Sphere 37.6% San Bernardino County - San Bernardino Sphere 23.1% San Bernardino County - San Bernardino Sphere 23.1% San Bernardino County - Upland Sphere 38.7% San Bernardino County - Upland Sphere 38.7% San Bernardino County - Victorville Sphere 17.8% San Bernardino County - Victorville Sphere 17.8% San Bernardino County - Yucaipa Sphere 39.5% San Bernardino County - Yucaipa Sphere 39.5% Town of Apple Valley 55.0%