materials. Additional placards shall be required inside the buildings when chemicals are segregated into separate areas. California Fire Code Chapter 50 & NFPA 704.
56. High-Piled Storage: The applicant shall submit an application for a High-Piled Storage permit for storage of over 12’ in height of Class I-IV commodities and/or over 6’ in height of high hazard commodities. Three (3) sets of detailed plans and a commodity analysis report shall be submitted to the Fire Department for review and approval. The applicant shall submit to the Fire Department concurrently with any racking permits to the Building and Safety division. California Fire Code Chapter 32 & SBCoFD Standard S-1.
57. Secondary Access: The development shall have a minimum of two (2) points of vehicular access during each phase of construction for fire and emergency access purposes and for evacuation routes. SBCoFD Standard A-1
58. San Bernardino County Fire Standards/Codes: Items not directly called out on these Conditions of Approval, shall also adhere to currently adopted San Bernardino County Fire Standards, California Fire Code, & NFPA.
END OF CONDITIONS
232
Resolution No. 2023-_____
EXHIBIT “C”
CITY OF FONTANA
CONDITIONS OF APPROVAL
PROJECT: Master Case No. (MCN) 22-079 DATE: November 14, 2023 Design Review (DRP) No. 22-040
LOCATION: The project site includes property located to the east side of Poplar Avenue, west of Catawba Avenue and north and south of Rose Avenue (APNs) 0237-171-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -13, -14, - 15, -6, -17, -18, -19, and 0237-172-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -19, -22, -23, -26, -27, -28, -30, -31, -32, 33.
PLANNING DEPARTMENT:
1. This Design Review shall become null and void two (2) years from the date of approval, unless the appropriate permits have been obtained and construction, defined as permit obtainment, commencement of construction of the primary building on site, and successful completion of the first Building and Safety Department inspection, has commenced within this period.
2. The applicant shall defend, indemnify, protect and hold harmless the City of Fontana or its agents, officers, attorneys and employees from any and all actual or alleged claims, actions or proceedings against the City of Fontana or its agents, officers, attorneys or employees to attack, set aside, void, annul or seek monetary damages arising out of any challenge to the applicant’s proposed project or to any approvals of the Planning Commission and/or City Council concerning this project, including but not limited to actions challenging CEQA actions, permits, variances, plot plans, design plans, maps, licenses, and amendments. The City of Fontana shall promptly notify the applicant of any claim, action, or proceeding and the City of Fontana shall cooperate in the defense.
233
Resolution No. 2023-_____
In the event of any such third-party action or proceeding, the City shall have the right to retain legal counsel. The applicant shall be responsible and reimburse the City for such legal fees and costs, in their entirety, including actual attorneys’ fees, which may be incurred by the City in defense of such action or proceeding. This indemnification shall also include, but not be limited to, damages, fees and/or costs awarded against the City, if any, and cost of suit, attorneys’ fees, and other costs, liabilities and expenses incurred in connection with such claim, action, or proceeding whether incurred by applicant, the City and/or any parties bringing such forth.
Except as required under applicable State and Federal law, the City of Fontana and the applicant acknowledge that the City would not have approved this project if the City were to be liable to applicant in damages under or with respect to all or any part of this application or this condition of approval. Accordingly, applicant shall not sue the City for damages or monetary relief for any matter arising from or related to this condition of approval. Applicant’s sole and exclusive remedy shall be limited to declaratory/injunctive relief, mandate, and/or specific performance.
3. This project shall comply with all applicable provisions, regulations and development standards of the Fontana Zoning Code and Development Code, Fontana Municipal Code (FMC) and the Southwest Industrial Park Specific Plan.
4. The applicant shall meet all requirements identified in the Industrial Commerce Sustainability Ordinance (Chapter 9, Article V of the Fontana Municipal Code).
5. A Register of Professional Archaeologists (RPA)-qualified archeologist experienced with Native American artifact identification and approved by the City of Fontana shall be present to monitor the first two (2) days of site preparation/ grubbing; the first two (2) days of mass grading; and the first two (2) days of utility trenching. Such monitoring activities may be reduced or terminated depending on the findings and recommendations of the archeologist. In the event that prehistoric or historic cultural resources be uncovered during these activities, representatives of the tribal entity(s) whom consider the project site to be within their traditional use area shall be contacted and invited to the site to review the find, and monitoring shall be continued at the discretion of archeologist.
6. Historic Archaeological Resources
A. Upon discovery of any tribal cultural or archaeological resources, cease construction activities in the immediate vicinity of the find until the find can be assessed. All tribal cultural and archaeological resources unearthed by project construction activities shall be evaluated by the qualified archaeologist and tribal monitor/consultant. If the resources are Native American in origin, interested Tribes (as a result of correspondence with area Tribes) shall coordinate with the landowner regarding treatment and curation of these resources. Typically, the Tribe will request preservation in place or recovery for educational purposes. Work may continue on other parts of the project while evaluation takes place.
234
Resolution No. 2023-_____
B. Preservation in place shall be the preferred manner of treatment. If preservation in place is not feasible, treatment may include implementation of archaeological data recovery excavation to remove the resource along the subsequent laboratory processing and analysis. All Tribal Cultural Resources shall be returned to the Tribe. Any historic archaeological material that is not Native American in origin shall be curated at a public, non-profit institution with a research interest in the materials, if such an institution agrees to accept the material. If no institution accepts the archaeological material, they shall be offered to the Tribe or a local school or historical society in the area for educational purposes.
C. Archaeological and Native American monitoring and excavation during construction projects shall be consistent with current professional standards.
All feasible care to avoid any unnecessary disturbance, physical modification, or separation of human remains and associated funerary objects shall be taken.
Principal personnel shall meet the Secretary of the Interior standards for archaeology and have a minimum of 10 years’ experience as a principal investigator working with Native American archaeological sites in southern California. The Qualified Archaeologist shall ensure that all other personnel are appropriately trained and qualified.
7. The construction contractor shall use the following source controls at all times:
A. Construction shall be limited to 7:00 am to 6:00 pm on weekdays, 8:00 am to 5:00 pm on Saturdays, and no construction on Sundays and holidays unless it is approved by the Building Inspector for cases that are considered urgently necessary as defined in Section No. 18-63(7) of the Municipal Code. For all noise-producing equipment, use types and models that have the lowest horsepower and the lowest noise generating potential practical for their intended use.
B. The construction contractor will ensure that all construction equipment, fixed or mobile, is properly operating (tuned-up) and lubricated, and that mufflers are working adequately.
C. Have only necessary equipment onsite.
D. Use manually-adjustable or ambient-sensitive backup alarms. When working adjacent to residential use(s), the construction contractor will also use the following path controls, except where not physically feasible, when necessary:
E. Install portable noise barriers, including solid structures and noise blankets, between the active noise sources and the nearest noise receivers.
F. Temporarily enclose localized and stationary noise sources.
G. Store and maintain equipment, building materials, and waste materials as far as practical from as many sensitive receivers as practical.
8. All Conditions of Approval contained herein shall be incorporated into all applicable final construction plans and a copy of these conditions, signed by the property owner or legal representative, shall be placed on a sheet in the final building and grading plans prior to issuance of any building or grading permits. 235
Resolution No. 2023-_____
9. The current development fees must be paid prior to issuance of building/construction permits.
10. In the event that one or more of the Conditions of Approval for this project needs to be amended and/or deleted due to health, safety or welfare concerns, the City Manager is authorized to approve or conditionally approve such amendment/deletion, provided that City Manager shall bring such proposed amendment/deletion to the City Council at the next available meeting for City Council ratification, but in no event later than sixty (60) days following the City Manager’s decision. The noticing of such City Council meeting for possible ratification shall be pursuant to Sections No. 30-30 and Sections No. 30-31 of the Municipal Code.
11. Color combinations and color schemes for buildings approved under a design review application shall not be modified or changed without prior approval of the original approving body by a revision to the original application. Minor hue color changes may be approved by the Director of Planning. The Director of Planning may refer minor hue color changes to the original approving body for consideration under a revision to the original application.
12. Exterior lighting compatible with the design of the building shall be provided for the parking lot. The lighting shall be directed and shielded so as to illuminate only the parking area and to avoid glare impacts on adjacent properties.
13. Sidewalks shall be provided for all new developments in accordance with the city’s circulation element of the General Plan.
14. All parking stalls shall be clearly marked by double striping pavement painting.
Parking stall sizes shall be measured from the mid-point between the striping. No parking spaces shall be designated in an industrial parking facility, except for disabled persons parking, van pool, carpool, or any other designated parking as required by law.
15. All signs shall be reviewed under a separate Design Review Sign application.
16. All roof-mounted equipment and ground mounted equipment shall be screened from view from adjacent properties and streets to the satisfaction of the Director of Planning.
17. All landscaping shall be healthy and maintained in a reasonable manner as determined by the Director of Planning or his/her designee.
18. The transformer shall be screened by a solid screen wall and mature, dense landscaping, and not visible from the public right-of-way.
19. There shall be no refrigerated uses on site; unless, a future tenant follows any applicable studies/memorandums to amend this Condition of Approval. 236
Resolution No. 2023-_____
20. Development fees and Planning Department final inspection fee must be paid prior to Certificate of Occupancy.
21. Applicant shall pay all applicable service fees pursuant to the City of Fontana Municipal Code.
22. The applicant/developer/property owner shall provide up-lighting on the perimeter and up-light proposed trees to the satisfaction of the Director of Planning and his/her designee.
23. In the event that any off-site utility and/or infrastructure improvements are required as a direct result of future projects, construction of such off-site utility and infrastructure improvements shall not occur concurrently with the demolition, site preparation, and grading phases of project construction. This requirement shall be clearly noted on all applicable grading and/or building plans.
24. Adhere to the City standard of one foot candle minimum for all entrances, exits, pedestrian paths, parking lots, and activity areas. Reflect all light fixtures on the site plan. All areas shall be illuminated during all hours of darkness and all luminaries utilized shall be vandal-resistant fixtures. The type of lighting shall be fluorescent, white L.E.D.s or metal halide. Provide a photometric layout under separate exhibit to ensure the minimum light standard is met.
25. Incorporate an anti-graffiti coating onto the exterior of all proposed block walls to discourage graffiti.
26. The applicant shall meet all requirements of the Trip Reduction Measures in of the Zoning Code (Section 30-962).
27. The developer shall be required to comply with Development Agreement (AGR) No. 22-003
Prior To Issuance of Grading Permit
28. All Conditions of Approval and Mitigation, Monitoring, and Reporting Program (MMRP) contained herein shall be incorporated into all applicable final construction plans and a copy of these conditions shall be placed on a sheet in the final building and grading plans prior to issuance of any building or grading permits.
BUILDING & SAFETY DEPARTMENT:
29. The applicant shall design the project to show compliance with the latest adopted edition of the following codes as applicable:
A. California Building Code
B. California Residential Code
C. California Electrical Code
237
Resolution No. 2023-_____
D. California Mechanical Code
E. California Plumbing Code
F. California Energy Code
G. California Fire Code
H. California Green Building Standards Code
30. The applicant shall install an automatic fire suppression system, which is required in all new construction per FMC Chapter 11 Article II. Design and type of system shall be based upon the requirements of the Building Code, Fire Code and the requirements of the Fontana Fire Prevention District.
31. The applicant shall comply with the requirements of the South Coast Air Quality Management District (909-396-2000). SCAQMD requirements shall be satisfied prior to the issuance of any permit if hazardous materials are stored and/or used.
32. The applicant shall verify that any temporary building, trailer, commercial coach, etc. installed and/or used in connection with a construction project complies with FMC Chapter 5 Article XIV.
33. The applicant shall verify that all perimeter/boundary walls are designed and constructed so that the outer/exterior face of the wall is as close as possible to the lot line. In any case, the outer/exterior face of the wall shall be within two (2) inches of the lot line. Distances greater than two (2) inches may be approved prior to construction by the Building Official on a case by case basis for extenuating circumstances.
34. The applicant shall have the tract or parcel map recorded prior to the issuance of any building permits.
35. The applicant shall comply with the following grading requirements:
A. Grading plans shall be submitted to and approved by Building & Safety. The grading plans shall indicate all site improvements and shall indicate complete drainage paths of all drainage water run-offs.
B. All drainage water shall drain via approved methods to an approved location, such as a public street, a public drainage system, etc.
C. Drainage water shall not cross over a public sidewalk. Drainage water may, however, cross under a sidewalk if an approved drainage structure is used.
D. A recorded drainage acceptance agreement is required from adjoining property(s) receiving flows from this property.
E. No water course or natural drainage shall be obstructed.
F. Minimum slope or grade for ALL drainage structures shall be one half (0.50) percent for concrete and one (1.0) percent for all other, or as otherwise approved by the Building Official.
238
Resolution No. 2023-_____
G. Drainage water shall not pass from an ‘improved’ type of drainage structure to an ‘unimproved’ type of drainage structure (e.g., concrete swale to a dirt swale) unless otherwise approved by the Building Official.
H. A complete hydrology study using the latest edition of the San Bernardino County Flood Control Hydrology Manual, and complete hydraulic calculations justifying the size, slope, capacity, etc. of any and all drainage structures being utilized, shall be submitted to and approved by Building & Safety.
I. The on site drainage system shall, as a minimum, be designed to handle the run off generated by a ten (10) year storm. Check for flooding of all on site structures (buildings) and all adjacent properties during a hundred (100) year storm.
J. The grading plans shall, as a minimum, contain sections at all lot lines and/or permit boundary lines. These sections shall clearly indicate:
1. The relationship between the proposed finished on site grade elevations and the existing adjacent property grade elevations (Indicate any additional drainage water that may come from an adjacent property.); and
2. The ground cover/finished surface material being proposed (e.g., type of pavement, plant material, etc.); and
3. All proposed drainage structures; and
4. Any proposed and/or required walls or fencing.
36. The applicant is required to obtain permits for the removal and/or demolition of structures.
37. The applicant shall verify that all exterior lighting shall be oriented, directed, and/or shielded as much as possible so that direct illumination does not infringe onto adjoining properties.
PRIOR TO ISSUANCE OF BUILDING/CONSTRUCTION PERMITS
38. The following items (as applicable) shall be completed by the applicant and submitted to Building & Safety prior to the issuance of building permits for this project:
A. Precise grading plans shall be approved
B. Rough grading completed
C. Compaction certification
D. Pad elevation certification
E. Rough grade inspection signed off by a City Building Inspector
39. If hazardous substances are used and/or stored, the applicant shall provide a technical opinion and report, identifying and developing methods of protection from the hazards presented by the hazardous materials, may be required. This report shall be prepared by a qualified person, firm, or corporation and submitted to Building & Safety. This report shall also explain the proposed facility's intended 239
Resolution No. 2023-_____
methods of operation and list all of the proposed materials, their quantities, classifications, and the effects of any chemical (material) inter mixing in the event of an accident or spill.
40. The applicant shall combine the existing parcels into a single parcel, or a lot line adjustment shall be done so that the proposed structure(s) does not cross any lot line and complies with all requirements of the California Building Code, prior to any building permits being issued.
ENGINEERING DEPARTMENT:
41. The Project shall be served by the City’s sanitary sewer system, all sewer facilities shall be constructed in accordance with the City Standards. Main trunk sewer line shall be in accordance with master sanitary sewer plan or as approved by the City Engineer.
42. The Applicant shall obtain design and plan approval from all utility providers having jurisdiction over the on-site and off-site utilities. Completion of all undergrounding of on-site and off-site utilities is required by Section 27-52 of the City Municipal Code and in accordance with plans and specifications approved by the City Engineer.
43. The Applicant shall maintain all improvements and utilities within the public right- ofway, including street sweeping, prior to issuance of final certificate of occupancy by the City.
PRIOR TO ISSUANCE OF GRADING PERMIT
44. The Applicant shall submit and gain approval of a complete Water Quality Management Plan report in accordance with the County of San Bernardino Technical Guidance Document and latest template.
45. The Applicant shall submit and gain approval of a final drainage study prepared in accordance with the County of San Bernardino Hydrology Manual and Fontana Master Plan of Drainage.
PRIOR TO MAP RECORDATION
46. The Applicant shall provide a Land Improvement Agreement, with accompanying security. The agreement shall be executed on City-provided forms.
PRIOR TO ISSUANCE OF CONSTRUCTION PERMITS
47. The Applicant shall record All map’s, lot line adjustments, right-of-way dedications, right-of-way vacations, easements, reciprocal access agreement as required for the development.
48. The Applicant shall submit engineered improvement plans and obtain full approval.
All required public improvements, including but not limited to streets, storm drainage systems, sewers, traffic signals, streetlights, striping, signs, landscape, and any required traffic control and/or detour plans. All plans shall 240
Resolution No. 2023-_____
49. conform to City Standards and Specifications, and as approved by the City Engineer.
PRIOR TO ISSUANCE OF FINAL CERFITICATE OF OCCUPANCY
50. The Applicant/Engineer to provide the City of Fontana with As Built/Record Drawings for all public improvement plans.
51. The Applicant/Engineer shall provide centerline ties to the City of Fontana reflecting proper setting of all survey monuments within the project limits and replace any existing survey monuments damaged or removed during construction.
52. The Applicant/Engineer shall set survey monuments as required by the map and corner records must be recorded with the County.
53. The Applicant/Landscape Architect shall provide a “Landscape Certificate of Compliance” certifying that the work has been designed, installed, and will be maintained in accordance with the City of Fontana’s Model Water Efficiency Landscape Ordinance (Ordinance 1743, FCC Section 28).
54. All sewers shall be video inspected by applicant/contractor. Sewer video shall include clean-out connection, clean-out to lateral segment, lateral, and main line.
Contractor performing the video inspection must have a NASSCO PACP, LACP, and MACP certification. Applicant shall provide a copy of the video on DVD or flash drive to inspection staff with an accompanying full report. Videos to be inspected and approved by City Inspector. If removal and replacement of any utility is required, a subsequent video of the repair will be required. If a TCO (Temporary Certificate of Occupancy) is required a full video inspection will be required as well at that time.
55. All storm drains shall be video inspected by applicant/contractor. Storm drain video shall include main lines and laterals. Applicant shall provide a copy of the video on DVD or flash drive to inspection staff. Videos to be inspected and approved by City Inspector. If removal and replacement of any utility is required, a subsequent video of the repair will be required.
56. The Applicant/Engineer of Record shall submit a conforming copy of the recorded Memorandum of Agreement for the Water Quality Management Plan and Storm Water Best Management Practice transfer. The Access, Maintenance, and the WQMP Certification for BMP Completion must be submitted to the City Project Engineer.
FIRE DEPARTMENT:
57. Jurisdiction: The above referenced project is under the jurisdiction of the Fontana fire Protection District (herein “Fire Department”). Prior to any construction occurring on any parcel, the applicant shall contact the Fire Department for verification of current fire protection requirements. All new construction shall comply with the 241
Resolution No. 2023-_____
current California Fire Code requirements and all applicable statutes, codes, ordinances, and standards of the Fire Department.
59. Fire Access Road Width: Prior to map recordation, all fire access roadways shall be designed to meet the requirements for this development and shall be approved by the Fire Department. All buildings shall have access provided by approved roads, alleys, and private drives with a minimum twenty-six (26) foot unobstructed width and vertically to fourteen (14) feet six (6) inches in height. Buildings three (3) stories in height or more shall have a minimum access of thirty (30) feet unobstructed width and vertically to fourteen (14) feet six (6) inches in height. California Fire Code Chapter 5 & SBCoFD Standard A-1.
60. Turnaround: An approved turnaround shall be provided at the end of each roadway one hundred and fifty (150) feet or more in length. Cul-de-sac length shall not exceed six hundred (600) feet; all roadways shall not exceed a 12% grade and have a minimum of nineteen (19) foot inside radius and a forty-five (45) foot outside radius for all turns. California Fire Code Chapter 5 & SBCoFD Standard A-1.
61. Fire Lanes: The applicant shall submit a site plan to the Fire Department for review and approval of all proposed signage and striping for all fire access roadways. All curbs adjacent to fire lanes shall be painted red and “No Parking, Fire Lane” signs shall be installed on public and private roads in accordance with approved standards. SBCoFD Standard A-2.
62. Water System Commercial: Prior to map recordation or lot line adjustment, all water supply systems shall be designed to meet the required fire flow for this development and shall be approved by the Fire Department. The required fire flow shall be determined by using Appendix BB of the California Fire Code. A minimum of one new six (6) inch fire hydrant assembly with two (2) two and one half (2 1/2) inch and one (1) four (4) inch outlet (4”x2.5”x2.5”) shall be provided. All fire hydrants shall be spaced no more than three hundred (300) feet apart as measured along vehicular travel-ways. California Fire Code Chapter 5 & SBCoFD Standard W-2. The Fire Flow for this project shall be: 4,000 GPM for a two-hour duration at 20 psi residual operating pressure. Fire Flow is based on a 490,550 Square Foot structure.
63. Hydrant Marking: Blue reflective pavement markers indicating fire hydrant locations shall be installed as specified by the Fire Department. SBCoFD Standard W-2.
64. Water Improvement Plan: The applicant shall submit “Water Improvement Plans” to Fontana Fire Prevention. W.I.P. to include site plan, existing & proposed PUBLIC fire hydrant locations, building construction type, largest building square footage details, lot size detail in square feet, and description of what is being constructed.
Once approved by Fire Department, applicant will provide stamped/approved W.I.P to water purveyor for their construction needs. ON-SITE PRIVATE FIRE WATER
SUPPLY SHALL BE INSPECTED AND IN WORKING CONDITION PRIOR TO 242
Resolution No. 2023-_____
PLACING COMBUSTIBLE MATERIALS ON THE JOBSITE. California Fire Code Chapter 5.
65. Combustible Protection: Prior to combustibles being placed on the project site an approved paved roadway providing fire access and fire hydrants providing an acceptable fire flow shall be installed. California Fire Code Chapter 5.
66. Fire Sprinkler-NFPA #13: An automatic fire sprinkler system complying with NFPA 13 and Fire Department standards is required. A fire sprinkler contractor shall submit three (3) sets of detailed plans to the Fire Department for review and approval. The plans shall include hydraulic calculations and manufacturer specification sheets. The required fees shall be paid at the time of plan submittal. California Fire Code Chapter 9 & SBCoFD Standard F-1.
67. Fire Alarm, Waterflow Monitoring: A water flow monitoring fire alarm system complying with the California Fire Code, NFPA and all applicable codes is required for fire sprinkler systems with twenty (20) sprinkler heads or more. A fire alarm contractor shall submit three (3) sets of detailed plans to the Fire Department for review and approval. The required fees shall be paid at the time of plan submittal.
California Fire Code Chapter 9, NFPA 72 & SBCoFD Standard F-5.
68. Smoke Removal: An automatic smoke removal system complying with the California Fire Code, NFPA and all applicable codes is required. The applicant shall submit three (3) sets of detailed smoke removal system plans to the Fire Department for review and approval. The required fees shall be paid at the time of plan submittal.
California Fire Code Chapter 9.
69. Fire Extinguishers: Hand portable fire extinguishers are required. The location, type, and cabinet design shall be approved by the Fire Department. California Fire Code Chapter 9.
70. Commercial (large facility) Addressing: Commercial and industrial developments in excess of 100,000 sq. ft. shall have the street address installed on the building with numbers that are a minimum twelve (12) inches in height and with a one and one half (1½) inch stroke. The street address shall be visible from the street. During the hours of darkness, the numbers shall be electrically illuminated (internal or external).
Where the building is two hundred (200) feet or more from the roadway, additional non-illuminated contrasting six (6) inch numbers shall be displayed at the property access entrances. California Fire Code Chapter 5 & SBCoFD Standard B-1
71. Key Box: An approved Fire Department key box is required. The key box shall be provided with a tamper switch and shall be monitored by a Fire Department approved central monitoring service. California Fire Code Chapter 5 & SBCoFD Standard A-4
243
Resolution No. 2023-_____
72. Security Gates: In commercial, industrial, and multi-family complexes, all swing gates shall have an approved fire department Knox Lock. Where an automatic electric security gate is used, an approved Fire Department override switch is required. California Fire Code Chapter 5 & SBCoFD Standard A-3
73. Material Identification Placards: The applicant shall install, in all locations deemed appropriate by the Fire Department, approved material identification placards on the outside of all buildings and/or storage tanks that store hazardous or flammable materials. Additional placards shall be required inside the buildings when chemicals are segregated into separate areas. California Fire Code Chapter 50 & NFPA 704.
74. High-Piled Storage: The applicant shall submit an application for a High-Piled Storage permit for storage of over 12’ in height of Class I-IV commodities and/or over 6’ in height of high hazard commodities. Three (3) sets of detailed plans and a commodity analysis report shall be submitted to the Fire Department for review and approval. The applicant shall submit to the Fire Department concurrently with any racking permits to the Building and Safety division. California Fire Code Chapter 32 & SBCoFD Standard S-1.
75. Secondary Access: The development shall have a minimum of two (2) points of vehicular access during each phase of construction for fire and emergency access purposes and for evacuation routes. SBCoFD Standard A-1
76. San Bernardino County Fire Standards/Codes: Items not directly called out on these Conditions of Approval, shall also adhere to currently adopted San Bernardino County Fire Standards, California Fire Code, & NFPA.
END OF CONDITIONS OF APPROVAL
244
16498.10025\41754502.1
ATTACHMENT NO. 14
ORDINANCE NO. _____
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF
FONTANA APPROVING, PURSUANT TO AN ENVIRONMENTAL
IMPACT REPORT, SPECIFIC PLAN AMENDMENT NO. 22-003, AN
AMENDMENT TO THE SOUTHWEST INDUSTRIAL PARK (SWIP)
SPECIFIC PLAN TO CHANGE 18.8 ACRES FROM THE RESIDENTIAL
TRUCKING DISTRICT (RTD) TO SLOVER EAST INDUSTRIAL
DISTRICT (SED) ALONG ROSE AVENUE EAST OF POPLAR AVENUE
AND WEST OF CATAWBA AVENUE.
WHEREAS, the City of Fontana (the “City”) received an application on July 07, 2022 from Seefried Industrial Properties, Inc. (“Applicant”) for a General Plan Amendment (GPA No. 22-007) to amend the General Plan land use designation for 18.8 acres of land located along Rose Avenue to the east side of Poplar Avenue and west of Catawba Avenue from Residential Trucking (R-T) to General Industrial (I-G) and to modify Exhibit 15.8 (Land Use Map) of the General Plan to reflect the same; Specific Plan Amendment (SPA No. 22-003) to amend the Southwest Industrial Park (SWIP) Specific Plan Land Use for the project site from Residential Trucking District (RTD) to Slover East Industrial District (SED); Development Agreement (AGR No. 22-003) to include an agreement for the payment of a public benefit fee; Tentative Parcel Map (TPM No. 22- 016) (TPM No. 20638) for the consolidation of 41 parcels into one parcel; and Design Review (DRP No. 22-040) for the development of an industrial commerce building totaling approximately 490,565 square feet along with site improvements for APNs 0237-171-01, - 02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -13, -14, -15, -6, -17, -18, -19, and 0237- 172-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -19, -22, -23, -26, -27, -28, -30, - 31, -32, 33). The amendments together are known as Master Case Number 22-079 (“MCN 22-079”); and
WHEREAS, SPA No. 22-003 will allow the development of an industrial commerce center building totaling approximately 490,565 square feet and associated on-site and off-site improvements; and
WHEREAS, on October 17, 2023, the Fontana Planning Commission (“Planning Commission”) held a noticed public hearing and received public testimony and evidence by the Applicant, City staff, and other interested parties for MCN 22-079 and Final Environmental Impact Report (EIR) and Mitigation Monitoring and Reporting Program (MMRP). After carefully considering all information pertaining to the project, the Planning Commission voted 3-0 to recommend approval to City Council (“City Council”) by Resolution No. PC 2023-037; and
WHEREAS, on November 14, 2023, the City Council held a noticed public hearing on the EIR, MMRP, and MCN No. 22-079, received testimony from all parties and documentation from the Planning Commission’s public hearing on October 17, 2023; and WHEREAS, on November 14, 2023, the City Council certified the EIR and adopted the MMRP; and
WHEREAS, based on the information presented to the City Council at the Public hearing held on November 14, 2023, the City Council found that the amendments and 245
16498.10025\41754502.1
Ordinance No.___
project are in conformance with the goals and policies of the General Plan to provide a community that is balanced between residential, commercial, and industrial uses, is developed with high standards, and provides diverse economic and social opportunities for our citizens and those who wish to invest in the City.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF FONTANA, CALIFORNIA DOES ORDAIN AS FOLLOWS:
SECTION 1. Recitals. The recitals are true, correct and incorporated herein by this reference.
SECTION 2. CEQA. Consistent with the California Environmental Quality Act (CEQA) (Pub. Resources Code § 21000 et seq.) and the State CEQA Guidelines (Cal.
Code Regs., tit. 14, § 15000 et seq.), the EIR was prepared for development, including Specific Plan Amendment No. 22-003. The City Council has certified the EIR and, based on the CEQA Sections 15162 through 15164, staff has determined that none of the criteria requiring a subsequent environmental document have been met and that further environmental analysis is not required. A Notice of Determination has been prepared.
SECTION 3. Findings. The City Council hereby makes the following findings for Specific Plan Amendment No. 22-003 in accordance with Section 30-67 “Purpose” of the Fontana Zoning and Development Code:
Finding: A Specific Plan may be amended by changing the development standards or zoning designation of any zone whenever such an amendment is deemed necessary to protect or promote the public's health, safety or general welfare or when modification is viewed as appropriate in the context of generally accepted planning principles, surrounding land uses, and the General Plan.
Findings of Fact: The specific plan amendment is to the remove an 18.8-acre site from the Residential Trucking District (RTD) and to include it in the Slover East Industrial District (SED) within the Southwest Industrial Park Specific Plan (SWIP) for the development of an industrial commerce building totaling 490,565 square feet. This development will provide an attractive development with quality modern architecture and vast landscaping. This type of development will enhance the area with an attractive street scene and high-quality industrial development. This type of development will be consistent with the industrial area.
SECTION 4. Approval. Based on the findings in Section 3, Specific Plan Amendment No. 22-003 is hereby approved and the Southwest Industrial Park Specific Plan is amended to establish the project within the Slover East Industrial District as shown on Exhibit “A”, attached hereto and by this reference incorporated herein.
SECTION 5. Effective Date/Publication. This Ordinance shall take effect thirty (30) days after the date of the adoption and prior to the expiration of fifteen (15) days from 246
16498.10025\41754502.1
Ordinance No.___
the passage thereof, shall be published by the City Clerk at least once in the Fontana Herald News, a local newspaper of the general circulation, published and circulated in the City of Fontana, and henceforth and thereafter the same shall be in full force and effect.
SECTION 6. Custodian of Records. The documents and materials that constitute the record of proceedings on which this Ordinance is based are located at the City Clerk’s office located at 8353 Sierra Avenue, Fontana, CA 92335. The custodian or records is the City Clerk.
SECTION 7. Certification. The City Clerk of the City Council shall certify to the adoption of this Ordinance.
SECTION 8. Severability. If any provision of this Ordinance or the application of any such provision to any person or circumstance is held invalid, such invalidity shall not affect other provisions or applications of this Ordinance that can be given effect without the invalid provision or application.
APPROVED AND ADOPTED this 14th day of November 2023.
READ AND APPROVED AS TO LEGAL FORM:
_________________________________________
City Attorney
I, Germaine Key, City Clerk of the City of Fontana, and Ex-Officio Clerk of the City Council, do hereby certify that the foregoing Ordinance is the actual Ordinance adopted by the City Council and was introduced at a regular meeting on the 14th day of November, 2023, and was finally passed and adopted not less than five days thereafter on the 14th day of November, 2023, by the following vote to wit:
AYES:
NOES:
ABSENT:
_________________________________________
City Clerk of the City of Fontana
_________________________________________
Mayor of the City of Fontana
ATTEST:
247
16498.10025\41754502.1
Ordinance No.___
_________________________________________
City Clerk
248
16498.10025\41754502.1
EXHIBIT “A”
SOUTHWEST INDUSTRIAL PARK SPECIFIC PLAN LAND USE MAP AMENDMENT
EXISTING
249
16498.10025\41754502.1
Ordinance No.___
SOUTHWEST INDUSTRIAL PARK SPECIFIC PLAN LAND USE MAP AMENDMENT
PROPOSED
250
ATTACHMENT NO. 15
ORDINANCE NO.______
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF
FONTANA APPROVING, PURSUANT TO THE POPLAR
SOUTH DISTRIBUTION CENTER PROJECT FINAL
ENVIRONMENTAL IMPACT REPORT (SCH #2022090611),
DEVELOPMENT AGREEMENT NO. 23-003 BETWEEN THE
CITY OF FONTANA AND LIT INDUSTRIAL LIMITED
PARTNERSHIP, WHICH PROVIDES A PUBLIC BENEFIT
FEE IN THE AMOUNT OF $2,084,901 DOLLARS
WHEREAS, the City Council ("City Council") of the City of Fontana ("City") is authorized by California Government Code sections 65864 et seq. and section 30-322 of the City's Development Code ("Development Code") to enter into an agreement for the development of real property with any person having a legal or equitable interest in such property in order to establish certain development rights in such property; and WHEREAS, City has found that development agreements will strengthen the public planning process, encourage private participation in comprehensive planning by providing a greater degree of certainty in that process, reduce the economic costs of development, allow for the orderly planning of public improvements and services, allocate costs to achieve maximum utilization of public and private resources in the development process, and ensure that appropriate measures to enhance and protect the environment are achieved; and
WHEREAS, because of the logistics, magnitude of the expenditure, and considerable lead time required to plan and develop the Poplar South Distribution Center (“Developer”) has proposed to enter into a development agreement concerning the Property (“Development Agreement”), to provide assurances that the Property can be developed without disruption caused by a change in the City’s planning policies and requirements except as provided in the Development Agreement, which assurances will thereby reduce the actual or perceived risk of planning for and proceeding with development of the Property; and
WHEREAS, the City of Fontana, a California Municipal Corporation ("City") and Developer are supportive of entering into a Development Agreement whereby Developer will acquire fee title to certain real property located at Catawba Avenue and Rose Avenue (the "Property"); and
WHEREAS, Developer's interest in the Property, including that interest to be conveyed pursuant to the DA, constitutes a legal or equitable interest in real property pursuant to California Government Code section 65865; and WHEREAS, Developer proposes the development of the Property for three industrial buildings totaling approximately 490,565 square feet, including up to 10,000 square feet of office space, entailing front end investment in the planning, entitlement and 251
2 of 5
development of the Property to achieve the goals of the City's General Plan ("General Plan"), as further described and conditioned in the Development Agreement (collectively, such development shall be referred to herein as the "Project"); and WHEREAS, City desires the timely, efficient, orderly and proper development of the Project in furtherance of the goals of the General Plan; and WHEREAS, City has found that the development agreement attached hereto as “Exhibit A” and incorporated herein by reference ("Development Agreement") is consistent with City's General Plan; and
WHEREAS, consistent with the California Environmental Quality Act (CEQA) (Pub.
Resources Code § 21000 et seq.) and the State CEQA Guidelines (Cal. Code Regs., tit. 14, § 15000 et seq.), an Environmental Impact Report (EIR) has been prepared for the Citrus/Oleander Project; and
WHEREAS, on November 14, 2023, pursuant to the California Environmental Quality Act (Pub. Res. Code §§ 21000 et seq.) (“CEQA”), and the State CEQA Guidelines (14 Cal. Code Regs. §§ 15000 et seq.) the City certified the Citrus/Oleander EIR (SCH #2022090611), and approved the Mitigation Monitoring and Reporting Program (MMRP); and
WHEREAS, City has determined that by entering into the Development Agreement: (i) City will promote orderly growth and quality development on the Property in accordance with the goals and policies set forth in the General Plan and (ii) City will benefit from increased employment and industrial opportunities created by the Project for residents of the City; and
WHEREAS, on November 14, 2023, the City Council introduced this Ordinance through a first reading of this Ordinance; and
WHEREAS, the terms and conditions of the Development Agreement have undergone review by City at publicly noticed hearings and have been found to be fair, just and reasonable, and consistent with the General Plan. Further, City finds that:
(i) the economic interests of the City's citizens and the public health, safety and welfare will be best served by entering into the Development Agreement; (ii) the Development Agreement is compatible with the uses authorized in, and the regulations prescribed for, the land use district in which the Property is located; (iii) the Development Agreement is consistent with the General Plan; (iv) the Development Agreement is in conformity with the public convenience, general welfare and good land use practice;
252
3 of 5
(v) the Development Agreement will not be detrimental to the public health, safety and general welfare; and
(vi) the Development Agreement will not adversely affect the orderly development or the preservation of property values for the Property or any other property.
THE CITY COUNCIL OF THE CITY OF FONTANA DOES ORDAIN AS
FOLLOWS:
SECTION 1. Recitals. The City Council hereby incorporates by reference the Recitals set forth herein and adopts those Recitals as its own as though fully set forth in this Ordinance. Pursuant to California Government Code section 65867.5(b), and based on the entire record before the City Council, including all written and oral evidence presented to the City Council, the City Council hereby finds that the Development Agreement is consistent with the General Plan because the Development Agreement will result in the development of the Property at the intensity and density allowed under the General Plan and with the restrictions and standards set forth in the City's Municipal Code.
SECTION 2. California Environmental Quality Act. As the decision-making body for the Development Agreement, the City Council has reviewed and considered the certified EIR, any oral or written comments received, and the administrative record prior to making any decision on the Development Agreement. Based on the substantial evidence set forth in the record, including but not limited to, the certified EIR, and all related information presented to the City Council, the Council finds that the Development Agreement does not necessitate any modifications to the certified EIR.
The Council further finds that no new or additional mitigation measures or alternatives are required, and that there is no substantial evidence in the administrative record supporting a fair argument that the Development Agreement may result in any significant environmental impacts beyond those analyzed in the certified EIR.
Therefore, pursuant to State CEQA section 15164 and Section 8.06 of the City of Fontana’s 2019 Local Guidelines for Implementing CEQA the Council finds that the preparation of a subsequent or supplemental EIR is not required for the Development Agreement.
SECTION 3. Findings of Public Health, Safety and Welfare. Based on the entire record before the City Council and all written and oral evidence presented to the City Council, the City Council finds this Ordinance promotes the public health, safety and welfare of the community because the Development Agreement will enable needed public improvements at the Property and the economic development of the Property will benefit the citizens of the City.
SECTION 4. Findings of Best Interest of City. Based on the entire record before the City Council and all written and oral evidence presented to the City Council, the City Council finds that the Development Agreement is in the best interests of the City, and represents good land use practices, as it ensures the orderly development of the Property with amenities and infrastructure that will be beneficial to the community. 253
4 of 5
SECTION 5. Findings of Public Benefit. The City Council further finds that among the public benefits to accrue to the residents of the City as a result of the Development Agreement are:
1. The revitalization of an underdeveloped site.
2. The development of onsite infrastructure upgrades that would not occur otherwise.
3. The generation of additional property tax.
4. The stimulation of adjacent areas in the City by introducing new industrial facility and opportunities.
5. The implementation of numerous City planning and economic development policies which benefit the health and fiscal welfare of the City and its residents.
The payment of a public benefit fee from the Developer to the City to offset certain private benefits received by Developer under the DA.
SECTION 6. Approval. Pursuant to California Government Code sections 65865 et seq., the City Council hereby approves Development Agreement No. 23-003, attached hereto as “Exhibit A” and incorporated by reference herein, between LIT Industrial Limited Partnership and the City of Fontana, a California municipal corporation.
SECTION 7. Certification. The City Clerk shall cause to be recorded with the San Bernardino County Recorder a copy of the executed Development Agreement at the time and in the manner provided for in the DA.
SECTION 8. Effective Date/Publication. This Ordinance shall take effect thirty (30) days after the date of the adoption and prior to the expiration of fifteen (15) days from the passage thereof, shall be published by the City Clerk at least once in the Fontana Herald News, a local newspaper of the general circulation, published and circulated in the City of Fontana, and henceforth and thereafter the same shall be in full force and effect.
SECTION 9. Severability. If any provision of this Ordinance or the application of any such provision to any person or circumstance is held invalid, such invalidity shall not affect other provisions or applications of this Ordinance that can be given effect without the invalid provision or application.
APPROVED and ADOPTED this 14th day of November 2023.
READ AND APPROVED AS TO LEGAL FORM:
City Attorney
I, Germaine Key, City Clerk of the City of Fontana, and Ex-Officio Clerk of the City Council, do hereby certify that the foregoing Ordinance is the actual Ordinance adopted 254
5 of 5
by the City Council and was introduced at a regular meeting on the 14th day of November 2023, and was finally passed and adopted not less than five days thereafter on the 12th day of December 2023 by the following vote to wit:
AYES:
NOES:
ABSENT:
City Clerk of the City of Fontana
Mayor of the City of Fontana
ATTEST:
City Clerk
255
EXHIBIT "A"
DEVELOPMENT AGREEMENT
256
7 RECORDING REQUESTED BY:
Order No:
WHEN RECORDED MAIL
DOCUMENT TO:
City of Fontana
8353 Sierra Avenue
Fontana, California 92335
Attn.: City Clerk
Space Above This Line for Recorder's Use Only
Exempt from Recording Fees Pursuant
to Gov. Code §§ 27383, 6103
ROSE PROJECT
DEVELOPMENT AGREEMENT No. 22-003
BETWEEN
THE CITY OF FONTANA,
a California municipal corporation
and
LIT INDUSTRIAL LIMITED PARTNERSHIP
a Delaware Limited Partnership
Dated as of November 14, 2023 for reference purposes
257
8 RECORDING REQUESTED BY:
Order No:
WHEN RECORDED MAIL
DOCUMENT TO:
City of Fontana
8353 Sierra Avenue
Fontana, California 92335
Attn.: City Clerk
Space Above This Line for Recorder's Use Only
Exempt from Recording Fees Pursuant
to Gov. Code §§ 27383, 6103
ROSE PROJECT
DEVELOPMENT AGREEMENT No. 22-003
BETWEEN
THE CITY OF FONTANA,
a California municipal corporation
and
LIT INDUSTRIAL LIMITED PARTNERSHIP
a Delaware Limited Partnership
Dated as of November 14, 2023 for reference purposes
258
9 259
10 ROSE AVENUE PROJECT DEVELOPMENT AGREEMENT
The ROSE AVENUE PROJECT DEVELOPMENT AGREEMENT ("Agreement") is entered into by the City of Fontana a California municipal corporation (hereinafter "City"), and LIT Industrial Limited Partnership, a Delaware limited partnership (hereinafter "Owner"). This Agreement is dated November 14, 2023 for reference purposes only; it will not become effective until the "Effective Date" (defined below). City and Owner are sometimes collectively referred to in this Agreement as the "Parties" and individually as a "Party."
RECITALS
WHEREAS, City is authorized to enter into binding development agreements with persons having legal or equitable interests in real property for the development of such property, pursuant to Section 65864 et seq. of the Government Code; and
WHEREAS, Owner has requested that City enter into this Development Agreement with respect to that certain real property located on Rose Avenue in the City, consisting of 41 parcels identified as Assessor’s Parcel Numbers (APNs) 0237-171-01 through -19, 0237-172-01 through -12, -19, -22, -23, -26, -27, -28, and -30 through -33, as more particularly described on Exhibit “A” and shown on Exhibit “B” to this Agreement (the “Property”), and proceedings have been taken in accordance with the rules and regulations of City; and WHEREAS, by electing to enter into this Agreement, City shall bind the City, including current and future City Councils of City, by the obligations specified herein and limit the future exercise of certain governmental and proprietary powers of City; and WHEREAS, the terms and conditions of this Agreement have undergone extensive review by City and the City Council and have been found to be fair, just and reasonable; and WHEREAS, the best interests of the citizens of the City and the public health, safety and welfare will be served by entering into this Agreement; and WHEREAS, prior to the adoption of the Development Approvals described in this Agreement, the City Council has reviewed and considered the Environmental Impact Report and made findings concerning the mitigation measures and adopted a Mitigation Monitoring and Reporting Program in accordance with CEQA and the State and City CEQA Guidelines; and WHEREAS, Owner has filed an application for, and the City Council has approved, General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Design Plan Review (DRP) No. 22-040 and Tentative Parcel Map No. 20638; and WHEREAS, this Agreement and the Project are consistent with the City's Comprehensive General Plan and Specific Plan (as defined in Section 1 below), as amended; and WHEREAS, all actions taken and approvals given by City have been duly taken or approved in accordance with all applicable legal requirements for notice, public hearings, findings, votes, and other procedural matters; and
260
11 WHEREAS, development of the Property in accordance with this Agreement and Development Plan (as defined in Section 1 below) will provide substantial benefits to City and will further important policies and goals of City;
WHEREAS, this Agreement will eliminate uncertainty in planning and provide for the orderly development of the Property, ensure the installation of necessary improvements, provide for public services appropriate to the development of the Project, and generally serve the purposes for which development agreements under Sections 65864 et seq. of the Government Code are intended; and
WHEREAS, Owner has incurred and will in the future incur substantial costs in excess of the generally applicable requirements in order to assure the vesting of its legal rights to develop the Property in accordance with this Agreement and Development Plan (defined below).
COVENANTS
NOW, THEREFORE, in consideration of the above recitals and of the mutual covenants hereinafter contained and for other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the Parties agree as follows:
1. DEFINITIONS AND EXHIBITS
1.1 Definitions. The following terms when used in this Agreement shall be defined as follows:
1.1.1 "Agreement" means this Development Agreement.
1.1.2 "City" means the City of Fontana, a municipal corporation, organized and existing pursuant to the laws of the State of California.
1.1.3 "Owner" means LIT Industrial Limited Partnership, a Delaware limited partnership, and its successors in interest to all or any part of the Property.
1.1.4 "Development" means the improvement of the Property for the purposes of completing the structures, improvements and facilities comprising the Project, including, but not limited to: grading; the construction of infrastructure and public facilities related to the Project whether located within or outside the Property; the construction of buildings and structures; and the installation of landscaping. "Development" does not include the repair or reconstruction of any building, structure, improvement, or facility after the construction and completion thereof if undertaken during the Term of this Agreement.
1.1.5 "Development Agreement Policies" means those certain development agreement policies approve by City pursuant to Ordinance No. , adopted on as may be amended, as Resolution No. , adopted on , as may be amended.
1.1.6 "Development Approvals" means all permits and other entitlements subject to approval or issuance by City in connection with the Development 261
12 of the Property as set forth in attached Exhibit C, including, but not limited to: general plan amendments; specific plans and specific plan amendments; tentative and final subdivision and parcel maps; design review; conditional use permits; zoning; and grading and building permits.
1.1.7 "Development Exaction" means any requirement of City in connection with or pursuant to any Land Use Regulation or Development Approval for the dedication of land, the construction of improvements or public facilities, or the payment of fees in order to lessen, offset, mitigate or compensate for the impacts of development on the environment or other public interests, including those imposed in accordance with the MMRP.
1.1.8 "Development Impact Fee" means a monetary exaction other than a tax or special assessment, whether established for a broad class of projects by legislation of general applicability or imposed on a specific project on an ad hoc basis, that is charged by City to the applicant in connection with the approval of a development project for the purpose of defraying all or a portion of the cost of public facilities related to the development project, but does not include park “in lieu” fees specified in Government Code Section 66477, fees for processing applications for governmental regulatory actions or approvals, fees collected under development agreements adopted pursuant to Article
2.5 of the Government Code (commencing with Section 65864) of Chapter 4, or fees collected pursuant to agreements with redevelopment agencies which provide for the redevelopment of property in furtherance or for the benefit of a redevelopment project for which a redevelopment plan has been adopted pursuant to the Community Redevelopment Law (Part 1 (commencing with Section 33000) of Division 24 of the Health and Safety Code)..
1.1.9 "Development Plan" means the development of the Property permitted by the Existing Development Approvals and the Existing Land Use Regulations applicable to development of the Property.
1.1.10 "Effective Date" means the date the ordinance approving this Agreement becomes effective.
1.1.11 "Existing Development Approvals" means all Development Approvals approved or issued prior to, or as of, the Effective Date. Existing Development Approvals includes the Development Approvals described on the attached Exhibit C and all other Development Approvals which are a matter of public record on the Effective Date.
The Existing Development Approvals are sufficient in order to develop the Property and to implement the Project.
1.1.12 "Existing Land Use Regulations" means all Land Use Regulations in effect on the Effective Date.
1.1.13 "Land Use Regulations" means all ordinances, resolutions, codes, rules, regulations and official policies of City governing the development and use of land, including, without limitation, the permitted use of land, the density or intensity of use, 262
13 subdivision requirements, the maximum height and size of proposed buildings, the provisions for reservation or dedication of land for public purposes, and the design, improvement and construction standards and specifications applicable to the Development of the Property. "Land Use Regulations" do not include any City ordinance, resolution, code, rule, regulation, or official policy governing: the conduct of businesses, professions, and occupations; taxes and assessments; the control and abatement of nuisances; the granting of encroachment permits and the conveyance of rights and interests which provide for the use of or the entry upon public property; or the exercise of the power of eminent domain.
1.1.14 "Mitigation Monitoring and Reporting Program" or "MMRP" means the mitigation monitoring and reporting program for assessing and ensuring compliance with required environmental impact mitigation measures approved by City Council Resolution No. _________ ___________, 2023 in conjunction with the City Council's certification of the EIR.
1.1.15 "Mortgagee" means a mortgagee of a mortgage, a beneficiary under a deed of trust, or any other security-device lender, and their successors and assigns in interest to all or any part of the Property.
1.1.16 "Parcel Map" means the subdivision map identified in City records as Tentative Parcel Map No. 20638 and approved by the City Council on ____________, 2023.
1.1.17 "Project" means the Development of the Property contemplated by the Development Plan, as such Development Plan may be further defined, enhanced, or modified pursuant to the provisions of this Agreement. The Project will consist of a logistics facility totaling approximately 490,565 square feet.
1.1.18 "Property" means the certain real property located on Rose Avenue in the City, consisting of 41 parcels identified as Assessor’s Parcel Numbers (APNs) 0237-171-01 through -19, 0237-172-01 through -12, -19, -22, -23, -26, -27, -28, and -30 through -33, as more particularly described in Exhibit A and shown on Exhibit B to this Agreement.
1.1.19 "Reservations of Authority" means the rights and authority excepted from the assurances and rights provided to Owner under this Agreement and reserved to City under Section 3.6 of this Agreement.
1.1.20 "Specific Plan" means the "Southwest Industrial Park Specific Plan (SWIP)" identified in City records as SP No. 09-02 and adopted by City Council Ordinance No. 1663 on June 12, 2012.
1.1.21 "Subdivision Map Act" means Government Code Sections 66410, et seq.
263
14 1.1.22 "Subsequent Development Approvals" means all Development Approvals required subsequent to the Effective Date in connection with the Development of the Property.
1.1.23 "Subsequent Land Use Regulations" means any Land Use Regulations adopted and effective after the Effective Date.
1.1.24 "Term" has the meaning given in Section 2.3 of this Agreement.
1.2 Exhibits. The following documents are attached to, and by this reference made a part of, this Agreement:
Exhibit A – Legal Description of the Property
Exhibit B – Map showing Property and its location
Exhibit C – Existing Development Approvals
2. GENERAL PROVISIONS
2.1 Binding Effect of Agreement. The Property is hereby made subject to this Agreement. The Development of the Property is hereby authorized and shall be carried out only in accordance with the provisions of this Agreement.
2.2 Property Ownership and Interest. The Owner represents and covenants that it is the legal or equitable owner of the fee simple title to the Property.
2.3 Term. The term of this Agreement shall commence on the Effective Date, and shall continue for a period of ten (10) years thereafter unless this term is modified or extended pursuant to the provisions of this Agreement.
2.4 Sale or Assignment.
2.4.1 Right to Assign. Subject to the City's written consent, which shall not be unreasonable withheld, delayed or conditioned, Owner shall have the right to sell, transfer, or assign the Property in whole or in part (provided that no such partial transfer shall violate the Subdivision Map Act) to any person, partnership, joint venture, affiliate, firm, or corporation at any time; provided, however, that any such sale, transfer or assignment shall include the assignment and assumption of the rights, duties and obligations arising under or from this Agreement and be made in strict compliance with the following conditions precedent:
(a) No sale, transfer or assignment of any right or interest under this Agreement shall be made unless made together with the sale, transfer or assignment of all or a part of the Property.
(b) Concurrent with any such sale, transfer, or assignment, or within fifteen (15) business days thereafter, Owner shall notify City, in writing, of such sale, transfer, or assignment and shall provide City with an executed agreement, in a form reasonably acceptable to 264
15 City, executed by the purchaser, transferee, or assignee and providing therein that the purchaser, transferee, or assignee expressly and unconditionally assumes all the duties and obligations of Owner under this Agreement.
Any sale, transfer or assignment not made in compliance with the foregoing conditions shall constitute a default by Owner under this Agreement. Notwithstanding the failure of any purchaser, transferee or assignee to execute this agreement required by Paragraph (b) of this Subsection 2.4.1, the burdens of this Agreement shall be binding upon such purchaser, transferee or assignee, but the benefits of this Agreement shall not inure to such purchaser, transferee or assignee until and unless such agreement is executed. Notwithstanding the foregoing, Owner shall have the right to transfer its interest in this Agreement to an “Owner Affiliate”. Notwithstanding the foregoing, Owner shall have the right to transfer its interest in this Agreement to an “Owner Affiliate.” An “Owner Affiliate” is an entity in which the original owner owns a majority financial or voting interest. Owner shall provide written notification to City concurrently with the completion of such a transfer.
2.4.2 Release of Transferring Owner. Notwithstanding any sale, transfer or assignment, Owner shall continue to be obligated under this Agreement as to that portion of the Property sold, transferred or assigned, unless Owner is given a release in writing by City, which release shall be provided by City upon the full satisfaction by Owner of all of the following conditions:
(a) Owner no longer has a legal or equitable interest in all or any part of the Property sold.
(b) Owner is not then in default under this Agreement.
(c) Owner has provided City with the notice and executed agreement required under paragraph (2) of subsection 2.4 above.
(d) The purchaser, transferee or assignee provides City with security equivalent to any security previously provided by Owner to secure performance of its obligations hereunder.
2.4.3 Subsequent Assignment. Any subsequent sale, transfer or assignment after an initial sale, transfer or assignment shall be made only in accordance with and subject to the terms and conditions of this Section.
2.4.4 Partial Release of Purchaser, Transferee or Assignee of Industrial or Commercial Lot. A purchaser, transferee or assignee of a lot, which has been finally subdivided as provided for in the Development Plan and for which a commercial or industrial plot plan for development of the lot has been finally approved pursuant to the Development Plan, may submit a request, in writing, to City to release said lot from the obligations under this Agreement relating to all other portions of the property. Within thirty (30) days of such request, City shall review, and if the above conditions are satisfied shall approve the request for release and notify the purchaser, transferee or assignee in writing thereof. No such release approved pursuant to this Subsection
2.4.4 shall cause, or otherwise affect, a release of Owner from its duties and obligations under this Agreement.
265
16 2.4.5 Termination of Agreement With Respect to Individual Lots Upon Sale to Public and Completion of Construction. The provisions of Subsection 2.4.1 shall not apply to the sale or lease (for a period longer than one year) of any lot which has been finally subdivided and is individually (and not in “bulk”) sold or leased to a member of the public or other ultimate user.
Notwithstanding any other provisions of this Agreement, this Agreement shall terminate with respect to any lot and such lot shall be released and no longer be subject to this Agreement without the execution or recordation of any further document upon satisfaction of both of the following conditions:
(a) The lot has been finally subdivided and individually (and not in “bulk”) sold or leased (for a period longer than one year) to a member of the public or other ultimate user; and,
(b) A certificate of occupancy has been issued for a building on the lot, and the fees set forth under Section 4 of this Agreement have been paid.
2.5 Amendment or Cancellation of Agreement. This Agreement may be amended or canceled in whole or in part only by written consent of all parties in the manner provided for in Government Code Section 65868 and the Development Agreement Policies. This provision shall not limit any remedy of City or Owner for a party's breach of the Agreement as provided by this Agreement.
2.6 Termination. This Agreement shall terminate and be of no further effect upon the occurrence of any of the following events:
2.6.1 Expiration of the stated term of this agreement as set forth herein.
2.6.2 Entry of a final judgment setting aside, voiding, or annulling the adoption of the ordinance approving this Agreement.
2.6.3 The adoption of a referendum measure overriding or repealing the ordinance approving this Agreement.
2.6.4 The completion of the Project in accordance with the terms of this Agreement, including, without limitation, the issuance of all required occupancy permits and acceptance by City (or other applicable public agency) of any required public dedications.
2.6.5 Termination by the City upon a default by Owner, as provided in this Agreement.
2.6.6 Termination of this Agreement will not operate to automatically terminate any Development Approvals or other land use entitlements approved for the Property. Upon the termination of this Agreement, no party shall have any further right or obligation hereunder except with respect to any obligation to have been performed prior to such termination or with respect to any default in the performance of the provisions of this Agreement that has occurred prior to such termination, or with respect to any obligations which are specifically set forth as surviving this Agreement. Upon such termination, any public facilities and services mitigation fees paid pursuant 266
17 to Section 4.2 of this Agreement by Owner to City buildings on which construction has not yet begun shall be refunded to Owner by City.
2.6.7 Notwithstanding any provision herein to the contrary, subject to the provisions of Section 4.3.3, the obligation of Owner to pay the Public Benefit Fee as set forth in Section 4.3.1 shall survive the termination of this Agreement until all buildings have been constructed on the Property pursuant to the Development Plan or otherwise.
2.7 Notices.
2.7.1 As used in this Agreement, "notice" includes, but is not limited to, the communication of notice, request, demand, approval, statement, report, acceptance, consent, waiver, appointment, or other communication required or permitted hereunder.
2.7.2 All notices shall be in writing and shall be considered given either: (i) when delivered in person to the recipient named below; (ii) on the date of delivery shown on the return receipt after deposit in the United States mail in a sealed envelope as either registered or certified mail with return receipt requested, postage and postal charges prepaid, and addressed to the recipient named below; or (iii) by overnight courier, on the first (1st) business day after being delivered to a recognized overnight courier. All notices shall be addressed as follows:
If to City:
City of Fontana
8353 Sierra Avenue
Fontana, CA 92335
Attn: City Manager
Telephone: (909) 350-7600
If to Owner:
LIT Industrial Limited Partnership
c/o Seefried Industrial Properties
2321 Rosecrans Ave. Suite 2220
El Segundo, CA 90245
Attn: Scott Irwin
Telephone: (310) 536-7900
with a copy to:
Best, Best & Krieger, LLP
2855 East Guasti Rd., Suite 400
Ontario, CA 91761
Attn: Fontana City Attorney
Telephone: (909) 989-8584
with a copy to:
Allen Matkins Leck Gamble
Mallory & Natsis LLP
2010 Main Street, Suite 800
Irvine, CA 92614
Attn: John C. Condas, Esq.
Telephone: (949) 553-1313
2.7.3 Either party may, by notice given at any time, require subsequent notices to be given to another person or entity, whether a party or an officer or representative of a party, or to a different address, or both. Notices given before actual receipt of notice of change shall not be invalidated by the change.
267
18 3. DEVELOPMENT OF THE PROPERTY
3.1 Rights to Develop. Subject to the terms of this Agreement, including the Reservations of Authority, Owner shall have the vested right to develop the Property in accordance with, and to the extent of, the Development Plan. The Project shall remain subject to all Subsequent Development Approvals required to complete the Project as contemplated by the Development Plan. Except as otherwise provided in this Agreement, the permitted uses of the Property, the density and intensity of use, the maximum height and size of proposed buildings, and provisions for reservation and dedication of land for public purposes shall be those set forth in the Development Plan. Notwithstanding the foregoing, nothing contained in this Agreement shall be deemed to be a covenant to develop or construct the Project or any portion of the Project.
3.2 Effect of Agreement on Land Use Regulations. Except as otherwise provided under the terms of this Agreement, including the Reservations of Authority, the rules, regulations, and official policies governing permitted uses of the Property, the density and intensity of use of the Property, the maximum height and size of proposed buildings, and the design, improvement and construction standards and specifications applicable to the Development of the Property shall be the Existing Land Use Regulations. In connection with any Subsequent Development Approval, City shall exercise its reasonable discretion in accordance with the Development Plan and as provided by this Agreement, including, but not limited to, the Reservations of Authority.
City shall accept for processing, review, and action all applications for Subsequent Development Approvals and such applications shall be processed in the normal manner for processing such matters.
3.3 Timing of Development. The parties acknowledge that Owner cannot at this time predict when or the rate at which phases of the Property will be developed. Such decisions depend upon numerous factors which are not within the control of Owner, such as market orientation and demand, interest rates, absorption, completion and other similar factors. Because the California Supreme Court held in Pardee Construction Co. v. City of Camarillo (1984) 37 Cal.3d 465, that the failure of the parties therein to provide for the timing of development resulted in a later adopted initiative restricting the timing of development to prevail over such parties' agreement, it is City's and Owner's intent to cure that deficiency by acknowledging and providing that Owner shall have the right to develop the Property, or not, in such order and at such rate and at such times as Owner deems appropriate within the exercise of its subjective business judgment, subject only to any timing or phasing requirements set forth in the Development Plan or the Phasing Plan set forth in Section 3.4.
3.4 Development Phasing Plan. The Development of the Property is subject to any timing and phasing requirements established by the Development Plan.
3.5 Changes and Amendments.
3.5.1 The parties acknowledge that refinement and further development of the Project may demonstrate that changes are appropriate and mutually desirable in the Existing Development Approvals. If in years one (1) through seven (7) during the Term of this Agreement, Owner finds that a change in the Existing Development Approvals is necessary or appropriate, Owner shall apply for a Subsequent Development Approval to effectuate such change and City 268
19 shall process and act on such application in accordance with the Existing Land Use Regulations, except as otherwise provided by this Agreement, including the Reservations of Authority. If approved, any such change in the Existing Development Approvals shall be incorporated herein as an addendum to Exhibit C and may be further changed from time to time as provided in this Section 3.5.
If in years eight (8) through ten (10) during the Term of this Agreement, Owner finds that changes to the Existing Development Approvals are necessary or appropriate for the refinement and further development of the Project, Owner shall apply for a Subsequent Development Approval and City shall process and act on such application in accordance with the land use regulations existing at the time of such application. Notwithstanding any provision herein to the contrary, Owner shall pay any and all fees and Development Exaction in place following years one (1) through five (5) and shall be required to pay any and all fees and exactions adopted at the time of applications for permits and approvals related to the Development Plan, including any amendments thereto.
3.5.2 Unless otherwise required by law, as determined in City's reasonable discretion, a change to the Existing Development Approvals shall be deemed "minor" and not require an amendment to this Agreement; but instead will require only the approval of City's Director of Planning; provided the change does not:
(a) Alter the permitted uses of the Property as a whole; or, (b) Increase the density or intensity of use of the Property as a whole; or,
(c) Increase the maximum height and size of permitted buildings; or, (d) Delete a requirement for the reservation or dedication of land for public purposes; or,(e) Constitute a project requiring a subsequent or supplemental environmental impact report pursuant to Section 21166 of the Public Resources Code. (e) The provisions of this Agreement require a close degree of cooperation between the City and the Owner. It is anticipated due to the term of this Agreement that refinements to the Development Approvals may be appropriate with respect to the details of performance of the City and the Owner. To the extent allowable by law, the Owner shall retain a certain degree of flexibility as provided herein with respect to all matters, items and provisions covered in general under this Agreement and exhibits thereto. When and if the Owner finds it necessary or appropriate to make changes, adjustments or clarifications, the Parties shall effectuate such changes, adjustments or clarifications through operating memoranda (“Operating Memoranda”) approved by the Parties in writing, which reference this Section of the Agreement.
Operating Memoranda are not intended to constitute an amendment to this Agreement but mere ministerial clarifications; therefore, public notices and hearings shall not be required. The City Attorney shall be authorized, upon consultation with the Owner, to determine whether a requested clarification may be effectuated pursuant to this Section or whether the requested clarification is of such character to constitute an amendment to the Agreement which requires compliance with the provisions of this Agreement pertaining to amendments. The authority to enter into such 269
20 Operating Memoranda is hereby delegated to the City Manager, and the City Manager is hereby authorized to execute any Operating Memoranda hereunder without Planning Commission or City Council action and without public hearing. Although other matters may also fall within the scope of Operating Memoranda, any amendment to this Agreement which does not relate to the Term, permitted uses of the Project, provisions for the reservation or dedication of land, grant of easement, or the conditions, terms, restrictions and requirements relating to Subsequent Development Approvals of City, revisions to Public Benefits (other than to the time for performance of such Public Benefits) or monetary exactions of Owner, shall be considered an “Operating Memorandum”.
3.6 Reservations of Authority.
3.6.1 Limitations, Reservations and Exceptions. Notwithstanding any other provision of this Agreement, the following Subsequent Land Use Regulations and fees and expenses shall apply to the Development of the Property (collectively, the "Reservations of Authority"):
(a) Processing fees and charges of every kind and nature imposed by City to cover the estimated actual costs to City of processing applications for Development Approvals or for monitoring compliance with any Development Approvals granted or issued. (b) Procedural regulations relating to hearing bodies, petitions, applications, notices, findings, records, hearings, reports, recommendations, appeals, and any other matter of procedure.
(c) Regulations governing construction standards and specifications, including, without limitation, the City's Building Code, Plumbing Code, Mechanical Code, Electrical Code, and Fire Code.
(d) Regulations imposing Development Exactions; In years one (1) through five (5) during Term of this Agreement, no such subsequently adopted Development Exaction shall be applicable to development of the Property unless such Development Exaction is applied uniformly to development, either throughout the City or within a defined area of benefit which includes the Property. No such subsequently adopted Development Exaction within the aforementioned timeframe shall apply if its application to the Property would physically prevent development of the Property for the uses and to the density or intensity of development set forth in the Development Plan. In the event any such subsequently adopted Development Exaction fulfills the same purposes, in whole or in part, as the fees set forth in Section 4 of this Agreement, City shall allow a credit against such subsequently adopted Development Exaction for the fees paid under Section 4 of this Agreement to the extent such fees fulfill the same purposes. (e) Regulations that may be in conflict with the Development Plan but that are reasonably necessary to eliminate or mitigate a serious threat to public health and safety.
To the extent possible, any such regulations shall be applied and construed so as to provide Owner with the rights and assurances provided under this Agreement. (f) Regulations that are not in conflict with the Development Plan. Any regulation, whether adopted by initiative or otherwise, limiting the rate or timing of development 270
21 of the Property, or which shall increase the cost of development of the Project, shall be deemed to conflict with the Development Plan and shall therefore not be applicable to the development of the property during years one (1) through five (5) of the Term of this Agreement.
3.6.2 Subsequent Development Approvals. This Agreement shall not prevent City, in acting on Subsequent Development Approvals, from applying Subsequent Land Use Regulations that do not conflict with the Development Plan, nor shall this Agreement prevent City from denying or conditionally approving any Subsequent Development Approval on the basis of the Existing Land Use Regulations or on the basis of any Subsequent Land Use Regulation which does not conflict with the Development Plan. Upon approval of any Subsequent Development Approval, such Subsequent Development Approval shall be deemed vested pursuant to the provisions of this Agreement, without any further action by City or Owner being required.
3.6.3 Modification or Suspension by State or Federal Law. In the event that State or Federal laws or regulations enacted after the Effective Date of this Agreement prevent or preclude compliance with one or more of the provisions of this Agreement, such provisions of this Agreement shall be modified or suspended as may be necessary to comply with such State or Federal laws or regulations; provided, however, that this Agreement shall remain in full force and effect to the extent it is not inconsistent with such laws or regulations and to the extent such laws or regulations do not render such remaining provisions impractical to enforce.
3.6.4 Intent. The parties acknowledge and agree that City is restricted in its authority to limit its police power by contract and that the foregoing limitations, reservations and exceptions are intended to reserve to City all of its police power which cannot be so limited.
3.7 Public Works. Owner shall construct all public improvements related to the Project in accordance with City's or other applicable public agency's then applicable public works engineering standards.
3.8 Provision of Real Property Interests by City. In any instance where Owner is required to construct any public improvement on land not owned by Owner, Owner shall at its sole cost and expense provide or cause to be provided, the real property interests necessary for the construction of such public improvements. In the event Owner is unable, after exercising reasonable efforts, including, but not limited to, the rights under Sections 1001 and 1002 of the Civil Code, to acquire the real property interests necessary for the construction of such public improvements, and if so instructed by Owner and upon Owner’s provision of adequate security for costs City may reasonably incur, City shall negotiate the purchase of the necessary real property interests to allow Owner to construct the public improvements as required by this Agreement and, if necessary, in accordance with the procedures established by law, use its power of eminent domain to acquire such required real property interests. Owner shall pay all costs associated with such acquisition or condemnation proceedings. This section 3.8 is not intended by the parties to impose upon the Owner an enforceable duty to acquire land or construct any public improvements on land not owned by Owner, except to the extent that the Owner elects to proceed with the development of the Project, and then only in accordance with valid conditions imposed by the City upon the development of the Project under the Subdivision Map Act or other legal authority. 271
22 3.9 Regulation by Other Public Agencies. It is acknowledged by the parties that other public agencies not within the control of City possess authority to regulate aspects of the development of the Property separately from or jointly with City and this Agreement does not limit the authority of such other public agencies.
3.10 Tentative Tract Map And Other Development Approval Extensions. Pursuant to the provisions of Section 66452.6 of the Government Code and relevant portions of the Fontana Municipal Code, all tentative subdivision maps or tentative parcel maps and all other Development Approvals approved in connection with development of the Project, shall automatically be granted extensions of time, for a seven (7) year lifespan.
3.11 Vesting Tentative Maps. If any tentative or final subdivision map, or tentative or final parcel map, heretofore or hereafter approved in connection with development of the Property, is a vesting map under the Subdivision Map Act (Government Code Section 66410 et seq.) and if this Agreement is determined by a final judgment to be invalid or unenforceable insofar as it grants a vested right to develop to Owner, then and to that extent the rights and protections afforded Owner under the laws and ordinances applicable to vesting maps shall supersede the provisions of this Agreement. Except as set forth immediately above, development of the Property shall occur only as provided in this Agreement, and the provisions in this Agreement shall be controlling over any conflicting provision of law or ordinance concerning vesting maps.
3.12 Utilities. The Project shall be connected to all utilities necessary to provide adequate water, sewer, gas, electric, and other utility service to the Project. Owner shall contract with the City for City-owned or operated utilities serving the Project for such prices and on such terms as may be mutually agreed to between the parties.
4. PUBLIC BENEFITS
4.1 Intent. The parties acknowledge and agree that the Development of the Property will result in substantial public needs which will not be fully met by the Development Plan and further acknowledge and agree that this Agreement confers substantial private benefits on Owner which should be balanced by commensurate public benefits. Accordingly, the parties intend to provide consideration to the public to balance the private benefits conferred on Owner by providing more fully for the satisfaction of the public needs resulting from the Project.
4.2 Development Impact Fees.
4.2.1 Amount and Components of Fee. The amount of the public facilities and services mitigation fees may be periodically adjusted by the City.
4.2.2 Time of Payment. The fees required pursuant to this section shall be paid to City prior to the issuance of building permits. No fees shall be payable for building permits issued prior to the Effective Date of this Agreement, but the fees required pursuant to Subsection 4.2.1 shall be paid prior to the re-issuance or extension of any building permit for which such fees have not previously been paid.
272
23 4.3 Public Benefit Fee.
4.3.1 As consideration for City's approval and performance of its obligations as set forth in this Agreement, Owner agrees to pay to the City a one-time public benefit fee in the amount of Four Dollars and Twenty five Cents ($4.25) per building square foot, which is estimated to be Two Million Eighty Four Thousand Nine Hundred One Dollars ($2,084,901) ("Public Benefit Fee"). Payment of the Public Benefit Fee shall be in addition to any other customary fees or charges to which the Project would otherwise be subject (e.g., development impact fees and application fees). The actual amount of the Public Benefit Fee shall be set, based upon the actual building square footage, prior to the issuance of any certificate of occupancy for the Project, and Owner shall pay the Public Benefit Fee to the City prior to the issuance of any certificate of occupancy for the Project.
4.3.2 The City has sole discretion to determine the uses for the Public Benefit Fee. The City has not designated a specific project or purpose for the Public Benefit Fee. Owner acknowledges by its approval and execution of this Agreement that it is voluntarily agreeing to pay the Public Benefit Fee, that its obligation to pay the Public Benefit Fee is an essential term of this Agreement, and that Owner expressly waives any constitutional, statutory, or common law right it might have in the absence of this Agreement to protest or challenge the payment of the Public Benefit Fee on any ground whatsoever, including without limitation pursuant to the Fifth and Fourteenth Amendments to the United States Constitution, California Constitution Article I Section 19, the Mitigation Fee Act (California Government Code Section 66000 et seq.), or otherwise.
4.3.3 Notwithstanding any provision herein to the contrary, the obligation of Owner to pay the Public Benefit Fee as set forth in Section 4.3.1 shall survive the termination of this Agreement until all buildings have been constructed on the Property pursuant to the Development Plan or otherwise. If the Public Benefit Fee has not been paid prior to the expiration of the Term, payment of the Public Benefit Fee shall be waived and shall no longer be due and payable if the City, after expiration of the Term, amends the Existing Land Use Regulations so that the Project, or other uses which previously were permitted under the Existing Land Use Regulations, no longer are legally permitted.
5. FINANCING OF PUBLIC IMPROVEMENTS.
If deemed appropriate, City and Owner will cooperate in the formation of any special assessment district, community facilities district or alternate financing mechanism to pay for the construction and/or maintenance and operation of public infrastructure facilities required as part of the Development Plan. City also agrees that, to the extent any such district or other financing entity is formed and sells bonds in order to finance such reimbursements, Owner may be reimbursed to the extent that Owner spends funds or dedicates land for the establishment of public facilities. Notwithstanding the foregoing, it is acknowledged and agreed by the parties that nothing contained in this Agreement shall be construed as requiring City or the City Council to form any such district or to issue and sell bonds.
273
24 6. REVIEW FOR COMPLIANCE
6.1 Periodic Review. As required by California Government Code Section 65865.1, the Director of Planning will review this Agreement annually, on or before each anniversary of the Effective Date, in order to ascertain the good faith compliance by Owner with the terms of the Agreement. Owner shall submit an Annual Monitoring Report, in a form acceptable to the Director of Planning, within 30 days after written notice from the Planning Director. The Annual Monitoring Report shall be accompanied by an annual review and administration fee sufficient to defray the estimated costs of review and administration of the Agreement during the succeeding year. The amount of the annual review and administration fee shall be set annually by resolution of the City Council.
6.2 Special Review. The City Council may order a special review of Owner's compliance with this Agreement at any time. The Director of Planning will conduct the special review.
6.2.1 During either an annual or special review. Owner will be required to demonstrate its good faith compliance with this Agreement. The burden of proof on this issue shall be on Owner.
6.2.2 Upon completion of an annual or special review, the Director of Planning will submit a report to the City Council setting forth the evidence concerning Owner's good faith compliance with this Agreement and his or her recommended finding on that issue.
6.2.3 If the City Council finds on the basis of substantial evidence that Owner has materially complied in good faith with the terms and conditions of this Agreement, then the review will be concluded.
6.2.4 If the City Council makes a preliminary finding that Owner has not materially complied in good faith with this Agreement, then, following notice and opportunity to cure as provided under Section 6.4, the City Council may modify or terminate this Agreement as provide in Section 6.4 and 6.5. Notice of default as provided under Section 7.4 of this Agreement shall be given to Owner prior to or concurrent with, proceedings under Section 6.4 and Section 6.5.
7. PROCEEDINGS FOR MODIFICATION OR TERMINATION.
7.1 Proceedings Upon Modification or Termination. If, upon a finding under Section
6.2, City determines to proceed with modification or termination of this Agreement, City shall give written notice to Owner of its intention so to do. The notice shall be given at least ten calendar days prior to the scheduled hearing and shall contain:
7.1.1 The time and place of the hearing;
7.1.2 A statement as to whether or not City proposes to terminate or to modify the Agreement; and
7.1.3 Such other information as is reasonably necessary to inform Owner of the nature of the proceeding.
274
25 7.2 Hearing on Modification or Termination. At the time and place set for the hearing on modification or termination, Owner shall be given an opportunity to be heard. Owner shall be required to demonstrate good faith compliance with the terms and conditions of this Agreement. The burden of proof on this issue shall be on Owner. If the City Council finds, based upon substantial evidence, that Owner has not complied in good faith with the terms or conditions of the Agreement, the City Council may terminate this Agreement or modify this Agreement and impose such conditions as are reasonably necessary to protect the interests of the City. The decision of the City Council shall be final, subject only to judicial review pursuant to Section 1094.5 of the Code of Civil Procedure.
7.3 Certificate of Agreement Compliance. If, at the conclusion of a Periodic or Special Review, Owner is found to be in compliance with this Agreement, City shall, upon request by Owner, issue a Certificate of Agreement Compliance (“Certificate”) to Owner stating that after the most recent Periodic or Special Review and based upon the information known or made known to the Planning Director and City Council that (1) this Agreement remains in effect and (2) Owner is not in default. The Certificate shall be in recordable form, shall contain information necessary to communicate constructive record notice of the finding of compliance, shall state whether the Certificate is issued after a Periodic or Special Review and shall state the anticipated date of commencement of the next Periodic Review. Owner may record the Certificate with the County Recorder.
Whether or not the Certificate is relied upon by assignees or other transferees or Owner, City shall not be bound by a Certificate if a default existed at the time of the Periodic or Special Review, but was concealed from or otherwise not known to the Planning Director or City Council.
8. DEFAULT AND REMEDIES
8.1 Remedies in General. The parties agree that the City would not have entered into this Agreement if it were to be liable for damages under this Agreement, or with respect to this Agreement or the application itself.
8.1.1 In general, and subject to those procedural prerequisites required under the Development Agreement Policies or this Agreement, each of the parties may pursue any remedy at law or equity available for the breach of this Agreement, except that CITY shall not be liable in damages to Owner, or to any successor in interest of Owner, or to any other person, and Owner covenants not to sue for damages or claim any damages:
(a) For any breach of this Agreement or for any cause of action that arises out of this Agreement; or
(b) For the taking, impairment, or restriction of any right or interest conveyed, provided under or arising under this Agreement; or (c) Arising out of or connected with any dispute, controversy or issue regarding the application or interpretation or effect of the provisions of this Agreement. 275
26 8.2 Specific Performance.
8.2.1 The parties acknowledge that money damages and remedies at law generally are inadequate and specific performance and other non-monetary relief are particularly appropriate remedies for the enforcement of this Agreement and should be available to all parties for the following reasons:
(a) Monetary damages are unavailable against City as provided in Section 8.1 above.
(b) Due to the size, nature and scope of the Project, it may not be practical or possible to restore the Property to its natural condition once implementation of this Agreement has begun. After such time, Owner may be precluded from other options it may have had with regard to the Property or any portions thereof. Moreover, Owner has invested significant time and resources in the planning and processing of the Project. Owner will be investing even more time and resources in implementing the Project in reliance upon this Agreement and it is not possible to determine the sum of money that would adequately compensate Owner for such efforts.
8.3 Release. Except for non-damage remedies, including the remedy of specific performance as provided in Section 8.2, Owner, for itself, its successors and assignees, releases City, its officials, officers, agents and employees from any and all claims, demands, actions, or suits of any kind or nature arising out of any liability, known or unknown, present or future, including, but not limited to, any claim or liability based upon Article I, Section 19 of the California Constitution, the Fifth Amendment of the United States Constitution, or any other law or ordinance that seeks to impose any other liability or damage, whatsoever upon City because it entered into this Agreement or because of the terms of this Agreement.
8.4 City's Termination of Agreement or Exercise of Other Remedies Upon Owner's Default. City may terminate or modify this Agreement as to all or a portion of the Property upon Owner's failure to perform any material duty or obligation under this Agreement, or to comply in good faith with the terms of this Agreement (hereinafter referred to as "default"); provided, however, City may modify or terminate this Agreement pursuant to this Section only after providing written notice to Owner of default setting forth the nature of the default and the actions, if any, required by Owner to cure such default and, where the default can be cured, if Owner fails to cure the default within sixty (60) days after its receipt of the notice, or if the default is of a type that cannot be cured within sixty (60) days but can be cured within a longer time, and Owner fails to commence the actions necessary to cure the default within sixty (60) days and to diligently proceed to cure the default.
8.5 Owner's Termination of Agreement or Exercise of Other Remedies Upon City's Default. Owner may terminate this Agreement only in the event of a default by City in the performance of a material term of this Agreement and only after providing written notice to City of default setting forth the nature of the default and the actions, if any, required by City to cure such default and, where the default can be cured, City has failed to take such actions and cure such default within 60 days after the effective date of such notice or, in the event that such default cannot be cured within such 60 day period but can be cured within a longer time, has failed to 276
27 commence the actions necessary to cure such default within such 60 day period and to diligently proceed to complete such actions and cure such default.
8.6 Informal Resolution. The parties recognize that good faith disagreements may arise between City and Owner during the administration and implementation of this Agreement.
The parties will meet and confer in a good-faith attempt to resolve any dispute and will consider alternative dispute resolution mechanisms.
9. THIRD PARTY LITIGATION
9.1 General Plan Litigation. City has determined that this Agreement is consistent with its Comprehensive General Plan, herein called General Plan, and that the General Plan meets all requirements of law. Owner has reviewed the General Plan and concurs with City’s determination.
City shall have no liability in damages under this Agreement for any failure of City to perform under this Agreement or the inability of Owner to develop the Property as contemplated by the Development Plan of this Agreement as the result of a judicial determination that on the Effective Date, or at any time thereafter, the General Plan, or portions thereof, are invalid or inadequate or not in compliance with law.
9.2 Third-Party Litigation Concerning Agreement. Owner shall defend, at its expense, including attorneys’ fees, indemnify, and hold harmless City, its agents, officers and employees from any claim, action or proceeding against City, its agents, officers, or employees to attack, set aside, void, or annul the approval of this Agreement or the approval of any permit granted pursuant to this Agreement. City shall promptly notify Owner of any such claim, action or proceeding, and City shall cooperate in the defense. If City fails to promptly notify Owner of any such claim, action or proceeding, or if City fails to cooperate in the defense, Owner shall not thereafter be responsible to defend, indemnify, or hold harmless City. City may in its discretion participate in the defense of any such claim, action or proceeding. Anything in this Agreement to the contrary notwithstanding, the Term set forth in Section 4.3 of this Agreement and the expiration date of all Development Approvals will automatically be extended by the longer of (i) the number of days in the period commencing on the date of filing any legal action of the type described in this Section and ending on the date that the claim, action or proceeding is either settled or fully and finally resolved in City’s and Owner’s favor, as evidenced by the expiration of all appeal periods with no further appeal being filed or the issuance of a full, final and non-appealable judgment or decisions; or (ii) the number of days in the period commencing on the date that a referendum conceding the Development Approvals is timely qualified for the ballot and the date that a referendum is certified resulting in upholding and approving the Development Approvals.
City will execute, in recordable form, any instrument which Owner may reasonably require to evidence the extension.
9.3 Indemnity. In addition to the provisions of Section 9.2, Owner shall indemnify and hold City, its officers, agents, employees and independent contractors free and harmless from any liability whatsoever, based or asserted upon any act or omission of Owner, its officers, agents, employees, subcontractors and independent contractors, for property damage, bodily injury, or death (Owner's employees included) or any other element of damage of any kind or nature, relating 277
28 to or in any way connected with or arising from the activities contemplated hereunder, including, but not limited to, the study, design, engineering, construction, completion, failure and conveyance of the public improvements, save and except claims and damages to the extent caused by the negligence or willful misconduct of City or its officers, agents, employees, contractors, subcontractors, and independent contractors. Owner shall defend, at its expense, including attorneys' fees, City, its officers, agents, employees and independent contractors in any legal action based upon such alleged acts or omissions. City may in its discretion participate in the defense of any such legal action.
9.4 Environmental Assurances. Owner shall indemnify and hold City, its officers, agents, and employees free and harmless from any liability, based or asserted, upon any act or omission of Owner, its officers, agents, employees, subcontractors, predecessors in interest, successors, assigns and independent contractors for any violation of any federal, state or local law, ordinance or regulation relating to industrial hygiene or to environmental conditions on, under or about the Property, including, but not limited to, soil and groundwater conditions, and Owner shall defend, at its expense, including attorneys' fees, City, its officers, agents and employees in any action based or asserted upon any such alleged act or omission. City may in its discretion participate in the defense of any such action.
9.5 Reservation of Rights. With respect to Sections 9.2, 9.3 and 9.4 herein, City reserves the right to either (1) approve the attorney(s) which Owner selects, hires or otherwise engages to defend City hereunder, which approval shall not be unreasonably withheld, or (2) conduct its own defense, provided, however, that Owner shall reimburse City upon written request for any and all reasonable expenses incurred for such defense, including attorneys' fees, upon billing and accounting therefor. If City chooses to conduct its own defense, City’s separate counsel’s billing rates shall be identical to the rates City pays for its typical municipal litigation rates for legal challenges for the type being defended.
10. MORTGAGEE PROTECTIONS
The parties hereto agree that this Agreement shall not prevent or limit Owner, in any manner, at Owner's sole discretion, from encumbering the Property or any portion thereof or any improvement thereon by any mortgage, deed of trust or other security device securing financing with respect to the Property. City acknowledges that the lenders providing such financing may require certain Agreement interpretations and modifications and agrees upon request, from time to time, to meet with Owner and representatives of such lenders to negotiate in good faith any such request for interpretation or modification. City will not unreasonably withhold its consent to any such requested interpretation or modification provided such interpretation or modification is consistent with the intent and purposes of this Agreement. Any Mortgagee of the Property shall be entitled to the following rights and privileges:
(a) Neither entering into this Agreement nor a breach of this Agreement shall defeat, render invalid, diminish, or impair the lien of any mortgage on the Property made in good faith and for value, unless otherwise required by law. (b) The Mortgagee of any mortgage or deed of trust encumbering the Property, or any part thereof, which Mortgagee, has submitted a request in writing to the City in 278
29 the manner specified herein for giving notices, shall be entitled to receive written notification from City of any default by Owner in the performance of Owner's obligations under this Agreement. (c) If City timely receives a request from a Mortgagee requesting a copy of any notice of default given to Owner under the terms of this Agreement, City shall provide a copy of that notice to the Mortgagee within ten (10) days of sending the notice of default to Owner.
The Mortgagee shall have the right, but not the obligation, to cure the default during the remaining cure period allowed Owner under this Agreement.
(d) Any Mortgagee who comes into possession of the Property, or any part thereof, pursuant to foreclosure of the mortgage or deed of trust, or deed in lieu of such foreclosure, shall take the Property, or part thereof, subject to the terms of this Agreement.
Notwithstanding any other provision of this Agreement to the contrary, no Mortgagee shall have an obligation or duty under this Agreement to perform any of Owner's obligations or other affirmative covenants of Owner hereunder, or to guarantee such performance; provided, however, that to the extent that any covenant to be performed by Owner is a condition precedent to the performance of a covenant by City, the performance thereof shall continue to be a condition precedent to City' s performance hereunder, and further provided that any sale, transfer or assignment by any Mortgagee in possession shall be subject to the provisions of Section 2.4 of this Agreement.
11. MISCELLANEOUS PROVISIONS
11.1 Recordation of Agreement. This Agreement and any amendment or cancellation thereof shall be recorded with the County Recorder by the City Clerk within the period required by Section 65868.5 of the Government Code. Owner agrees that immediately following recordation of the grant deed by which the Owner acquires title, the Owner will immediately record this Development Agreement against the real property.
11.2 Entire Agreement. This Agreement sets forth and contains the entire understanding and agreement of the parties, and there are no oral or written representations, understandings or ancillary covenants, undertakings or agreements which are not contained or expressly referred to herein. No testimony or evidence of any such representations, understandings or covenants shall be admissible in any proceeding of any kind or nature to interpret or determine the terms or conditions of this Agreement.
11.3 Severability. If any term, provision, covenant or condition of this Agreement shall be determined invalid, void or unenforceable, the remainder of this Agreement shall not be affected thereby to the extent such remaining provisions are not rendered impractical to perform taking into consideration the purposes of this Agreement. Notwithstanding the foregoing, the provision of the public benefits set forth in Section 4 of this Agreement, including the payment of the fees set forth therein, are essential elements of this Agreement and City would not have entered into this Agreement but for such provisions, and therefore in the event such provisions are determined to be invalid, void or unenforceable, this entire Agreement shall be null and void and of no force and effect whatsoever.
279
30 11.4 Interpretation and Governing Law. This Agreement and any dispute arising hereunder shall be governed and interpreted in accordance with the laws of the State of California.
This Agreement shall be construed as a whole according to its fair language and common meaning to achieve the objectives and purposes of the parties hereto, and the rule of construction to the effect that ambiguities are to be resolved against the drafting party shall not be employed in interpreting this Agreement, all parties having been represented by counsel in the negotiation and preparation hereof.
11.5 Section Headings. All Section headings and subheadings are inserted for convenience only and shall not affect the construction or interpretation of this Agreement.
11.6 Singular and Plural. As used herein, the singular of any word includes the plural.
11.7 Joint and Several Obligations. If at any time during the term of this Agreement the Property is owned, in whole or in part, by more than one Owner, all obligations of such Owner under this Agreement shall be joint and several, and the default of any such Owner shall be the default of all such Owners. Notwithstanding the foregoing, no Owner of a single lot which has been finally subdivided and sold to such Owner as a member of the general public or otherwise as an ultimate user shall have any obligation under this Agreement except as provided under Section 4 hereof.
11.8 Time of Essence. Time is of the essence in the performance of the provisions of this Agreement as to which time is an element.
11.9 Waiver. Failure by a party to insist upon the strict performance of any of the provisions of this Agreement by the other party, or the failure by a party to exercise its rights upon the default of the other party, shall not constitute a waiver of such party's right to insist and demand strict compliance by the other party thereafter.
11.10 No Third Party Beneficiaries. This Agreement is made and entered into for the sole protection and benefit of the parties and their successors and assigns. No other person shall have any right of action based upon any provision of this Agreement.
11.11 Force Majeure. Neither party shall be deemed to be in default where failure or delay in performance of any of its obligations under this Agreement is caused by floods, earthquakes, epidemics, pandemics, other acts of God, fires, wars, riots or similar hostilities, strikes and other labor difficulties beyond the party's control, (including the party's employment force), government regulations, court actions (such as restraining orders or injunctions), or other causes beyond the party's control. If any such events shall occur, the Term of this Agreement and the time for performance by either party of any of its obligations hereunder will be extended for the period of time that such events prevented such performance, provided that the Term of this Agreement shall not be extended under any circumstances due to a force majeure event for more than five (5) years.
11.12 Mutual Covenants. The covenants contained herein are mutual covenants and also constitute conditions to the concurrent or subsequent performance by the party benefited thereby of the covenants to be performed hereunder by such benefited party. 280
31 11.13 Successors in Interest. Except as specifically set forth in this Agreement, the burdens of this Agreement shall be binding upon, and the benefits of this Agreement shall inure to, all successors in interest to the parties to this Agreement. All provisions of this Agreement shall be enforceable as equitable servitudes and constitute covenants running with the land. Each covenant to do or refrain from doing some act hereunder with regard to the Development of the Property: (a) is for the benefit of and is a burden upon every portion of the Property; (b) runs with the Property and each portion thereof; and, (c) is binding upon each party and each successor in interest during ownership of the Property or any portion thereof.
11.14 Counterparts. This Agreement may be executed by the parties in counterparts, which counterparts shall be construed together and have the same effect as if all of the parties had executed the same instrument.
11.15 Jurisdiction and Venue. Any action at law or in equity arising under this Agreement or brought by a party hereto for the purpose of enforcing, construing or determining the validity of any provision of this Agreement shall be filed and tried in the Superior Court of the County of San Bernardino, State of California, and the parties hereto waive all provisions of law providing for the filing, removal or change of venue to any other court.
11.16 Project as a Private Undertaking. It is specifically understood and agreed by and between the parties hereto that the development of the Project is a private development, that neither party is acting as the agent of the other in any respect hereunder, and that each party is an independent contracting entity with respect to the terms, covenants and conditions contained in this Agreement. No partnership, joint venture, or other association of any kind is formed by this Agreement. The only relationship between City and Owner is that of a government entity regulating the development of private property by the Owner of such property.
11.17 Further Actions and Instruments. Each of the parties shall cooperate with and provide reasonable assistance to the other to the extent contemplated hereunder in the performance of all obligations under this Agreement and the satisfaction of the conditions of this Agreement.
Upon the request of either party at any time, the other party shall promptly execute, with acknowledgment or affidavit if reasonably required, and file or record such required instruments and writings and take any actions as may be reasonably necessary under the terms of this Agreement to carry out the intent and to fulfill the provisions of this Agreement or to evidence or consummate the transactions contemplated by this Agreement.
11.18 Eminent Domain. No provision of this Agreement shall be construed to limit or restrict the exercise by City of its power of eminent domain.
11.19 Agent for Service of Process. In the event Owner is not a resident of the State of California or it is an association, partnership or joint venture without a member, partner or joint venturer resident of the State of California, or it is a foreign corporation, then in any such event, Owner shall file with the Planning Director, upon its execution of this Agreement, a designation of a natural person residing in the State of California, giving his or her name, residence and business addresses, as its agent for the purpose of service of process in any court action arising out of or based upon this Agreement, and the delivery to such agent of a copy of any process in any such action shall constitute valid service upon Owner. If for any reason service of such process 281
32 upon such agent is not feasible, then in such event Owner may be personally served with such process out of this County and such service shall constitute valid service upon Owner. Owner is amenable to the process so served, submits to the jurisdiction of the Court so obtained and waives any and all objections and protests thereto. Owner for itself, assigns and successors hereby waives the provisions of the Hague Convention (Convention on the Service Abroad of Judicial and Extra Judicial Documents in Civil or Commercial Matters, 20 U.S.T. 361, T.I.A.S. No. 6638).
11.20 Authority to Execute. The person or persons executing this Agreement on behalf of Owner warrants and represents that he or she/they have the authority to execute this Agreement on behalf of his or her/their corporation, partnership, or business entity and warrants and represents that he or she/they has/have the authority to bind Owner to the performance of its obligations hereunder.
[Signatures on following pages]
282
33 SIGNATURE PAGE TO
DEVELOPMENT AGREEMENT BETWEEN
THE CITY OF FONTANA
AND POPLAR SOUTH DC, LLC
City
CITY OF FONTANA,
a California municipal corporation
By:
Acquanetta Warren, Mayor
By:
Matthew Ballantyne, City Manager
LIT INDUSTRIAL LIMITED PARTNERSHIP,
a Delaware limited partnership
By: LIT Holdings, GP, LLC,
a Delaware limited liability company,
its general partner
By:
Name: Michael Marrone
Title: Senior Vice President
ATTEST:
By:
Germaine Key, City Clerk
APPROVED AS TO LEGAL FORM:
BEST BEST & KRIEGER LLP
Ruben Duran, City Attorney
283
34 ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California )
County of ______________________ )
On _________________________, before me, ,
(insert name of notary)
Notary Public, personally appeared ,
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
284
35 ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California )
County of ______________________ )
On _________________________, before me, ,
(insert name of notary)
Notary Public, personally appeared ,
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
285
36 EXHIBIT A
TO DEVELOPMENT AGREEMENT BETWEEN
THE City OF FONTANA AND POPLAR SOUTH DC, LLC
Legal Description of the Property
Real property in the City of Fontana, County of San Bernardino, State of California, described as follows: TENTATIVE PARCEL MAP NO. 20638, BEING A DIVISION OF THEFOLLOWING:
TRACT 1: (APN 0237-171-04-0-000)
LOT 16, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 2: (APN 0237-171-03-0-000)
LOT 17 OF TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OFSAID COUNTY.
TRACT 3: (APN 0237-171-02-0-000)
LOT 18 OF TRACT NO. 3074 IN THE UNINCORPORATED AREA, COMMONLY
KNOWN AS FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE14 OF MISCELLANEOUS MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAN BERNARDINO COUNTY.
TRACT 4: (APN 0237-171-01-0-000)
LOT 19 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATEOF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 5: (APN 0237-171-05-0-000)
LOT 15, TRACT 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 6: (APN 0237-171-06-0-000)
LOT 14 OF TRACT NO. 3074, AS PER MAP RECORDED IN BOOK 43, PAGE 14 286
37 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 7: (APN 0237-171-07-0-000)
LOT 13 OF TRACT 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA AS PER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAIDCOUNTY.
TRACT 8: (APN 0237-171-08-0-000)
LOT 12, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 9: (APN 0237-171-09-0-000)
LOT 11 OF TRACT 3074, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICEOF THE SAN BERNARDINO COUNTY RECORDER.
TRACT 10: (APN 0237-171-10-0-000)
LOT 10, TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, RECORDS OF SAIDCOUNTY.
TRACT 11: (APN 0237-171-11-0-000)
LOT 9 OF TRACT 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, CALIFORNIA ASPER MAP RECORDED IN BOOK 43, PAGE(S) 14, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 12: (APN 0237-171-12-0-000)
LOT 8 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATEOF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAN BERNARDINO COUNTY.
TRACT 13: (APN 0237-171-13-0-000)
LOT 7, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, OF MISCELLANEOUS MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 14: (APN 0237-171-14-0-000)
LOT 6, TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS 287
38 OF SAID COUNTY.
TRACT 15: (APN 0237-171-15-0-000)
LOT 5, TRACT NO. 3074, AS PER PLAT RECORDED IN BOOK 43, OF MAPS PAGE 14, IN THE OFFICEOF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 16: (APN 0237-171-16-0-000)
LOT 4 OF TRACT 3074 AS SHOWN ON A MAP THEREOF RECORDED IN BOOK 43, PAGE(S) 44 OF MISCELLANEOUS MAPS IN THE OFFICE OF THE COUNTY RECORDER OF SAIDCOUNTY.
TRACT 17: (APN 0237-171-17-0-000)
LOT 1, TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 18: (APN 0237-171-18-0-000)
LOT 2, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 19: (APN 0237-171-19-0-000)
LOT 3 OF TRACT 3074, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICEOF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 20: (APN 0237-172-05-0-000)
LOT 20 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF
SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 21: (APN 0237-172-04-0-000)
LOT 21 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATEOF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 22: (APN 0237-172-03-0-000)
LOT 22, TRACT 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE(S) 14, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OFSAID COUNTY.
288
39 TRACT 23: (APN 0237-172-02-0-000)
LOT 23, TRACT 3074, COUNTY OF SAN BERNARDINO, STATE OF
CALIFORNIA, AS PER PLATRECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 24: (APN 0237-172-01-0-000)
LOT 24, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 25: (APNS 0237-172-06-0-000 AND0237-172-07-0-000) LOT 25 AND 26 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO,STATE OF CALIFORNIA, AS PER MAP, RECORDED IN BOOK 43, PAGE 14 OF MAPS IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 26: (APN 0237-172-08-0-000)
LOT 27, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 27: (APN 0237-172-09-0-000)
LOT 28, TRACT NO. 3074, AS PER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 28: (APN 0237-172-10-0-000)
LOT 29 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 29: (APN 0237-172-11-0-000)
LOT 30, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 30: (APN 0237-172-12)
THE WEST 75 FEET OF THE SOUTH 340 FEET OF THE EAST ONE-HALF OF THE FARM LOT 863, ACCORDING TO THE MAP SHOWING SUBDIVISION OF
LANDS BELONGING TO THE SEMI-TROPIC LAND AND WATER COMPANY, IN THE
COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 11 OF MAPS, PAGE 12, IN THE OFFICE OF COUNTY 289
40 RECORDER OF SAIDCOUNTY.
TRACT 31: (APN 0237-172-32-0-000)
PARCEL NO. 1:
THE WEST 1/2 OF THE EAST 150 FEET OF THE WEST 225 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF LOT 863, ACCORDING TO MAP SHOWING
SUBDIVISION OF LAND BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
PARCEL NO. 2:
AN EASEMENT FOR INGRESS AND EGRESS OVER THE WESTERLY 10 FEET OF THE EAST 1/2 OF THE EAST 150 FEET OF THE WEST 225 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF LOT 863, ACCORDING TO MAP SHOWING
SUBDIVISION OF LAND BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
TRACT 32: (APN 0237-172-33-0-000)
THE EAST 75.00 FEET OF THE WEST 225 FEET OF THE SOUTH 340.00 FEET TO THE EAST HALF OFLOT 863, ACCORDING TO THE MAP SHOWING
SUBDIVISION OF LAND BELONGING TO SEMI TROPIC LAND AND WATER COMPANY, AS PER MAY RECORDED IN BOOK 11, PAGE 12, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 33: (APN 0237-172-26-0-000)
THE EAST 75 FEET OF THE WEST 300 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF FARM LOT 863, ACCORDING TO MAP SHOWING SUBDIVISION OF
LANDS BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY, AS PER PLAT RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
AREA AND DISTANCES OF THE ABOVE DESCRIBED PROPERTY
COMPUTED TO STREETCENTERS. TRACT 34: (APN 0237-172-27-0-000) THE EAST 75 FEET OF THE WEST 375 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF FARM LOT 863 ACCORDING TO MAP SHOWING SUBDIVISION
OF LANDS BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY IN THE
CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
TRACT 35: (APN 0237-172-19-0-000)
THE WEST 75 FEET OF THE EAST 285 FEET OF THE SOUTH 340 FEET OF THE 290
41 FARM LOT 863, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO,
STATE OF CALIFORNIA, ACCORDING TO MAP SHOWING SUBDIVISION OF LAND
BELONGINGS TO SEMI-TROPIC LAND AND WATER COMPANY AS PER MAP RECORDED IN BOOK 11, PAGE 12 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 36: (APN 0237-172-23-0-000)
THE SOUTH 340 FEET OF THE EAST 1/2 OF LOT 863, ACCORDING TO THE
MAP SHOWN IN SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC
LAND AND WATER COMPANY, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 11 PAGE12, OF MAPS, RECORDS OF SAID COUNTY.
EXCEPTING THEREFROM THE WEST 450 FEET THEREOF.
ALSO EXCEPTING THEREFROM THE SOUTH 260 FEET THEREOF.
AREA AND DISTANCES ARE COMPUTED TO STREET CENTERS
AS SHOWN ON SAID MAP. TRACT 37: (APN 0237-172-30-0-000) PARCEL 1:
THE NORTH 65 FEET OF THE SOUTH 260 FEET OF THE EAST 1/2 OF FARM LOT 863, ACCORDINGTO MAP SHOWING SUBDIVISION OF LANDS BELONGING
TO THE SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAIDCOUNTY.
EXCEPT THE WEST 450 FEET THEREOF.
AREAS AND DISTANCES COMPUTED TO STREET CENTERS AS
SHOWN ON SAID MAP. PARCEL 2:
A RIGHT OF WAY FOR INGRESS AND EGRESS OVER AND ACROSS THE NORTH 6 FEET OF THE EAST125 FEET OF THE SOUTH 195 FEET OF SAID LOT 863.
TRACT 38: (APN 0237-172-31-0-000)
THE NORTH 65 FEET OF THE SOUTH 195 FEET OF THE EAST 1/2 OF FARM LOT 863, ACCORDING TO MAP SHOWING SUBDIVISION OF LANDS BELONGING
TO THE SEMI-TROPIC LAND AND WATER COMPANY, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 11, PAGE 12, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
EXCEPTING THEREFROM, THE WEST 450 FEET THEREOF.
AREAS AND DISTANCES COMPUTED TO STREET CENTERS AS
SHOWN ON SAID MAP. TRACT 39: (APN 0237-172-28-0-000)
THE SOUTH 65 FEET OF THE NORTH 195 FEET OF THE SOUTH 260 FEET OF 291
42 THE EAST HALF OF FARM LOT 863, IN THE CITY OF FONTANA, COUNTY OF SAN
BERNARDINO, STATE OF CALIFORNIA, ACCORDING TO MAP SHOWING
SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
EXCEPTING THEREFROM THE WEST 150 FEET THEREOF, AREAS AND DISTANCES COMPUTEDTO STREET CENTERS.
TRACT 40: (APN 0237-172-22-0-000)
THE SOUTH 65 FEET OF THE EAST 1/2 OF FARM LOT 863, ACCORDING TO
MAP SHOWING SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC LAND
AND WATER COMPANY, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 11 OFMAPS, PAGE(S) 12, RECORDS OF SAID COUNTY.
EXCEPTING THEREFROM THE WEST 450 FEET THEREOF.
NOTE: AREA AND DISTANCES COMPUTED TO STREET CENTERS.
APN: 0237-171-01, 0-000, 0237-171-02-0-000, 0237-171-03-0-000, 0237-171-04-0- 000, 0237-171-05-0-000, 0237-171-06-0-000, 0237-171-07-0-000, 0237-171-08-0-000, 0237- 171-09-0-000, 0237-171-10-0-000, 0237-171-11-0-000, 0237-171-12-0-000, 0237-171-13-0- 000, 0237-171-14-0-000, 0237-171-15-0-000, 0237-171-16-0-000, 0237-171-17-0-000, 0237- 171-18-0-000, 0237-171-19-0-000, 0237-172-01-0-000, 0237-172-02-0-000, 0237-172-03-0- 000, 0237-172-04-0-000, 0237-172-05-0-000, 0237-172-06-0-000, 0237-172-07-0-000, 0237- 172-08-0-000, 0237-172-09-0-000, 0237-172-10-0-000, 0237-172-11-0-000, 0237-172-12-0- 000, 0237-172-19-0-000, 0237-172-22-0-000, 0237-172-23-0-000, 0237-172-26-0-000, 0237- 172-27-0-000, 0237-172-28-0-000, 0237-172-30-0-000, 0237-172-31-0-000, 0237-172-32-0- 000 and 0237-172-33-0-000 (Referenced for informational purposesonly) 292
43 EXHIBIT B
TO DEVELOPMENT AGREEMENT BETWEEN
THE City OF FONTANA AND POPLAR SOUTH DC, LLC
EXHIBIT B – Map Showing Property and its location:
293
44 294
EXHIBIT C
TO DEVELOPMENT AGREEMENT BETWEEN
THE City OF FONTANA AND POPLAR SOUTH DC, LLC
Existing Development Approval
295
46 296
47 297
48 298
49 299
50 300
51 301
City of Fontana
Action Report
Planning Commission
8353 Sierra Avenue
Fontana, CA 92335
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
FROM:
Planning Department
TITLE:
Master Case No. 22-079: General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Agreement (AGR) No. 22-003, Tentative Parcel Map (TPM No. 20638) No. 22-016, Design Review (DRP) No. 22-040, and Final Environmental Impact Report for the development of an industrial commerce building totaling approximately 490,565 square feet within a project site comprised of approximately 18.8 acres.
RECOMMENDATION:
Based on the information contained in this staff report, staff recommends that the Planning Commission adopt Resolution No. PC 2023-_____, and forward a recommendation to the City Council to:
1. Adopt a resolution to certify the EIR, a Mitigation Monitoring and Reporting Program, and a Statement of Facts and Findings, and direct staff to file a Notice of Determination; and,
2. Adopt a resolution approving General Plan Amendment (GPA) No. 22-007; and,
3. Adopt an ordinance approving Specific Plan Amendment (SPA) No. 22-003; and,
4. Adopt an ordinance approving Development Agreement (AGR) No. 22-003; and,
5. Adopt a resolution approving Tentative Parcel Map No. 22-016 (TPM No. 20638) and Design Review No. 22-040 subject to the attached Findings and Conditions of Approval.
APPLICANT:
Seefried Industrial Properties, INC
2321 Rosecrans Ave, Suite No. 2220
El Segundo, CA 90245
LOCATION:
The project site includes property located to the east side of Poplar Avenue, west of Catawba Avenue and on properties along Rose Avenue (APNs) 0237-171-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -13, -14, -15, -6, -17, -18, -19, and 0237-172-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, - 11, -12, -19, -22, -23, -26, -27, -28, -30, -31, -32, and 33.
REQUEST:
1. General Plan Amendment (GPA) No. 22-007 - a request to amend Exhibit 15.8 of the General Plan for an 18.8-acre site from Residential Trucking (R-T) to General Industrial (I-G).
City of Fontana Page 1 of 7 Printed on 10/11/2023
powered by Legistar™30253
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
2. Specific Plan Amendment (SPA) No. 22-003 - a request to amend the Southwest Industrial Park (SWIP) Specific Plan Land Use Plan to remove the entire 18.8-acre site from the Residential Trucking District (RTD) and include it in the Slover East Industrial District (SED).
3. Development Agreement (AGR) No. 22-003 - an agreement to include the payment of a public benefit fee.
4. Tentative Parcel Map No. 22-016 (TPM No. 20638) - a request to consolidate forty-one (41) parcels comprised of approximately 18.8 acres into one parcel for the development of the project.
5. Design Review (DRP) No. 22-040 - a request for review of the architecture, site design and associated improvements for an industrial commerce center building totaling 490,565 square feet on a site comprised of approximately 18.8 acres.
PROJECT PLANNER:
Alejandro Rico, Associate Planner
BACKGROUND INFORMATION:
A. Existing Land Use Designation:
General Plan Zoning Existing Land Use
Site: Residential Trucking (R
-T)
Southwest Industrial
Park Specific Plan -
Residential Trucking
District (RTD)
Vacant and
existing singlefamily residential
North: General Industrial (I-G) Southwest Industrial
Park Specific Plan -
Slover East Industrial
District (SED)
Industrial
commerce
buildings
South: General Industrial (I-G) Southwest Industrial
Park Specific Plan -
Slover East Industrial
District (SED)
Industrial
commerce
buildings
West: General Industrial (I-G) Southwest Industrial
Park Specific Plan -
Slover East Industrial
District (SED)
Manheim vehicle
storage
PROJECT DESCRIPTION:
A. Project Site Area: Approximately 18.8 acres.
B. Lot Coverage:
City of Fontana Page 2 of 7 Printed on 10/11/2023
powered by Legistar™30354
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
Building Allowed: 63% Percent
Provided: 60% Percent
C. Building/Unit Analysis - Industrial Commerce Building :
Building: Office Area: Approximately 10,000 square feet Commerce Area: Approximately 480,565 square feet
D. Parking Analysis: Required: 158 Spaces
Provided: 210 Spaces
E. Landscaping: Building Required: 15 Percent
Provided: 18 Percent
ANALYSIS:
The applicant is requesting approval of General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Tentative Parcel Map (TPM) No. 22-016, Development Agreement (AGR) No. 22-003 and Design Review (DRP) No. 22-040. The project includes amendment of Chapter 15, Exhibit 15.8, of the General Plan to change the General Plan land use designation from Residential Trucking (RT) to General Industrial (I
‐
G), revision of the Southwest Industrial Park
Specific Plan land use designation of the project site from Residential Trucking District (RTD) to Slover East Industrial District (SED), consolidation of 41 parcels into one parcel, and a request for development of an industrial commerce center building of approximately 490,565 square feet, all on approximately 18.8 acres. The applicant has also prepared a development agreement for consideration that includes a public benefit fee.
General Plan Amendment (GPA) No. 22-007
The current general plan land use designation for the project site is Residential Trucking (R-T) which does not allow for industrial commerce center uses. Therefore, the applicant has applied for a General Plan Amendment to amend Exhibit 15.8 (General Plan Land Use Map) as part of Chapter 15 of the General Plan and change the General Plan land use designation of the 18.8-acre site from Residential Trucking (R-T) to General Industrial (I-G) as shown in Attachment No. 4.
The proposed project is consistent with the goals and policies of the General Plan and Housing Element, as described below:
Chapter 13, Goal No. 1, Action A: Establish a balance of industrial and manufacturing development along with services, especially in sectors with living wage jobs. The developer is proposing to construct an industrial commerce building which will require construction labor. Labor leaders have emphasized that construction jobs have supported families. The operations of the commerce building will require employees for day-to-day operations which will in turn provide jobs for local communities in the long term.
Chapter 15, Goal 1, Action A: Warehousing, trucking, manufacturing, and support industries are focused especially along regional transportation routes. Some of these areas need upgrades in order to increase or maintain competitiveness. The project will include off-site improvements to Poplar Avenue and Catawba Avenue and enhance streets. Santa Ana Avenue and Jurupa Avenue are two truck routes that are located in close proximity to the site and will be accessed from Poplar Avenue City of Fontana Page 3 of 7 Printed on 10/11/2023
powered by Legistar™30455
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
truck routes that are located in close proximity to the site and will be accessed from Poplar Avenue and Catawba Avenue.
Specific Plan Amendment (SPA) No. 22-003
The proposed Specific Plan Amendment would amend the Southwest Industrial Park (SWIP) Specific Plan Land Use Plan (Attachment No. 5) to redesignate the property from Residential Trucking (RTD) to the Slover East Industrial District (SED) land use district.
Development Agreement (AGR) No. 22-003
The application includes a review of development agreement for the provision of a public benefit fee of $2,084,901.
Tentative Parcel Map No. 22-016 (TPM No. 20638)
The applicant has filed for a Tentative Parcel Map to support a proposed development of 18.8 acres and consolidation of forty-one (41) parcels into one parcel for the development of an industrial commerce building. The project is located to the east of Poplar Avenue, west of Catawba Avenue and north and south of Rose Avenue. As part of the project the developer will construct all on-site and offsite improvements per the City Standards. Rose Avenue will be vacated between Poplar Avenue and Catawba Avenue as this street area will be used for the industrial commerce building. Vehicular access to the site will come from four (4) entries from Catawba Avenue and Poplar Avenue.
Design Review (DRP) No. 22-040
The project includes the development of an industrial commerce center building. The industrial commerce center building has been designed with a combination of office and industrial areas and will contain approximately 490,565 square feet of floor area. The developer will construct the necessary on-site and off-site improvements required by city standards. A gate-secured truck court with 42 loading docks is proposed on the south side of the building. The building’s tower entries, glass features, painted bands, articulated window framing with glazing provide structural and visual interest. The applicant has incorporated a variety of architectural features on all sides of the building to meet or exceed the design guidelines of the Southwest Industrial Park Specific Plan, Slover East Industrial District design guidelines.
The project site is physically suitable in size and shape to support the development of the proposed industrial commerce building. The applicable building codes, zoning codes, and fire codes and standards will be incorporated and will make for a safe, attractive, and well-designed project. As proposed, the project site is consistent with the standards of the Southwest Industrial Park Specific Plan, Slover East Industrial District. The proposal has been designed to be compatible with the industrial uses of nearby, while also providing a development that has been designed with features (architectural relief, added landscaping along the north side of the property, street improvements, and lighting), to enhance the character of the area. The project meets all the requirements of the recently adopted Industrial Commerce Centers Sustainability Standards Ordinance.
Circulation/Grading
City of Fontana Page 4 of 7 Printed on 10/11/2023
powered by Legistar™30556
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
Trucks will have access from the southern driveways on Poplar Avenue and Catawba Avenue and regular vehicles will have access from separate driveways on the northern portion of the site. The proposed landscaping would be ornamental in nature and would feature trees, shrubs, and droughttolerant accent plants in addition to a variety of groundcover. The area surrounding the building will drain to the west with the use of underground chambers towards Poplar Avenue. Trucks will be traveling south and north from Santa Ana Avenue and Jurupa Avenue to and from the project site to access the 10 freeway.
Walls
The project site will have an eight-foot-high sliding gate for the loading areas and a 14-foot-high screen wall surrounding the loading areas. The project includes multiple retaining walls on the south and west side of the building.
SB330
As currently zoned, this property would have allowed for the development of thirty-eight (38) residential units. To comply with California’s Housing Crisis Act of 2019 (SB 330), the project will participate with the City of Fontana Municipal Code Chapter 30 Article XV “No Net Loss Density Bonus/Replacement Program.” The 38 units will be available as density bonuses for other residential properties throughout the city. The program will enable, on a first come, first served basis, density bonuses of up to 20% on other residential parcels until the 38 residential units are reclaimed within future planned residential projects.
Pursuant to FMC section 30-967, the Unit Bank cannot exceed 2,200 units. The Unit Bank currently has 1,280 units. These 38 units will be added to the Unit Bank increasing the number of units in the Unit Bank to 1,318, which is less than the 2,200 units authorized by the FMC.
Environmental
Technical Studies
Subsequent to the preparation and distribution of the Notice of Preparation (NOP), the Draft Environmental Impact Report (DEIR) was prepared for the project. The environmental analysis contained in the Draft EIR is based in part on specific studies and assessments undertaken for the City by qualified environmental scientists, specialists, and consultants. This analysis addresses aesthetics, agriculture and forestry resources, air quality, biological resources, cultural resources, energy, geology and soils, greenhouse gas emissions, hazards and hazardous materials, hydrology and water quality, land use and planning, mineral resources, noise, population and housing, public services, recreation, transportation, tribal cultural resources, utilities and services systems, and wildfire. These technical studies are contained in the Technical Appendices document of the Draft EIR and are made available for the public review. The Draft and Final EIR and Technical Appendices can be viewed at the following URL: <<https://www.fontanaca.gov/2137/Environmental-Documents> >.
The Final EIR describes the environmental impacts of the project and the mitigation measures to help minimize the project impacts on the environment. The scope of this Final EIR includes analysis of City of Fontana Page 5 of 7 Printed on 10/11/2023
powered by Legistar™30657
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
minimize the project impacts on the environment. The scope of this Final EIR includes analysis of environmental issues identified and raised in response to the Notice of Preparation (IS/NOP) and during the DEIR comment period.
The Final EIR determined that seventeen (17) categories of environmental effects for the project would have impacts found not to be significant. These categories are Aesthetics, Agriculture and Forestry, Air Quality, Biological Resources, Cultural Resources, Energy, Geology and Soils, Hazards and Hazardous Materials, Hydrology and Water Quality, Greenhouse Gas Emissions, Land Use and Planning, Mineral Resources, Noise, Population and Housing, Public Services, Recreation, Tribal Cultural Resources, Transportation, Utilities and Services Systems, and Wildfire. The potential impacts from the aforementioned topical areas are fully addressed in the DEIR and can be brought to a level of less than significant with mitigations.
The analysis in the Final EIR and supporting studies found that, even with incorporation of proposed mitigation measures, impacts to Air Quality would remain significant and unavoidable. As a result of the proposed project having an impact that is significant and unavoidable, adoption of a Statement of Overriding Consideration (SOC) by the City Council is required.
Alternatives
As required by CEQA, an EIR shall describe a range of reasonable alternatives to the project which meets the basic objectives of the project but would avoid or substantially lessen any of the significant effects of the project and evaluate the comparative merits of the alternatives. The proposed alternatives for this project include “No Project” and “Reduced Project.” Circulation
The project Draft EIR (DEIR) was circulated for the 45-day public review period beginning on July 14, 2023, and ending on August 28, 2023. The document was submitted to the State Clearinghouse for notification to State agencies for their possible comment. The Planning Commission conducted a public hearing on the DEIR on August 15, 2023 to receive public comments. Prior to the end of the comment period of August 28, 2023, the City received comments on the DEIR from the following public agencies, organizations, and individuals:
Letter Date Received Organization/Name
1 SCAQMD August 18, 2023
2 Golden State Environmental
Justice Alliance
August 25, 2023
3 CARE CA August 28, 2023
4 CARB August 30, 2023
The City, along with the environmental consultant, has reviewed and provided responses to the letters/comments above; these are included in the Final EIR. The Final EIR along with errata has been included with the environmental documentation made available at the following link: < <https://www.fontanaca.gov/2137/Environmental-Documents>>. To approve the project, the City Council must adopt a Statement of Overriding Considerations indicating that the project benefits City of Fontana Page 6 of 7 Printed on 10/11/2023
powered by Legistar™30758
File #: 21-2518 Agenda Date: 10/17/2023
Agenda #: PH-B Category: Public Hearing
override or outweigh the project identified unavoidable environmental impacts.
MOTION:
Approve staff’s recommendation.
ATTACHMENTS:
1. Vicinity Map
2. Tentative Parcel Map No. 20638
3. Project Plans
4. Existing/Proposed General Plan Land Use Designation
5. Existing/Proposed Specific Plan
6. Planning Commission Resolution PC 2023-
7. Development Agreement
8. Notice of Determination
9. Public Hearing Notice
City of Fontana Page 7 of 7 Printed on 10/11/2023
powered by Legistar™30859
ATTACHMENT NO. 1
VICINITY MAP
DATE: October 17, 2023
CASE: Master Case No. 22-079: General Plan
Amendment No. 22-007, Specific Plan
Amendment No. 22-003, Development
Agreement No. 22-003, Tentative Parcel Map
(TPM No. 20638) No. 22-016, Design Review
No. 22-040
NORTH
CITY OF FONTANA PLANNING DEPARTMENT
Project Site
30960
ATTACHMENT NO. 2
TENTATIVE
PARCEL MAP
No. 20638
DATE: October 17, 2023
CASE: Master Case No. 22-079: General Plan
Amendment No. 22-007, Specific Plan
Amendment No. 22-003, Development
Agreement No. 22-003, Tentative Parcel Map
(TPM No. 20638) No. 22-016, Design Review
No. 22-040
NORTH
CITY OF FONTANA PLANNING DEPARTMENT
31061
EVCS
EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV
EV EV EV EV EVCS
EV EV EV EV
EV EV EVCS EVCS EVCS EVCS EVCS EVCS
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL EV EV EVCS EVCS EVCS EVCS LOADING LOADING LOADING T
WB-67 - Interstate Semi-Trailer WB-67 - Interstate Semi-Trailer WB-67 - Interstate Semi-Trailer
WB-67 - Interstate Semi-Trailer
WB-67 - Interstate Semi-Trailer
RGA
Office of Architectural Design
15231 Alton Parkway, Suite 100
Irvine, CA 92618
T 949-341-0920
FX 949-341-0922
POPLAR SOUTH DISTRIBUTION CENTER
FONTANA, CA SHEET TITLE
MARK DATE DESCRIPTION
A1-1P
COPYRIGHT: RGA, OFFICE OF ARCHITECTURAL DESIGN
CHK'D BY:
DRAWN BY:
CAD FILE NAME:
RGA PROJECT NO:
CS
CS
22016-00-A1-01
22016.00
SCHEMATIC SITE PLAN
SCALE: 1" = 50'-0"
Scott Irwin
Senior Vice President – Southern California
SEEFRIED INDUSTRIAL PROPERTIES, INC.
2301 Rosecrans Avenue, Suite 3165
El Segundo, CA 90245
Office: +1 310 536 7900
Cell: +1 562 484 8761
[email protected]
5/20/22 PLANNING SUBMITTAL
50' MIN.
9/2/22 2ND PLANNING SUBMITTAL
9/21/23 PC HEARING SET C A T A W B A A V E .
TYPE III-B
DRY STORAGE WAREHOUSE
40' CLR.
MAX. HT.: 50'
P O P L A R A V E .
0' 10' 20' 50' 100'
30'
34'
30'
44'
81.5' 392'-0" 185'
1,196'-0"
GENERAL PROJECT INFO:
ZONE:
SPECIFIC PLAN:
APN:
SOUTHWEST INDUSTRIAL PARK
SLOVER EAST INDUSTRIAL DISTRICT
PROJECT DATA:
NET SITE AREA:
FOOTPRINT AREA:
MEZZANINE AREA:
TOTAL FLOOR AREA:
OFFICE AREA:
WAREHOUSE AREA:
TOTAL:
BASE ALLOWABLE F.A.R.:
** DEVELOPMENT INCENTIVE FOR LEED CERTIFICATION
PROPOSED F.A.R.
AUTO PARKING REQUIRED
10,000 SF OFFICE (1/250 SF)
0 SF MANUFACTURING (1/600 SF)
480,550 SF WAREHOUSE
1 TO 20,000 SF (1/1,000 SF)
20K TO 40,000 SF (1/2,000 SF)
> 40,0000 SF (1/5,000 SF)
TOTAL REQUIRED:
AUTO PARKING PROVIDED
TRAILER PARKING REQUIRED - 1/5,000 SF
LANDSCAPE:
REQUIRED: 818,382 - 483,500 X 15%
PROVIDED:
819,701 SF / 18.82 AC
480,550 SF
10,000 SF
490,550 SF
10,000 SF
480,550 SF
490,550 SF
0.55 0.6325
0.60 40 STSALLS
0 STALLS
20 STALLS
10 STALLS
88 STALLS
158 STALLS
210 STALLS
98 98
50,232 SF
62,000 SF
VICINITY MAP:
PROJECT DESCRIPTION:
ONE NEW 490,550 SF SPECULATIVE WAREHOUSE BUILDING INTENDED FOR
HIGH CUBE STORAGE, INCLUDING DOCK HIGH LOADING FACILITIES, TRAILER PARKING, 210 AUTO PARKING STALLS, AND LANDSCAPE IMPROVEMENTS.
THE PROJECT WILL BE PURSUING LEED CERTIFICATION, AND PROPOSES TO
UTILIZE THE AVAILABLE INTENSITY BONUS RELATED TO THE GREEN BUILDING INCENTIVE IN TABLE 10-10 OF THE S.W.I.P. SPECIFIC PLAN.
CODE ANALYSIS:
CONSTRUCTION TYPE:
OCCUPANCY:
FIRE SPRINKLERS:
BUILDING HEIGHT:
MAX. ALLOWABLE:
PROPOSED:
STORIES:
MAX. ALLOWABLE:
PROPOSED:
ALLOWABLE AREA
III-B
S-1 PRIMARY OCC.
B / F-1 ACCESSORY
FULLY SPRINKLERED
75'
50'
3 2
UNLIMITED PER CBC 507
21 DOCK POSITIONS
77 TRAILER STALLS
8'H GATE
OFFICE OFFICE RAMP
20' 20'
490,550 SF
8 TRAILER
STALLS
RAMP
202 AUTO STALLS
TRASH
ENCLOSURE
PER CITY STD.
FIRE PUMP
ROOM - SCREEN
W/ LANDSCAPE
942'-8" - 6'H RETAINING WALL + 8'H SCREENWALL
(11) BIKE
RACKS
SEATING
AREA
SANTA ANA AVE.
JURUPA AVE.
POPLAR AVE.
CATAWBA AVE.
CITRUS AVE.
SITE
7' 19' 30' 19' 6.5'
56'
146' 153'
56'
8 AUTOS
35'35'
RIDGELINE - 46'-7" RIDGELINE - 46'-7"
9' TYP.
8'H GATE
14'DEDICATION
SETBACK
SETBACK
SETBACK
SETBACK
RAD.: 50'
RAD.: 50'
RAD.: 50'
RAD.: 50'
RAD.: 25'
RAD.: 25'
RAD.: 25'
RAD.: 25'
1. ANY EXISTING STRUCTURES ONSITE ARE TO BE DEMOLISHED.
2. ALL PROPOSED NEW ONSITE UTILITY SERVICES SHALL BE UNDERGROUND.
3. CONCRETE BANDS, 24" IN WIDTH, SHALL BE PROVIDED AT LANDSCAPE FINGERS.
4. DRIVEWAYS SHALL BE CONSTRUCTED PER CITY STANDARD PLANS.
5. STATE OF CALIFORNIA "GENERAL CONSTRUCTION NPDES PERMITS AND WDID NUMBERS MUST BE OBTAINED PRIOR TO PERMIT.
6. PARKING STALL DIMENSIONS: 9'W X 19'D - DOUBLE STRIPED PER CITY REQUIREMENTS. CLEAN AIR / CARPOOL PARKING SHALL BE PROVIDED PER CALGREEN REQUIREMENTS.
7. FIRE DEPT. APPROVED KNOX LOCKS SHALL BE PROVIDED AT ALL GATES.
8. FIRE DEPT. ACCESS SHALL BE PROVIDED PER STANDARDS:
ACCESS LANE WIDTH: 30'-0"
ACCESS LANE HEIGHT: 14'-6"
INSIDE TURN RADIUS: 19'-0"
GENERAL NOTES:
12' TYP.
8 TRAILER
STALLS
55' 60' 70'
5 TRAILER
STALLS
21 DOCK POSITIONS
13' TYP.
6" X 6" CONC. CURB
3" WIDE WHITE
TRAFFIC PAINT
STRIPING
24" WIDE STEP-OFF
CURB AT
LANDSCAPE
FINGERS / END
STALLS
9'-0" 9'-0" 9'-0"
AUTO PARKING DETAIL:
STANDARD
STALL
END
STALL
19'-0"
24" TYP.
EA. SIDE
9' TYP. 7'
PARKING
FINGER
14'H SCREENWALL
14'H SCREENWALL
14'H SCREENWALL 14'H SCREENWALL
STRIPED MEDIAN
STRIPED MEDIAN
50'
680' - NEW CMU PROPERTY LINE RET. WALL
6' MAX. HEIGHT
30" MAX. HT.
SPLITFACE CMU
RETAINING WALL
30" MAX. HT.
SPLITFACE CMU
RETAINING WALL
(E) 6'-8'H SCREENWALL ON ADJ. PROPERTY TO REMAIN (E) 6'-8'H SCREENWALL ON ADJ. PROPERTY TO REMAIN (E) 6'-8'H SCREENWALL ON ADJ. PROPERTY TO REMAIN 31162
RGA
Office of Architectural Design
15231 Alton Parkway, Suite 100
Irvine, CA 92618
T 949-341-0920
FX 949-341-0922
POPLAR SOUTH DISTRIBUTION CENTER
FONTANA, CA SHEET TITLE
MARK DATE DESCRIPTION
A2-1P
COPYRIGHT: RGA, OFFICE OF ARCHITECTURAL DESIGN
CHK'D BY:
DRAWN BY:
CAD FILE NAME:
RGA PROJECT NO:
CS
CS
22016-00-A2-1P
22016.00
SCHEMATIC FLOOR PLAN 5/20/22 PLANNING SUBMITTAL
9/2/22 2ND PLANNING SUBMITTAL
Scott Irwin
Senior Vice President – Southern California
SEEFRIED INDUSTRIAL PROPERTIES, INC.
2301 Rosecrans Avenue, Suite 3165
El Segundo, CA 90245
Office: +1 310 536 7900
Cell: +1 562 484 8761
[email protected]
9/21/23 PC HEARING SET
TYPE III-B
DRY STORAGE WAREHOUSE
40' CLR.
MAX. HT.: 50'
42 DOCK POSITIONS
OFFICE OFFICE RAMP
480,550 SF +
10,000 SF MEZZANINE
490,550 SF G.F.A.
RAMP
RIDGELINE - 46'-7" RIDGELINE - 46'-7"
SCALE: 1" = 40'-0" 0' 10' 20' 50' 100'
1,196'-0"
54'-0" 9'-6" 176'-0" 81'-0" 175'-0" 81'-0" 175'-0" 81'-0" 175'-0" 9'-6" 54'-0" 56'-6" 448'-0"448'-0"
13'-4"13'-4"
32'-6"32'-6"
54'-0"54'-0"
228'-8"228'-8"
54'-0"54'-0"
56'-6"56'-6"
56'-6"
1,196'-0"
22'-0" 54'-0" 41'-5" 941'-2" 53'-5" 54'-0" 22'-0"
1 TYPICAL TRASH ENLARGED PLAN
SCALE: 1/4" = 1'-0"
15'-8"
4'-8" 7'-6"
3'-8" 12'-0" 6'-4"
12'-2"
3'-2"
8'H STEEL
GATE (34"
MIN. CLR.)
2 -
2 PAINTED METAL GATE -
3" X 3" X 3/8" ANGLE
FRAME WITH 16 GA.
CORRUGATED PANEL -
PAINT TO MATCH
BUILDING
CONCRETE TILT-UP
WALL PAINTED TO
MATCH BUILDING
6'-0"
4"
2"
6" 2'-0" 2'-0" 6" 5" 1"
TRASH ENCLOSURE GATE ELEVATION
SCALE: 1/2" = 1'-0" 01201
2'-0" CLEAR
RESERVED FOR
RECYCLABLES
PLASTICS / METALS
PAPER / GLASS
CARDBOARD
50% OF THE TRASH ENCLOSURE AREA
SHALL BE DESIGNATED FOR STORAGE OF
RECYCLABLE MATERIALS - PROVIDE 24" X
18" METAL SIGN PLATE W/ GREEN
BACKGROUND & WHITE LETTERING
PAINTED CORRUGATED
ROOF DECK, FLASHING
AND STEEL TUBE
STRUCTURE - SEE
STRUCTURAL DRAWINGS
31263
TYP.
TYP.
SHEET TITLE
MARK DATE DESCRIPTION A3-1P
COPYRIGHT: RGA, OFFICE OF ARCHITECTURAL DESIGN
CHK'D BY:
DRAWN BY:
CAD FILE NAME:
RGA PROJECT NO:
CS
CS
22016-00-A3-1
22016.00
SCALE: 1" = 30'-0" 0' 10' 20' 50' 100'
RGA
Office of Architectural Design
15231 Alton Parkway, Suite 100
Irvine, CA 92618
T 949-341-0920
FX 949-341-0922
POPLAR SOUTH DISTRIBUTION CENTER
FONTANA, CA
SCHEMATIC ELEVATIONS
Scott Irwin
Senior Vice President – Southern California
SEEFRIED INDUSTRIAL PROPERTIES, INC.
2301 Rosecrans Avenue, Suite 3165
El Segundo, CA 90245
Office: +1 310 536 7900
Cell: +1 562 484 8761
[email protected]
P-1 SHERWIN WILLIAMS
SW 7005 - PURE WHITE
P-2 SHERWIN WILLIAMS
SW 7072 - ONLINE
P-3 SHERWIN WILLIAMS
SW 7073 - NETWORK GRAY
P-4 SHERWIN WILLIAMS
SW 7005 - SOFTWARE
P-5 CLARION RED
PANTONE 7626C
GL-1 SOLARBAN 60 (2) SOLARGRAY
+ CLEAR INSULATED
9/2/22 2ND PLANNING SUBMITTAL
11/16/22 3RD PLANNING SUBMITTAL
5/20/22 PLANNING SUBMITTAL
9/5/23 4TH PLANNING SUBMITTAL
9/21/23 PC HEARING SET
NORTH ELEVATION
EAST ELEVATION
WEST ELEVATION
SOUTH ELEVATION
51'-0"51'-0"
47'-0"
51'-0"
47'-0"
51'-0"
47'-0"
49'-0"
45'-0"
49'-0"
49'-0"
45'-0"
FINISH LEGEND
14'
14'
PAINTED DOCK
DOOR
8' HIGH BLACK TUBE
STEEL ROLLING GATE AT
TRUCK ENTRANCE
FORMLINER
VERTICAL BAND
14' PAINTED CONCRETE
TILT-UP SCREENWALL
CLERESTORY
WAREHOUSE
WINDOWS
FORMLINER
VERTICAL BAND
PRIMARY
ENTRANCE
PRIMARY
ENTRANCE
STEEL TRELLIS
OVER ENTRY
PAINTED GRADE
RAMP DOOR
8' HIGH BLACK TUBE
STEEL ROLLING GATE AT
TRUCK ENTRANCE
14' PAINTED CONCRETE
TILT-UP SCREENWALL
NOTES:
1. ALL ROOFTOP MECH. EQUIPMENT
SHALL BE SCREENED FROM VIEW.
14'H FIRE PUMP
BUILDING
4'
51'-0"
51'-0"
47'-0"
4'
4'
4'
4'4'4'
4'4'
51'-0"
4'
FIRE PUMP
ELEVATIONS
SOUTH EAST NORTH
SOUTH RETAINING WALL / SCREENWALL ELEVATION
8'
8'
31364
206 AUTO STALLS 9'
5'-9"
5'-9"
5'-9" 9' 9' 9' 2 211 FOUNDATION PLANTING / HEDGE SCREEN - MED WATER - 5 GAL Buxus microphylla japonica `Green Beauty` / Green Beauty Boxwood Juniperus chinensis `Spartan` / Spartan Juniper
Ligustrum texanum / Texas Privet
Nandina domestica / Heavenly BambooPodocarpus gracilior `Column` / Fern PineRhaphiolepis indica `Jack Evans` / Indian Hawthorn Xylosma congestum / Shiny Xylosma SCREEN PLANTING - LOW WATER - 5 & 15 GAL Callistemon citrinus `Little John` / Dwarf Bottle Brush Eleagnus pungens / Silverberry Rosmarinus officinalis `Tuscan Blue` / Tuscan Blue Rosemary Westringia fruticosa / Coast Rosemary CONCEPT PLANT SCHEDULE TREES BOTANICAL / COMMON NAME CONT WUCOLS QTY Geijera parviflora / Australian Willow 24"box Med 14 Koelreuteria bipinnata / Chinese Flame Tree - Standard 24"box Med 16 Koelreuteria bipinnata / Chinese Flame Tree Standard 36"box Med 20 Lagerstroemia x `Muskogee` / Lavender Crape Myrtle Std. 24"box Med 15 Pinus eldarica / Afghan Pine 24"box Low 52 SIZE - 24" BOX - WATER USE - WULCOL - LOW Pinus eldarica / Afghan Pine 36"box Low 5 Rhus lancea / African Sumac 24"box Low 40 Tristania conferta / Brisbane Box 24"box Med 32 TREE LEGEND ACCENT SHRUBS - LOW WATER USE - 5 GAL. Agave desmettiana `Variegata` / Variegated Agave Agave x `Blue Flame` / Blue Flame Agave Callistemon citrinus `Little John` / Dwarf Bottle Brush Leucophyllum frutescens `Green Cloud` TM / Green Cloud Texas Ranger Muhlenbergia capillaris / Pink Muhly Muhlenbergia capillaris `Autumn Blush` / Pink Muhly Rosmarinus officinalis `Tuscan Blue` / Tuscan Blue Rosemary Salvia clevelandii `Allen Chickering` / Cleveland Sage Salvia greggii `Furmans Red` / Furman`s Red Salvia Westringia fruticosa / Coast Rosemary SHRUB PALETTE - MEDIUM WATER USE Buxus x `Green Gem` / Green Gem Boxwood Ligustrum texanum / Texas Privet Nandina domestica / Heavenly Bamboo Rhaphiolepis indica `Clara` / Indian Hawthorn Rhaphiolepis indica `Jack Evans` / Indian Hawthorn Rosa floribunda `Iceberg` / Iceberg Rose Xylosma congestum / Shiny Xylosma GROUND COVER PALETTE - LOW WATER USE - 1 GAL Acacia redolens `Desert Carpet` TM / Bank Catclaw Space 4` o.c. Baccharis pilularis `Pigeon Point` / Coyote Brush - Space 4` o.c. Myoporum parvifolium `Putah Creek` / Putah Creek Myoporum Space 3` o.c. Rosmarinus officinalis `Huntington Carpet` / Huntington Carpet Rosemary - Space 3` o.c. GROUND COVER PALETTE - MEDIUM WATER USE - 1 GAL Rosa x `Flower Carpet Pink` / Rose Rosa x `Flower Carpet Red` / Rose Trachelospermum jasminoides / Star Jasmine EARTHWORKS (951)782-0260 SHREDDED MULCH NOTE ALL PLANTER AREAS TO RECEIVE A 3" LAYER OF SHREDDED COVER MULCH AVAILABLE FROM BOTH DIRECTIONS FOR A TOTAL OF 10' 1. ALL TREES WITHIN 6' OF HARDSCAPE SHALL BE IN A SHAWTOWN LINEAR (WRAP AROUND NOT ALLOWED) ROOT BARRIER 24" HIGH LINEAR ROOT BARRIER SHALL BE CENTERED ON TREE AND EXTEND 5' IN NOTES 2. NOTE: QUANTITIES AND AREA CALCULATIONS SHOWN IN LEGEND ARE FOR REFERENCE ONLY . CONTRACTOR REPONSIBLE FOR ALL QUANTITY TAKE-OFFS AND AREA CALCULATIONS FOR DETERMINING COST AND DELIVERY OF MATERIALS TO SITE. SYMBOL DESCRIPTION 3" THICK 3/4" NATURAL COLORED CRUSHED ROCK OVER WEED BARRIER 6"X6" CONCRETE MOW CURB TO SEPARATE SHRUB AREAS FROM DECORATIVE GRAVEL 12REFERENCE NOTES SCHEDULE 09/06/22 RGA00152 2 BFK SHEET TITLE:
PROPOSED DEVELOPMENT:
DEVELOPED BY:
CATAWBA AVE. SPEC. INDUSTRIAL
FONTANA, CA L-1
PRELIMINARY LANDSCAPE PLAN PROPOSED BUILDING
POPLAR AVENUE 1
CATAWBA AVENUE RETAINING WALL- SEE CIVIL / ARCH. PLANS 56 DOCK DOORS GATE GATE FIRE PUMP ROOM OFFICE AREA OFFICE AREA TRASH ENCLOSURE BIKE RACKS SEATING AREA SIDEWALK R/W DRIVE ENTRY DRIVE ENTRY SIDEWALK R/W DRIVE ENTRY DRIVE ENTRY RETAINING WALL- SEE CIVIL'S PLANS P.L. P.L. NORTH 0 80 feet 1" = 40' 40 120 160 RETAINING WALL- SEE CIVIL'S PLANS LINE-OF-SIGHT LINE-OF-SIGHT LINE-OF-SIGHT LINE-OF-SIGHT LINE-OF-SIGHT LINE-OF-SIGHT LINE-OF-SIGHT LINE-OF-SIGHT TRANSFORMER 65 314
Engineering, Inc. Civil Engineering/Land Surveying/Land Planning NOT FOR CONSTRUCTION · · ···· 31566
Engineering, Inc. Civil Engineering/Land Surveying/Land Planning NOT FOR CONSTRUCTION 31667
Engineering, Inc. Civil Engineering/Land Surveying/Land Planning NOT FOR CONSTRUCTION 31768
10 DRC Engineering, Inc.
Civil Engineering/Land Surveying/Land Planning
31869
31970
32071
32172
32273
32374
32475
32576
32677
32778
ATTACHMENT NO. 4
EXISTING &
PROPOSED
GENERAL PLAN
LAND USE
DATE: October 17, 2023
CASE: Master Case No. 22-079: General Plan
Amendment No. 22-007, Specific Plan
Amendment No. 22-003, Development
Agreement No. 22-003, Tentative Parcel Map
(TPM No. 20638) No. 22-016, Design Review
No. 22-040
NORTH
CITY OF FONTANA PLANNING DEPARTMENT
EXISTING
PROPOSED
Legend
32879
ATTACHMENT NO. 5
EXISTING &
PROPOSED
SPECIFIC PLAN
DATE: October 17, 2023
CASE: Master Case No. 22-079: General Plan
Amendment No. 22-007, Specific Plan
Amendment No. 22-003, Development
Agreement No. 22-003, Tentative Parcel Map
(TPM No. 20638) No. 22-016, Design Review
No. 22-040
NORTH
CITY OF FONTANA PLANNING DEPARTMENT
EXISTING
PROPOSED
Legend
32980
ATTACHMENT NO. 6
RESOLUTION PC NO. 2023-___
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
FONTANA RECOMMENDING THE FONTANA CITY COUNCIL
ADOPT A RESOLUTION TO CERTIFY THE FINAL ENVIRONMENTAL
IMPACT REPORT (STATE CLEARINGHOUSE NO. 2022090611),
STATEMENT OF OVERRIDING CONSIDERATIONS, MITIGATION
MONITORING AND REPORTING PROGRAM, AND STATEMENT OF
FACTS AND FINDINGS AND APPROVE GENERAL PLAN
AMENDMENT (GPA) NO. 22-007, SPECIFIC PLAN AMENDMENT
(SPA) NO. 22-003, DEVELOPMENT AGREEMENT NO. 23-003,
TENTATIVE PARCEL MAP (TPM NO. 20638) NO. 22-016 AND
DESIGN REVIEW (DRP) NO. 22-040 FOR THE CONSTRUCTION OF
AN INDUSTRIAL COMMERCE CENTER BUILDING TOTALING
490,565 SQUARE FEET ON A SITE OF APPROXIMATELY 18.8
GROSS ACRES.
WHEREAS, the City of Fontana General Plan was adopted by the City Council on November 13, 2018, and the City of Fontana Housing Element was adopted by the City Council on February 8, 2022; and
WHEREAS, the City of Fontana received an application on July 07, 2022 from Seefried Industrial Properties, Inc. (“Applicant”) for General Plan Amendment (GPA) No. 22-007 to amend the General Plan land use designation for 18.8-acres of land located to the east side of Poplar Avenue, west of Catawba Avenue and on the properties along Rose Avenue from Residential Trucking (R-T) to General Industrial (I-G) and to modify Exhibit 15.8 (Land Use Map) of the General Plan to reflect the same; Specific Plan Amendment (SPA) No. 22-003 to amend the Southwest Industrial Park (SWIP) Specific Plan Land Use Plan to amend the land use designation of the project site from Residential Trucking District (RTD) to Slover East Industrial District (SED); Development Agreement (AGR) No. 22-003 to establish an agreement for the payment of a public benefit fee; Tentative Parcel Map No. 22-016 (TPM No. 20638) for the consolidation of 41 parcels into one parcel; and Design Review No. 22-040 for the development of an industrial commerce building totaling approximately 490,565 square feet along with site improvements for APNs 0237-171-01, -02, -03, -04, -05, - 06, -07, -08, -09, -10, -11, -12, -13, -14, -15, -6, -17, -18, -19, and 0237-172-01, -02, - 03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -19, -22, -23, -26, -27, -28, -30, -31, -32, 33); and
WHEREAS, the subject site includes 41 parcels that were annexed from San Bernardino County into the City of Fontana on September 19, 2006; and WHEREAS, the subject property is to be developed below the assumed capacity identified in the approved Housing Element, however there is still sufficient capacity in the city at the “extremely low/very low” income category to meet the City’s Regional House Needs Assessment (RHNA) allocated numbers; and
WHEREAS, to comply with California’s Housing Crisis Act of 2019 (SB 330), the project will participate in the City of Fontana Municipal Code (FMC) Chapter 30 Article 33081
Resolution PC No. 2023-____
XV “No Net Loss Density Bonus/Replacement Program.” Pursuant to FMC section 30- 967, the Unit Bank cannot exceed 2,200 units. The Unit Bank is currently 1,280 units.
These 38 units will be added to the Unit Bank increasing the number of units in the Unit Bank to 1,318 which is less than the 2,200 units authorized by the FMC. The units in the Unit Bank shall be available as density bonuses for other residential properties throughout the city. The program will enable, on a first come, first served basis, density bonuses of up to 20% on other parcels until these 38 residential units are reclaimed within future planned residential projects; and
WHEREAS, all the notices required by statute and the Fontana City Code have been given as required; and
WHEREAS, on October 17, 2023, the Planning Commission received public testimony and evidence presented by the applicant, City staff, and other interested parties, at the Public Hearing held on Poplar South Distribution Center (State Clearinghouse No. 2022090611), General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Agreement (AGR) No. 23- 005, Tentative Parcel Map No. 20638 (TPM No. 22-016), and Design Review (DRP) No. 22-040; and,
WHEREAS, the City of Fontana wishes to protect and preserve the quality of the life throughout the City, through effective land use and planning; and, WHEREAS, the City has prepared a Final EIR, consisting of the comments received during the 45-day public review and comment period on the Draft EIR, written responses to those comments, revisions to the Draft EIR, and an errata making minor, non-substantive changes to the Final EIR. For the purposes of this Resolution, the “EIR” shall refer to the Draft EIR, as revised by the Final EIR, together with the other sections of the Final EIR; and
WHEREAS, based on the information contained in Environmental Impact Report (State Clearing House No. 2022090611) prepared for the proposed project which has been circulated for the proposed project and has been submitted with the inclusion of a Statement of Overriding Consideration and a Mitigation Monitoring Program with a recommendation for certification by the City Council; and WHEREAS, the Conditions of Approval have been prepared and are attached hereto as Exhibit “A through B” for Tentative Parcel Map (TPM) No. 22-016 (TPM No. 20638) and Design Review (DRP) No. 22-040, and,
WHEREAS, General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Agreement (AGR) No. 22-003, Tentative Parcel Map (TPM) No. 22-016 (TPM No. 20638), and Design Review No. 22-040 is consistent with the goals and policies of the General Plan; and, WHEREAS, the owners of property within 660 feet of the proposed project site were notified via public hearing notice mailer prior to the Public Hearing; and a notice of the public hearing was published in the Fontana Herald newspaper on October 7, 2023, at City Hall and at the project site; and,
33182
Resolution PC No. 2023-____
WHEREAS, the Planning Commission carefully considered all information, evidence and testimony pertaining to the proposed project presented at its public hearing on October 17, 2023, and,
WHEREAS, all other legal prerequisites to the adoption of this resolution have occurred.
NOW, THEREFORE, the Planning Commission RESOLVES as follows:
Section 1. Recitals. The above recitals are true, correct and incorporated herein by reference.
Section 2. CEQA. The Planning Commission has reviewed and considered the Environmental Impact Report (EIR) and Mitigation Monitoring and Reporting Program (MMRP), any oral or written comments received, and the administrative record prior to making any recommendation on the proposed project. The Planning Commission finds that the EIR and Mitigation Monitoring and Reporting Program contain a complete and accurate reporting of all the environmental impacts associated with the Project. The Planning Commission further finds that the EIR and Mitigation Monitoring and Reporting Program have been completed in compliance with the 2019 Local CEQA Guidelines and the State CEQA Guidelines.
Section 3. General Plan Amendment. The City of Fontana Planning Commission hereby makes the following findings for General Plan Amendment (GPA) No. 22-003 in accordance with Section 30-31 “Purpose” of the Fontana Zoning and Development Code:
Finding: The purpose and intent is to keep an updated General Plan to reflect the current desires and needs of the citizens for the long-term growth of the City.
Findings of Fact: Changing the General Plan Land Use Designation of the site from Residential Trucking (R‐T) to General Industrial (I‐G) would allow for the construction of an industrial commerce center building totaling approximately 490,565 square feet. This development will assist with the growing the industrial commerce center demand in the City and the surrounding area. The construction and operations of the project site will provide employment
opportunities for the local workforce and address demands related to products being transported into the area. Additionally, properties to the south and west also have a General Plan designation of General Industrial.
Section 4. Specific Plan Amendment. The City of Fontana Planning Commission hereby makes the following findings for Specific Plan Amendment (SPA) No. 22-003 in accordance with Section 30-67 “Purpose” of the Fontana Zoning and Development Code:
33283
Resolution PC No. 2023-____
Finding: A Specific Plan may be amended by changing the development standards or zoning designation of any zone whenever such an amendment is deemed necessary to
protect or promote the public's health, safety or general welfare or when modification is viewed as appropriate in the context of generally accepted planning principles,
surrounding land uses, and the General Plan.
Findings of Fact: A specific plan amendment to the existing Southwest Industrial Park Specific Plan (SWIP) to change the land use of the project site from Residential Trucking District (RTD) to Slover East Industrial District (SED) would accommodate the development of an industrial commerce center building totaling 490,565 square feet. This project will provide attractive development with quality modern architecture with additional landscaping. This type of development will enhance the industrial areas with an attractive street scene and high-quality landscaping. This type of development will be consistent with the areas to the south and west.
Section 5. Tentative Parcel Map. The City of Fontana’s Planning Commission hereby makes the following findings for Tentative Parcel Map No. 22-016 (TPM No. 20638), pursuant to Section 30-284 of the Fontana Zoning and Development code, and in accordance with Section No. 26 218(d) “Processing of application,” of the Fontana Municipal Code:
Finding No. 1: That the proposed map is consistent with the city's general plan and any applicable specific plan.
Findings of Fact: Tentative Parcel Map No. 22- 016 (TPM No. 20638) is consistent with the General Plan Land Use Designation for the project site, which is General Industrial (I-G). The lot size with the consolidation will meet the lot standards of the Specific Plan. The tentative parcel map consolidates forty-one (41) existing parcels (APNs: 0237-171-01 through -19, 0237-172-01 through -12, - 19, -22, -23, -26, -27, -28, -30 through -33) into one parcel for the construction of a concrete tilt-up industrial commerce center building totaling approximately 490,565 square feet, which is within the land use permitted in the General Plan. The project incorporates the project site into the Southwest Industrial Park Specific Plan, Slover East Industrial District. Rose Avenue is vacated and the site designation will reflect Slover East Industrial District (SED) between Poplar Avenue and Catawba Avenue. This section of Rose Avenue is listed as a local street on Hierarchy of the Streets Plan Chapter of the General Plan and Transportation and Circulation Chapter of SWIP. The vacation of Rose Avenue will not conflict with the General Plan or SWIP.
33384
Resolution PC No. 2023-____
Finding No. 2: That the design or improvements of the proposed subdivision are consistent with the general plan and any applicable specific plan.
Findings of Fact: The site design for Tentative Parcel Map No. 20638 is consistent with the General Plan. The lot size and street configuration conform to the requirements of the Land Use, Zoning, and Urban Design and Community Mobility and Circulation Elements of the City of Fontana General Plan, Subdivisions (Chapter No. 26) Chapter of the City of Fontana Municipal Code and the General Industrial development standards. The project includes all on-site and off-site improvements to meet all the General Plan goals and objectives; as well as, all of the zoning requirements of the Southwest Industrial Specific Plan, Slover East Industrial District zone. Improvements consist of public sewer, public storm drain, streets, gutter, sidewalks, drainage, and grading to provide a safe and well-designed project for the area.
Finding No. 3: The site is physically suitable for the type and density of development proposed.
Findings of Fact: The project site for the industrial commerce center is approximately 18.8 acres which is adequate in size to
accommodate the development. The existing topography is conducive for the project and development of the site did not require setback variances; therefore, the site is suitable for this type of development. The lot size is consistent with surrounding industrial developments.
Finding No. 4: The design of the subdivision or the proposed improvements are not likely to cause substantial environmental damage or will not substantially and avoidably injure fish or wildlife or their habitat.
Findings of Fact: The design of Tentative Parcel Map No. 22-016 (TPM No. 20638) is not likely to cause substantial environmental damage or substantially and unavoidably injure fish or wildlife or their habitat.
The area surrounding the project site has been developed with of industrial, high school, adult school and warehouses uses.
An Environmental Impact Report (EIR) has been prepared for this project pursuant to the California Environmental Quality Act (CEQA) and the 2019 Local Guidelines for Implementing CEQA.
Based on the information in the EIR, the project does not represent significant effect on the environment as a result of project implementation. The mitigation measures establish within the EIR will reduce any significant impacts to the surrounding area. The use is anticipated based on the Land Use Designation and the Zoning and Development Code. The design of the map 33485
Resolution PC No. 2023-____
will not cause substantial environmental damage or will not substantially and avoidably injure fish or wildlife or their habitat.
The design of the map will not cause substantial environmental damage or will not substantially and avoidably injure fish or wildlife or their habitat.
Finding No. 5: The design of the subdivision or type of improvements will not cause serious public health problems.
Findings of Fact: The design of Tentative Parcel Map No. 22-016 (TPM No. 20638) will not cause public health problems. The development will comply with the Zoning and Development Code and General Plan.
Improvements include connection to the public sewer, connection to the public storm drain, modification to the existing sidewalks, drainage, and grading to provide a safe and well-designed project for the area. Therefore, the project shall promote the public health, safety, and welfare of the surrounding community.
Finding No. 6: That the design of the subdivision or the type of improvements will not conflict with easements acquired by the public at large for access through or use of property within the proposed subdivision.
Findings of Fact: The design of Tentative Parcel Map No. 22-016 (TPM No. 20638) and public improvements will not conflict with access easements acquired by the public. Access to and from the project site would be provided from driveways on Poplar Avenue and Catawba Avenue. The truck traffic will come in and out from the southern driveway along Poplar and Catawba Avenue and vehicle traffic will use two separate entrances on the north accessed from Poplar Avenue and Catawba Avenue.
Section 6. Design Review. The City of Fontana Planning Commission hereby makes the following findings for a Design Review No. 22-040 in accordance with Section 30-120 “Findings for approval” of the Fontana Zoning and Development Code:
Finding No. 1: The proposal is consistent with the General Plan and applicable Specific Plan.
Findings of Fact: The General Plan land use designation of General Industrial (IG) is intended for employee-intensive uses, including business parking, research and development, technology centers,
corporate and support office uses, clean industry, supporting retail uses, truck and equipment sales and related services. The industrial commerce facility provides for a consistent blend of welldesigned industrial development in the immediate vicinity. The specific plan amendment incorporates the project into the Southwest Industrial Park Specific Plan, Slover East Industrial District. The industrial commerce facilities provide for a consistent 33586
Resolution PC No. 2023-____
blend of well-designed industrial development in the immediate vicinity because it provides consistency with the industrial uses south to the west of the project site.
Finding No. 2: This proposal meets or exceeds the criteria contained in Chapter 30 of the Zoning and Development Code and will
result in an appropriate, safe and desirable development promoting the public health, safety, and welfare of the community.
Findings of Fact: The site and architectural design for the 490,565 square foot industrial commerce center building has been designed with office space totaling approximately 10,000 square feet. A gate-secured truck court with 42 loading docks are on the south side of the building. The use of glazing, parapets, accent colors and painted banding will add structural and visual interest to the building.
Additionally, variations to the building face and roof lines will be architecturally pleasing. Access to and from the project site would be provided from driveways on Poplar Avenue and Catawba Avenue. Landscaping would be ornamental in nature and includes trees, shrubs, and drought-tolerant accent plants in addition to a variety of groundcovers.
The project will be an appropriate and desirable development for the area. With the requested associated general plan amendment and specific plan amendment from Residential Trucking (R-T) to General Industrial (I-G), the project will meet or exceed the criteria contained in the Design Review section of the Fontana Zoning and Development Code and the SWIP specific plan.
The project will result in the construction of an industrial commerce center building totaling approximately 490,565 square feet. All new improvements such as driveways, streets,
sidewalks, drive aisles, and setbacks will comply with all applicable building, zoning, and fire codes and shall promote the public health, safety, and welfare of the surrounding community.
Finding No. 3: The proposal is in its design and appearance is aesthetically and architecturally pleasing resulting in a safe, well-designed facility while enhancing the character of the surrounding neighborhood.
Findings of Fact: The industrial commerce center facility has been designed with the use of glazing, parapets, canopies, accent colors and painted banding will add structural and visual interest to the building.
Additionally, variations to the building face and roof lines will be architecturally pleasing. Access to and from the project site would be provided from driveways on Poplar Avenue and Catawba Avenue with vehicle traffic utilizing separate entrances from 33687
Resolution PC No. 2023-____
commercial vehicles. Landscaping would be ornamental in nature and features trees, shrubs, and drought-tolerant accent plants in addition to a variety of groundcover. The building will be compatible with the industrial commerce centers to the south and west of the project site and will provide a quality, aesthetically please development for the surrounding neighborhood.
Finding No. 4: The site improvements are appropriate and will result in a safe, well-designed facility.
Findings of Fact: The development complies with the Zoning and Development Code standards and the newly adopted sustainability ordinance.
The improvements include sewer and storm drain systems, site circulation, parking, landscaping, parks, lighting, driveways, sidewalks and decorative paving.
Section 7. Approval. Based on the foregoing, the Planning Commission hereby recommends that the City Council adopt the following:
A resolution to certify the Final Environmental Impact Report (State Clearinghouse No. 2022090611), pursuant to Section 15126 through 15164 of the California Environmental Quality Act (CEQA) Guidelines and Section 8.1 of the City of Fontana’s 2019 Local CEQA Guidelines and direct staff to file the Notice of Determination;
A resolution approving General Plan Amendment (GPA) No. 22-007; An ordinance approving Specific Plan Amendment (SPA) No. 22-003; An ordinance approving Development Agreement (AGR) No. 23-003; and A resolution approving Design Review No. 22-040 and Tentative Parcel Map (TPM) No. 22-016 (TPM No. 20638), subject to the findings as indicated herein and the Conditions of Approval, have been prepared and are attached hereto as Exhibit “A” and Exhibit “B”.
Section 8. Resolution Regarding Custodian of Record. The documents and materials that constitute the record of proceedings on which this Resolution has been based are located at the Planning Department, 8353 Sierra Avenue, Fontana, CA 92335. This information is provided in compliance with Public Resources Code section 21081.6.
Section 9. Certification. The Secretary of the Planning Commission shall certify to the adoption of this Resolution.
Section 10. Effective Date. This Resolution shall become effective immediately upon its adoption.
Section 11. Severability. If any provision of this Resolution or the application of any provision to any person or circumstance is held invalid, such invalidity shall not affect other provisions or applications of this Resolution that can be given effect without the invalid provision or application.
33788
Resolution PC No. 2023-____
PASSED, APPROVED AND ADOPTED by the Planning Commission of the City of Fontana, California, at a regular meeting held on this 17th day of October, 2023.
City of Fontana
___________________________
Cathline Fort, Chairperson
ATTEST:
I, Ralph Thrasher, Secretary of the Planning Commission of the City of Fontana, California, do hereby certify that the foregoing resolution was duly and regularly adopted by the Planning Commission at a regular meeting thereof, held on this 17th day of October 2023, by the following vote, to-wit:
AYES:
NOES:
ABSENT:
ABSTAIN:
___________________________
Ralph Thrasher, Secretary
33889
Resolution PC No. 2023-____
EXHIBIT “A”
CITY OF FONTANA
CONDITIONS OF APPROVAL
PROJECT: Master Case No. (MCN) 22-079 October 17, 2023
Tentative Parcel Map No. 20638 (TPM No. 22-016)
LOCATION: The project site includes property located to the east side of Poplar Avenue, west of Catawba Avenue and north and south of Rose Avenue (APNs) 0237-171-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -13, -14, -15, -6, -17, -18, -19, and 0237-172-01, -02, -03, -04, -05, -06, - 07, -08, -09, -10, -11, -12, -19, -22, -23, -26, -27, -28, -30, -31, -32, 33.
PLANNING DEPARTMENT:
1. The rights and privileges granted by this project shall not become effective, nor shall the applicant commence the use for which this project is granted, until both of the following have occurred:
A. All requirements of the Fontana City’s Municipal Code shall be complied with.
B. All Conditions of Approval imposed on this project have been fulfilled.
2. The applicant shall defend, indemnify, and hold harmless the City of Fontana or its agents, officers, and employees from any claim, action or proceeding against the City of Fontana or its agents, officers, or employees to attack, set aside, void, or annul an approval of the Planning Commission and/or City Council concerning this subdivision, which action is brought within the time period provided for in Government Code Section 66499.37. The City of Fontana shall promptly notify the applicant of any claim, action, or proceeding and the City of Fontana shall cooperate in the defense. The applicant shall defend, indemnify, protect and hold harmless the City of Fontana or its agents, officers, attorneys and employees from any and all actual or alleged claims, actions or proceedings against the City of Fontana or its agents, officers, attorneys or employees to attack, set aside, void, annul or seek monetary damages arising out of any challenge to the applicant’s proposed project or to any approvals of the Planning Commission and/or City Council concerning this project, including but not limited to actions challenging CEQA actions, permits, variances, plot plans, design plans, maps, licenses, and amendments. The City of Fontana shall promptly notify the 33990
Resolution PC No. 2023-____
applicant of any claim, action, or proceeding and the City of Fontana shall cooperate in the defense.
In the event of any such third-party action or proceeding, the City shall have the right to retain its own separate legal counsel to defend the interests of the City.
The applicant shall be responsible for reimbursing the City for such legal fees and costs, in their entirety, including actual attorneys’ fees, which may be incurred by the City in defense of such action or proceeding. This indemnification shall also include, but not be limited to, damages, fees and/or costs awarded against the City, if any, and cost of suit, attorneys’ fees, and other costs, liabilities and expenses incurred in connection with such claim, action, or proceeding whether incurred by applicant, the City and/or any parties bringing such forth.
The City of Fontana and the applicant acknowledge that the City would not have approved this project if the City were to be liable to applicant in damages under or with respect to all or any part of this application or this condition of approval.
Accordingly, applicant shall not sue the City for damages or monetary relief for any matter arising from or related to this condition of approval. Applicant’s sole and exclusive remedy shall be limited to declaratory/injunctive relief, mandate, and/or specific performance.
3. Tentative Parcel Map No. 20638 (TPM No. 22-016) shall comply with all applicable development standards of, Chapter 26 (Subdivisions), Southwest Industrial Park Specific, Chapter 30 (Zoning and Development), Fontana Municipal Code (FMC) and the Subdivision Map Act.
4. The applicant/developer shall underground all utilities, which for the purpose of this condition shall also include all boxes, structures and/or other equipment located in the public right-of-way, any public utility easement(s) and on any private property, to the satisfaction of the Director of Planning. A note to this effect shall be placed on the map prior to recordation of the final map.
5. The applicant/developer shall comply with the mitigation measures identified in the Final Environmental Impact Report (FEIR), and Mitigation Monitoring and Reporting Program (MMRP) as approved by the Planning Commission.
6. All Conditions of Approval and Mitigation Monitoring and Reporting Program (MMRP) contained herein shall be incorporated into all applicable final construction plans and a copy of these conditions shall be placed on a sheet in the final building and grading plans prior to issuance of any building or grading permits.
7. Tentative Parcel Map No. 20638 (TPM No. 22-016) shall become null and void two (2) years from the date of approval, unless the appropriate permits have been obtained and construction, defined as permit obtainment, commencement of construction of the primary building on site, and successful completion of the first Building and Safety Division inspection, has commenced within this period.
8. In the event that one or more of the Conditions of Approval for this project needs to be amended and/or deleted due to health, safety or welfare concerns, the City 34091
Resolution PC No. 2023-____
Manager is authorized to approve or conditionally approve such amendment/deletion, provided that City Manager shall bring such proposed amendment/deletion to the City Council at the next available meeting for City Council ratification, but in no event later than sixty (60) days following the City Manager’s decision. The noticing of such City Council meeting for possible ratification shall be pursuant to Section No. 30-23 of the Municipal Code.
9. The applicant shall post a publicly visible sign on the project site with the telephone number and 24-hour point of contact for dust, noise and construction complaints. The 24-hour point of contact shall be available 24 hours a day, 7 days a week and have authority to commit additional assets to control dust, or respond to construction complaints after hours, on weekends and on holidays.
Construction shall be limited to 7:00 am to 6:00 pm on weekdays, 8:00 am to 5:00 pm on Saturdays, and no construction on Sundays and Holidays.
10. The applicant shall meet all requirements identified in the Industrial Commerce Sustainability Ordinance (Chapter 9, Article V of the Fontana Municipal Code).
11. The applicant shall meet all requirements of the Trip Reduction Measures in of the Zoning and Development Code (Section 30-962).
BUILDING & SAFETY DEPARTMENT:
12. The applicant shall design the project to show compliance with the latest adopted edition of the following codes as applicable:
A. California Building Code
B. California Residential Code
C. California Electrical Code
D. California Mechanical Code
E. California Plumbing Code
F. California Energy Code
G. California Fire Code
H. California Green Building Standards Code
13. The applicant shall install an automatic fire suppression system, which is required in all new construction per FMC Chapter 11 Article II. Design and type of system shall be based upon the requirements of the Building Code, Fire Code and the requirements of the Fontana Fire Prevention District.
14. The applicant shall comply with the requirements of the South Coast Air Quality Management District (909-396-2000). SCAQMD requirements shall be satisfied prior to the issuance of any permit if hazardous materials are stored and/or used.
15. The applicant shall verify that any temporary building, trailer, commercial coach, etc. installed and/or used in connection with a construction project complies with FMC Chapter 5 Article XIV.
34192
Resolution PC No. 2023-____
16. The applicant shall verify that all perimeter/boundary walls are designed and constructed so that the outer/exterior face of the wall is as close as possible to the lot line. In any case, the outer/exterior face of the wall shall be within two (2) inches of the lot line. Distances greater than two (2) inches may be approved prior to construction by the Building Official on a case by case basis for extenuating circumstances.
17. The applicant shall have the tract or parcel map recorded prior to the issuance of any building permits.
18. The applicant shall comply with the following grading requirements:
A. Grading plans shall be submitted to and approved by Building & Safety.
The grading plans shall indicate all site improvements and shall indicate complete drainage paths of all drainage water run-offs.
B. All drainage water shall drain via approved methods to an approved location, such as a public street, a public drainage system, etc.
C. Drainage water shall not cross over a public sidewalk. Drainage water may, however, cross under a sidewalk if an approved drainage structure is used.
D. A recorded drainage acceptance agreement is required from adjoining property(s) receiving flows from this property.
E. No water course or natural drainage shall be obstructed.
F. Minimum slope or grade for ALL drainage structures shall be one half (0.50) percent for concrete and one (1.0) percent for all other, or as otherwise approved by the Building Official.
G. Drainage water shall not pass from an ‘improved’ type of drainage structure to an ‘unimproved’ type of drainage structure (e.g., concrete swale to a dirt swale) unless otherwise approved by the Building Official.
H. A complete hydrology study using the latest edition of the San Bernardino County Flood Control Hydrology Manual, and complete hydraulic calculations justifying the size, slope, capacity, etc. of any and all drainage structures being utilized, shall be submitted to and approved by Building & Safety.
I. The on site drainage system shall, as a minimum, be designed to handle the run off generated by a ten (10) year storm. Check for flooding of all on site structures (buildings) and all adjacent properties during a hundred (100) year storm.
J. The grading plans shall, as a minimum, contain sections at all lot lines and/or permit boundary lines. These sections shall clearly indicate:
34293
Resolution PC No. 2023-____
1. The relationship between the proposed finished on site grade elevations and the existing adjacent property grade elevations (Indicate any additional drainage water that may come from an adjacent property.); and
2. The ground cover/finished surface material being proposed (e.g., type of pavement, plant material, etc.); and
3. All proposed drainage structures; and
4. Any proposed and/or required walls or fencing.
19. The applicant is required to obtain permits for the removal and/or demolition of structures.
20. The applicant shall verify that all exterior lighting shall be oriented, directed, and/or shielded as much as possible so that direct illumination does not infringe onto adjoining properties.
PRIOR TO ISSUANCE OF BUILDING/CONSTRUCTION PERMITS
21. The following items (as applicable) shall be completed by the applicant and submitted to Building & Safety prior to the issuance of building permits for this project:
A. Precise grading plans shall be approved
B. Rough grading completed
C. Compaction certification
D. Pad elevation certification
E. Rough grade inspection signed off by a City Building Inspector
22. If hazardous substances are used and/or stored, the applicant shall provide a technical opinion and report, identifying and developing methods of protection from the hazards presented by the hazardous materials, may be required. This report shall be prepared by a qualified person, firm, or corporation and submitted to Building & Safety. This report shall also explain the proposed facility's intended methods of operation and list all of the proposed materials, their quantities, classifications, and the effects of any chemical (material) inter mixing in the event of an accident or spill.
23. The applicant shall combine the existing parcels into a single parcel, or a lot line adjustment shall be done so that the proposed structure(s) does not cross any lot line and complies with all requirements of the California Building Code, prior to any building permits being issued.
ENGINEERING DEPARTMENT:
24. The Project shall be served by the City’s sanitary sewer system, all sewer facilities shall be constructed in accordance with the City Standards. Main trunk sewer line shall be in accordance with master sanitary sewer plan or as approved by the City Engineer.
34394
Resolution PC No. 2023-____
25. The Applicant shall obtain design and plan approval from all utility providers having jurisdiction over the on-site and off-site utilities. Completion of all undergrounding of on-site and off-site utilities is required by Section 27-52 of the City Municipal Code and in accordance with plans and specifications approved by the City Engineer.
26. The Applicant shall maintain all improvements and utilities within the public rightof-way, including street sweeping, prior to issuance of final certificate of occupancy by the City.
PRIOR TO ISSUANCE OF GRADING PERMIT
27. The Applicant shall submit and gain approval of a complete Water Quality Management Plan report in accordance with the County of San Bernardino Technical Guidance Document and latest template.
28. The Applicant shall submit and gain approval of a final drainage study prepared in accordance with the County of San Bernardino Hydrology Manual and Fontana Master Plan of Drainage.
PRIOR TO MAP RECORDATION
29. The Applicant shall provide a Land Improvement Agreement, with accompanying security. The agreement shall be executed on City-provided forms.
PRIOR TO ISSUANCE OF CONSTRUCTION PERMITS
30. The Applicant shall record All map’s, lot line adjustments, right-of-way dedications, right-of-way vacations, easements, reciprocal access agreement as required for the development.
31. The Applicant shall submit engineered improvement plans and obtain full approval. All required public improvements, including but not limited to streets, storm drainage systems, sewers, traffic signals, streetlights, striping, signs, landscape, and any required traffic control and/or detour plans. All plans shall
32. conform to City Standards and Specifications, and as approved by the City Engineer.
PRIOR TO ISSUANCE OF FINAL CERFITICATE OF OCCUPANCY
33. The Applicant/Engineer to provide the City of Fontana with As Built/Record Drawings for all public improvement plans.
34. The Applicant/Engineer shall provide centerline ties to the City of Fontana reflecting proper setting of all survey monuments within the project limits and replace any existing survey monuments damaged or removed during construction.
35. The Applicant/Engineer shall set survey monuments as required by the map and corner records must be recorded with the County.
34495
Resolution PC No. 2023-____
36. The Applicant/Landscape Architect shall provide a “Landscape Certificate of Compliance” certifying that the work has been designed, installed, and will be maintained in accordance with the City of Fontana’s Model Water Efficiency Landscape Ordinance (Ordinance 1743, FCC Section 28).
37. All sewers shall be video inspected by applicant/contractor. Sewer video shall include clean-out connection, clean-out to lateral segment, lateral, and main line.
Contractor performing the video inspection must have a NASSCO PACP, LACP, and MACP certification. Applicant shall provide a copy of the video on DVD or flash drive to inspection staff with an accompanying full report. Videos to be inspected and approved by City Inspector. If removal and replacement of any utility is required, a subsequent video of the repair will be required. If a TCO (Temporary Certificate of Occupancy) is required a full video inspection will be required as well at that time.
38. All storm drains shall be video inspected by applicant/contractor. Storm drain video shall include main lines and laterals. Applicant shall provide a copy of the video on DVD or flash drive to inspection staff. Videos to be inspected and approved by City Inspector. If removal and replacement of any utility is required, a subsequent video of the repair will be required.
39. The Applicant/Engineer of Record shall submit a conforming copy of the recorded Memorandum of Agreement for the Water Quality Management Plan and Storm Water Best Management Practice transfer. The Access, Maintenance, and the WQMP Certification for BMP Completion must be submitted to the City Project Engineer.
FIRE DEPARTMENT:
40. Jurisdiction: The above referenced project is under the jurisdiction of the Fontana fire Protection District (herein “Fire Department”). Prior to any construction occurring on any parcel, the applicant shall contact the Fire Department for verification of current fire protection requirements. All new construction shall comply with the current California Fire Code requirements and all applicable statutes, codes, ordinances, and standards of the Fire Department.
41. Fire Access Road Width: Prior to map recordation, all fire access roadways shall be designed to meet the requirements for this development and shall be approved by the Fire Department. All buildings shall have access provided by approved roads, alleys, and private drives with a minimum twenty-six (26) foot unobstructed width and vertically to fourteen (14) feet six (6) inches in height. Buildings three (3) stories in height or more shall have a minimum access of thirty (30) feet unobstructed width and vertically to fourteen (14) feet six (6) inches in height.
California Fire Code Chapter 5 & SBCoFD Standard A-1.
42. Turnaround: An approved turnaround shall be provided at the end of each roadway one hundred and fifty (150) feet or more in length. Cul-de-sac length shall not exceed six hundred (600) feet; all roadways shall not exceed a 12% grade and have a minimum of nineteen (19) foot inside radius and a forty-five (45) 34596
Resolution PC No. 2023-____
foot outside radius for all turns. California Fire Code Chapter 5 & SBCoFD Standard A-1.
43. Fire Lanes: The applicant shall submit a site plan to the Fire Department for review and approval of all proposed signage and striping for all fire access roadways. All curbs adjacent to fire lanes shall be painted red and “No Parking, Fire Lane” signs shall be installed on public and private roads in accordance with approved standards. SBCoFD Standard A-2.
44. Water System Commercial: Prior to map recordation or lot line adjustment, all water supply systems shall be designed to meet the required fire flow for this development and shall be approved by the Fire Department. The required fire flow shall be determined by using Appendix BB of the California Fire Code. A minimum of one new six (6) inch fire hydrant assembly with two (2) two and one half (2 1/2) inch and one (1) four (4) inch outlet (4”x2.5”x2.5”) shall be provided.
All fire hydrants shall be spaced no more than three hundred (300) feet apart as measured along vehicular travel-ways. California Fire Code Chapter 5 & SBCoFD Standard W-2. The Fire Flow for this project shall be: 4,000 GPM for a two-hour duration at 20 psi residual operating pressure. Fire Flow is based on a 490,550 Square Foot structure.
45. Hydrant Marking: Blue reflective pavement markers indicating fire hydrant locations shall be installed as specified by the Fire Department. SBCoFD Standard W-2.
46. Water Improvement Plan: The applicant shall submit “Water Improvement Plans” to Fontana Fire Prevention. W.I.P. to include site plan, existing & proposed PUBLIC fire hydrant locations, building construction type, largest building square footage details, lot size detail in square feet, and description of what is being constructed. Once approved by Fire Department, applicant will provide stamped/approved W.I.P to water purveyor for their construction needs. ON-SITE
PRIVATE FIRE WATER SUPPLY SHALL BE INSPECTED AND IN WORKING
CONDITION PRIOR TO PLACING COMBUSTIBLE MATERIALS ON THE JOBSITE. California Fire Code Chapter 5.
47. Combustible Protection: Prior to combustibles being placed on the project site an approved paved roadway providing fire access and fire hydrants providing an acceptable fire flow shall be installed. California Fire Code Chapter 5.
48. Fire Sprinkler-NFPA #13: An automatic fire sprinkler system complying with NFPA 13 and Fire Department standards is required. A fire sprinkler contractor shall submit three (3) sets of detailed plans to the Fire Department for review and approval. The plans shall include hydraulic calculations and manufacturer specification sheets. The required fees shall be paid at the time of plan submittal.
California Fire Code Chapter 9 & SBCoFD Standard F-1.
49. Fire Alarm, Waterflow Monitoring: A water flow monitoring fire alarm system complying with the California Fire Code, NFPA and all applicable codes is required for fire sprinkler systems with twenty (20) sprinkler heads or more. A fire 34697
Resolution PC No. 2023-____
alarm contractor shall submit three (3) sets of detailed plans to the Fire Department for review and approval. The required fees shall be paid at the time of plan submittal. California Fire Code Chapter 9, NFPA 72 & SBCoFD Standard F-5.
50. Smoke Removal: An automatic smoke removal system complying with the California Fire Code, NFPA and all applicable codes is required. The applicant shall submit three (3) sets of detailed smoke removal system plans to the Fire Department for review and approval. The required fees shall be paid at the time of plan submittal. California Fire Code Chapter 9.
51. Fire Extinguishers: Hand portable fire extinguishers are required. The location, type, and cabinet design shall be approved by the Fire Department. California Fire Code Chapter 9.
52. Commercial (large facility) Addressing: Commercial and industrial developments in excess of 100,000 sq. ft. shall have the street address installed on the building with numbers that are a minimum twelve (12) inches in height and with a one and one half (1½) inch stroke. The street address shall be visible from the street.
During the hours of darkness, the numbers shall be electrically illuminated (internal or external). Where the building is two hundred (200) feet or more from the roadway, additional non-illuminated contrasting six (6) inch numbers shall be displayed at the property access entrances. California Fire Code Chapter 5 & SBCoFD Standard B-1
53. Key Box: An approved Fire Department key box is required. The key box shall be provided with a tamper switch and shall be monitored by a Fire Department approved central monitoring service. California Fire Code Chapter 5 & SBCoFD Standard A-4
54. Security Gates: In commercial, industrial, and multi-family complexes, all swing gates shall have an approved fire department Knox Lock. Where an automatic electric security gate is used, an approved Fire Department override switch is required. California Fire Code Chapter 5 & SBCoFD Standard A-3
55. Material Identification Placards: The applicant shall install, in all locations deemed appropriate by the Fire Department, approved material identification placards on the outside of all buildings and/or storage tanks that store hazardous or flammable materials. Additional placards shall be required inside the buildings when chemicals are segregated into separate areas. California Fire Code Chapter 50 & NFPA 704.
56. High-Piled Storage: The applicant shall submit an application for a High-Piled Storage permit for storage of over 12’ in height of Class I-IV commodities and/or over 6’ in height of high hazard commodities. Three (3) sets of detailed plans and a commodity analysis report shall be submitted to the Fire Department for review and approval. The applicant shall submit to the Fire Department concurrently with any racking permits to the Building and Safety division. California Fire Code Chapter 32 & SBCoFD Standard S-1.
34798
Resolution PC No. 2023-____
57. Secondary Access: The development shall have a minimum of two (2) points of vehicular access during each phase of construction for fire and emergency access purposes and for evacuation routes. SBCoFD Standard A-1
58. San Bernardino County Fire Standards/Codes: Items not directly called out on these Conditions of Approval, shall also adhere to currently adopted San Bernardino County Fire Standards, California Fire Code, & NFPA.
END OF CONDITIONS
34899
Resolution PC No. 2023-____
EXHIBIT “B”
CITY OF FONTANA
CONDITIONS OF APPROVAL
PROJECT: Master Case No. (MCN) 22-079 DATE: October 17, 2023 Design Review (DRP) No. 22-040
LOCATION: The project site includes property located to the east side of Poplar Avenue, west of Catawba Avenue and north and south of Rose Avenue (APNs) 0237-171-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -13, -14, -15, -6, -17, -18, -19, and 0237-172-01, -02, -03, -04, -05, -06, - 07, -08, -09, -10, -11, -12, -19, -22, -23, -26, -27, -28, -30, -31, -32, 33.
PLANNING DEPARTMENT:
1. This Design Review shall become null and void two (2) years from the date of approval, unless the appropriate permits have been obtained and construction, defined as permit obtainment, commencement of construction of the primary building on site, and successful completion of the first Building and Safety Department inspection, has commenced within this period.
2. The applicant shall defend, indemnify, protect and hold harmless the City of Fontana or its agents, officers, attorneys and employees from any and all actual or alleged claims, actions or proceedings against the City of Fontana or its agents, officers, attorneys or employees to attack, set aside, void, annul or seek monetary damages arising out of any challenge to the applicant’s proposed project or to any approvals of the Planning Commission and/or City Council concerning this project, including but not limited to actions challenging CEQA actions, permits, variances, plot plans, design plans, maps, licenses, and amendments. The City of Fontana shall promptly notify the applicant of any claim, action, or proceeding and the City of Fontana shall cooperate in the defense. 100 349
Resolution PC No. 2023-____
In the event of any such third-party action or proceeding, the City shall have the right to retain legal counsel. The applicant shall be responsible and reimburse the City for such legal fees and costs, in their entirety, including actual attorneys’ fees, which may be incurred by the City in defense of such action or proceeding.
This indemnification shall also include, but not be limited to, damages, fees and/or costs awarded against the City, if any, and cost of suit, attorneys’ fees, and other costs, liabilities and expenses incurred in connection with such claim, action, or proceeding whether incurred by applicant, the City and/or any parties bringing such forth.
Except as required under applicable State and Federal law, the City of Fontana and the applicant acknowledge that the City would not have approved this project if the City were to be liable to applicant in damages under or with respect to all or any part of this application or this condition of approval. Accordingly, applicant shall not sue the City for damages or monetary relief for any matter arising from or related to this condition of approval. Applicant’s sole and exclusive remedy shall be limited to declaratory/injunctive relief, mandate, and/or specific performance.
3. This project shall comply with all applicable provisions, regulations and development standards of the Fontana Zoning Code and Development Code, Fontana Municipal Code (FMC) and the Southwest Industrial Park Specific Plan.
4. The applicant shall meet all requirements identified in the Industrial Commerce Sustainability Ordinance (Chapter 9, Article V of the Fontana Municipal Code).
5. A Register of Professional Archaeologists (RPA)-qualified archeologist experienced with Native American artifact identification and approved by the City of Fontana shall be present to monitor the first two (2) days of site preparation/ grubbing; the first two (2) days of mass grading; and the first two (2) days of utility trenching. Such monitoring activities may be reduced or terminated depending on the findings and recommendations of the archeologist. In the event that prehistoric or historic cultural resources be uncovered during these activities, representatives of the tribal entity(s) whom consider the project site to be within their traditional use area shall be contacted and invited to the site to review the find, and monitoring shall be continued at the discretion of archeologist.
6. Historic Archaeological Resources
A. Upon discovery of any tribal cultural or archaeological resources, cease construction activities in the immediate vicinity of the find until the find can be assessed. All tribal cultural and archaeological resources unearthed by project construction activities shall be evaluated by the qualified archaeologist and tribal monitor/consultant. If the resources are Native American in origin, interested Tribes (as a result of correspondence with area Tribes) shall coordinate with the landowner regarding treatment and curation of these resources. Typically, the Tribe will request preservation in place or recovery for educational purposes. Work may continue on other parts of the project while evaluation takes place.
B. Preservation in place shall be the preferred manner of treatment. If 101 350
Resolution PC No. 2023-____
preservation in place is not feasible, treatment may include implementation of archaeological data recovery excavation to remove the resource along the subsequent laboratory processing and analysis. All Tribal Cultural Resources shall be returned to the Tribe. Any historic archaeological material that is not Native American in origin shall be curated at a public, non-profit institution with a research interest in the materials, if such an institution agrees to accept the material. If no institution accepts the archaeological material, they shall be offered to the Tribe or a local school or historical society in the area for educational purposes.
C. Archaeological and Native American monitoring and excavation during construction projects shall be consistent with current professional standards.
All feasible care to avoid any unnecessary disturbance, physical modification, or separation of human remains and associated funerary objects shall be taken. Principal personnel shall meet the Secretary of the Interior standards for archaeology and have a minimum of 10 years’ experience as a principal investigator working with Native American archaeological sites in southern California. The Qualified Archaeologist shall ensure that all other personnel are appropriately trained and qualified.
7. The construction contractor shall use the following source controls at all times:
A. Construction shall be limited to 7:00 am to 6:00 pm on weekday, 8:00 am to 5:00 pm on Saturdays, and no construction on Sundays and holidays unless it is approved by the Building Inspector for cases that are considered urgently necessary as defined in Section No. 18-63(7) of the Municipal Code. For all noise-producing equipment, use types and models that have the lowest horsepower and the lowest noise generating potential practical for their intended use.
B. The construction contractor will ensure that all construction equipment, fixed or mobile, is properly operating (tuned-up) and lubricated, and that mufflers are working adequately.
C. Have only necessary equipment onsite.
D. Use manually-adjustable or ambient-sensitive backup alarms. When working adjacent to residential use(s), the construction contractor will also use the following path controls, except where not physically feasible, when necessary:
E. Install portable noise barriers, including solid structures and noise blankets, between the active noise sources and the nearest noise receivers.
F. Temporarily enclose localized and stationary noise sources.
G. Store and maintain equipment, building materials, and waste materials as far as practical from as many sensitive receivers as practical.
8. All Conditions of Approval contained herein shall be incorporated into all applicable final construction plans and a copy of these conditions, signed by the property owner or legal representative, shall be placed on a sheet in the final building and grading plans prior to issuance of any building or grading permits.
9. The current development fees must be paid prior to issuance of building/construction permits.
102 351
Resolution PC No. 2023-____
10. In the event that one or more of the Conditions of Approval for this project needs to be amended and/or deleted due to health, safety or welfare concerns, the City Manager is authorized to approve or conditionally approve such amendment/deletion, provided that City Manager shall bring such proposed amendment/deletion to the City Council at the next available meeting for City Council ratification, but in no event later than sixty (60) days following the City Manager’s decision. The noticing of such City Council meeting for possible ratification shall be pursuant to Sections No. 30-30 and Sections No. 30-31 of the Municipal Code.
11. Color combinations and color schemes for buildings approved under a design review application shall not be modified or changed without prior approval of the original approving body by a revision to the original application. Minor hue color changes may be approved by the Director of Planning. The Director of Planning may refer minor hue color changes to the original approving body for consideration under a revision to the original application.
12. Exterior lighting compatible with the design of the building shall be provided for the parking lot. The lighting shall be directed and shielded so as to illuminate only the parking area and to avoid glare impacts on adjacent properties.
13. Sidewalks shall be provided for all new developments in accordance with the city’s circulation element of the General Plan.
14. All parking stalls shall be clearly marked by double striping pavement painting.
Parking stall sizes shall be measured from the mid-point between the striping. No parking spaces shall be designated in an industrial parking facility, except for disabled persons parking, van pool, carpool, or any other designated parking as required by law.
15. All signs shall be reviewed under a separate Design Review Sign application.
16. All roof-mounted equipment and ground mounted equipment shall be screened from view from adjacent properties and streets to the satisfaction of the Director of Planning.
17. All landscaping shall be healthy and maintained in a reasonable manner as determined by the Director of Planning or his/her designee.
18. The transformer shall be screened by a solid screen wall and mature, dense landscaping, and not visible from the public right-of-way.
19. There shall be no refrigerated uses on site; unless, a future tenant follows any applicable studies/memorandums to amend this Condition of Approval.
20. Development fees and Planning Department final inspection fee must be paid prior to Certificate of Occupancy.
103 352
Resolution PC No. 2023-____
21. Applicant shall pay all applicable service fees pursuant to the City of Fontana Municipal Code.
22. The applicant/developer/property owner shall provide up-lighting on the perimeter and up-light proposed trees to the satisfaction of the Director of Planning and his/her designee.
23. In the event that any off-site utility and/or infrastructure improvements are required as a direct result of future projects, construction of such off-site utility and infrastructure improvements shall not occur concurrently with the demolition, site preparation, and grading phases of project construction. This requirement shall be clearly noted on all applicable grading and/or building plans.
24. Adhere to the City standard of one foot candle minimum for all entrances, exits, pedestrian paths, parking lots, and activity areas. Reflect all light fixtures on the site plan. All areas shall be illuminated during all hours of darkness and all luminaries utilized shall be vandal-resistant fixtures. The type of lighting shall be fluorescent, white L.E.D.s or metal halide. Provide a photometric layout under separate exhibit to ensure the minimum light standard is met.
25. Incorporate an anti-graffiti coating onto the exterior of all proposed block walls to discourage graffiti.
26. The applicant shall meet all requirements of the Trip Reduction Measures in of the Zoning Code (Section 30-962).
27. There shall be no refrigerated uses on site; unless, a future tenant proposing to have such uses conducts an update of the California Environmental Quality Act (CEQA) document (i.e. Environmental Impact Report) and any applicable studies/memorandums to amend this Condition of Approval.
28. The developer shall be required to comply with Development Agreement (AGR) No. 22-003.
Prior To Issuance of Grading Permit
29. All Conditions of Approval and Mitigation, Monitoring, and Reporting Program (MMRP) contained herein shall be incorporated into all applicable final construction plans and a copy of these conditions shall be placed on a sheet in the final building and grading plans prior to issuance of any building or grading permits.
BUILDING & SAFETY DEPARTMENT:
30. The applicant shall design the project to show compliance with the latest adopted edition of the following codes as applicable:
A. California Building Code
B. California Residential Code
C. California Electrical Code
D. California Mechanical Code
104 353
Resolution PC No. 2023-____
E. California Plumbing Code
F. California Energy Code
G. California Fire Code
H. California Green Building Standards Code
31. The applicant shall install an automatic fire suppression system, which is required in all new construction per FMC Chapter 11 Article II. Design and type of system shall be based upon the requirements of the Building Code, Fire Code and the requirements of the Fontana Fire Prevention District.
32. The applicant shall comply with the requirements of the South Coast Air Quality Management District (909-396-2000). SCAQMD requirements shall be satisfied prior to the issuance of any permit if hazardous materials are stored and/or used.
33. The applicant shall verify that any temporary building, trailer, commercial coach, etc. installed and/or used in connection with a construction project complies with FMC Chapter 5 Article XIV.
34. The applicant shall verify that all perimeter/boundary walls are designed and constructed so that the outer/exterior face of the wall is as close as possible to the lot line. In any case, the outer/exterior face of the wall shall be within two (2) inches of the lot line. Distances greater than two (2) inches may be approved prior to construction by the Building Official on a case by case basis for extenuating circumstances.
35. The applicant shall have the tract or parcel map recorded prior to the issuance of any building permits.
36. The applicant shall comply with the following grading requirements:
A. Grading plans shall be submitted to and approved by Building & Safety.
The grading plans shall indicate all site improvements and shall indicate complete drainage paths of all drainage water run-offs.
B. All drainage water shall drain via approved methods to an approved location, such as a public street, a public drainage system, etc.
C. Drainage water shall not cross over a public sidewalk. Drainage water may, however, cross under a sidewalk if an approved drainage structure is used.
D. A recorded drainage acceptance agreement is required from adjoining property(s) receiving flows from this property.
E. No water course or natural drainage shall be obstructed.
F. Minimum slope or grade for ALL drainage structures shall be one half (0.50) percent for concrete and one (1.0) percent for all other, or as otherwise approved by the Building Official.
G. Drainage water shall not pass from an ‘improved’ type of drainage structure to an ‘unimproved’ type of drainage structure (e.g., concrete swale to a dirt swale) unless otherwise approved by the Building Official.
H. A complete hydrology study using the latest edition of the San Bernardino County Flood Control Hydrology Manual, and complete hydraulic 105 354
Resolution PC No. 2023-____
calculations justifying the size, slope, capacity, etc. of any and all drainage structures being utilized, shall be submitted to and approved by Building & Safety.
I. The on site drainage system shall, as a minimum, be designed to handle the run off generated by a ten (10) year storm. Check for flooding of all on site structures (buildings) and all adjacent properties during a hundred (100) year storm.
J. The grading plans shall, as a minimum, contain sections at all lot lines and/or permit boundary lines. These sections shall clearly indicate:
1. The relationship between the proposed finished on site grade elevations and the existing adjacent property grade elevations (Indicate any additional drainage water that may come from an adjacent property.); and
2. The ground cover/finished surface material being proposed (e.g., type of pavement, plant material, etc.); and
3. All proposed drainage structures; and
4. Any proposed and/or required walls or fencing.
37. The applicant is required to obtain permits for the removal and/or demolition of structures.
38. The applicant shall verify that all exterior lighting shall be oriented, directed, and/or shielded as much as possible so that direct illumination does not infringe onto adjoining properties.
PRIOR TO ISSUANCE OF BUILDING/CONSTRUCTION PERMITS
39. The following items (as applicable) shall be completed by the applicant and submitted to Building & Safety prior to the issuance of building permits for this project:
A. Precise grading plans shall be approved
B. Rough grading completed
C. Compaction certification
D. Pad elevation certification
E. Rough grade inspection signed off by a City Building Inspector
40. If hazardous substances are used and/or stored, the applicant shall provide a technical opinion and report, identifying and developing methods of protection from the hazards presented by the hazardous materials, may be required. This report shall be prepared by a qualified person, firm, or corporation and submitted to Building & Safety. This report shall also explain the proposed facility's intended methods of operation and list all of the proposed materials, their quantities, classifications, and the effects of any chemical (material) inter mixing in the event of an accident or spill.
41. The applicant shall combine the existing parcels into a single parcel, or a lot line adjustment shall be done so that the proposed structure(s) does not cross any lot line and complies with all requirements of the California Building Code, prior to any building permits being issued.
106 355
Resolution PC No. 2023-____
ENGINEERING DEPARTMENT:
42. The Project shall be served by the City’s sanitary sewer system, all sewer facilities shall be constructed in accordance with the City Standards. Main trunk sewer line shall be in accordance with master sanitary sewer plan or as approved by the City Engineer.
43. The Applicant shall obtain design and plan approval from all utility providers having jurisdiction over the on-site and off-site utilities. Completion of all undergrounding of on-site and off-site utilities is required by Section 27-52 of the City Municipal Code and in accordance with plans and specifications approved by the City Engineer.
44. The Applicant shall maintain all improvements and utilities within the public rightof-way, including street sweeping, prior to issuance of final certificate of occupancy by the City.
PRIOR TO ISSUANCE OF GRADING PERMIT
45. The Applicant shall submit and gain approval of a complete Water Quality Management Plan report in accordance with the County of San Bernardino Technical Guidance Document and latest template.
46. The Applicant shall submit and gain approval of a final drainage study prepared in accordance with the County of San Bernardino Hydrology Manual and Fontana Master Plan of Drainage.
PRIOR TO MAP RECORDATION
47. The Applicant shall provide a Land Improvement Agreement, with accompanying security. The agreement shall be executed on City-provided forms.
PRIOR TO ISSUANCE OF CONSTRUCTION PERMITS
48. The Applicant shall record All map’s, lot line adjustments, right-of-way dedications, right-of-way vacations, easements, reciprocal access agreement as required for the development.
49. The Applicant shall submit engineered improvement plans and obtain full approval. All required public improvements, including but not limited to streets, storm drainage systems, sewers, traffic signals, streetlights, striping, signs, landscape, and any required traffic control and/or detour plans. All plans shall
50. conform to City Standards and Specifications, and as approved by the City Engineer.
PRIOR TO ISSUANCE OF FINAL CERFITICATE OF OCCUPANCY
51. The Applicant/Engineer to provide the City of Fontana with As Built/Record Drawings for all public improvement plans.
52. The Applicant/Engineer shall provide centerline ties to the City of Fontana reflecting proper setting of all survey monuments within the project limits and 107 356
Resolution PC No. 2023-____
replace any existing survey monuments damaged or removed during construction.
53. The Applicant/Engineer shall set survey monuments as required by the map and corner records must be recorded with the County.
54. The Applicant/Landscape Architect shall provide a “Landscape Certificate of Compliance” certifying that the work has been designed, installed, and will be maintained in accordance with the City of Fontana’s Model Water Efficiency Landscape Ordinance (Ordinance 1743, FCC Section 28).
55. All sewers shall be video inspected by applicant/contractor. Sewer video shall include clean-out connection, clean-out to lateral segment, lateral, and main line.
Contractor performing the video inspection must have a NASSCO PACP, LACP, and MACP certification. Applicant shall provide a copy of the video on DVD or flash drive to inspection staff with an accompanying full report. Videos to be inspected and approved by City Inspector. If removal and replacement of any utility is required, a subsequent video of the repair will be required. If a TCO (Temporary Certificate of Occupancy) is required a full video inspection will be required as well at that time.
56. All storm drains shall be video inspected by applicant/contractor. Storm drain video shall include main lines and laterals. Applicant shall provide a copy of the video on DVD or flash drive to inspection staff. Videos to be inspected and approved by City Inspector. If removal and replacement of any utility is required, a subsequent video of the repair will be required.
57. The Applicant/Engineer of Record shall submit a conforming copy of the recorded Memorandum of Agreement for the Water Quality Management Plan and Storm Water Best Management Practice transfer. The Access, Maintenance, and the WQMP Certification for BMP Completion must be submitted to the City Project Engineer.
FIRE DEPARTMENT:
58. Jurisdiction: The above referenced project is under the jurisdiction of the Fontana fire Protection District (herein “Fire Department”). Prior to any construction occurring on any parcel, the applicant shall contact the Fire Department for verification of current fire protection requirements. All new construction shall comply with the current California Fire Code requirements and all applicable statutes, codes, ordinances, and standards of the Fire Department.
59. Fire Access Road Width: Prior to map recordation, all fire access roadways shall be designed to meet the requirements for this development and shall be approved by the Fire Department. All buildings shall have access provided by approved roads, alleys, and private drives with a minimum twenty-six (26) foot unobstructed width and vertically to fourteen (14) feet six (6) inches in height. Buildings three (3) stories in height or more shall have a minimum access of thirty (30) feet unobstructed width and vertically to fourteen (14) feet six (6) inches in height.
California Fire Code Chapter 5 & SBCoFD Standard A-1.
108 357
Resolution PC No. 2023-____
60. Turnaround: An approved turnaround shall be provided at the end of each roadway one hundred and fifty (150) feet or more in length. Cul-de-sac length shall not exceed six hundred (600) feet; all roadways shall not exceed a 12% grade and have a minimum of nineteen (19) foot inside radius and a forty-five (45) foot outside radius for all turns. California Fire Code Chapter 5 & SBCoFD Standard A-1.
61. Fire Lanes: The applicant shall submit a site plan to the Fire Department for review and approval of all proposed signage and striping for all fire access roadways. All curbs adjacent to fire lanes shall be painted red and “No Parking, Fire Lane” signs shall be installed on public and private roads in accordance with approved standards. SBCoFD Standard A-2.
62. Water System Commercial: Prior to map recordation or lot line adjustment, all water supply systems shall be designed to meet the required fire flow for this development and shall be approved by the Fire Department. The required fire flow shall be determined by using Appendix BB of the California Fire Code. A minimum of one new six (6) inch fire hydrant assembly with two (2) two and one half (2 1/2) inch and one (1) four (4) inch outlet (4”x2.5”x2.5”) shall be provided.
All fire hydrants shall be spaced no more than three hundred (300) feet apart as measured along vehicular travel-ways. California Fire Code Chapter 5 & SBCoFD Standard W-2. The Fire Flow for this project shall be: 4,000 GPM for a two-hour duration at 20 psi residual operating pressure. Fire Flow is based on a 490,550 Square Foot structure.
63. Hydrant Marking: Blue reflective pavement markers indicating fire hydrant locations shall be installed as specified by the Fire Department. SBCoFD Standard W-2.
64. Water Improvement Plan: The applicant shall submit “Water Improvement Plans” to Fontana Fire Prevention. W.I.P. to include site plan, existing & proposed PUBLIC fire hydrant locations, building construction type, largest building square footage details, lot size detail in square feet, and description of what is being constructed. Once approved by Fire Department, applicant will provide stamped/approved W.I.P to water purveyor for their construction needs. ON-SITE
PRIVATE FIRE WATER SUPPLY SHALL BE INSPECTED AND IN WORKING
CONDITION PRIOR TO PLACING COMBUSTIBLE MATERIALS ON THE JOBSITE. California Fire Code Chapter 5.
65. Combustible Protection: Prior to combustibles being placed on the project site an approved paved roadway providing fire access and fire hydrants providing an acceptable fire flow shall be installed. California Fire Code Chapter 5.
66. Fire Sprinkler-NFPA #13: An automatic fire sprinkler system complying with NFPA 13 and Fire Department standards is required. A fire sprinkler contractor shall submit three (3) sets of detailed plans to the Fire Department for review and approval. The plans shall include hydraulic calculations and manufacturer 109 358
Resolution PC No. 2023-____
specification sheets. The required fees shall be paid at the time of plan submittal.
California Fire Code Chapter 9 & SBCoFD Standard F-1.
67. Fire Alarm, Waterflow Monitoring: A water flow monitoring fire alarm system complying with the California Fire Code, NFPA and all applicable codes is required for fire sprinkler systems with twenty (20) sprinkler heads or more. A fire alarm contractor shall submit three (3) sets of detailed plans to the Fire Department for review and approval. The required fees shall be paid at the time of plan submittal. California Fire Code Chapter 9, NFPA 72 & SBCoFD Standard F-5.
68. Smoke Removal: An automatic smoke removal system complying with the California Fire Code, NFPA and all applicable codes is required. The applicant shall submit three (3) sets of detailed smoke removal system plans to the Fire Department for review and approval. The required fees shall be paid at the time of plan submittal. California Fire Code Chapter 9.
69. Fire Extinguishers: Hand portable fire extinguishers are required. The location, type, and cabinet design shall be approved by the Fire Department. California Fire Code Chapter 9.
70. Commercial (large facility) Addressing: Commercial and industrial developments in excess of 100,000 sq. ft. shall have the street address installed on the building with numbers that are a minimum twelve (12) inches in height and with a one and one half (1½) inch stroke. The street address shall be visible from the street.
During the hours of darkness, the numbers shall be electrically illuminated (internal or external). Where the building is two hundred (200) feet or more from the roadway, additional non-illuminated contrasting six (6) inch numbers shall be displayed at the property access entrances. California Fire Code Chapter 5 & SBCoFD Standard B-1
71. Key Box: An approved Fire Department key box is required. The key box shall be provided with a tamper switch and shall be monitored by a Fire Department approved central monitoring service. California Fire Code Chapter 5 & SBCoFD Standard A-4
72. Security Gates: In commercial, industrial, and multi-family complexes, all swing gates shall have an approved fire department Knox Lock. Where an automatic electric security gate is used, an approved Fire Department override switch is required. California Fire Code Chapter 5 & SBCoFD Standard A-3
73. Material Identification Placards: The applicant shall install, in all locations deemed appropriate by the Fire Department, approved material identification placards on the outside of all buildings and/or storage tanks that store hazardous or flammable materials. Additional placards shall be required inside the buildings when chemicals are segregated into separate areas. California Fire Code Chapter 50 & NFPA 704.
110 359
Resolution PC No. 2023-____
74. High-Piled Storage: The applicant shall submit an application for a High-Piled Storage permit for storage of over 12’ in height of Class I-IV commodities and/or over 6’ in height of high hazard commodities. Three (3) sets of detailed plans and a commodity analysis report shall be submitted to the Fire Department for review and approval. The applicant shall submit to the Fire Department concurrently with any racking permits to the Building and Safety division. California Fire Code Chapter 32 & SBCoFD Standard S-1.
75. Secondary Access: The development shall have a minimum of two (2) points of vehicular access during each phase of construction for fire and emergency access purposes and for evacuation routes. SBCoFD Standard A-1
76. San Bernardino County Fire Standards/Codes: Items not directly called out on these Conditions of Approval, shall also adhere to currently adopted San Bernardino County Fire Standards, California Fire Code, & NFPA.
END OF CONDITIONS OF APPROVAL
111 360
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh
RECORDING REQUESTED BY:
ALEJANDRO RICO
Order No:
WHEN RECORDED MAIL
DOCUMENT TO:
City of Fontana
8353 Sierra Avenue
Fontana, California 92335
Attn.: City Clerk
Space Above This Line for Recorder's Use Only
Exempt from Recording Fees Pursuant
to Gov. Code §§ 27383, 6103
ROSE PROJECT
DEVELOPMENT AGREEMENT
BETWEEN
THE CITY OF FONTANA,
a California municipal corporation
and
LIT INDUSTRIAL LIMITED PARTNERSHIP
a Delaware Limited Partnership
Dated as of _________, 2023 for reference purposes
112 361
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh
ROSE AVENUE PROJECT DEVELOPMENT AGREEMENT
The ROSE AVENUE PROJECT DEVELOPMENT AGREEMENT ("Agreement") is entered into by the City of Fontana a California municipal corporation (hereinafter "City"), and LIT Industrial Limited Partnership, a Delaware limited partnership (hereinafter "Owner"). This Agreement is dated ___________, 2023 for reference purposes only; it will not become effective until the "Effective Date" (defined below). City and Owner are sometimes collectively referred to in this Agreement as the "Parties" and individually as a "Party."
RECITALS
WHEREAS, City is authorized to enter into binding development agreements with persons having legal or equitable interests in real property for the development of such property, pursuant to Section 65864 et seq. of the Government Code; and
WHEREAS, Owner has requested that City enter into this Development Agreement with respect to that certain real property located on Rose Avenue in the City, consisting of 41 parcels identified as Assessor’s Parcel Numbers (APNs) 0237-171-01 through -19, 0237-172-01 through -12, -19, -22, -23, -26, -27, -28, and -30 through -33, as more particularly described on Exhibit “A” and shown on Exhibit “B” to this Agreement (the “Property”), and proceedings have been taken in accordance with the rules and regulations of City; and WHEREAS, by electing to enter into this Agreement, City shall bind the City, including current and future City Councils of City, by the obligations specified herein and limit the future exercise of certain governmental and proprietary powers of City; and WHEREAS, the terms and conditions of this Agreement have undergone extensive review by City and the City Council and have been found to be fair, just and reasonable; and WHEREAS, the best interests of the citizens of the City and the public health, safety and welfare will be served by entering into this Agreement; and WHEREAS, prior to the adoption of the Development Approvals described in this Agreement, the City Council has reviewed and considered the Environmental Impact Report and made findings concerning the mitigation measures and adopted a Mitigation Monitoring and Reporting Program in accordance with CEQA and the State and City CEQA Guidelines; and WHEREAS, Owner has filed an application for, and the City Council has approved, General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Plan Review (DRP) No. 22-22-040 and Tentative Parcel Map No. 20638; and WHEREAS, this Agreement and the Project are consistent with the City's Comprehensive General Plan and Specific Plan (as defined in Section 1 below), as amended; and WHEREAS, all actions taken and approvals given by City have been duly taken or approved in accordance with all applicable legal requirements for notice, public hearings, findings, votes, and other procedural matters; and
113 362
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -2-
WHEREAS, development of the Property in accordance with this Agreement and Development Plan (as defined in Section 1 below) will provide substantial benefits to City and will further important policies and goals of City;
WHEREAS, this Agreement will eliminate uncertainty in planning and provide for the orderly development of the Property, ensure the installation of necessary improvements, provide for public services appropriate to the development of the Project, and generally serve the purposes for which development agreements under Sections 65864 et seq. of the Government Code are intended; and
WHEREAS, Owner has incurred and will in the future incur substantial costs in excess of the generally applicable requirements in order to assure the vesting of its legal rights to develop the Property in accordance with this Agreement and Development Plan (defined below).
COVENANTS
NOW, THEREFORE, in consideration of the above recitals and of the mutual covenants hereinafter contained and for other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the Parties agree as follows:
1. DEFINITIONS AND EXHIBITS
1.1 Definitions. The following terms when used in this Agreement shall be defined as follows:
1.1.1 "Agreement" means this Development Agreement.
1.1.2 "City" means the City of Fontana, a municipal corporation, organized and existing pursuant to the laws of the State of California.
1.1.3 "Owner" means LIT Industrial Limited Partnership, a Delaware limited partnership, and its successors in interest to all or any part of the Property.
1.1.4 "Development" means the improvement of the Property for the purposes of completing the structures, improvements and facilities comprising the Project, including, but not limited to: grading; the construction of infrastructure and public facilities related to the Project whether located within or outside the Property; the construction of buildings and structures; and the installation of landscaping. "Development" does not include the repair or reconstruction of any building, structure, improvement, or facility after the construction and completion thereof if undertaken during the Term of this Agreement.
1.1.5 "Development Agreement Policies" means those certain development agreement policies approve by City pursuant to Ordinance No. , adopted on as may be amended, as Resolution No. , adopted on , as may be amended.
1.1.6 "Development Approvals" means all permits and other entitlements subject to approval or issuance by City in connection with the Development of the Property as set forth in attached Exhibit C, including, but not limited to: general plan amendments; specific plans and 114 363
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -3-
specific plan amendments; tentative and final subdivision and parcel maps; design review; conditional use permits; zoning; and grading and building permits.
1.1.7 "Development Exaction" means any requirement of City in connection with or pursuant to any Land Use Regulation or Development Approval for the dedication of land, the construction of improvements or public facilities, or the payment of fees in order to lessen, offset, mitigate or compensate for the impacts of development on the environment or other public interests, including those imposed in accordance with the MMRP.
1.1.8 "Development Impact Fee" means a monetary exaction other than a tax or special assessment, whether established for a broad class of projects by legislation of general applicability or imposed on a specific project on an ad hoc basis, that is charged by City to the applicant in connection with the approval of a development project for the purpose of defraying all or a portion of the cost of public facilities related to the development project, but does not include park “in lieu” fees specified in Government Code Section 66477, fees for processing applications for governmental regulatory actions or approvals, fees collected under development agreements adopted pursuant to Article 2.5 of the Government Code (commencing with Section 65864) of Chapter 4, or fees collected pursuant to agreements with redevelopment agencies which provide for the redevelopment of property in furtherance or for the benefit of a redevelopment project for which a redevelopment plan has been adopted pursuant to the Community Redevelopment Law (Part 1 (commencing with Section 33000) of Division 24 of the Health and Safety Code)..
1.1.9 "Development Plan" means the development of the Property permitted by the Existing Development Approvals and the Existing Land Use Regulations applicable to development of the Property.
1.1.10 "Effective Date" means the date the ordinance approving this Agreement becomes effective.
1.1.11 "Existing Development Approvals" means all Development Approvals approved or issued prior to, or as of, the Effective Date. Existing Development Approvals includes the Development Approvals described on the attached Exhibit C and all other Development Approvals which are a matter of public record on the Effective Date. The Existing Development Approvals are sufficient in order to develop the Property and to implement the Project.
1.1.12 "Existing Land Use Regulations" means all Land Use Regulations in effect on the Effective Date.
1.1.13 "Land Use Regulations" means all ordinances, resolutions, codes, rules, regulations and official policies of City governing the development and use of land, including, without limitation, the permitted use of land, the density or intensity of use, subdivision requirements, the maximum height and size of proposed buildings, the provisions for reservation or dedication of land for public purposes, and the design, improvement and construction standards and specifications applicable to the Development of the Property. "Land Use Regulations" do not include any City ordinance, resolution, code, rule, regulation, or official policy governing: the conduct of businesses, professions, and occupations; taxes and assessments; the control and 115 364
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -4-
abatement of nuisances; the granting of encroachment permits and the conveyance of rights and interests which provide for the use of or the entry upon public property; or the exercise of the power of eminent domain.
1.1.14 "Mitigation Monitoring and Reporting Program" or "MMRP" means the mitigation monitoring and reporting program for assessing and ensuring compliance with required environmental impact mitigation measures approved by City Council Resolution No. _________ ___________, 2023 in conjunction with the City Council's certification of the EIR.
1.1.15 "Mortgagee" means a mortgagee of a mortgage, a beneficiary under a deed of trust, or any other security-device lender, and their successors and assigns in interest to all or any part of the Property.
1.1.16 "Parcel Map" means the subdivision map identified in City records as Tentative Parcel Map No. 20638 and approved by the City Council on ____________, 2023.
1.1.17 "Project" means the Development of the Property contemplated by the Development Plan, as such Development Plan may be further defined, enhanced, or modified pursuant to the provisions of this Agreement. The Project will consist of a logistics facility totaling approximately 490,565 square feet.
1.1.18 "Property" means the certain real property located on Rose Avenue in the City, consisting of 41 parcels identified as Assessor’s Parcel Numbers (APNs) 0237-171-01 through -19, 0237-172-01 through -12, -19, -22, -23, -26, -27, -28, and -30 through -33, as more particularly described in Exhibit A and shown on Exhibit B to this Agreement.
1.1.19 "Reservations of Authority" means the rights and authority excepted from the assurances and rights provided to Owner under this Agreement and reserved to City under Section 3.6 of this Agreement.
1.1.20 "Specific Plan" means the "Southwest Industrial Park Specific Plan (SWIP)" identified in City records as SP No. 09-02 and adopted by City Council Ordinance No. 1663 on June 12, 2012.
1.1.21 "Subdivision Map Act" means Government Code Sections 66410, et seq.
1.1.22 "Subsequent Development Approvals" means all Development Approvals required subsequent to the Effective Date in connection with the Development of the Property.
1.1.23 "Subsequent Land Use Regulations" means any Land Use Regulations adopted and effective after the Effective Date.
1.1.24 "Term" has the meaning given in Section 2.3 of this Agreement.
1.2 Exhibits. The following documents are attached to, and by this reference made a part of, this Agreement:
Exhibit A – Legal Description of the Property
116 365
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -5-
Exhibit B – Map showing Property and its location
Exhibit C – Existing Development Approvals
2. GENERAL PROVISIONS
2.1 Binding Effect of Agreement. The Property is hereby made subject to this Agreement. The Development of the Property is hereby authorized and shall be carried out only in accordance with the provisions of this Agreement.
2.2 Property Ownership and Interest. The Owner represents and covenants that it is the legal or equitable owner of the fee simple title to the Property.
2.3 Term. The term of this Agreement shall commence on the Effective Date, and shall continue for a period of ten (10) years thereafter unless this term is modified or extended pursuant to the provisions of this Agreement.
2.4 Sale or Assignment.
2.4.1 Right to Assign. Subject to the City's written consent, which shall not be unreasonable withheld, delayed or conditioned, Owner shall have the right to sell, transfer, or assign the Property in whole or in part (provided that no such partial transfer shall violate the Subdivision Map Act) to any person, partnership, joint venture, affiliate, firm, or corporation at any time; provided, however, that any such sale, transfer or assignment shall include the assignment and assumption of the rights, duties and obligations arising under or from this Agreement and be made in strict compliance with the following conditions precedent:
(a) No sale, transfer or assignment of any right or interest under this Agreement shall be made unless made together with the sale, transfer or assignment of all or a part of the Property.
(b) Concurrent with any such sale, transfer, or assignment, or within fifteen (15) business days thereafter, Owner shall notify City, in writing, of such sale, transfer, or assignment and shall provide City with an executed agreement, in a form reasonably acceptable to City, executed by the purchaser, transferee, or assignee and providing therein that the purchaser, transferee, or assignee expressly and unconditionally assumes all the duties and obligations of Owner under this Agreement.
Any sale, transfer or assignment not made in compliance with the foregoing conditions shall constitute a default by Owner under this Agreement. Notwithstanding the failure of any purchaser, transferee or assignee to execute this agreement required by Paragraph (b) of this Subsection 2.4.1, the burdens of this Agreement shall be binding upon such purchaser, transferee or assignee, but the benefits of this Agreement shall not inure to such purchaser, transferee or assignee until and unless such agreement is executed. Notwithstanding the foregoing, Owner shall have the right to transfer its interest in this Agreement to an “Owner Affiliate”. Notwithstanding the foregoing, Owner shall have the right to transfer its interest in this Agreement to an “Owner Affiliate.” An “Owner Affiliate” is an entity in which the original owner owns a majority financial 117 366
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -6-
or voting interest. Owner shall provide written notification to City concurrently with the completion of such a transfer.
2.4.2 Release of Transferring Owner. Notwithstanding any sale, transfer or assignment, Owner shall continue to be obligated under this Agreement as to that portion of the Property sold, transferred or assigned, unless Owner is given a release in writing by City, which release shall be provided by City upon the full satisfaction by Owner of all of the following conditions:
(a) Owner no longer has a legal or equitable interest in all or any part of the Property sold.
(b) Owner is not then in default under this Agreement.
(c) Owner has provided City with the notice and executed agreement required under paragraph (2) of subsection 2.4 above.
(d) The purchaser, transferee or assignee provides City with security equivalent to any security previously provided by Owner to secure performance of its obligations hereunder.
2.4.3 Subsequent Assignment. Any subsequent sale, transfer or assignment after an initial sale, transfer or assignment shall be made only in accordance with and subject to the terms and conditions of this Section.
2.4.4 Partial Release of Purchaser, Transferee or Assignee of Industrial or Commercial Lot. A purchaser, transferee or assignee of a lot, which has been finally subdivided as provided for in the Development Plan and for which a commercial or industrial plot plan for development of the lot has been finally approved pursuant to the Development Plan, may submit a request, in writing, to City to release said lot from the obligations under this Agreement relating to all other portions of the property. Within thirty (30) days of such request, City shall review, and if the above conditions are satisfied shall approve the request for release and notify the purchaser, transferee or assignee in writing thereof. No such release approved pursuant to this Subsection
2.4.4 shall cause, or otherwise affect, a release of Owner from its duties and obligations under this Agreement.
2.4.5 Termination of Agreement With Respect to Individual Lots Upon Sale to Public and Completion of Construction. The provisions of Subsection 2.4.1 shall not apply to the sale or lease (for a period longer than one year) of any lot which has been finally subdivided and is individually (and not in “bulk”) sold or leased to a member of the public or other ultimate user.
Notwithstanding any other provisions of this Agreement, this Agreement shall terminate with respect to any lot and such lot shall be released and no longer be subject to this Agreement without the execution or recordation of any further document upon satisfaction of both of the following conditions:
(a) The lot has been finally subdivided and individually (and not in “bulk”) sold or leased (for a period longer than one year) to a member of the public or other ultimate user; and,
118 367
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -7-
(b) A certificate of occupancy has been issued for a building on the lot, and the fees set forth under Section 4 of this Agreement have been paid.
2.5 Amendment or Cancellation of Agreement. This Agreement may be amended or canceled in whole or in part only by written consent of all parties in the manner provided for in Government Code Section 65868 and the Development Agreement Policies. This provision shall not limit any remedy of City or Owner for a party's breach of the Agreement as provided by this Agreement.
2.6 Termination. This Agreement shall terminate and be of no further effect upon the occurrence of any of the following events:
2.6.1 Expiration of the stated term of this agreement as set forth herein.
2.6.2 Entry of a final judgment setting aside, voiding, or annulling the adoption of the ordinance approving this Agreement.
2.6.3 The adoption of a referendum measure overriding or repealing the ordinance approving this Agreement.
2.6.4 The completion of the Project in accordance with the terms of this Agreement, including, without limitation, the issuance of all required occupancy permits and acceptance by City (or other applicable public agency) of any required public dedications.
2.6.5 Termination by the City upon a default by Owner, as provided in this Agreement.
2.6.6 Termination of this Agreement will not operate to automatically terminate any Development Approvals or other land use entitlements approved for the Property. Upon the termination of this Agreement, no party shall have any further right or obligation hereunder except with respect to any obligation to have been performed prior to such termination or with respect to any default in the performance of the provisions of this Agreement that has occurred prior to such termination, or with respect to any obligations which are specifically set forth as surviving this Agreement. Upon such termination, any public facilities and services mitigation fees paid pursuant to Section 4.2 of this Agreement by Owner to City buildings on which construction has not yet begun shall be refunded to Owner by City.
2.6.7 Notwithstanding any provision herein to the contrary, subject to the provisions of Section 4.3.3, the obligation of Owner to pay the Public Benefit Fee as set forth in Section 4.3.1 shall survive the termination of this Agreement until all buildings have been constructed on the Property pursuant to the Development Plan or otherwise.
2.7 Notices.
2.7.1 As used in this Agreement, "notice" includes, but is not limited to, the communication of notice, request, demand, approval, statement, report, acceptance, consent, waiver, appointment, or other communication required or permitted hereunder. 119 368
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -8-
2.7.2 All notices shall be in writing and shall be considered given either: (i) when delivered in person to the recipient named below; (ii) on the date of delivery shown on the return receipt after deposit in the United States mail in a sealed envelope as either registered or certified mail with return receipt requested, postage and postal charges prepaid, and addressed to the recipient named below; or (iii) by overnight courier, on the first (1st) business day after being delivered to a recognized overnight courier. All notices shall be addressed as follows:
If to City:
City of Fontana
8353 Sierra Avenue
Fontana, CA 92335
Attn: City Manager
Telephone: (909) 350-7600
If to Owner:
LIT Industrial Limited Partnership
c/o Seefried Industrial Properties
2321 Rosecrans Ave. Suite 2220
El Segundo, CA 90245
Attn: Scott Irwin
Telephone: (310) 536-7900
with a copy to:
Best, Best & Krieger, LLP
2855 East Guasti Rd., Suite 400
Ontario, CA 91761
Attn: Fontana City Attorney
Telephone: (909) 989-8584
with a copy to:
Allen Matkins Leck Gamble
Mallory & Natsis LLP
2010 Main Street, Suite 800
Irvine, CA 92614
Attn: John C. Condas, Esq.
Telephone: (949) 553-1313
2.7.3 Either party may, by notice given at any time, require subsequent notices to be given to another person or entity, whether a party or an officer or representative of a party, or to a different address, or both. Notices given before actual receipt of notice of change shall not be invalidated by the change.
3. DEVELOPMENT OF THE PROPERTY
3.1 Rights to Develop. Subject to the terms of this Agreement, including the Reservations of Authority, Owner shall have the vested right to develop the Property in accordance with, and to the extent of, the Development Plan. The Project shall remain subject to all Subsequent Development Approvals required to complete the Project as contemplated by the Development Plan. Except as otherwise provided in this Agreement, the permitted uses of the Property, the density and intensity of use, the maximum height and size of proposed buildings, and provisions for reservation and dedication of land for public purposes shall be those set forth in the Development Plan. Notwithstanding the foregoing, nothing contained in this Agreement shall be deemed to be a covenant to develop or construct the Project or any portion of the Project.
3.2 Effect of Agreement on Land Use Regulations. Except as otherwise provided under the terms of this Agreement, including the Reservations of Authority, the rules, regulations, and official policies governing permitted uses of the Property, the density and intensity of use of the Property, the maximum height and size of proposed buildings, and the design, improvement 120 369
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -9-
and construction standards and specifications applicable to the Development of the Property shall be the Existing Land Use Regulations. In connection with any Subsequent Development Approval, City shall exercise its reasonable discretion in accordance with the Development Plan and as provided by this Agreement, including, but not limited to, the Reservations of Authority.
City shall accept for processing, review, and action all applications for Subsequent Development Approvals and such applications shall be processed in the normal manner for processing such matters.
3.3 Timing of Development. The parties acknowledge that Owner cannot at this time predict when or the rate at which phases of the Property will be developed. Such decisions depend upon numerous factors which are not within the control of Owner, such as market orientation and demand, interest rates, absorption, completion and other similar factors. Because the California Supreme Court held in Pardee Construction Co. v. City of Camarillo (1984) 37 Cal.3d 465, that the failure of the parties therein to provide for the timing of development resulted in a later adopted initiative restricting the timing of development to prevail over such parties' agreement, it is City's and Owner's intent to cure that deficiency by acknowledging and providing that Owner shall have the right to develop the Property, or not, in such order and at such rate and at such times as Owner deems appropriate within the exercise of its subjective business judgment, subject only to any timing or phasing requirements set forth in the Development Plan or the Phasing Plan set forth in Section 3.4.
3.4 Development Phasing Plan. The Development of the Property is subject to any timing and phasing requirements established by the Development Plan.
3.5 Changes and Amendments.
3.5.1 The parties acknowledge that refinement and further development of the Project may demonstrate that changes are appropriate and mutually desirable in the Existing Development Approvals. If in years one (1) through five (5) during the Term of this Agreement, Owner finds that a change in the Existing Development Approvals is necessary or appropriate, Owner shall apply for a Subsequent Development Approval to effectuate such change and City shall process and act on such application in accordance with the Existing Land Use Regulations, except as otherwise provided by this Agreement, including the Reservations of Authority. If approved, any such change in the Existing Development Approvals shall be incorporated herein as an addendum to Exhibit C and may be further changed from time to time as provided in this Section 3.5.
If in years six (6) through ten (10) during the Term of this Agreement, Owner finds that changes to the Existing Development Approvals are necessary or appropriate for the refinement and further development of the Project, Owner shall apply for a Subsequent Development Approval and City shall process and act on such application in accordance with the land use regulations existing at the time of such application. Notwithstanding any provision herein to the contrary, Owner shall pay any and all fees and Development Exaction in place following years one (1) through five (5) and shall be required to pay any and all fees and exactions adopted at the time of applications for permits and approvals related to the Development Plan, including any amendments thereto. 121 370
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -10-
3.5.2 Unless otherwise required by law, as determined in City's reasonable discretion, a change to the Existing Development Approvals shall be deemed "minor" and not require an amendment to this Agreement; but instead will require only the approval of City's Director of Planning; provided the change does not:
(a) Alter the permitted uses of the Property as a whole; or, (b) Increase the density or intensity of use of the Property as a whole; or,
(c) Increase the maximum height and size of permitted buildings; or, (d) Delete a requirement for the reservation or dedication of land for public purposes; or,(e) Constitute a project requiring a subsequent or supplemental environmental impact report pursuant to Section 21166 of the Public Resources Code. (e) The provisions of this Agreement require a close degree of cooperation between the City and the Owner. It is anticipated due to the term of this Agreement that refinements to the Development Approvals may be appropriate with respect to the details of performance of the City and the Owner. To the extent allowable by law, the Owner shall retain a certain degree of flexibility as provided herein with respect to all matters, items and provisions covered in general under this Agreement and exhibits thereto. When and if the Owner finds it necessary or appropriate to make changes, adjustments or clarifications, the Parties shall effectuate such changes, adjustments or clarifications through operating memoranda (“Operating Memoranda”) approved by the Parties in writing, which reference this Section of the Agreement.
Operating Memoranda are not intended to constitute an amendment to this Agreement but mere ministerial clarifications; therefore, public notices and hearings shall not be required. The City Attorney shall be authorized, upon consultation with the Owner, to determine whether a requested clarification may be effectuated pursuant to this Section or whether the requested clarification is of such character to constitute an amendment to the Agreement which requires compliance with the provisions of this Agreement pertaining to amendments. The authority to enter into such Operating Memoranda is hereby delegated to the City Manager, and the City Manager is hereby authorized to execute any Operating Memoranda hereunder without Planning Commission or City Council action and without public hearing. Although other matters may also fall within the scope of Operating Memoranda, any amendment to this Agreement which does not relate to the Term, permitted uses of the Project, provisions for the reservation or dedication of land, grant of easement, or the conditions, terms, restrictions and requirements relating to Subsequent Development Approvals of City, revisions to Public Benefits (other than to the time for performance of such Public Benefits) or monetary exactions of Owner, shall be considered an “Operating Memorandum”.
3.6 Reservations of Authority.
3.6.1 Limitations, Reservations and Exceptions. Notwithstanding any other provision of this Agreement, the following Subsequent Land Use Regulations and fees and expenses shall apply to the Development of the Property (collectively, the "Reservations of Authority"):
122 371
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -11-
(a) Processing fees and charges of every kind and nature imposed by City to cover the estimated actual costs to City of processing applications for Development Approvals or for monitoring compliance with any Development Approvals granted or issued. (b) Procedural regulations relating to hearing bodies, petitions, applications, notices, findings, records, hearings, reports, recommendations, appeals, and any other matter of procedure.
(c) Regulations governing construction standards and specifications, including, without limitation, the City's Building Code, Plumbing Code, Mechanical Code, Electrical Code, and Fire Code.
(d) Regulations imposing Development Exactions; In years one (1) through five (5) during Term of this Agreement, no such subsequently adopted Development Exaction shall be applicable to development of the Property unless such Development Exaction is applied uniformly to development, either throughout the City or within a defined area of benefit which includes the Property. No such subsequently adopted Development Exaction within the aforementioned timeframe shall apply if its application to the Property would physically prevent development of the Property for the uses and to the density or intensity of development set forth in the Development Plan. In the event any such subsequently adopted Development Exaction fulfills the same purposes, in whole or in part, as the fees set forth in Section 4 of this Agreement, City shall allow a credit against such subsequently adopted Development Exaction for the fees paid under Section 4 of this Agreement to the extent such fees fulfill the same purposes. (e) Regulations that may be in conflict with the Development Plan but that are reasonably necessary to eliminate or mitigate a serious threat to public health and safety.
To the extent possible, any such regulations shall be applied and construed so as to provide Owner with the rights and assurances provided under this Agreement. (f) Regulations that are not in conflict with the Development Plan. Any regulation, whether adopted by initiative or otherwise, limiting the rate or timing of development of the Property, or which shall increase the cost of development of the Project, shall be deemed to conflict with the Development Plan and shall therefore not be applicable to the development of the property during years one (1) through five (5) of the Term of this Agreement.
3.6.2 Subsequent Development Approvals. This Agreement shall not prevent City, in acting on Subsequent Development Approvals, from applying Subsequent Land Use Regulations that do not conflict with the Development Plan, nor shall this Agreement prevent City from denying or conditionally approving any Subsequent Development Approval on the basis of the Existing Land Use Regulations or on the basis of any Subsequent Land Use Regulation which does not conflict with the Development Plan. Upon approval of any Subsequent Development Approval, such Subsequent Development Approval shall be deemed vested pursuant to the provisions of this Agreement, without any further action by City or Owner being required.
3.6.3 Modification or Suspension by State or Federal Law. In the event that State or Federal laws or regulations enacted after the Effective Date of this Agreement prevent or preclude compliance with one or more of the provisions of this Agreement, such provisions of this 123 372
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -12-
Agreement shall be modified or suspended as may be necessary to comply with such State or Federal laws or regulations; provided, however, that this Agreement shall remain in full force and effect to the extent it is not inconsistent with such laws or regulations and to the extent such laws or regulations do not render such remaining provisions impractical to enforce.
3.6.4 Intent. The parties acknowledge and agree that City is restricted in its authority to limit its police power by contract and that the foregoing limitations, reservations and exceptions are intended to reserve to City all of its police power which cannot be so limited.
3.7 Public Works. Owner shall construct all public improvements related to the Project in accordance with City's or other applicable public agency's then applicable public works engineering standards.
3.8 Provision of Real Property Interests by City. In any instance where Owner is required to construct any public improvement on land not owned by Owner, Owner shall at its sole cost and expense provide or cause to be provided, the real property interests necessary for the construction of such public improvements. In the event Owner is unable, after exercising reasonable efforts, including, but not limited to, the rights under Sections 1001 and 1002 of the Civil Code, to acquire the real property interests necessary for the construction of such public improvements, and if so instructed by Owner and upon Owner’s provision of adequate security for costs City may reasonably incur, City shall negotiate the purchase of the necessary real property interests to allow Owner to construct the public improvements as required by this Agreement and, if necessary, in accordance with the procedures established by law, use its power of eminent domain to acquire such required real property interests. Owner shall pay all costs associated with such acquisition or condemnation proceedings. This section 3.8 is not intended by the parties to impose upon the Owner an enforceable duty to acquire land or construct any public improvements on land not owned by Owner, except to the extent that the Owner elects to proceed with the development of the Project, and then only in accordance with valid conditions imposed by the City upon the development of the Project under the Subdivision Map Act or other legal authority.
3.9 Regulation by Other Public Agencies. It is acknowledged by the parties that other public agencies not within the control of City possess authority to regulate aspects of the development of the Property separately from or jointly with City and this Agreement does not limit the authority of such other public agencies.
3.10 Tentative Tract Map Extensions. Notwithstanding the provisions of Section 66452.6 of the Government Code, no tentative subdivision map or tentative parcel map, heretofore or hereafter approved in connection with development of the Property, shall be granted an extension of time except in accordance with the Existing Land Use Regulations.
3.11 Vesting Tentative Maps. If any tentative or final subdivision map, or tentative or final parcel map, heretofore or hereafter approved in connection with development of the Property, is a vesting map under the Subdivision Map Act (Government Code Section 66410 et seq.) and if this Agreement is determined by a final judgment to be invalid or unenforceable insofar as it grants a vested right to develop to Owner, then and to that extent the rights and protections afforded Owner under the laws and ordinances applicable to vesting maps shall supersede the provisions of this Agreement. Except as set forth immediately above, development of the Property shall occur 124 373
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -13-
only as provided in this Agreement, and the provisions in this Agreement shall be controlling over any conflicting provision of law or ordinance concerning vesting maps.
3.12 Utilities. The Project shall be connected to all utilities necessary to provide adequate water, sewer, gas, electric, and other utility service to the Project. Owner shall contract with the City for City-owned or operated utilities serving the Project for such prices and on such terms as may be mutually agreed to between the parties.
4. PUBLIC BENEFITS
4.1 Intent. The parties acknowledge and agree that the Development of the Property will result in substantial public needs which will not be fully met by the Development Plan and further acknowledge and agree that this Agreement confers substantial private benefits on Owner which should be balanced by commensurate public benefits. Accordingly, the parties intend to provide consideration to the public to balance the private benefits conferred on Owner by providing more fully for the satisfaction of the public needs resulting from the Project.
4.2 Development Impact Fees.
4.2.1 Amount and Components of Fee. The amount of the public facilities and services mitigation fees may be periodically adjusted by the City.
4.2.2 Time of Payment. The fees required pursuant to this section shall be paid to City prior to the issuance of building permits. No fees shall be payable for building permits issued prior to the Effective Date of this Agreement, but the fees required pursuant to Subsection 4.2.1 shall be paid prior to the re-issuance or extension of any building permit for which such fees have not previously been paid.
4.3 Public Benefit Fee.
4.3.1 As consideration for City's approval and performance of its obligations as set forth in this Agreement, Owner agrees to pay to the City a one-time public benefit fee in the amount of Four Dollars and Twenty five Cents ($4.25) per building square foot, which is estimated to be Two Million Eighty Four Thousand Nine Hundred One Dollars ($2,084,901) ("Public Benefit Fee"). Payment of the Public Benefit Fee shall be in addition to any other customary fees or charges to which the Project would otherwise be subject (e.g., development impact fees and application fees). The actual amount of the Public Benefit Fee shall be set, based upon the actual building square footage, prior to the issuance of any certificate of occupancy for the Project, and Owner shall pay the Public Benefit Fee to the City prior to the issuance of any certificate of occupancy for the Project.
4.3.2 The City has sole discretion to determine the uses for the Public Benefit Fee. The City has not designated a specific project or purpose for the Public Benefit Fee. Owner acknowledges by its approval and execution of this Agreement that it is voluntarily agreeing to pay the Public Benefit Fee, that its obligation to pay the Public Benefit Fee is an essential term of this Agreement, and that Owner expressly waives any constitutional, statutory, or common law right it might have in the absence of this Agreement to protest or challenge the payment of the Public Benefit Fee on any ground whatsoever, including without limitation pursuant to the Fifth 125 374
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -14-
and Fourteenth Amendments to the United States Constitution, California Constitution Article I Section 19, the Mitigation Fee Act (California Government Code Section 66000 et seq.), or otherwise.
4.3.3 Notwithstanding any provision herein to the contrary, the obligation of Owner to pay the Public Benefit Fee as set forth in Section 4.3.1 shall survive the termination of this Agreement until all buildings have been constructed on the Property pursuant to the Development Plan or otherwise. If the Public Benefit Fee has not been paid prior to the expiration of the Term, payment of the Public Benefit Fee shall be waived and shall no longer be due and payable if the City, after expiration of the Term, amends the Existing Land Use Regulations so that the Project, or other uses which previously were permitted under the Existing Land Use Regulations, no longer are legally permitted.
5. FINANCING OF PUBLIC IMPROVEMENTS.
If deemed appropriate, City and Owner will cooperate in the formation of any special assessment district, community facilities district or alternate financing mechanism to pay for the construction and/or maintenance and operation of public infrastructure facilities required as part of the Development Plan. City also agrees that, to the extent any such district or other financing entity is formed and sells bonds in order to finance such reimbursements, Owner may be reimbursed to the extent that Owner spends funds or dedicates land for the establishment of public facilities. Notwithstanding the foregoing, it is acknowledged and agreed by the parties that nothing contained in this Agreement shall be construed as requiring City or the City Council to form any such district or to issue and sell bonds.
6. REVIEW FOR COMPLIANCE
6.1 Periodic Review. As required by California Government Code Section 65865.1, the Director of Planning will review this Agreement annually, on or before each anniversary of the Effective Date, in order to ascertain the good faith compliance by Owner with the terms of the Agreement. Owner shall submit an Annual Monitoring Report, in a form acceptable to the Director of Planning, within 30 days after written notice from the Planning Director. The Annual Monitoring Report shall be accompanied by an annual review and administration fee sufficient to defray the estimated costs of review and administration of the Agreement during the succeeding year. The amount of the annual review and administration fee shall be set annually by resolution of the City Council.
6.2 Special Review. The City Council may order a special review of Owner's compliance with this Agreement at any time. The Director of Planning will conduct the special review.
6.2.1 During either an annual or special review. Owner will be required to demonstrate its good faith compliance with this Agreement. The burden of proof on this issue shall be on Owner.
6.2.2 Upon completion of an annual or special review, the Director of Planning will submit a report to the City Council setting forth the evidence concerning Owner's good faith compliance with this Agreement and his or her recommended finding on that issue. 126 375
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -15-
6.2.3 If the City Council finds on the basis of substantial evidence that Owner has materially complied in good faith with the terms and conditions of this Agreement, then the review will be concluded.
6.2.4 If the City Council makes a preliminary finding that Owner has not materially complied in good faith with this Agreement, then, following notice and opportunity to cure as provided under Section 6.4, the City Council may modify or terminate this Agreement as provide in Section 6.4 and 6.5. Notice of default as provided under Section 7.4 of this Agreement shall be given to Owner prior to or concurrent with, proceedings under Section 6.4 and Section 6.5.
7. PROCEEDINGS FOR MODIFICATION OR TERMINATION.
7.1 Proceedings Upon Modification or Termination. If, upon a finding under Section
6.2, City determines to proceed with modification or termination of this Agreement, City shall give written notice to Owner of its intention so to do. The notice shall be given at least ten calendar days prior to the scheduled hearing and shall contain:
7.1.1 The time and place of the hearing;
7.1.2 A statement as to whether or not City proposes to terminate or to modify the Agreement; and
7.1.3 Such other information as is reasonably necessary to inform Owner of the nature of the proceeding.
7.2 Hearing on Modification or Termination. At the time and place set for the hearing on modification or termination, Owner shall be given an opportunity to be heard. Owner shall be required to demonstrate good faith compliance with the terms and conditions of this Agreement. The burden of proof on this issue shall be on Owner. If the City Council finds, based upon substantial evidence, that Owner has not complied in good faith with the terms or conditions of the Agreement, the City Council may terminate this Agreement or modify this Agreement and impose such conditions as are reasonably necessary to protect the interests of the City. The decision of the City Council shall be final, subject only to judicial review pursuant to Section 1094.5 of the Code of Civil Procedure.
7.3 Certificate of Agreement Compliance. If, at the conclusion of a Periodic or Special Review, Owner is found to be in compliance with this Agreement, City shall, upon request by Owner, issue a Certificate of Agreement Compliance (“Certificate”) to Owner stating that after the most recent Periodic or Special Review and based upon the information known or made known to the Planning Director and City Council that (1) this Agreement remains in effect and (2) Owner is not in default. The Certificate shall be in recordable form, shall contain information necessary to communicate constructive record notice of the finding of compliance, shall state whether the Certificate is issued after a Periodic or Special Review and shall state the anticipated date of commencement of the next Periodic Review. Owner may record the Certificate with the County Recorder.
127 376
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -16-
Whether or not the Certificate is relied upon by assignees or other transferees or Owner, City shall not be bound by a Certificate if a default existed at the time of the Periodic or Special Review, but was concealed from or otherwise not known to the Planning Director or City Council.
8. DEFAULT AND REMEDIES
8.1 Remedies in General. The parties agree that the City would not have entered into this Agreement if it were to be liable for damages under this Agreement, or with respect to this Agreement or the application itself.
8.1.1 In general, and subject to those procedural prerequisites required under the Development Agreement Policies or this Agreement, each of the parties may pursue any remedy at law or equity available for the breach of this Agreement, except that CITY shall not be liable in damages to Owner, or to any successor in interest of Owner, or to any other person, and Owner covenants not to sue for damages or claim any damages:
(a) For any breach of this Agreement or for any cause of action that arises out of this Agreement; or
(b) For the taking, impairment, or restriction of any right or interest conveyed, provided under or arising under this Agreement; or (c) Arising out of or connected with any dispute, controversy or issue regarding the application or interpretation or effect of the provisions of this Agreement.
8.2 Specific Performance.
8.2.1 The parties acknowledge that money damages and remedies at law generally are inadequate and specific performance and other non-monetary relief are particularly appropriate remedies for the enforcement of this Agreement and should be available to all parties for the following reasons:
(a) Monetary damages are unavailable against City as provided in Section 8.1 above.
(b) Due to the size, nature and scope of the Project, it may not be practical or possible to restore the Property to its natural condition once implementation of this Agreement has begun. After such time, Owner may be precluded from other options it may have had with regard to the Property or any portions thereof. Moreover, Owner has invested significant time and resources in the planning and processing of the Project. Owner will be investing even more time and resources in implementing the Project in reliance upon this Agreement and it is not possible to determine the sum of money that would adequately compensate Owner for such efforts.
8.3 Release. Except for non-damage remedies, including the remedy of specific performance as provided in Section 8.2, Owner, for itself, its successors and assignees, releases City, its officials, officers, agents and employees from any and all claims, demands, actions, or suits of any kind or nature arising out of any liability, known or unknown, present or future, including, but not limited to, any claim or liability based upon Article I, Section 19 of the 128 377
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -17-
California Constitution, the Fifth Amendment of the United States Constitution, or any other law or ordinance that seeks to impose any other liability or damage, whatsoever upon City because it entered into this Agreement or because of the terms of this Agreement.
8.4 City's Termination of Agreement or Exercise of Other Remedies Upon Owner's Default. City may terminate or modify this Agreement as to all or a portion of the Property upon Owner's failure to perform any material duty or obligation under this Agreement, or to comply in good faith with the terms of this Agreement (hereinafter referred to as "default"); provided, however, City may modify or terminate this Agreement pursuant to this Section only after providing written notice to Owner of default setting forth the nature of the default and the actions, if any, required by Owner to cure such default and, where the default can be cured, if Owner fails to cure the default within sixty (60) days after its receipt of the notice, or if the default is of a type that cannot be cured within sixty (60) days but can be cured within a longer time, and Owner fails to commence the actions necessary to cure the default within sixty (60) days and to diligently proceed to cure the default.
8.5 Owner's Termination of Agreement or Exercise of Other Remedies Upon City's Default. Owner may terminate this Agreement only in the event of a default by City in the performance of a material term of this Agreement and only after providing written notice to City of default setting forth the nature of the default and the actions, if any, required by City to cure such default and, where the default can be cured, City has failed to take such actions and cure such default within 60 days after the effective date of such notice or, in the event that such default cannot be cured within such 60 day period but can be cured within a longer time, has failed to commence the actions necessary to cure such default within such 60 day period and to diligently proceed to complete such actions and cure such default.
8.6 Informal Resolution. The parties recognize that good faith disagreements may arise between City and Owner during the administration and implementation of this Agreement.
The parties will meet and confer in a good-faith attempt to resolve any dispute and will consider alternative dispute resolution mechanisms.
9. THIRD PARTY LITIGATION
9.1 General Plan Litigation. City has determined that this Agreement is consistent with its Comprehensive General Plan, herein called General Plan, and that the General Plan meets all requirements of law. Owner has reviewed the General Plan and concurs with City’s determination.
City shall have no liability in damages under this Agreement for any failure of City to perform under this Agreement or the inability of Owner to develop the Property as contemplated by the Development Plan of this Agreement as the result of a judicial determination that on the Effective Date, or at any time thereafter, the General Plan, or portions thereof, are invalid or inadequate or not in compliance with law.
9.2 Third-Party Litigation Concerning Agreement. Owner shall defend, at its expense, including attorneys’ fees, indemnify, and hold harmless City, its agents, officers and employees from any claim, action or proceeding against City, its agents, officers, or employees to 129 378
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -18-
attack, set aside, void, or annul the approval of this Agreement or the approval of any permit granted pursuant to this Agreement. City shall promptly notify Owner of any such claim, action or proceeding, and City shall cooperate in the defense. If City fails to promptly notify Owner of any such claim, action or proceeding, or if City fails to cooperate in the defense, Owner shall not thereafter be responsible to defend, indemnify, or hold harmless City. City may in its discretion participate in the defense of any such claim, action or proceeding. Anything in this Agreement to the contrary notwithstanding, the Term set forth in Section 4.3 of this Agreement and the expiration date of all Development Approvals will automatically be extended by the longer of (i) the number of days in the period commencing on the date of filing any legal action of the type described in this Section and ending on the date that the claim, action or proceeding is either settled or fully and finally resolved in City’s and Owner’s favor, as evidenced by the expiration of all appeal periods with no further appeal being filed or the issuance of a full, final and non-appealable judgment or decisions; or (ii) the number of days in the period commencing on the date that a referendum conceding the Development Approvals is timely qualified for the ballot and the date that a referendum is certified resulting in upholding and approving the Development Approvals.
City will execute, in recordable form, any instrument which Owner may reasonably require to evidence the extension.
9.3 Indemnity. In addition to the provisions of Section 9.2, Owner shall indemnify and hold City, its officers, agents, employees and independent contractors free and harmless from any liability whatsoever, based or asserted upon any act or omission of Owner, its officers, agents, employees, subcontractors and independent contractors, for property damage, bodily injury, or death (Owner's employees included) or any other element of damage of any kind or nature, relating to or in any way connected with or arising from the activities contemplated hereunder, including, but not limited to, the study, design, engineering, construction, completion, failure and conveyance of the public improvements, save and except claims and damages to the extent caused by the negligence or willful misconduct of City or its officers, agents, employees, contractors, subcontractors, and independent contractors. Owner shall defend, at its expense, including attorneys' fees, City, its officers, agents, employees and independent contractors in any legal action based upon such alleged acts or omissions. City may in its discretion participate in the defense of any such legal action.
9.4 Environmental Assurances. Owner shall indemnify and hold City, its officers, agents, and employees free and harmless from any liability, based or asserted, upon any act or omission of Owner, its officers, agents, employees, subcontractors, predecessors in interest, successors, assigns and independent contractors for any violation of any federal, state or local law, ordinance or regulation relating to industrial hygiene or to environmental conditions on, under or about the Property, including, but not limited to, soil and groundwater conditions, and Owner shall defend, at its expense, including attorneys' fees, City, its officers, agents and employees in any action based or asserted upon any such alleged act or omission. City may in its discretion participate in the defense of any such action.
9.5 Reservation of Rights. With respect to Sections 9.2, 9.3 and 9.4 herein, City reserves the right to either (1) approve the attorney(s) which Owner selects, hires or otherwise engages to defend City hereunder, which approval shall not be unreasonably withheld, or (2) conduct its own defense, provided, however, that Owner shall reimburse City upon written request for any and all reasonable expenses incurred for such defense, including attorneys' fees, 130 379
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -19-
upon billing and accounting therefor. If City chooses to conduct its own defense, City’s separate counsel’s billing rates shall be identical to the rates City pays for its typical municipal litigation rates for legal challenges for the type being defended.
10. MORTGAGEE PROTECTIONS
The parties hereto agree that this Agreement shall not prevent or limit Owner, in any manner, at Owner's sole discretion, from encumbering the Property or any portion thereof or any improvement thereon by any mortgage, deed of trust or other security device securing financing with respect to the Property. City acknowledges that the lenders providing such financing may require certain Agreement interpretations and modifications and agrees upon request, from time to time, to meet with Owner and representatives of such lenders to negotiate in good faith any such request for interpretation or modification. City will not unreasonably withhold its consent to any such requested interpretation or modification provided such interpretation or modification is consistent with the intent and purposes of this Agreement. Any Mortgagee of the Property shall be entitled to the following rights and privileges:
(a) Neither entering into this Agreement nor a breach of this Agreement shall defeat, render invalid, diminish, or impair the lien of any mortgage on the Property made in good faith and for value, unless otherwise required by law. (b) The Mortgagee of any mortgage or deed of trust encumbering the Property, or any part thereof, which Mortgagee, has submitted a request in writing to the City in the manner specified herein for giving notices, shall be entitled to receive written notification from City of any default by Owner in the performance of Owner's obligations under this Agreement. (c) If City timely receives a request from a Mortgagee requesting a copy of any notice of default given to Owner under the terms of this Agreement, City shall provide a copy of that notice to the Mortgagee within ten (10) days of sending the notice of default to Owner.
The Mortgagee shall have the right, but not the obligation, to cure the default during the remaining cure period allowed Owner under this Agreement.
(d) Any Mortgagee who comes into possession of the Property, or any part thereof, pursuant to foreclosure of the mortgage or deed of trust, or deed in lieu of such foreclosure, shall take the Property, or part thereof, subject to the terms of this Agreement.
Notwithstanding any other provision of this Agreement to the contrary, no Mortgagee shall have an obligation or duty under this Agreement to perform any of Owner's obligations or other affirmative covenants of Owner hereunder, or to guarantee such performance; provided, however, that to the extent that any covenant to be performed by Owner is a condition precedent to the performance of a covenant by City, the performance thereof shall continue to be a condition precedent to City' s performance hereunder, and further provided that any sale, transfer or assignment by any Mortgagee in possession shall be subject to the provisions of Section 2.4 of this Agreement.
11. MISCELLANEOUS PROVISIONS
11.1 Recordation of Agreement. This Agreement and any amendment or cancellation thereof shall be recorded with the County Recorder by the City Clerk within the period required 131 380
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -20-
by Section 65868.5 of the Government Code. Owner agrees that immediately following recordation of the grant deed by which the Owner acquires title, the Owner will immediately record this Development Agreement against the real property.
11.2 Entire Agreement. This Agreement sets forth and contains the entire understanding and agreement of the parties, and there are no oral or written representations, understandings or ancillary covenants, undertakings or agreements which are not contained or expressly referred to herein. No testimony or evidence of any such representations, understandings or covenants shall be admissible in any proceeding of any kind or nature to interpret or determine the terms or conditions of this Agreement.
11.3 Severability. If any term, provision, covenant or condition of this Agreement shall be determined invalid, void or unenforceable, the remainder of this Agreement shall not be affected thereby to the extent such remaining provisions are not rendered impractical to perform taking into consideration the purposes of this Agreement. Notwithstanding the foregoing, the provision of the public benefits set forth in Section 4 of this Agreement, including the payment of the fees set forth therein, are essential elements of this Agreement and City would not have entered into this Agreement but for such provisions, and therefore in the event such provisions are determined to be invalid, void or unenforceable, this entire Agreement shall be null and void and of no force and effect whatsoever.
11.4 Interpretation and Governing Law. This Agreement and any dispute arising hereunder shall be governed and interpreted in accordance with the laws of the State of California.
This Agreement shall be construed as a whole according to its fair language and common meaning to achieve the objectives and purposes of the parties hereto, and the rule of construction to the effect that ambiguities are to be resolved against the drafting party shall not be employed in interpreting this Agreement, all parties having been represented by counsel in the negotiation and preparation hereof.
11.5 Section Headings. All Section headings and subheadings are inserted for convenience only and shall not affect the construction or interpretation of this Agreement.
11.6 Singular and Plural. As used herein, the singular of any word includes the plural.
11.7 Joint and Several Obligations. If at any time during the term of this Agreement the Property is owned, in whole or in part, by more than one Owner, all obligations of such Owner under this Agreement shall be joint and several, and the default of any such Owner shall be the default of all such Owners. Notwithstanding the foregoing, no Owner of a single lot which has been finally subdivided and sold to such Owner as a member of the general public or otherwise as an ultimate user shall have any obligation under this Agreement except as provided under Section 4 hereof.
11.8 Time of Essence. Time is of the essence in the performance of the provisions of this Agreement as to which time is an element.
11.9 Waiver. Failure by a party to insist upon the strict performance of any of the provisions of this Agreement by the other party, or the failure by a party to exercise its rights upon 132 381
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -21-
the default of the other party, shall not constitute a waiver of such party's right to insist and demand strict compliance by the other party thereafter.
11.10 No Third Party Beneficiaries. This Agreement is made and entered into for the sole protection and benefit of the parties and their successors and assigns. No other person shall have any right of action based upon any provision of this Agreement.
11.11 Force Majeure. Neither party shall be deemed to be in default where failure or delay in performance of any of its obligations under this Agreement is caused by floods, earthquakes, epidemics, pandemics, other acts of God, fires, wars, riots or similar hostilities, strikes and other labor difficulties beyond the party's control, (including the party's employment force), government regulations, court actions (such as restraining orders or injunctions), or other causes beyond the party's control. If any such events shall occur, the Term of this Agreement and the time for performance by either party of any of its obligations hereunder will be extended for the period of time that such events prevented such performance, provided that the Term of this Agreement shall not be extended under any circumstances due to a force majeure event for more than five (5) years.
11.12 Mutual Covenants. The covenants contained herein are mutual covenants and also constitute conditions to the concurrent or subsequent performance by the party benefited thereby of the covenants to be performed hereunder by such benefited party.
11.13 Successors in Interest. Except as specifically set forth in this Agreement, the burdens of this Agreement shall be binding upon, and the benefits of this Agreement shall inure to, all successors in interest to the parties to this Agreement. All provisions of this Agreement shall be enforceable as equitable servitudes and constitute covenants running with the land. Each covenant to do or refrain from doing some act hereunder with regard to the Development of the Property: (a) is for the benefit of and is a burden upon every portion of the Property; (b) runs with the Property and each portion thereof; and, (c) is binding upon each party and each successor in interest during ownership of the Property or any portion thereof.
11.14 Counterparts. This Agreement may be executed by the parties in counterparts, which counterparts shall be construed together and have the same effect as if all of the parties had executed the same instrument.
11.15 Jurisdiction and Venue. Any action at law or in equity arising under this Agreement or brought by a party hereto for the purpose of enforcing, construing or determining the validity of any provision of this Agreement shall be filed and tried in the Superior Court of the County of San Bernardino, State of California, and the parties hereto waive all provisions of law providing for the filing, removal or change of venue to any other court.
11.16 Project as a Private Undertaking. It is specifically understood and agreed by and between the parties hereto that the development of the Project is a private development, that neither party is acting as the agent of the other in any respect hereunder, and that each party is an independent contracting entity with respect to the terms, covenants and conditions contained in this Agreement. No partnership, joint venture, or other association of any kind is formed by this 133 382
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -22-
Agreement. The only relationship between City and Owner is that of a government entity regulating the development of private property by the Owner of such property.
11.17 Further Actions and Instruments. Each of the parties shall cooperate with and provide reasonable assistance to the other to the extent contemplated hereunder in the performance of all obligations under this Agreement and the satisfaction of the conditions of this Agreement.
Upon the request of either party at any time, the other party shall promptly execute, with acknowledgment or affidavit if reasonably required, and file or record such required instruments and writings and take any actions as may be reasonably necessary under the terms of this Agreement to carry out the intent and to fulfill the provisions of this Agreement or to evidence or consummate the transactions contemplated by this Agreement.
11.18 Eminent Domain. No provision of this Agreement shall be construed to limit or restrict the exercise by City of its power of eminent domain.
11.19 Agent for Service of Process. In the event Owner is not a resident of the State of California or it is an association, partnership or joint venture without a member, partner or joint venturer resident of the State of California, or it is a foreign corporation, then in any such event, Owner shall file with the Planning Director, upon its execution of this Agreement, a designation of a natural person residing in the State of California, giving his or her name, residence and business addresses, as its agent for the purpose of service of process in any court action arising out of or based upon this Agreement, and the delivery to such agent of a copy of any process in any such action shall constitute valid service upon Owner. If for any reason service of such process upon such agent is not feasible, then in such event Owner may be personally served with such process out of this County and such service shall constitute valid service upon Owner. Owner is amenable to the process so served, submits to the jurisdiction of the Court so obtained and waives any and all objections and protests thereto. Owner for itself, assigns and successors hereby waives the provisions of the Hague Convention (Convention on the Service Abroad of Judicial and Extra Judicial Documents in Civil or Commercial Matters, 20 U.S.T. 361, T.I.A.S. No. 6638).
11.20 Authority to Execute. The person or persons executing this Agreement on behalf of Owner warrants and represents that he or she/they have the authority to execute this Agreement on behalf of his or her/their corporation, partnership, or business entity and warrants and represents that he or she/they has/have the authority to bind Owner to the performance of its obligations hereunder.
[Signatures on following pages]
134 383
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -23-
SIGNATURE PAGE TO
DEVELOPMENT AGREEMENT BETWEEN
THE CITY OF FONTANA
AND POPLAR SOUTH DC, LLC
City
CITY OF FONTANA,
a California municipal corporation
By:
Acquanetta Warren, Mayor
By:
Matthew Ballantyne, City Manager
LIT INDUSTRIAL LIMITED PARTNERSHIP,
a Delaware limited partnership
By: LIT Holdings, GP, LLC,
a Delaware limited liability company,
its general partner
By:
Name: Michael Marrone
Title: Senior Vice President
ATTEST:
By:
Germaine Key, City Clerk
APPROVED AS TO LEGAL FORM:
BEST BEST & KRIEGER LLP
Ruben Duran, City Attorney
135 384
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -24-
ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California )
County of ______________________ )
On _________________________, before me, ,
(insert name of notary)
Notary Public, personally appeared ,
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
136 385
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh -25-
ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
State of California )
County of ______________________ )
On _________________________, before me, ,
(insert name of notary)
Notary Public, personally appeared ,
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
137 386
Order Number: NCS-1099426-M-ONT1
Page Number: 14
First American Title Insurance Company
EXHIBIT A
TO DEVELOPMENT AGREEMENT BETWEEN
THE City OF FONTANA AND POPLAR SOUTH DC, LLC
Legal Description of the Property
Real property in the City of Fontana, County of San Bernardino, State of California, described as follows: TENTATIVE PARCEL MAP NO. 20638, BEING A DIVISION OF THE FOLLOWING:
TRACT 1: (APN 0237-171-04-0-000)
LOT 16, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 2: (APN 0237-171-03-0-000)
LOT 17 OF TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OFSAID COUNTY.
TRACT 3: (APN 0237-171-02-0-000)
LOT 18 OF TRACT NO. 3074 IN THE UNINCORPORATED AREA, COMMONLY KNOWN
AS FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE14 OF MISCELLANEOUS MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAN BERNARDINO COUNTY.
TRACT 4: (APN 0237-171-01-0-000)
LOT 19 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATEOF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 5: (APN 0237-171-05-0-000)
LOT 15, TRACT 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 6: (APN 0237-171-06-0-000)
138 387
Order Number: NCS-1099426-M-ONT1
Page Number: 15
First American Title Insurance Company
LOT 14 OF TRACT NO. 3074, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 7: (APN 0237-171-07-0-000)
LOT 13 OF TRACT 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA AS PER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAIDCOUNTY.
TRACT 8: (APN 0237-171-08-0-000)
LOT 12, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 9: (APN 0237-171-09-0-000)
139 388
Order Number: NCS-1099426-M-ONT1
Page Number: 16
First American Title Insurance Company
LOT 11 OF TRACT 3074, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICEOF THE SAN BERNARDINO COUNTY RECORDER.
TRACT 10: (APN 0237-171-10-0-000)
LOT 10, TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, RECORDS OF SAIDCOUNTY.
TRACT 11: (APN 0237-171-11-0-000)
LOT 9 OF TRACT 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, CALIFORNIA ASPER MAP RECORDED IN BOOK 43, PAGE(S) 14, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 12: (APN 0237-171-12-0-000)
LOT 8 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAN BERNARDINO COUNTY.
TRACT 13: (APN 0237-171-13-0-000)
LOT 7, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, OF
MISCELLANEOUS MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 14: (APN 0237-171-14-0-000)
LOT 6, TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 15: (APN 0237-171-15-0-000)
LOT 5, TRACT NO. 3074, AS PER PLAT RECORDED IN BOOK 43, OF MAPS PAGE 14, IN THE OFFICEOF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 16: (APN 0237-171-16-0-000)
LOT 4 OF TRACT 3074 AS SHOWN ON A MAP THEREOF RECORDED IN BOOK 43, PAGE(S) 44 OF MISCELLANEOUS MAPS IN THE OFFICE OF THE COUNTY RECORDER OF SAIDCOUNTY.
140 389
Order Number: NCS-1099426-M-ONT1
Page Number: 17
First American Title Insurance Company
TRACT 17: (APN 0237-171-17-0-000)
LOT 1, TRACT NO. 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PERPLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 18: (APN 0237-171-18-0-000)
LOT 2, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 19: (APN 0237-171-19-0-000)
LOT 3 OF TRACT 3074, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICEOF THE COUNTY RECORDER OF SAID COUNTY.
141 390
Order Number: NCS-1099426-M-ONT1
Page Number: 18
First American Title Insurance Company
TRACT 20: (APN 0237-172-05-0-000)
LOT 20 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 43, PAGE(S) 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 21: (APN 0237-172-04-0-000)
LOT 21 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATEOF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 22: (APN 0237-172-03-0-000)
LOT 22, TRACT 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE(S) 14, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OFSAID COUNTY.
TRACT 23: (APN 0237-172-02-0-000)
LOT 23, TRACT 3074, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLATRECORDED IN BOOK 43 OF MAPS, PAGE 14, RECORDS OF SAID COUNTY.
TRACT 24: (APN 0237-172-01-0-000)
LOT 24, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 25: (APNS 0237-172-06-0-000 AND0237-172-07-0-000) LOT 25 AND 26 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO,STATE OF CALIFORNIA, AS PER MAP, RECORDED IN BOOK 43, PAGE 14 OF MAPS IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 26: (APN 0237-172-08-0-000)
LOT 27, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
TRACT 27: (APN 0237-172-09-0-000)
142 391
Order Number: NCS-1099426-M-ONT1
Page Number: 19
First American Title Insurance Company
LOT 28, TRACT NO. 3074, AS PER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE 14, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 28: (APN 0237-172-10-0-000)
LOT 29 OF TRACT NO. 3074, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 43, PAGE 14 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 29: (APN 0237-172-11-0-000)
LOT 30, TRACT NUMBER 3074, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, ASPER PLAT RECORDED IN BOOK 43 OF MAPS, PAGE(S) 14, INCLUSIVE, RECORDS OF SAIDCOUNTY.
143 392
Order Number: NCS-1099426-M-ONT1
Page Number: 20
First American Title Insurance Company
TRACT 30: (APN 0237-172-12)
THE WEST 75 FEET OF THE SOUTH 340 FEET OF THE EAST ONE-HALF OF THE FARM LOT 863, ACCORDING TO THE MAP SHOWING SUBDIVISION OF LANDS
BELONGING TO THE SEMI-TROPIC LAND AND WATER COMPANY, IN THE COUNTY
OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 11 OF MAPS, PAGE 12, IN THE OFFICE OF COUNTY RECORDER OF SAIDCOUNTY.
TRACT 31: (APN 0237-172-32-0-000)
PARCEL NO. 1:
THE WEST 1/2 OF THE EAST 150 FEET OF THE WEST 225 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF LOT 863, ACCORDING TO MAP SHOWING SUBDIVISION
OF LAND BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
PARCEL NO. 2:
AN EASEMENT FOR INGRESS AND EGRESS OVER THE WESTERLY 10 FEET OF THE EAST 1/2 OF THE EAST 150 FEET OF THE WEST 225 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF LOT 863, ACCORDING TO MAP SHOWING
SUBDIVISION OF LAND BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
TRACT 32: (APN 0237-172-33-0-000)
THE EAST 75.00 FEET OF THE WEST 225 FEET OF THE SOUTH 340.00 FEET TO THE EAST HALF OFLOT 863, ACCORDING TO THE MAP SHOWING SUBDIVISION OF
LAND BELONGING TO SEMI TROPIC LAND AND WATER COMPANY, AS PER MAY RECORDED IN BOOK 11, PAGE 12, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
TRACT 33: (APN 0237-172-26-0-000)
THE EAST 75 FEET OF THE WEST 300 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF FARM LOT 863, ACCORDING TO MAP SHOWING SUBDIVISION OF LANDS
BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY, AS PER PLAT RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
AREA AND DISTANCES OF THE ABOVE DESCRIBED PROPERTY COMPUTED TO STREETCENTERS. TRACT 34: (APN 0237-172-27-0-000)
144 393
Order Number: NCS-1099426-M-ONT1
Page Number: 21
First American Title Insurance Company
THE EAST 75 FEET OF THE WEST 375 FEET OF THE SOUTH 340 FEET OF THE EAST 1/2 OF FARM LOT 863 ACCORDING TO MAP SHOWING SUBDIVISION OF LANDS
BELONGING TO SEMI-TROPIC LAND AND WATER COMPANY IN THE CITY OF
FONTANA, COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAIDCOUNTY.
TRACT 35: (APN 0237-172-19-0-000)
THE WEST 75 FEET OF THE EAST 285 FEET OF THE SOUTH 340 FEET OF THE FARM LOT 863, IN THE CITY OF FONTANA, COUNTY OF SAN BERNARDINO, STATE OF
CALIFORNIA, ACCORDING TO MAP SHOWING SUBDIVISION OF LAND
BELONGINGS TO SEMI-TROPIC LAND AND WATER COMPANY AS PER MAP RECORDED IN BOOK 11, PAGE 12 OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAID COUNTY.
145 394
Order Number: NCS-1099426-M-ONT1
Page Number: 22
First American Title Insurance Company
TRACT 36: (APN 0237-172-23-0-000)
THE SOUTH 340 FEET OF THE EAST 1/2 OF LOT 863, ACCORDING TO THE MAP
SHOWN IN SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC LAND AND
WATER COMPANY, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 11 PAGE12, OF MAPS, RECORDS OF SAID COUNTY.
EXCEPTING THEREFROM THE WEST 450 FEET THEREOF.
ALSO EXCEPTING THEREFROM THE SOUTH 260 FEET THEREOF.
AREA AND DISTANCES ARE COMPUTED TO STREET CENTERS AS
SHOWN ON SAID MAP. TRACT 37: (APN 0237-172-30-0-000)
PARCEL 1:
THE NORTH 65 FEET OF THE SOUTH 260 FEET OF THE EAST 1/2 OF FARM LOT 863,
ACCORDINGTO MAP SHOWING SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAIDCOUNTY.
EXCEPT THE WEST 450 FEET THEREOF.
AREAS AND DISTANCES COMPUTED TO STREET CENTERS AS SHOWN ON SAID MAP. PARCEL 2:
A RIGHT OF WAY FOR INGRESS AND EGRESS OVER AND ACROSS THE NORTH 6 FEET OF THE EAST125 FEET OF THE SOUTH 195 FEET OF SAID LOT 863.
TRACT 38: (APN 0237-172-31-0-000)
THE NORTH 65 FEET OF THE SOUTH 195 FEET OF THE EAST 1/2 OF FARM LOT 863,
ACCORDING TO MAP SHOWING SUBDIVISION OF LANDS BELONGING TO THE
SEMI-TROPIC LAND AND WATER COMPANY, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER MAP RECORDED IN BOOK 11, PAGE 12, OF MAPS, IN THE OFFICE OF THE COUNTY RECORDER OF SAIDCOUNTY.
EXCEPTING THEREFROM, THE WEST 450 FEET THEREOF.
AREAS AND DISTANCES COMPUTED TO STREET CENTERS AS SHOWN ON SAID MAP. TRACT 39: (APN 0237-172-28-0-000)
146 395
Order Number: NCS-1099426-M-ONT1
Page Number: 23
First American Title Insurance Company
THE SOUTH 65 FEET OF THE NORTH 195 FEET OF THE SOUTH 260 FEET OF THE EAST HALF OF FARM LOT 863, IN THE CITY OF FONTANA, COUNTY OF SAN
BERNARDINO, STATE OF CALIFORNIA, ACCORDING TO MAP SHOWING
SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC LAND AND WATER COMPANY, AS PER MAP RECORDED IN BOOK 11 OF MAPS, PAGE 12, RECORDS OF SAID COUNTY.
EXCEPTING THEREFROM THE WEST 150 FEET THEREOF, AREAS AND DISTANCES COMPUTEDTO STREET CENTERS.
TRACT 40: (APN 0237-172-22-0-000)
147 396
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh
EXHIBIT A
-1-
THE SOUTH 65 FEET OF THE EAST 1/2 OF FARM LOT 863, ACCORDING TO MAP
SHOWING SUBDIVISION OF LANDS BELONGING TO THE SEMI-TROPIC LAND AND
WATER COMPANY, IN THE COUNTY OF SAN BERNARDINO, STATE OF CALIFORNIA, AS PER PLAT RECORDED IN BOOK 11 OFMAPS, PAGE(S) 12, RECORDS OF SAID COUNTY.
EXCEPTING THEREFROM THE WEST 450 FEET THEREOF.
NOTE: AREA AND DISTANCES COMPUTED TO STREET CENTERS.
APN: 0237-171-01, 0-000, 0237-171-02-0-000, 0237-171-03-0-000, 0237-171-04-0-000, 0237-171-05-0-
000, 0237-171-06-0-000, 0237-171-07-0-000, 0237-171-08-0-000, 0237-171-09-0-000, 0237- 171-10-0-
000, 0237-171-11-0-000, 0237-171-12-0-000, 0237-171-13-0-000, 0237-171-14-0-000, 0237- 171-15-0-
000, 0237-171-16-0-000, 0237-171-17-0-000, 0237-171-18-0-000, 0237-171-19-0-000, 0237- 172-01-0-
000, 0237-172-02-0-000, 0237-172-03-0-000, 0237-172-04-0-000, 0237-172-05-0-000, 0237- 172-06-0-
000, 0237-172-07-0-000, 0237-172-08-0-000, 0237-172-09-0-000, 0237-172-10-0-000, 0237- 172-11-0-
000, 0237-172-12-0-000, 0237-172-19-0-000, 0237-172-22-0-000, 0237-172-23-0-000, 0237- 172-26-0-
000, 0237-172-27-0-000, 0237-172-28-0-000, 0237-172-30-0-000, 0237-172-31-0-000, 0237- 172-32-0-
000 and 0237-172-33-0-000 (Referenced for informational purposesonly) 148 397
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh
EXHIBIT B
-1-
EXHIBIT B
TO DEVELOPMENT AGREEMENT BETWEEN
THE City OF FONTANA AND POPLAR SOUTH DC, LLC
EXHIBIT B – Map Showing Property and its location:
149 398
4862
-4501-8737.9
377876.00016/10-11-23/jcc/dh
EXHIBIT B -2-
150 399
4862-4501-8737.9
377876.00016/10-11-23/jcc/dh
EXHIBIT C
-1-
EXHIBIT C
TO DEVELOPMENT AGREEMENT BETWEEN
THE City OF FONTANA AND POPLAR SOUTH DC, LLC
Existing Development Approval
151 400
EVCS
EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV EV
EV EV EV EV EVCS
EV EV EV EV
EV EV EVCS EVCS EVCS EVCS EVCS EVCS
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL
CARPOOL/
VANPOOL EV EV EVCS EVCS EVCS EVCS LOADING LOADING LOADING T
WB-67 - Interstate Semi-Trailer WB-67 - Interstate Semi-Trailer WB-67 - Interstate Semi-Trailer
WB-67 - Interstate Semi-Trailer
WB-67 - Interstate Semi-Trailer
RGA
Office of Architectural Design
15231 Alton Parkway, Suite 100
Irvine, CA 92618
T 949-341-0920
FX 949-341-0922
POPLAR SOUTH DISTRIBUTION CENTER
FONTANA, CA SHEET TITLE
MARK DATE DESCRIPTION
A1-1P
COPYRIGHT: RGA, OFFICE OF ARCHITECTURAL DESIGN
CHK'D BY:
DRAWN BY:
CAD FILE NAME:
RGA PROJECT NO:
CS
CS
22016-00-A1-01
22016.00
SCHEMATIC SITE PLAN
SCALE: 1" = 50'-0"
Scott Irwin
Senior Vice President – Southern California
SEEFRIED INDUSTRIAL PROPERTIES, INC.
2301 Rosecrans Avenue, Suite 3165
El Segundo, CA 90245
Office: +1 310 536 7900
Cell: +1 562 484 8761
[email protected]
5/20/22 PLANNING SUBMITTAL
50' MIN.
9/2/22 2ND PLANNING SUBMITTAL
9/21/23 PC HEARING SET C A T A W B A A V E .
TYPE III-B
DRY STORAGE WAREHOUSE
40' CLR.
MAX. HT.: 50'
P O P L A R A V E .
0' 10' 20' 50' 100'
30'
34'
30'
44'
81.5' 392'-0" 185'
1,196'-0"
GENERAL PROJECT INFO:
ZONE:
SPECIFIC PLAN:
APN:
SOUTHWEST INDUSTRIAL PARK
SLOVER EAST INDUSTRIAL DISTRICT
PROJECT DATA:
NET SITE AREA:
FOOTPRINT AREA:
MEZZANINE AREA:
TOTAL FLOOR AREA:
OFFICE AREA:
WAREHOUSE AREA:
TOTAL:
BASE ALLOWABLE F.A.R.:
** DEVELOPMENT INCENTIVE FOR LEED CERTIFICATION
PROPOSED F.A.R.
AUTO PARKING REQUIRED
10,000 SF OFFICE (1/250 SF)
0 SF MANUFACTURING (1/600 SF)
480,550 SF WAREHOUSE
1 TO 20,000 SF (1/1,000 SF)
20K TO 40,000 SF (1/2,000 SF)
> 40,0000 SF (1/5,000 SF)
TOTAL REQUIRED:
AUTO PARKING PROVIDED
TRAILER PARKING REQUIRED - 1/5,000 SF
LANDSCAPE:
REQUIRED: 818,382 - 483,500 X 15%
PROVIDED:
819,701 SF / 18.82 AC
480,550 SF
10,000 SF
490,550 SF
10,000 SF
480,550 SF
490,550 SF
0.55 0.6325
0.60 40 STSALLS
0 STALLS
20 STALLS
10 STALLS
88 STALLS
158 STALLS
210 STALLS
98 98
50,232 SF
62,000 SF
VICINITY MAP:
PROJECT DESCRIPTION:
ONE NEW 490,550 SF SPECULATIVE WAREHOUSE BUILDING INTENDED FOR
HIGH CUBE STORAGE, INCLUDING DOCK HIGH LOADING FACILITIES, TRAILER PARKING, 210 AUTO PARKING STALLS, AND LANDSCAPE IMPROVEMENTS.
THE PROJECT WILL BE PURSUING LEED CERTIFICATION, AND PROPOSES TO
UTILIZE THE AVAILABLE INTENSITY BONUS RELATED TO THE GREEN BUILDING INCENTIVE IN TABLE 10-10 OF THE S.W.I.P. SPECIFIC PLAN.
CODE ANALYSIS:
CONSTRUCTION TYPE:
OCCUPANCY:
FIRE SPRINKLERS:
BUILDING HEIGHT:
MAX. ALLOWABLE:
PROPOSED:
STORIES:
MAX. ALLOWABLE:
PROPOSED:
ALLOWABLE AREA
III-B
S-1 PRIMARY OCC.
B / F-1 ACCESSORY
FULLY SPRINKLERED
75'
50'
3 2
UNLIMITED PER CBC 507
21 DOCK POSITIONS
77 TRAILER STALLS
8'H GATE
OFFICE OFFICE RAMP
20' 20'
490,550 SF
8 TRAILER
STALLS
RAMP
202 AUTO STALLS
TRASH
ENCLOSURE
PER CITY STD.
FIRE PUMP
ROOM - SCREEN
W/ LANDSCAPE
942'-8" - 6'H RETAINING WALL + 8'H SCREENWALL
(11) BIKE
RACKS
SEATING
AREA
SANTA ANA AVE.
JURUPA AVE.
POPLAR AVE.
CATAWBA AVE.
CITRUS AVE.
SITE
7' 19' 30' 19' 6.5'
56'
146' 153'
56'
8 AUTOS
35'35'
RIDGELINE - 46'-7" RIDGELINE - 46'-7"
9' TYP.
8'H GATE
14'DEDICATION
SETBACK
SETBACK
SETBACK
SETBACK
RAD.: 50'
RAD.: 50'
RAD.: 50'
RAD.: 50'
RAD.: 25'
RAD.: 25'
RAD.: 25'
RAD.: 25'
1. ANY EXISTING STRUCTURES ONSITE ARE TO BE DEMOLISHED.
2. ALL PROPOSED NEW ONSITE UTILITY SERVICES SHALL BE UNDERGROUND.
3. CONCRETE BANDS, 24" IN WIDTH, SHALL BE PROVIDED AT LANDSCAPE FINGERS.
4. DRIVEWAYS SHALL BE CONSTRUCTED PER CITY STANDARD PLANS.
5. STATE OF CALIFORNIA "GENERAL CONSTRUCTION NPDES PERMITS AND WDID NUMBERS MUST BE OBTAINED PRIOR TO PERMIT.
6. PARKING STALL DIMENSIONS: 9'W X 19'D - DOUBLE STRIPED PER CITY REQUIREMENTS. CLEAN AIR / CARPOOL PARKING SHALL BE PROVIDED PER CALGREEN REQUIREMENTS.
7. FIRE DEPT. APPROVED KNOX LOCKS SHALL BE PROVIDED AT ALL GATES.
8. FIRE DEPT. ACCESS SHALL BE PROVIDED PER STANDARDS:
ACCESS LANE WIDTH: 30'-0"
ACCESS LANE HEIGHT: 14'-6"
INSIDE TURN RADIUS: 19'-0"
GENERAL NOTES:
12' TYP.
8 TRAILER
STALLS
55' 60' 70'
5 TRAILER
STALLS
21 DOCK POSITIONS
13' TYP.
6" X 6" CONC. CURB
3" WIDE WHITE
TRAFFIC PAINT
STRIPING
24" WIDE STEP-OFF
CURB AT
LANDSCAPE
FINGERS / END
STALLS
9'-0" 9'-0" 9'-0"
AUTO PARKING DETAIL:
STANDARD
STALL
END
STALL
19'-0"
24" TYP.
EA. SIDE
9' TYP. 7'
PARKING
FINGER
14'H SCREENWALL
14'H SCREENWALL
14'H SCREENWALL 14'H SCREENWALL
STRIPED MEDIAN
STRIPED MEDIAN
50'
680' - NEW CMU PROPERTY LINE RET. WALL
6' MAX. HEIGHT
30" MAX. HT.
SPLITFACE CMU
RETAINING WALL
30" MAX. HT.
SPLITFACE CMU
RETAINING WALL
(E) 6'-8'H SCREENWALL ON ADJ. PROPERTY TO REMAIN (E) 6'-8'H SCREENWALL ON ADJ. PROPERTY TO REMAIN (E) 6'-8'H SCREENWALL ON ADJ. PROPERTY TO REMAIN 152 401
TYP.
TYP.
SHEET TITLE
MARK DATE DESCRIPTION A3-1P
COPYRIGHT: RGA, OFFICE OF ARCHITECTURAL DESIGN
CHK'D BY:
DRAWN BY:
CAD FILE NAME:
RGA PROJECT NO:
CS
CS
22016-00-A3-1
22016.00
SCALE: 1" = 30'-0" 0' 10' 20' 50' 100'
RGA
Office of Architectural Design
15231 Alton Parkway, Suite 100
Irvine, CA 92618
T 949-341-0920
FX 949-341-0922
POPLAR SOUTH DISTRIBUTION CENTER
FONTANA, CA
SCHEMATIC ELEVATIONS
Scott Irwin
Senior Vice President – Southern California
SEEFRIED INDUSTRIAL PROPERTIES, INC.
2301 Rosecrans Avenue, Suite 3165
El Segundo, CA 90245
Office: +1 310 536 7900
Cell: +1 562 484 8761
[email protected]
P-1 SHERWIN WILLIAMS
SW 7005 - PURE WHITE
P-2 SHERWIN WILLIAMS
SW 7072 - ONLINE
P-3 SHERWIN WILLIAMS
SW 7073 - NETWORK GRAY
P-4 SHERWIN WILLIAMS
SW 7005 - SOFTWARE
P-5 CLARION RED
PANTONE 7626C
GL-1 SOLARBAN 60 (2) SOLARGRAY
+ CLEAR INSULATED
9/2/22 2ND PLANNING SUBMITTAL
11/16/22 3RD PLANNING SUBMITTAL
5/20/22 PLANNING SUBMITTAL
9/5/23 4TH PLANNING SUBMITTAL
9/21/23 PC HEARING SET
NORTH ELEVATION
EAST ELEVATION
WEST ELEVATION
SOUTH ELEVATION
51'-0"51'-0"
47'-0"
51'-0"
47'-0"
51'-0"
47'-0"
49'-0"
45'-0"
49'-0"
49'-0"
45'-0"
FINISH LEGEND
14'
14'
PAINTED DOCK
DOOR
8' HIGH BLACK TUBE
STEEL ROLLING GATE AT
TRUCK ENTRANCE
FORMLINER
VERTICAL BAND
14' PAINTED CONCRETE
TILT-UP SCREENWALL
CLERESTORY
WAREHOUSE
WINDOWS
FORMLINER
VERTICAL BAND
PRIMARY
ENTRANCE
PRIMARY
ENTRANCE
STEEL TRELLIS
OVER ENTRY
PAINTED GRADE
RAMP DOOR
8' HIGH BLACK TUBE
STEEL ROLLING GATE AT
TRUCK ENTRANCE
14' PAINTED CONCRETE
TILT-UP SCREENWALL
NOTES:
1. ALL ROOFTOP MECH. EQUIPMENT
SHALL BE SCREENED FROM VIEW.
14'H FIRE PUMP
BUILDING
4'
51'-0"
51'-0"
47'-0"
4'
4'
4'
4'4'4'
4'4'
51'-0"
4'
FIRE PUMP
ELEVATIONS
SOUTH EAST NORTH
SOUTH RETAINING WALL / SCREENWALL ELEVATION
8'
8'
153 402
Engineering, Inc. Civil Engineering/Land Surveying/Land Planning NOT FOR CONSTRUCTION · · ···· 154 403
10 DRC Engineering, Inc.
Civil Engineering/Land Surveying/Land Planning
155 404
NOTICE OF DETERMINATION
TO:_X_ County Clerk, County of FROM: City of Fontana
San Bernardino Planning Department
8353 Sierra Avenue
_X_ Office of Planning and Research Fontana, CA 92335
SUBJECT: Filing of Notice of Determination in Compliance with Section 21152 of the Public Resources Code.
Project Title: Master Case No. 22-079: General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Agreement (AGR) No. 22-003, Tentative Parcel Map (TPM No. 20638) No. 22-016, Design Review (DRP) No. 22-040.
State Clearinghouse Number: 2022090611
Name of Person or Agency carrying out project: Seefried Industrial Properties, INC, 2321 Rosecrans Ave, Suite No. 2220 El Segundo, CA 90245.
Project Location: The project site includes property located to the east side of Poplar Avenue, west of Catawba Avenue and on properties along Rose Avenue (APNs) 0237-171-01, -02, -03, - 04, -05, -06, -07, -08, -09, -10, -11, -12, -13, -14, -15, -6, -17, -18, -19, and 0237-172-01, -02, -03, -04, -05, -06, -07, -08, -09, -10, -11, -12, -19, -22, -23, -26, -27, -28, -30, -31, - 32, and 33.
Project Description: Master Case No. 22-079: General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Agreement (AGR) No. 22-003, Tentative Parcel Map (TPM No. 20638) No. 22-016, Design Review (DRP) No. 22-040, and Final Environmental Impact Report for the development of an industrial commerce building totaling approximately 490,565 square feet within a project site comprised of approximately 18.8 acres.
This is to certify that the City of Fontana approved the above described project on November 14, 2023 and made the following determinations:
1. The project __X__ will ___ will not have a significant effect on the environment.
2. An Environmental Impact Report (EIR) was prepared and fully analyzed the effects of the project. The EIR thoroughly analyzed and discussed all potential environmental impacts.
3. Mitigation measures X were ____ were not made a condition of the approval of the project.
4. A Statement of Overriding Considerations X_ was __ was not adopted for this project.
5. Findings X were ___ were not made pursuant to the provisions of CEQA.
6. The location and custodian of the documents which comprise the record of proceedings for the Addenda are specified as follows:
Custodian: City of Fontana, Planning Department
Location: 8353 Sierra Avenue, Fontana, CA 92335
____________________________
DiTanyon Johnson
Principal Planner
Date Received for Filing
ATTACHMENT NO. 8
156 405
NOTICE OF PUBLIC HEARING
SI DESEA INFORMACION EN ESPAÑOL REFERENTE A ESTA NOTIFICACION O PROYECTO, FAVOR DE COMUNICARSE AL (909) 350-6728.
In compliance with Section 202 of the Americans with Disabilities Act of 1990 (42 U.S.C. Sec. 12132) and the federal rules and regulations adopted in implementation thereof, the Agenda will be made available in appropriate alternative formats to persons with a disability. Should you need special assistance to participate in this meeting, please contact the City Clerk’s Department by calling (909) 350-7602. Notification 48 hours prior to the meeting will enable the City to make reasonable arrangements to ensure accessibility to this meeting.
A PUBLIC HEARING HAS BEEN SCHEDULED BEFORE THE PLANNING COMMISSION OF THE CITY OF FONTANA FOR THE FOLLOWING:
Master Case (MCN) No. 22-079, General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Tentative Parcel Map (TPM) No. 22-016, Development Agreement (AGR) No. 22-003 and Design Review (DRP) No. 22- 040: Request for development of an approximately 18.8‐acre property with an industrial commerce center building of approximately 490,565 square feet, consolidation of 41 parcels into 1 parcel, amendment of the General Plan land use designation from Residential Trucking (RT) to General Industrial (I‐G), and revision of the Southwest Industrial Park Specific Plan from Residential Trucking District (RTD) to Slover East Industrial District (SED). The industrial commerce center project also includes a screened dock area along the south side of the building, vehicular parking areas, drive aisles, and landscaping. The applicant has also prepared a development agreement.
Environmental
Determination:
This project has been
determined to have a potentially
significant effect on the
environment and a Draft
Environmental Impact Report
(EIR) (SCH No. 2022090611)
has been prepared pursuant to
Sections 15080 and 15097 of the
California Environmental Quality
Act (CEQA).
Location of
Property:
The Project Site is located to
the north and south sides of
Rose Avenue between Poplar
Avenue and Catawba Avenue
Date of
Hearing:
October 17, 2023
Place of
Hearing:
City Hall Council
Chambers
8353 Sierra Avenue
Fontana, CA 92335
Time of
Hearing: 6:00 P.M.
ATTACHMENT NO. 9
Rose Avenue
Santa Ana Avenue
Poplar Avenue
Catawba Avenue
Project Area
157 406
The City of Fontana (City) has prepared an Environmental Impact Report (EIR) for the proposed project. The Draft and Final EIR are available for review at City Hall (8353 Sierra Avenue Fontana, CA 92335) and online at https://www.fontanaca.gov/2137/Environmental-Documents. Should you have any questions concerning this project, please contact Alejandro Rico, Associate Planner at (909) 350-6558 or [email protected].
ANY INTERESTED PARTY MAY PROVIDE INFORMATION BY LETTER OR EMAIL WHICH MAY BE OF ASSISTANCE TO THE PLANNING COMMISSION. A COPY OF THE APPLICATION AND ENVIRONMENTAL DOCUMENTATION IS AVAILABLE FOR INSPECTION. PLEASE CONTACT THE PLANNER LISTED ABOVE.
IF YOU CHALLENGE IN COURT ANY ACTION TAKEN CONCERNING A PUBLIC HEARING ITEM, YOU MAY
BE LIMITED TO RAISING ONLY THOSE ISSUES YOU OR SOMEONE ELSE RAISED AT THE PUBLIC
HEARING DESCRIBED IN THIS NOTICE, OR IN WRITTEN CORRESPONDENCE TO THE CITY AT, OR PRIOR TO, THE PUBLIC HEARING.
Publish: October 6, 2023
158 407
Draft Planning Commission Minutes of October 17, 2023 hearing - item PH-B ATTACHMENT NO. 17
PH-B Master Case No. 22-079: General Plan Amendment (GPA) No. 22-007, Specific Plan Amendment (SPA) No. 22-003, Development Agreement (AGR) No. 22-003, Tentative Parcel Map (TPM No. 20638) No. 22-016, Design Review (DRP) No. 22-040, and Final Environmental Impact Report for the development of an industrial commerce building totaling approximately 490,565 square feet within a project site comprised of approximately 18.8 acres.
Vice Chair Sanchez opened Public Hearing.
Alejandro Rico, Associate Planner, presented the staff report and mentioned that staff provided the Commission a separate memo indicating the modification of the project’s development agreement.
The commission requested staff to clarify the project’s zoning designation and the assigned zoning on the property above the project along Santa Ana Avenue.
The commission and staff also discussed the queuing of the project and the Sustainability Ordinance.
The applicant, Dan Bick, on behalf of Seefried Industrial Properties, Inc., stated that he read and agreed to the Conditions of Approval and thanked the Planning Commission for the opportunity to work and operate within the city and gave a brief description of the proposed project.
Commissioner Sangha complimented the project’s nighttime renderings.
Planning Attorney, Steven Deithsch addressed the applicant and asked to confirm his understanding of the alteration of the Draft Development Agreement.
The following individuals spoke in favor:
Anthony Bolano
Zach Strasters
David Mitchel
Jr. Ortiz
The following individuals spoke in opposition:
Amy Smith
The Public Hearing was closed.
RECOMMENDATION:
Based on the information contained in this staff report, staff recommends that the Planning Commission adopt Resolution No. PC 2023-037, and forward a 408
Planning Commission Draft Minutes October 17, 2023