Final Touch Construction & Design16466 Foothill Blvd Fontana, CA 92335(909) 350-3658
CHANGE ORDER
City of Fontana JobsJob #223020 - Fontana Theatre (Stage RED Interior)8463 Sierra AveFontana, CA 92335 Invoice # 222159
Date 6/10/2024
Amount Due$325,000.00
Due Date Due on Receipt
Item Description Qty Price Amount
Change Order Change Order List: 1.00 $0.00 $0.00
Change Order Change Order #1:
Compressor Rental:A high-capacity air compressor is required topower pneumatic tools and equipment on-site.The rental includes delivery, setup, andoperational support for the duration of the project.
Breaker Hammer:A hydraulic breaker hammer will be rented fordemolition and concrete breaking tasks.The equipment will be compatible with the skidsteer and other machinery on-site.
Skid Steer:A skid steer loader is essential for materialhandling, excavation, and other constructionactivities.The rental includes various attachments such as abucket, forks, and the breaker hammer adapter.
Additional Equipment:Additional tools and machinery as required,including but not limited to compactors, trenchers,and loaders.Safety equipment and accessories to ensurecompliance with project safety standards.
1.00 $9,000.00$9,000.00
Item Description Qty Price Amount
Change Order Change Order #2: Temporary Carpet Purchase:
A high-quality temporary carpet has been selectedto meet the specific requirements of a dance floor.This includes durability to withstand heavy foottraffic, non-slip backing for safety, and ease ofmaintenance.The carpet color and texture have been chosen tocomplement the event decor and ensure anaesthetically pleasing appearance.
Installation of Temporary Carpet Roll:The installation will be carried out by a team ofexperienced professionals who specialize in eventflooring.The installation process will include precisemeasurements, cutting, and secure placement ofthe carpet to ensure it fits perfectly within thedesignated dance floor area.Special attention will be given to the edges andseams to prevent any tripping hazards and tomaintain the carpet's integrity throughout theevent.
1.00 $5,325.15$5,325.15
Change Order Change Oder #3:Service Bar 118Supply and installation of cabinets, includingupper and lower units, as per city request.Cabinets constructed from [solid wood], featuring[Red accents], and will include hardware such ashandles, hinges, and drawer slides.The scope includes all necessary preparations,site measurements, and adjustments for plumbingand electrical fixtures.Countertop Installation:
Supply and installation of countertops, selectedfrom quartz, including necessary edge profilesand finishes.Countertops will be measured and templated on-site to ensure a precise fit.
Additional Work:Necessary modifications to electrical systems toaccommodate the new installations.Final finishing touches, including caulking,sealing, and ensuring all installed items are leveland secure.
1.00 $8,267.25$8,267.25
Item Description Qty Price Amount
Change Order Change Oder #4: Identification of AbandonedElectrical Boxes:
Conduct a thorough inspection to identify allelectrical boxes that have been abandoned andare no longer in use.
Removal of Electrical Boxes:Safely disconnect and remove the wiring from theabandoned electrical boxes.Carefully remove the electrical boxes from thefloors.
Infilling and Patching:Infilling the openings left by the removed electricalboxes using appropriate materials to match thesurrounding surfaces.For masonry or concrete surfaces, use suitablefiller material to ensure a durable and consistentfinish.
Finishing Work:Sand the patched areas to create a smooth, evensurface. Infill void with spray foam and use6000PSI concrete.Patched areas to match the floor finishes.
1.00 $1,965.50$1,965.50
Change Order Change Oder #4: Step modification for soundbooth. Adjust step landing on concrete to agradual slope.Saw cut walk way and jack hammer concrete.Initial step location was changed after if had beeninstalled per plan due to potential tripping hazard.Adding aux light for step. (Light provided byowner)
1.00 $5,772.00$5,772.00
Change Order Change Oder #5: HSS 4x4 Support Columns:
Supply and installation of HSS 4x4 steel columnsto provide structural support within the booth wall.Columns will be installed at specified locations toenhance the load-bearing capacity and stability ofthe wall.
All-Thread Rods:Supply and installation of all-thread rods toreinforce the wall structure between existing wallstuds.Rods will be placed horizontally as required toensure optimal structural integrity and loaddistribution.
Integration with Existing Structure:Careful removal and replacement of wallcoverings as necessary to install the HSScolumns and all-thread rods.Ensuring that the installation does not interferewith existing electrical utilities within the wall.
Finishing Work:Reinstalling wall coverings and ensuring allsurfaces are finished to match the existing wallappearance.Applying any necessary touch-up work, includingpainting or sealing, to achieve a seamless finish.
1.00 $4,115.00 $4,115.00
Item Description Qty Price Amount
Change Order Change Oder #6: Soffit Construction:
Wood Framing: Installation of wood framing tocreate the soffit structure. This includesmeasuring, cutting, and securing the framingmembers to the existing structure.Fasteners: Use of appropriate fasteners to ensurethe stability and integrity of the wood framing.
Drywall Installation: Attachment of drywall to thewood framing, creating a smooth surface for thesoffit.Mud and Tape: Application of joint compound(mud) and tape to the drywall seams, ensuring aseamless finish.
Painting: Painting the soffit to match the existingdecor, ensuring a consistent and professionalappearance.
Modifications to Uni-Strut System: Adjustments tothe uni-strut system on the upstairs balconies toaccommodate the new soffit structure. Thisincludes any necessary reconfiguration orreinforcement to ensure compatibility and stability.
Scissor Lift Rental: Rental of a scissor lift to safelyaccess the balcony area and perform the soffitinstallation and uni-strut modifications. Thisincludes delivery, setup, and rental fees for theduration of the work.
1.00 $6,185.50$6,185.50
Item Description Qty Price Amount
Change Order Change Order #7:
Removal of Temporary Framing: Carefully removeany temporary framing or supports installed duringthe creation of the door opening.
Reinstallation of Structural Framing: Install newlumber to restore the structural integrity of theshear wall. This includes studs, and anynecessary blocking to match the original wallconstruction.
Drywall Installation:Drywall Placement: Install drywall to cover therestored framing. This includes cutting, fitting, andsecuring the drywall panels to the new framing.
Seam Treatment: Apply joint compound (mud)and tape to all seams and joints to create asmooth surface.
Patching and Finishing:Surface Patching: Ensure all patched areas aresmooth and flush with the surrounding wallsurface.Sanding: Sand the patched areas to ensure aseamless finish.
Painting:Primer Application: Apply a primer coat to thepatched areas to prepare for final painting.Final Paint: Paint the restored wall area to matchthe existing wall color and finish, ensuring aconsistent appearance.
Rationale:The deletion of the door scope and the restorationof the shear wall are necessary to comply with thecity's request and to maintain the structuralintegrity and design of the building.Restoring the wall to its original condition ensuressafety and adherence to building codes.
1.00 $3,645.00$3,645.00
Item Description Qty Price Amount
Change Order Change Order #8: Construction of ElectricalRoom:
Framing: Install wood framing to create the newwalls for the electrical room within VIP 210. Thisincludes constructing studs, headers, and anynecessary supports.
Lumber and Materials: Supply and useappropriate lumber and materials for the framingand structural integrity of the room.
Drywall Placement: Attach drywall to the newframing to enclose the electrical room. Thisincludes measuring, cutting, and securing thedrywall panels.Mud and Tape: Apply joint compound (mud) andtape to all seams and joints to create a smoothsurface.
Painting:Primer and Paint: Apply primer and paint to thenew walls to match the existing decor and ensurea professional finish.
Metal Door Installation:Supply and Install Metal Door: Provide and installa secure metal door for the electrical room,including the door frame, hardware, and lockset.
Relocation of Light Fixture and HVAC Thermostat:Light Fixture: Relocate the existing light fixture toan appropriate location outside the electrical roomas needed.HVAC Thermostat: Relocate the HVAC thermostatto a suitable location to ensure proper climatecontrol and functionality.
Adjustments to Exhaust and Return Systems:Exhaust System: Relocate & modify the existingexhaust system to ensure proper ventilation forthe new electrical room.Return System: Relocation & adjustment theHVAC return system to maintain balanced airflowand environmental control.
1.00 $16,150.00$16,150.00
Item Description Qty Price Amount
Change Order Change Order #9: Framing Installation:
Furring Strips: Install furring strips on the flatagainst the existing concrete walls. This involvesmeasuring, cutting, and securing the strips toprovide a surface for drywall attachment.Shot Pins: Use shot pins to securely attach thefurring strips to the concrete wall, ensuring astable and durable installation.
Drywall Panels: Attach drywall panels to theinstalled furring strips, creating a smooth andeven surface. This includes cutting and fitting thedrywall to cover the entire wall area up to andthrough the underside of the roof.Joint Compound and Tape: Apply joint compound(mud) and tape to all seams and joints, ensuring aseamless and professional finish.
Finishing:Sanding: Sand the mudded areas to create asmooth and even surface ready for painting orother finishing treatments.Apply primer and paint to the finished drywall tomatch the existing decor and ensure a consistentappearance.
Rationale:Furring up the existing concrete walls asrequested by the city improves the aesthetic andfunctional qualities of the stage area, providing asuitable surface for finishes and ensuringcompliance with building standards.The use of shot pins ensures a secure attachmentof the furring strips to the concrete wall,maintaining the integrity of the installation.
1.00 $11,660.00$11,660.00
Item Description Qty Price Amount
Change Order Change Order #10: Lowering 1/4" U Plate: Modifythe existing 1/4" U plates by lowering them toensure the floor joists can sit directly on theglulam beams. This involves precise cutting,aligning, and securing of the plates to achieve thedesired configuration.Glulam Beam Integration: Ensure the floor joistsare properly seated on the glulam beams toenhance the structural support system. Thisincludes adjusting the positioning of the joists andverifying the load distribution.
General Admission Area 111:Modify the balcony framing as specified, ensuringthat all structural changes comply with thedetailed references and structural engineeringrequirements.Conduct necessary reinforcements andadjustments to the framing to accommodate themodified U plate and glulam beam setup.
VIP Right 211 and VIP Left 212:Apply similar structural modifications to the VIPsections, ensuring that the U plates and floorjoists are correctly positioned on the glulambeams.Verify the stability and integrity of themodifications through appropriate inspections andtesting.
Detail References 212 & 208/210:Follow the detailed references and structuralengineering drawings (212 & 208/210) to ensureall modifications meet the specified requirementsand standards.
1.00 $6,245.51$6,245.51
Change Order Change Order #11: Cold Water ConnectionInstallation:
Plumbing: Install new plumbing lines to provide acold water connection for the coffee makingstation. This includes piping, fittings, and anynecessary connections.Connection Point: Determine the optimal locationfor the water connection, ensuring convenientaccess for the coffee making equipment.
Sheer Wall Patching:Patch Preparation: Prepare the sheer wall area forpatching, including cleaning and smoothing anyrough or damaged surfaces.Patch Installation: Install patches to cover anyopenings or penetrations created during theinstallation of the plumbing lines. Use appropriatematerials to ensure a secure and watertight seal.
Door Panel Installation: Install a door panel tocover the opening and provide access to thecoffee making station. Ensure the panel isproperly aligned, secure, and functional.
Rebuttal:The addition of a cold water connection isessential to support the operation of the coffeemaking station, providing convenience andfunctionality for users.Sheer wall patching and door panel installationare necessary to maintain the integrity andaesthetics of the surrounding areas following theinstallation of the plumbing lines.
1.00 $6,789.00$6,789.00
Item Description Qty Price Amount
Change Order Change Order #12: Stage Nose Modification:
City's Request: Modify the stage nose inaccordance with the city's requirements. This mayinvolve adjustments to the shape, size, orstructure of the nose to ensure compliance withregulations.
Void Identification: Identify any voids or gaps inthe floor level of the stage area that requiresealing.Sealing Material: Use appropriate sealing materialto fill and seal the voids, ensuring a smooth andlevel surface across the stage floor.Painting: Paint the sealed areas to match thesurrounding floor finish, providing a seamlessappearance.
Nose Surface Repair:Surface Assessment: Assess the condition of thestage nose surface to identify any areas requiringrepair.Repair Work: Perform necessary repairs, such asfilling cracks, smoothing rough patches, orreplacing damaged sections, to restore thesurface to a safe and functional condition.Finishing: Apply finishing treatments, such assanding and painting, to ensure a uniform andprofessional appearance.Surface repair of the stage nose is essential tomaintain its structural integrity and aestheticappeal, enhancing the overall appearance of thestage.
1.00 $3,846.00$3,846.00
Change Order Change Order #13: Reframing:
Identify and assess the extent of reframingrequired for both low walls.Supply and install new framing members asnecessary to ensure structural integrity andsupport for the walls.Includes materials and labor for reframing work.
Hanging of Walls:Hang the low walls in the designated locations,ensuring proper alignment and stability.Securely attach the walls to the framing andexisting structure.Includes materials and labor for hanging the walls.
Finishing:Apply drywall to the framed walls, covering theentire surface area.Use joint compound (mud) and tape to seal andsmooth the seams and joints.Sand the dried mud to create a smooth anduniform surface.Apply primer and paint to finish the walls to thedesired color and finish.Includes materials and labor for finishing work.
1.00 $4,135.00$4,135.00
Item Description Qty Price Amount
Change Order Change Order #14: Design and Fabrication:
Collaborate with City to create a custom railingthat complements the existing decor andarchitectural features of the bar area.Fabricate the railing using high-quality materialssuch as stainless steel, wrought iron, oraluminum, depending on the desired aestheticand durability.
Installation:Measure and assess the installation area toensure precise fitting and alignment of the customrail.Securely install the railing to the designatedlocation adjacent to bar 117, ensuring stability andstructural integrity.
Finishing:Apply a protective finish to the railing to enhanceits resistance to corrosion, wear, and weathering.Added decorative elements or custom finishes tofurther enhance the visual appeal of the railing.
1.00 $1,450.00$1,450.00
Change Order Change Order #15:Assessment and Design:
Assess the current height and structure of thepony wall to determine the required modifications.Collaborate with city of Fontana official to create acustom handrail that meets safety regulations andenhances visibility without compromisingstructural integrity.
Modification of Pony Wall:Cut down the existing pony wall to the specifiedheight to accommodate the installation of thecustom handrail.Ensure precise cutting and alignment to achieve aseamless integration with the handrail.
Installation of Custom Handrail:Install the custom handrail securely to themodified pony wall, ensuring stability and support.Use high-quality materials and fasteners to ensuredurability and compliance with safety standards.
Finishing:Apply a protective finish to the handrail toenhance its resistance to weathering andcorrosion.Added decorative elements or custom finishes tocomplement the aesthetic of the deck area.
1.00 $9,635.00$9,635.00
Item Description Qty Price Amount
Change Order Change Order #16: Installation of AdditionalCircuits:
Coordinate with electrical engineers to design andplan the layout of the additional circuits, ensuringcompliance with safety codes and regulations.Install 9x20A circuits for the sound booth andstage area, providing sufficient power capacity tomeet the electrical demands of equipment andlighting.
Relocation of Circuits:Identify the existing circuits slated for relocationbased on project requirements and siteconditions.Safely disconnect and relocate the identifiedcircuits to their new designated locations,ensuring minimal disruption to existing electricalsystems.
Wiring and Connection:Run wiring for the new circuits from the mainelectrical panel to the sound booth and stagearea, following approved routing paths.Connect the wiring to appropriate outlets,switches, and distribution panels, ensuring propergrounding and insulation.
Testing and Inspection:Conduct thorough testing of all newly installedcircuits and relocated circuits to verify properfunctionality and safety.
1.00 $4,767.00$4,767.00
Change Order Change Order #17:
Assess the existing HVAC return cover grill andproposed BQ-4 specifications to determine therequired modifications.
Modification of Return Cover Grill:Modify the existing return cover grill to create asuitable opening or mounting mechanism for theinstallation of the cover.Ensure precise cutting and fitting of the grill toaccommodate the dimensions and mountingrequirements of BQ-4 sitting area.
Modified HVAC return cover grill, ensuring properalignment and connection to the HVAC system.
Finishing:Apply finishing treatments to the modified returncover grill to ensure a seamless appearance withthe surrounding HVAC components.Ensure that the modification does not compromisethe structural integrity or safety of the return covergrill.
1.00 $7,845.71$7,845.71
Item Description Qty Price Amount
Change Order Change Order #18: Preparation of subfloor,ensuring it is clean, dry, and level.Apply primer or underlayment if necessary toensure a smooth surface for LVT installation.
Installation:Measure and cut the LVT planks to fit thedimensions of BQ-2, BQ-3, and BQ-4.Install the LVT planks, ensuring proper alignmentand spacing.Use adhesive or interlocking mechanisms as perthe LVT specifications for a secure fit.
Finishing:Trim and finish the edges of the LVT flooring,ensuring a neat and professional appearance.Apply any necessary sealants or protectivecoatings to enhance durability and longevity.
1.00 $5,016.00$5,016.00
Change Order Change Order #19: Preparation existing surfacesin the front lobby/vestibule area to determine theextent of preparation required.Clean, and prime the surfaces to ensure a smoothand even base for the new paint.Protect surrounding areas with drop cloths andmasking tape to prevent paint splatters andensure clean edges.
Repainting Vestibule Pattern:Assess the existing pattern in the vestibule todetermine the level of detail and color scheme.Repaint the vestibule pattern using high-qualitypaints, ensuring consistency with the originaldesign or updated specifications.Apply multiple coats as needed to achieve thedesired finish and durability.
Finishing:Inspect the painted areas for any imperfectionsand perform touch-ups as required.Remove protective coverings and clean up thework area, ensuring no paint residues or debrisare left behind.Review the completed work with the client toensure satisfaction with the final results.
1.00 $4,675.00$4,675.00
Item Description Qty Price Amount
Change Order Change Order #20: Assess the specificrequirements for the temporary chair platform,including size, height, and load capacity.Create detailed design plans that meet safetystandards and ensure structural stability.
Materials Procurement:Source high-quality materials required for theplatform construction, including lumber, fasteners,and non-slip surfaces.
Construction:Construct the platform frame using sturdy lumber,ensuring a secure and stable foundation.Install platform decking, ensuring a level andsmooth surface for chairs.Add any necessary reinforcements to meet safetyand load-bearing requirements.
Finishing:Apply a non-slip finish to the platform surface toensure safety.Optionally, paint or stain the platform to match theexisting decor of the VIP areas.
Installation and Setup:Transport the constructed platforms to VIP Left212 and VIP Right 211.Securely install the platforms in the designatedlocations, ensuring stability and safety.Arrange seating on the platforms as specified.
Removal:Once the temporary use period is over,disassemble the platforms.Remove all materials and restore the VIP areas totheir original condition.
1.00 $9,715.00$9,715.00
Change Order Change Order #21: Overtime for Contract Work:
All contracted trades will work extended hours,including nights and weekends, to meet theaccelerated schedule.
Additional Supervision:Due to the increased number of trades workingsimultaneously (trade stacking), additionalsupervisors and project managers will be requiredon-site to ensure coordination and safety.Calculate the cost of additional supervisory staff,including project managers and safety officers.
Expedited Material Costs:Materials required for the project will be orderedon an expedited basis to meet the acceleratedtimeline.Include the additional costs for faster shipping andhandling, as well as any premium prices formaterials due to rushed orders.
1.00 $88,573.00$88,573.00
Item Description Qty Price Amount
Change Order Change Order #22: Scope of Work:
Design and Planning:
Collaborate with the client to determine the designspecifications for the custom iron rail, includingstyle, dimensions, and finishes.
Materials Procurement:Source high-quality iron and other necessarymaterials for the rail fabrication.Ensure that materials meet safety standards anddesign requirements.
Fabrication:Fabricate the custom iron rail according to theapproved design, ensuring precision inmeasurements and craftsmanship.Incorporate any specified design elements, suchas decorative patterns or custom finishes.Finishing:
Apply protective coatings to the iron rail to preventcorrosion and enhance durability.Optionally, apply paint or other finishes asspecified by the client.
Installation:Transport the fabricated iron rail to the installationsite.Securely install the rail on the balcony wall,ensuring proper alignment and stability.Verify that the installation meets all safetystandards and client specifications.
1.00 $22,872.00$22,872.00
Change Order Change Order #23: Assess the area around thesound booth to determine the optimal size andconfiguration for the dust-free zone.Design the dust-free enclosure, including barriers,air filtration systems, and access points.
Materials Procurement:PVC tubing, including plastic sheeting, frames,and sealing materials.Acquire air filtration systems, to maintain airquality within the enclosure.
Fabrication and Installation:Construct and install the barriers around thesound booth, ensuring a secure and sealedenclosure.Install air filtration systems to continuously removedust particles from the air within the enclosure.Ensure all seams and joints are properly sealed toprevent dust ingress.
Management and Maintenance:Monitor the dust-free area regularly to ensure theintegrity of the enclosure and the effectiveness ofthe air filtration system.
1.00 $2,625.00$2,625.00
Item Description Qty Price Amount
Change Order Change Order #24: Assess the surfaces to bepainted and identify any repairs or preparationsneeded.Clean and sand the surfaces to ensure properpaint adhesion.Fill any cracks or holes and prime the surfaces asneeded.Protect adjacent areas with drop cloths andmasking tape to prevent paint splatters.
Painting:Dance Floor: Apply a durable, non-slip paintsuitable for high-traffic areas. Ensure evenapplication and proper drying time between coats.Stage: Use high-quality paint to withstand heavyuse and lighting conditions. Ensure a smoothfinish.Back Wall: Apply paint that complements theoverall design and lighting of the space. Userollers and brushes for an even finish.Doors: Paint the doors with a durable, easy-to-clean paint. Ensure a smooth and professionalfinish.Office: Use interior paint that matches the officedecor. Ensure a professional and clean finish.
Finishing:Inspect all painted surfaces for any imperfectionsand perform touch-ups as needed.Remove protective coverings and clean up thework area, ensuring no paint residues or debrisare left behind.
1.00 $9,382.00$9,382.00
Change Order Change Order #25: (Damage created by formercontractor)Inspect the damaged areas to determine theextent of repairs needed.Clean and sand the affected surfaces to removeany debris, old paint, or damage.Fill any cracks, holes, or imperfections caused bythe damage.Apply primer to the repaired areas to ensureproper paint adhesion.
Affected Areas: Repaint the damaged areas usinghigh-quality paint that matches the existing colorand finish.Apply multiple coats as necessary to achieve asmooth and uniform finish.Ensure proper drying time between coats toprevent any further damage.
Finishing:Inspect the repainted areas for any imperfectionsand perform touch-ups as needed.Remove protective coverings and clean up thework area, ensuring no paint residues or debrisare left behind.
1.00 $4,267.00$4,267.00
Item Description Qty Price Amount
Change Order Change Order #26:
Coordination with interior designer of installationplan and obtain client approval.
Materials Procurement:Acquire any additional supplies needed forinstallation, such as adhesives, mountinghardware, and fasteners.
Installation:Prepare the surfaces where the acoustic materialwill be installed, ensuring they are clean and freeof debris.Install the acoustic material according to theapproved plan, ensuring proper placement andalignment.Secure the material using appropriate mountingtechniques to ensure durability and effectiveness.
Finishing:Inspect the installed acoustic material to ensure itmeets quality standards and performanceexpectations.Perform any necessary touch-ups or adjustments.Clean up the work area, removing any debris orwaste materials.
1.00 $6,337.00$6,337.00
Change Order Change Order #27: Acquire any additional materials or hardwareneeded for installation, such as hooks, screws, ormounting brackets.
Installation of Wall Art:Prepare the walls where the art will be installed,ensuring they are clean and free of debris.Install the wall art according to the approved plan,ensuring proper placement and alignment.Use appropriate mounting techniques to securethe art safely and securely.
Loading Furnishings:Load furnishings such as chairs, tables, cabinets,and decorative items in the designated areas.Ensure proper spacing and alignment to create acohesive and visually appealing environment.
Finishing:Inspect the installed wall art and loadedfurnishings to ensure they meet quality standardsand client expectations.Perform any necessary adjustments or touch-ups.Clean up the work area, removing any debris orwaste materials.
1.00 $1,750.00$1,750.00
Change Order Change Order #28: Rental Extension:Contacted the equipment rental provider toarrange for the extension of the rental period forscissor lifts and any other necessary equipment.Negotiate rental rates and terms for the extendedduration, ensuring cost-effectiveness andavailability.
Equipment Delivery and Pickup:Coordinate with the rental provider to schedulethe delivery of the equipment for the extendedperiod.Arrange for timely pickup of the equipment at theend of the extended rental period to avoidadditional charges.
1.00 $3,500.00$3,500.00
Item Description Qty Price Amount
Change Order Change Order #29: Determine the dimensions and specifications ofthe modesty panel based on the workspaceconfiguration and design requirements.
Materials Procurement:Acquire any additional materials or hardwareneeded for installation, such as mountingbrackets, screws, or adhesive.
Installation:Prepare the workstations or designated areas forinstallation, ensuring they are clean and free ofdebris.Mount the modesty panels according to theapproved installation plan, ensuring properalignment and stability.Use appropriate mounting techniques to securethe panels safely and securely to the work surfaceor support structure.
Finishing:Inspect the installed modesty panels to ensurethey meet quality standards and clientexpectations.Perform any necessary adjustments or touch-upsto ensure a professional and finished appearance.Clean up the work area, removing any debris orwaste materials.
1.00 $3,505.00$3,505.00
Change Order Change Order #30: Select an appropriate doorstyle, size, and material based on the design andfunctional requirements of the space.Door to have matching laminate and gold trim tomatch adjacent finishes Materials Procurement:Source a high-quality door that meets thespecified dimensions, style, and materialrequirements.Acquire any additional materials needed forinstallation, such as door frame components,hinges, handles, and locks.
Installation:Prepare the doorway for installation, ensuring theopening is properly framed and aligned.Install the door frame and hinges per city'srequest.Mount the door onto the frame and secure it inplace, ensuring smooth operation and properclearance.Install hardware such as handles, locks, and doorclosers as needed for functionality and security.
Finishing:Inspect the installed door to ensure it meetsquality standards and operates smoothly.
1.00 $1,446.00$1,446.00
Print: ___________________________________________ Sign: ____________________________________________ Date: ___________________
SPECIAL INSTRUCTIONS
Item Description Qty Price Amount
Change Order Change Order #31:Review the remaining tasks and deliverables toensure they are completed according to projectrequirements and timelines.
Issue Resolution:Identify and address any issues or concerns thatarise during the final weeks of the project.Implement corrective actions as needed to resolveissues and prevent delays or disruptions.
Stakeholder Coordination:Coordinate final inspections, approvals, and sign-offs to facilitate project closeout.
Documentation and Closeout:Ensure all project documentation, includingcontracts, permits, and warranties, is finalized andproperly archived.
1.00 $44,538.38$44,538.38
Sub Total $325,000.00
Total $325,000.00
Amount Paid $0.00
Balance Due $325,000.00