TASK
NO. DESCRIPTION

PRINCIPAL IN CHARGE
Matt Brudin
(President)

PROJECT MANAGER
Lori Askew
(Principal Engr.)

PROJECT ENGINEER
Ben Booth,P.E.
(Engineer V)

PROJECT DESIGNER
Katherine Hernandez
(Engineer III)

PROJECT DESIGNER
(Engineer I)
Principal Surveyor
Erik Howard, PE, PLS
Sr. Principal Engineer
SURVEY
Senior Engineering
Associate
SURVEY
2-Man Crew
Sub-consultant
SURVEY
Inland Aerial
$220 $185 $140 $110 $82 $190 $149 $276
1 Project Management, Meetings 2 24 8 8 42 6,880.00$
2 Survey/Base Mapping 1 2 8 8 60 110 18,600$ 189 60,481.00$ 3 As-built Research 2 2 6 4 14 1,638.00$
4 Utility Research 1 4 8 13 1,236.00$
5 Site Review 4 8 8 20 2,740.00$
6 Street Improvements Plans 4 16 24 80 240 364 35,680.00$ 7 Specifications & Cost Estimates 4 16 24 44 5,620.00$
8 Bidding Assistance/Construction Support 1 8 4 13 1,745.00$ 9 Record Drawings 1 2 4 4 8 19 2,246.00$
7 54 71 140 268 8 60 110 718 99,666.00$
1,540$ 9,990$ 9,940$ 15,400$ 21,976$ 1,520$ 8,940$ 30,360$ 18,600$ 118,266.00$

REIMBURSABLES
i Mileage 200.00$
ii Reimbursables, Reproduction, etc. 100.00$
SUBTOTAL 300.00$
PROJECT TOTAL- Not to Exceed Amount 118,566.00$
Estimated Total Labor Costs
City of Fontana - Pavement Rehabilitation & Street Improvement Project Estimated Labor Hours

ESTIMATED TOTAL HOURS

ESTIMATED TOTAL COST