Resolution no. 2025-022
Resolution OF THE CITY OF FONTANA, CALIFONRIA, Adopting a list of projects for Fiscal Year 2025-26 Funded by SB 1: The Road Repair and Accountability Act of 2017.

WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewide; and WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of the City of Fontana are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and WHEREAS, the City of Fontana must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and WHEREAS, the City of Fontana, will receive an estimated $5,620,523.00 in RMRA funding in Fiscal Year 2025-26 from SB 1; and WHEREAS, this is the ninth year in which the City of Fontana is receiving SB 1 funding and will enable the City of Fontana to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and WHEREAS, the City of Fontana has undergone a robust public process to ensure public input into our community’s transportation priorities/the project list; and WHEREAS, the City of Fontana used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the communities priorities for transportation investment; and Whereas, the funding from SB 1 will help the City of Fontana maintain and rehabilitate up to 58 lane miles of streets/roads, and all of the required ADA curb ramp, curb and gutter, and striping upgrades throughout the City of Fontana this year and many more of similar projects into the future; and WHEREAS, the Final Report August 2021 California Statewide Local Streets and Roads Needs Assessment found that the City of Fontana streets and roads are “estimated” to be in “good” condition, and this revenue will help us maintain or increase the overall quality of our road system and over the next decade will keep our streets and roads in an “estimated good” condition, or bring our streets and roads into a “excellent” condition; and WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide.

NOW, THEREFORE BE IT RESOLVED by the City Council of the City of Fontana, California, as follows:

Section 1. Recitals. The foregoing recitals are true and correct.

Section 2. The following list of newly proposed projects will be funded in-part or solely with Fiscal Year 2025-26 Road Maintenance and Rehabilitation Account revenues:

Project Title: Southridge Grid 52 Collector Streets Pavement Rehabilitation Project Description: 2” mill & overlay and/or slurry seal Project to include all pre-construction and construction costs, which include design, survey, Geotech, mill and overlay, pavement repairs, crack sealing, slurry seal, ADA ramp upgrades, curb and gutter, cross gutters, loops, striping, and testing, but may include additional work.

Project Location: Various collector streets south of Jurupa Avenue, including, but not limited to, Beech Avenue, Citrus Avenue, Poplar, Avenue, and Village Drive Estimated Pre-Construction Schedule: Start (07/25) – Completion (01/26) Estimated Construction Schedule: Start (02/26) – Completion (10/26) based on the component being funded with RMRA funds Estimated Project Useful Life: 7 to 15 years
Project Title: Village of Heritage Yosemite Loop Pavement Rehabilitation (Phase 1) Project Description: 2” mill & overlay, full depth removal and replacement, and/or slurry seal Project to include all pre-construction and construction costs, which include design, survey, Geotech, mill and overlay, full depth removal and replacement, pavement repairs, crack sealing, slurry seal, ADA ramp upgrades, curb and gutter, cross gutters, loops, striping, and testing, but may include additional work.

Project Location: Various residential and collector streets around the Yosemite Loop Road, in between Baseline Avenue and Foothill Boulevard & between West Liberty Parkway and Grand Avenue Estimated Pre-Construction Schedule: Start (07/25) – Completion (01/26) Estimated Construction Schedule: Start (02/26) – Completion (10/26) based on the component being funded with RMRA funds Estimated Project Useful Life: 7 to 15 years
Project Title: Grid 48 Residential Pavement Rehabilitation Project Description: 2” mill & overlay and/or slurry seal Project to include all pre-construction and construction costs, which include design, survey, Geotech, mill and overlay, pavement repairs, crack sealing, slurry seal, ADA ramp upgrades, curb and gutter, cross gutters, loops, striping, and testing, but may include additional work.

Project Location: Various residential and collector streets between Santa Ana Avenue and Jurupa Avenue & between Sierra Avenue and Tamarind Avenue Estimated Pre-Construction Schedule: Start (07/25) – Completion (01/26) Estimated Construction Schedule: Start (02/26) – Completion (10/26) based on the component being funded with RMRA funds Estimated Project Useful Life: 7 to 15 years
Project Title: Hunter’s Ridge/Coyote Canyon – South Pavement Rehabilitation Project Description: 2” mill & overlay and/or slurry seal Project to include all pre-construction and construction costs, which include design, survey, Geotech, grind and overlay, pavement repairs, crack sealing, slurry seal, ADA ramp upgrades, curb and gutter, cross gutters, loops, striping, and testing, but may include additional work.

Project Location: Various residential streets south of the Edison right of way and Beech Avenue & between the City line and Coyote Canyon Road Estimated Pre-Construction Schedule: Start (07/25) – Completion (01/26) Estimated Construction Schedule: Start (02/26) – Completion (10/26) based on the component being funded with RMRA funds Estimated Project Useful Life: 7 to 15 years
Project Title: Grid 26 Residential and Collector Street Pavement Rehabilitation Project Description: 2” mill & overlay, full depth removal and replacement, and slurry seal Project to include all pre-construction and construction costs, which include design, survey, Geotech, grind and overlay, full depth removal and replacement, pavement repairs, crack sealing, slurry seal, ADA ramp upgrades, curb and gutter, cross gutters, loops, striping, and testing, but may include additional work.

Project Location: Various residential and collector streets between Foothill Boulevard and Arrow Boulevard & between the City line and Citrus Avenue Estimated Pre-Construction Schedule: Start (07/25) – Completion (01/26) Estimated Construction Schedule: Start (02/26) – Completion (10/26) based on the component being funded with RMRA funds Estimated Project Useful Life: 7 to 15 years
Project Title: Citywide Slurry Seal Pavement Maintenance Project Description: Slurry seal
Project to include all pre-construction and construction costs, which include design, survey, Geotech, pavement repairs, crack sealing, slurry seal, striping, and testing, but may include additional work.

Project Location: Various locations throughout the City Estimated Pre-Construction Schedule: Start (07/25) – Completion (01/26) Estimated Construction Schedule: Start (02/26) – Completion (10/26) based on the component being funded with RMRA funds Estimated Project Useful Life: 5 to 7 years
APPROVED AND ADOPTED this 13th day of May, 2025.

READ AND APPROVED AS TO LEGAL FORM:
________________________________
City Attorney
I, Germaine Key, City Clerk of the City of Fontana, and Ex-Officio Clerk of the City Council, do hereby certify that the foregoing Resolution is the actual Resolution duly and regularly adopted by the City Council at a regular meeting held on the 13th day of May, 2025, by the following vote to-wit:

AYES:

NOES:

ABSENT:

ABSTAIN:

City Clerk of the City of Fontana
Mayor of the City of Fontana
ATTEST:

City Clerk
2 of 2
2 of 5
Resolution No. 2025-022

← All documents from this meeting