Project: Change Proposal No: 002 R1
Bid No:
Contractor: Western State Builders
2141 Orange Ave. Date: 7/24/2025
Escondido, CA 92029
To: Due Date:
Attachments:
Net Amount of This Proposed Change (Add) DEDUCT (NO CHANGE) * $147,153.37 Net Change in Working Days Due to the Proposed Change (ADD) DEDUCT (NO CHANGE) 13 *Attach Detailed Cost Breakdown
Contractor:
By: Date 7/24/2025
Architect's Review Owner's Review
Recommend Acceptance Accept
Do Not Recommend Acceptance Do Not Accept
No Recommendation - Price Marginal
Other:
By: By:
Date: Date:
Combination of Cor 2: Demolition and removal of 1 shade structure and footings $19,680.37 And COR 3: Installation of Concrete 3200SF $127,473.00
Total combine amount $147,153.37
Change Order Proposal Request
(TO BE COMPLETED BY CONTRACTOR)
(NOT A CHANGE ORDER)
DESCRIPTION OF THE PROPOSED CHANGE:
North Tamarind Park
Project: North Tamarind Park
Date: 7/24/2025
Contractor: Western State Builders
Date Rate Hours Ext. Costs
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Unit $/Unit Qty Ext. Costs
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0% $0.00
$0.00
Costs
$19,680.37
$127,473.00
$147,153.37
0% $0.00
$147,153.37
$147,153.37
Bond Cost 0.0% $0.00
$147,153.37
Change Order Proposal Request - Cost Breakdown
Labor (General Contractor Self-Performed) - attach labor rate sheets Material & Equipment (General Contractor Self-Performed) - attach invoices Subcontractor/Supplier Cost Summary - attach supporting proposals/invoices Labor Subtotal
Material & Equipment Subtotal
Subtotal Contractor (Self-Performed) Costs:
Overhead/Profit on Direct Costs:
Request for Change Order Total Cost:
Sub / Supplier Subtotal
Subcontractor / Supplier Costs:
General Contractor Total Costs & Total Subcontractor/Supplier Costs Item Description
COR concrete and flatwork Installation 1
General Contractor Total Costs:
General Contractor O/P on Sub/Supplier Costs:
Trade Description
Unit
1 CORs
COR 2 Demolition