Duncan Canyon & Citrus Avenue Traffic Signal Improvements Total Change Order Construction Contingency
(10%)
Excess of Contingency
(10%)
Engineering,
Surveying
City Inspection,
Permit Fees SCE Fees Bonds (2%) Administrative
Overhead (15%)
1,167,381.00 - 848,303.00 84,830.00 - 72,700.00 - 2,914.00 18,663.00 139,970.00 - 55,463.94 - 29,366.06 - - - - - - - - 848,303.00 - - 72,700.00 - 2,914.00 18,663.00 139,970.00 - 33,267.20 - - - - - - - - - - 848,303.00 - 3,901.14 72,700.00 - 2,914.00 18,663.00 139,970.00 1,167,381.00 - - - 3,901.14 - - - - - Original Reimbursable Contract…...............................................................................
Change Order No. 01…...............................................................................
Change Order No. 01 Cost After Contingency Applied…...............................................................................
Change Order No. 02…...............................................................................
Change Order No. 02 Cost After Contingency Applied…...............................................................................
Updated Reimbursable Contract (if Approved)…...............................................................................
CHANGE ORDER NO. 2
EXHIBIT C
Improvement:
Hard Costs Soft Costs
MUROW | 16800 Aston St. Suite 200, Irvine, CA 92606
Change Order Form for Construction Contracts Under a Reimbursement Agreement.
PART I.
Project: Change Order Date: 10/06/25
Agreement Type: Agreement Date: 04/14/25
Discrete Component:
Developer:
Telephone: Telephone:
PART II.
Unit
Measure Cash --
1. 2.0 EA 16,633.60 33,267.20 33,267.20 - TOTAL: 33,267.20 33,267.20 -
PART III.
Acknowledge by:
Acknowledge by:
Acknowledge by:
Date
Contractor (Belco) Date
Agency (City of Fontana) Date
Remove & Replace Curb Ramp
Developer (The Previti Group)
Description of Work: GT General Inc. has provided a Change Order Request to remove and replace the curb ramps for the Duncan Canyon & Citrus Avenue Traffic Signal.
GT General's proposal includes total costs of $33,267.20. This additional work is the result of the revised drawings approved by the City of Fontana for the northeast and southeast corner curb ramps. GT General's scope includes removing and replacing the curb ramps and constructing new curb ramps per the City of Fontana's Standard 1003.
GT General to call for City Inspector at least 24 hours in advance to monitor all work associated with Change Order. GT General will provide material receipts, equipment charges, and timesheets on a daily basis to the City Inspector.
Breakdown of Change Order:
Item Description Qty Unit Cost Total Eligible for Reimbursement Chino, CA 91710 Ontario, CA 91764
909.993.5470 909.354.8000
Plan Revision Required:
Field Change Required:
Traffic Signal
Contractor: Elecnor Belco Electric, Inc. The Previti Group 14320 Albers Way 2151 E. Convention Center Way, Ste. 114 CHANGE ORDER NO. 2
Jurisdiction:City of Fontana
Duncan Canyon & Citrus Avenue Improvements
Cash
Yes
Yes
No
No
MUROW | 16800 Aston St. Suite 200, Irvine, CA 92606
1912 Elise Circle., Corona, Ca 92879
25-079A Date:
Customer: Project Name:
Address: 2151 E. Convention Center Way, Suite 114
City: Ontario, CA 91764 Project address:
Attn: [email protected] City: Fontana, CA
Scope of Work: Provide and place, labor and material to complete the following:
Item No. Bid Qty U/M Unit Price Item Total
PREVAILING WAGE
01-01 2.00 EA 16,633.60$ 33,267.20$
33,267.20
Proposal:
Item Description
9/10/2025
The Previti Group
Thank you for the opportunity to bid on this project. GT General proposes to perform the following scope of work based on quantities Scale measured on FOUSCO Engineering NOT Dated.
Remove & Replace Curb Ramp Per City Of Fontana
Standard 1003.
Duncan Canyon South - Subgrade Grading.
Duncan Caanyon Rd & Citrus Ave.
(951) 545-5402 [email protected] Or (951) 768-2035 [email protected] 1912 Elise Circle., Corona, Ca 92879 | Lic. #1105565 | DIR# 1001051342
1912 Elise Circle., Corona, Ca 92879
GENERAL CONDITIONS
1. Job is bid Prevailing wage for labor, ready mix company, & other suppliers.
2. Job is Based on Grade Ready.
3. 4. Work to be done during normal business hours Monday-Friday 7 am – 3:30 pm
5. 6.
7. Bonding is NOT included.
8. Prices are good through 08/30/25 and subject to change after expiration date due material costs.
9. 10.
11. 12. Traffic Control NOT included In any item Unless Otherwise Noted or Priced.
13. Price Excludes Trench Plates, Light towers, CMS Boards, and Traffic Control Plan.
14. All Dirt spoils will be hauled and left onsite. Processing and moister by others.
15. All Landscape Irrigation will be Lowered, Moved, Cut, Capped And restored By others.
16. 17.
CONCRETE CONDITIONS
1. 2.
3. 4.
5. 6.
7. Adjusting and supplying of utility box’s, water valves, man holes, etc. in PCC is not included.
8. 9. Backfilling and grading after concrete to be done by others.
10. CONDITIONS
Cost to apply water is included, water to be supplied by others.
Contract must include all items listed on proposal. If individual line items are wanted and others not wanted, pricing may be subject to change.
Quantities used are approximate and subject to physical measurement on site. Corrections, if necessary, will be made using the unit price.
This proposal includes all labor and material to complete as listed above. This proposal excludes plans, permits & Deputy inspector.
GT General Bills on a Net 30 Basis Unless Noted Different in Contract. A 1.5% Fee Will Be added per Month to any Late Progress Payment and/or Invoice.
Job is base on THREE (3) mobilization. (1) Demo, (2) Concrete, (1) Asphalt Slot Patch. Additional move’s will be $2,500 each.
Grade will be compacted to a relative 95% compaction only if existing soil conditions are feasible. Any deemed wet/saturated areas determined by inspector/testing areas will be stabilized by others or on T&M.
Surveyor to set line and grade stakes and locations for curb and gutter, ramps and driveways, limits, etc.
Surveyor provided by others.
Excludes any landscape and irrigation repair, underground utility repair, caulking, joint seal, weed kill, concrete additives, reinforcing steel UNO, AC slot patch and repairs UNO.
GT will not and cannot be held responsible for scheduling conflicts and/or as a result of material and trucking shortages, and/or as a result of raw material unavailability, including but not limited to the unavailability of power.
GT General is not responsible for Damage to underground utilities not shown on blue prints, details, not marked on or off site, not buried at appropriate depths or found to be buried in or directly beneath the concrete or asphalt being removed. GT will not be responisble damages or repairs to confliting utilities.
Following Equipment and Services Includes: Tailgate Pour [Yes], Trailer Pump [No], Boom Pump [No], Roller Screed [No], Pressure Washing Pre Or Post [No],
Concrete & Finishes: 3250 Max PSI [Yes], Accelerators [No], High Early [No], Natrual Grey [Yes], Color [No].
Broom Finish [Yes], Exposed Aggregate [No], Stamped [No], Textured [No], Sawcut [No].
All concrete work is to have access to be provided and maintained by Contractor.
Concrete washout and washout haul off done by others.
Storm drain structures, catch basin, local depressions, etc. to be done by others. (951) 545-5402 [email protected] Or (951) 768-2035 [email protected] 1912 Elise Circle., Corona, Ca 92879 | Lic. #1105565 | DIR# 1001051342
1912 Elise Circle., Corona, Ca 92879
11. 12.
PAVING CONDITIONS
1. 2.
3. 4.
5. 6.
7. 8.
9. 10.
11. 12.
13. 14.
15 Due to the Volatility of asphalted oil from asphalt concrete suppliers, the asphalt concrete used in this bid is subject to price adjustments, every 30 days, adjusted for the current price of a barrel of oil.
Asphalt is to be installed in ONE (1) course.
Adjusting and supplying of utility box’s, water valves, man holes, etc. in AC is not included.
Tack is to be applied on vertical edges only.
Reflective cracking or water drainage problems from any new asphalt patching overlays due to preexisting pavement conditions, including but not limited to poor or unstable base conditions improper grades, or underlying water problem, etc.
GT General not responsible for Damage to cars, concrete, shoes, clothes, carports, or any other items as a result of getting onto the asphalt prematurely.
GT General cannot be held liable for unforeseeable conditions and additional labor, material, equipment, disposal charges, etc. will be applied if, and not limited to: Asphalt fabric of any kind is found in the existing asphalt during the grinding or demolition of said pavement. When removing and replacing existing asphalt it is discovered that thickness is more than stated in the body of the contract. Standing time or work delays that are incurred, which will be billed as an additional cost to the customer as per the crew onsite.Striping is not Included in Asphalt Item.
Notification and/or posting of signs in preparation for street work to be done by others.
GT General is not responsible Pavement sinking or settling resulting from failure or settling of sub-grade from water erosion, improper compaction or other causes beyond control of scope of work.
GT General is not liable for Drainage of existing and/or designed pavement or existing with fall of less than 2% and less than 1% of fall for concrete.
Grade will be compacted to a relative 95% compaction only if existing soil conditions are feasible. Any deemed wet/saturated areas determined by inspector/testing areas will be stabilized by others or on T&M.
GT General is not responsible for Damage to underground utilities not shown on blue prints, details, not marked on job site, not buried at appropriate depths or found to be buried in or directly beneath the concrete or asphalt being removed.
Excludes any Landscape and Irrigation Repair, Underground Utility repair, Caulking, Joint seal, Prime Coat, Redwood Header, Weed kill, Underground removals, Patch back at new curbs, gutters, ramps or driveways, reinforcing steel Unless Otherwise Noted(UON).
Backfilling and grading after asphalt patch/paving to be done by others.
Concrete cracking are to be anticipated in post concrete finishing, GT is not liable for cracking during its natrual curing frame of 28 days
GC or Prime Contractor is to protect Concrete from damages after concrete finish. (951) 545-5402 [email protected] Or (951) 768-2035 [email protected] 1912 Elise Circle., Corona, Ca 92879 | Lic. #1105565 | DIR# 1001051342
1912 Elise Circle., Corona, Ca 92879
GT General is fully licensed, bonded and insured.
If this proposal is acceptable and returned signed, a contract shall be signed by both parties and attached to the contract.
Date
Authorized Customer/Agency Name Printed
Date
GT Authorized Name Printed
GT Authorized Signature
Authorized Customer/Agency Signature
(951) 545-5402 [email protected] Or (951) 768-2035 [email protected] 1912 Elise Circle., Corona, Ca 92879 | Lic. #1105565 | DIR# 1001051342
1912 Elise Circle., Corona, Ca 92879
(951) 545-5402 [email protected] Or (951) 768-2035 [email protected] 1912 Elise Circle., Corona, Ca 92879 | Lic. #1105565 | DIR# 1001051342