Fontana Elm And Valley East Side CulvertProject Name: Bid Number:02-02-26 Fontana Fax:

Address: Fontana, CA Phone:

Project Location: Bid Date: 2/2/2026
Total PriceUnit PriceUnitItem DescriptionItem # Estimated Quantity 1 1.00 LS $68,139.00 $68,139.00Construct 34' Long, 3'x1'-1.5' Reinforced Concrete Box Storm Drain Per Caltrans Standard D80, With 8' Wide
Pavement Replacement
2 1.00 EACH $4,708.00 $4,708.00Construct Headwall With Wings Per City Of Fontana Standard 3020, Modified As Necessary To Fit Site
Conditions (Dimensions To Be Determined In-Field As
Space Permits)
Total Price for above Items: $72,847.00
Total Bid Price: $72,847.00
Notes:
• This proposal only includes 320 square feet (8' x 40') of asphalt finish course. If requested, pricing will be given to increase square footage to the next full lane or quadrant of the intersection.
• Pricing includes one mobilization unless otherwise specified in bid documents. Add $2,500 for additional mobilizations. • Pricing will remain valid if accepted within 30 calendar days. • Billings to be issued monthly unless otherwise specified in contract. • Payment to be received within 30 calendar days of billing date unless otherwise specified in contract. • Billing retention not to exceed 5% unless otherwise specified in contract. • Prevailing wages are not included. If project is subject to prevailing wage rates, additional costs will be incurred. • Pricing includes the California DIR prevailing wage rates in effect at the project advertisement date. If different wage rates are required, additional costs may be incurred.
• Pricing assumes construction water provided on-site by project and/or property owner. • Inspection fees are not included.
• Permit fees are not included.
• Differing site conditions and unforeseen utilities/improvements not identified in the bid documents are not included and may incur additional cost if encountered.
• Pricing assumes uninterrupted and unimpeded access to the work site(s) during all working hours. Limited access may incur additional cost. • Working hours to be 7:00am to 5:00pm unless otherwise specified in contract. • Water pollution and erosion control measures are included only for the scope of work covered by this proposal. • Traffic control is included only for the scope of work covered by this proposal. • Traffic control to be per MUTCD standards. Engineered traffic control plans are not included unless otherwise specified in bid documents. • Material and compaction testing are not included unless otherwise specified in bid documents. • All improvements to be constructed per 2021 Standard Plans for Public Works Construction ("Greenbook") unless otherwise specified in bid documents.
• Pre- and post-construction video inspection is not included unless otherwise specified in bid documents. • Dewatering of any kind is not included unless otherwise specified in bid documents. • Pricing assumes the absence of groundwater within project limits unless otherwise specified in bid documents; any groundwater encountered may incur additional cost.
• Field engineering, surveying and staking to be provided by others unless otherwise specified in bid documents. • We reserve the right to modify our pricing in response to any design, engineering, specification, or other changes made to the project after issuance of this proposal.
• Handling and/or disposal of hazardous materials is not included. • Pricing assumes performance of all items included in this proposal. We reserve the right to modify our pricing if items are deleted. • We reserve the right to modify our pricing if constructed quantities differ by more than 25% from those specified in the bid documents. • Anything not included in the bid documents is excluded from this proposal. • Anything not specifically included in this proposal is excluded. 2/2/2026 10:33:49 AM Page 1 of 2
ACCEPTED:

The above prices, specifications and conditions are satisfactory and are hereby accepted.

Buyer:

Signature:

Date of Acceptance:

CONFIRMED:

Gentry General Engineering, Inc
Authorized Signature:

Estimator:
2/2/2026 10:33:49 AM Page 2 of 2
To: Contact: City Of Fontana
Fontana Hemlock And Valley Southeast Corner CulvertProject Name: Bid Number:02-02-26 Fontana Fax:

Address: Fontana, CA Phone:

Project Location:Hemlock And Valley, Fontana, CA Bid Date: 2/2/2026 Total PriceUnit PriceUnitItem DescriptionItem # Estimated Quantity 1 1.00 LS $68,139.00 $68,139.00Construct 34' Long, 3'x1'-1.5' Reinforced Concrete Box Storm Drain Per Caltrans Standard D80, With 8' Wide
Pavement Replacement
Total Price for above Items: $68,139.00
Total Bid Price: $68,139.00
Notes:
• This proposal only includes 320 square feet (8' x 40') of asphalt finish course. If requested, pricing will be given to increase square footage to the next full lane or quadrant of the intersection.
• Pricing includes one mobilization unless otherwise specified in bid documents. Add $2,500 for additional mobilizations. • Pricing will remain valid if accepted within 30 calendar days. • Billings to be issued monthly unless otherwise specified in contract. • Payment to be received within 30 calendar days of billing date unless otherwise specified in contract. • Billing retention not to exceed 5% unless otherwise specified in contract. • Prevailing wages are not included. If project is subject to prevailing wage rates, additional costs will be incurred. • Pricing includes the California DIR prevailing wage rates in effect at the project advertisement date. If different wage rates are required, additional costs may be incurred.
• Pricing assumes construction water provided on-site by project and/or property owner. • Inspection fees are not included.
• Permit fees are not included.
• Differing site conditions and unforeseen utilities/improvements not identified in the bid documents are not included and may incur additional cost if encountered.
• Pricing assumes uninterrupted and unimpeded access to the work site(s) during all working hours. Limited access may incur additional cost. • Working hours to be 7:00am to 5:00pm unless otherwise specified in contract. • Water pollution and erosion control measures are included only for the scope of work covered by this proposal. • Traffic control is included only for the scope of work covered by this proposal. • Traffic control to be per MUTCD standards. Engineered traffic control plans are not included unless otherwise specified in bid documents. • Material and compaction testing are not included unless otherwise specified in bid documents. • All improvements to be constructed per 2021 Standard Plans for Public Works Construction ("Greenbook") unless otherwise specified in bid documents.
• Pre- and post-construction video inspection is not included unless otherwise specified in bid documents. • Dewatering of any kind is not included unless otherwise specified in bid documents. • Pricing assumes the absence of groundwater within project limits unless otherwise specified in bid documents; any groundwater encountered may incur additional cost.
• Field engineering, surveying and staking to be provided by others unless otherwise specified in bid documents. • We reserve the right to modify our pricing in response to any design, engineering, specification, or other changes made to the project after issuance of this proposal.
• Handling and/or disposal of hazardous materials is not included. • Pricing assumes performance of all items included in this proposal. We reserve the right to modify our pricing if items are deleted. • We reserve the right to modify our pricing if constructed quantities differ by more than 25% from those specified in the bid documents. • Anything not included in the bid documents is excluded from this proposal. • Anything not specifically included in this proposal is excluded. 2/2/2026 10:34:57 AM Page 1 of 2
ACCEPTED:

The above prices, specifications and conditions are satisfactory and are hereby accepted.

Buyer:

Signature:

Date of Acceptance:

CONFIRMED:

Gentry General Engineering, Inc
Authorized Signature:

Estimator:
2/2/2026 10:34:57 AM Page 2 of 2
To: Contact: City Of Fontana
Fontana Elm And Valley West Side CulvertProject Name: Bid Number:02-02-26 Fontana Fax:

Address: Fontana, CA Phone:

Project Location:Elm And Valley, Fontana, CA Bid Date: 2/2/2026 Total PriceUnit PriceUnitItem DescriptionItem # Estimated Quantity 1 1.00 LS $58,743.00 $58,743.00Construct 30' Long, 3'x1'-1.5' Reinforced Concrete Box Storm Drain Per Caltrans Standard D80, With 8' Wide
Pavement Replacement
Total Price for above Items: $58,743.00
Total Bid Price: $58,743.00
Notes:
• This proposal only includes 320 square feet (8' x 40') of asphalt finish course. If requested, pricing will be given to increase square footage to the next full lane or quadrant of the intersection.
• Pricing includes one mobilization unless otherwise specified in bid documents. Add $2,500 for additional mobilizations. • Pricing will remain valid if accepted within 30 calendar days. • Billings to be issued monthly unless otherwise specified in contract. • Payment to be received within 30 calendar days of billing date unless otherwise specified in contract. • Billing retention not to exceed 5% unless otherwise specified in contract. • Prevailing wages are not included. If project is subject to prevailing wage rates, additional costs will be incurred. • Pricing includes the California DIR prevailing wage rates in effect at the project advertisement date. If different wage rates are required, additional costs may be incurred.
• Pricing assumes construction water provided on-site by project and/or property owner. • Inspection fees are not included.
• Permit fees are not included.
• Differing site conditions and unforeseen utilities/improvements not identified in the bid documents are not included and may incur additional cost if encountered.
• Pricing assumes uninterrupted and unimpeded access to the work site(s) during all working hours. Limited access may incur additional cost. • Working hours to be 7:00am to 5:00pm unless otherwise specified in contract. • Water pollution and erosion control measures are included only for the scope of work covered by this proposal. • Traffic control is included only for the scope of work covered by this proposal. • Traffic control to be per MUTCD standards. Engineered traffic control plans are not included unless otherwise specified in bid documents. • Material and compaction testing are not included unless otherwise specified in bid documents. • All improvements to be constructed per 2021 Standard Plans for Public Works Construction ("Greenbook") unless otherwise specified in bid documents.
• Pre- and post-construction video inspection is not included unless otherwise specified in bid documents. • Dewatering of any kind is not included unless otherwise specified in bid documents. • Pricing assumes the absence of groundwater within project limits unless otherwise specified in bid documents; any groundwater encountered may incur additional cost.
• Field engineering, surveying and staking to be provided by others unless otherwise specified in bid documents. • We reserve the right to modify our pricing in response to any design, engineering, specification, or other changes made to the project after issuance of this proposal.
• Handling and/or disposal of hazardous materials is not included. • Pricing assumes performance of all items included in this proposal. We reserve the right to modify our pricing if items are deleted. • We reserve the right to modify our pricing if constructed quantities differ by more than 25% from those specified in the bid documents. • Anything not included in the bid documents is excluded from this proposal. • Anything not specifically included in this proposal is excluded. 2/2/2026 10:32:34 AM Page 1 of 2
ACCEPTED:

The above prices, specifications and conditions are satisfactory and are hereby accepted.

Buyer:

Signature:

Date of Acceptance:

CONFIRMED:

Gentry General Engineering, Inc
Authorized Signature:

Estimator:
2/2/2026 10:32:34 AM Page 2 of 2
To: Contact: City Of Fontana
Fontana Hemlock And Valley Southwest Corner CulvertProject Name: Bid Number:02-02-26 Fontana Fax:

Address: Fontana, CA Phone:

Project Location:Hemlock And Valley, Fontana, CA Bid Date: 2/2/2026 Total PriceUnit PriceUnitItem DescriptionItem # Estimated Quantity 1 1.00 LS $58,743.00 $58,743.00Construct 30' Long, 3'x1'-1.5' Reinforced Concrete Box Storm Drain Per Caltrans Standard D80, With 8' Wide
Pavement Replacement
Total Price for above Items: $58,743.00
Total Bid Price: $58,743.00
Notes:
• This proposal only includes 320 square feet (8' x 40') of asphalt finish course. If requested, pricing will be given to increase square footage to the next full lane or quadrant of the intersection.
• Pricing includes one mobilization unless otherwise specified in bid documents. Add $2,500 for additional mobilizations. • Pricing will remain valid if accepted within 30 calendar days. • Billings to be issued monthly unless otherwise specified in contract. • Payment to be received within 30 calendar days of billing date unless otherwise specified in contract. • Billing retention not to exceed 5% unless otherwise specified in contract. • Prevailing wages are not included. If project is subject to prevailing wage rates, additional costs will be incurred. • Pricing includes the California DIR prevailing wage rates in effect at the project advertisement date. If different wage rates are required, additional costs may be incurred.
• Pricing assumes construction water provided on-site by project and/or property owner. • Inspection fees are not included.
• Permit fees are not included.
• Differing site conditions and unforeseen utilities/improvements not identified in the bid documents are not included and may incur additional cost if encountered.
• Pricing assumes uninterrupted and unimpeded access to the work site(s) during all working hours. Limited access may incur additional cost. • Working hours to be 7:00am to 5:00pm unless otherwise specified in contract. • Water pollution and erosion control measures are included only for the scope of work covered by this proposal. • Traffic control is included only for the scope of work covered by this proposal. • Traffic control to be per MUTCD standards. Engineered traffic control plans are not included unless otherwise specified in bid documents. • Material and compaction testing are not included unless otherwise specified in bid documents. • All improvements to be constructed per 2021 Standard Plans for Public Works Construction ("Greenbook") unless otherwise specified in bid documents.
• Pre- and post-construction video inspection is not included unless otherwise specified in bid documents. • Dewatering of any kind is not included unless otherwise specified in bid documents. • Pricing assumes the absence of groundwater within project limits unless otherwise specified in bid documents; any groundwater encountered may incur additional cost.
• Field engineering, surveying and staking to be provided by others unless otherwise specified in bid documents. • We reserve the right to modify our pricing in response to any design, engineering, specification, or other changes made to the project after issuance of this proposal.
• Handling and/or disposal of hazardous materials is not included. • Pricing assumes performance of all items included in this proposal. We reserve the right to modify our pricing if items are deleted. • We reserve the right to modify our pricing if constructed quantities differ by more than 25% from those specified in the bid documents. • Anything not included in the bid documents is excluded from this proposal. • Anything not specifically included in this proposal is excluded. 2/2/2026 10:35:37 AM Page 1 of 2
ACCEPTED:

The above prices, specifications and conditions are satisfactory and are hereby accepted.

Buyer:

Signature:

Date of Acceptance:

CONFIRMED:

Gentry General Engineering, Inc
Authorized Signature:

Estimator:
2/2/2026 10:35:37 AM Page 2 of 2

← All documents from this meeting