FIRST AMENDMENT

TO PROFESSIONAL SERVICES AGREEMENT WITH
R.E.Y. ENGINEERS, INC.

THIS FIRST AMENDMENT is made and entered into this ___ day of February, 2022, by and between the CITY OF FORT BRAGG, hereinafter referred to as “City,” and R.E.Y. ENGINEERS, INC., hereinafter referred to as "Consultant.”
WHEREAS, the City and Consultant entered into a Professional Services Agreement (“Contract”) on December 14, 2021 to provide engineering and design services for the 2022 Streets Rehab Project, City Project No. PWP-00120 in the amount of $175,000.00; and WHEREAS, the scope of the design project has changed for the betterment of the project, as set forth in City Council Resolution ___-2022, adopted on February 14, 2022; and WHEREAS, the parties desire to amend the Contract to modify the Scope of Work, as set forth in Exhibit A attached hereto;
WHEREAS, the cost of the additional work described in Exhibit A is $82,000.00, making the total sum of the project Not to Exceed $257,000.00; and WHEREAS, there are still sufficient funds budgeted for these activities; NOW, THEREFORE, for the aforementioned reasons and other valuable consideration, the receipt and sufficiency of which is acknowledged, City and Consultant hereby agree that the Professional Services Agreement for engineering and design services for the 2022 Streets Rehab Project between the City and Consultant dated December 14, 2021, is hereby amended as follows:

1. Scope of Work:

Paragraph 1.1 (Scope of Work) is hereby amended to include the additional work described in Exhibit A attached hereto and incorporated herein by reference.

2. Compensation and Billing:

Paragraph 2.1 (Compensation) is hereby amended to state that total compensation shall not exceed Two Hundred Fifty-seven Dollars ($257,000.00).

3. Except as expressly amended herein, the Professional Services Agreement between the City and Consultant dated December 14, 2021, is hereby reaffirmed.

IN WITNESS WHEREOF, the parties have executed this Amendment the day and year first above written.

CITY OF FORT BRAGG: CONSULTANT:

By:________________________________ By:________________________________ David Spaur Jim Fisher, PE
City Manager Principal in Charge

Page 2 of 2 ends

ATTEST:
__________________________________
June Lemos, MMC
City Clerk
APPROVED AS TO FORM:
_________________________________
Keith F. Collins
City Attorney
February 2, 2022
Chantell O’Neal,
Assistant Director - Public Works
City of Fort Bragg
416 N. Franklin St.

Fort Bragg, CA 95437
Sent via email only
Subject: Contract Change Order Request No. 1
2022 Street Rehab Project, Street Striping, and Bollard Installation City Project No. PWP-00120
Dear Ms. O’Neal,
As we have discussed, the City of Fort Bragg is interested in adding additional improvements beyond what was originally included in our proposal. The project limits for street rehabilitation and striping have increased by 7,305 centerline feet, additional minor miscellaneous items such as repainting of specific light poles in the downtown area have been added, an extension of 290 lf of water main and 46 ft of sewer line on Halsey Way have been added, and 1,692 lf of underground storm drainage improvements, within the limits of the proposed pavement rehabilitation, have been added.

The estimated cost to perform the additional design effort; including utility mark and locate, geotechnical investigation, identification of utility conflicts, surveying, pavement condition assessment verification and preparation of the plans; is outlined below.

Base Scope Changes
Utility Coordination
Surveying
Pavement Condition Assessment Verification
Plans, Specifications, and Estimates
Proposal Budget $92,298
Base Scope Metrics
Proposal Quantity (centerline length) 30,218 lf
Unit Cost ($92,298/30,218 lf) 3.05 $/lf
Estimated Budget – Base Scope Changes
Estimated Budget for Increased Limits (7,305 lf x 3.05 $/lf) $22,300 Estimated Budget for Miscellaneous Items $2,700
Budget for Increased Limits and Miscellaneous Items $25,000 Utility Improvements: Storm Drainage, Water and Sewer
Surveying (Utility Mark and Locate)
Soils Investigation
Plans, Specifications, and Estimates
Budget for Utility Improvements $57,000
Requested Change in Contract Value $82,000
Exhibit A
R.E.Y. respectfully requests Contract Change Order No. 1 in the amount of $82,000 for the items of work which are identified as beyond the approved scope of work.

The value of Contract Change Order No. 1 will be distributed among our Scope of Work tasks as shown in the table below.

Should you have any questions during your evaluation of this request, please do not hesitate to call me.

Sincerely,
Aaron Brusatori, PE
Project Manager