CITY OF FORT BRAGG

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
PROJECT NAME: Pudding Creek Water Main Line Relocation DESIGN CITY OF FORT BRAGG Date of Issuance: 16-Dec-21

PUBLIC WORKS DEPARTMENT
416 N. Franklin Street City's Project No.: WTR-00014
Fort Bragg, CA 95437
(707) 961-2823 Engineer of Record: Diane O'Connor
Contractor: LACO Associates Engineer's Project No.: WTR-00014 Contract for: Design services for the Pudding Creek water main line relocation.

You are directed to proceed promptly with the following change(s):

Description: N/A - No change of service, contract extension only.

Purpose of Change Order: Additional six (6) month contract extension due to Caltran's delay in projects review and approval. No additional funding necessary. Currently set to expire December 31, 2021. New expiration date of June 30, 2022 requested.

CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price: Original contract time:
$ 114,000.00 362 Working days
Contract price prior to this Change Order: Contract time prior to this Change Order:
$ 114,000.00 362 Working days
Net Increase or decrease in contract price: Net increase or decrease in days:
$0.00 Increase 311 Working days
Net contract price with all Change Orders: New contract time with all Change Orders:
$ 114,000.00 673 Working days
Upon execution by representatives authorized to bind the parties, this Change Order will become a part price, an adjustment of time, and/or other consideration) is the full and sole compensation owed to the contractor as a result of the changes and issues described in this Change Order. Such consideration includes, but is not limited to, any and all direct and indirect costs incurred by the contractor as a result concerning any of the changes and issues specified in this Change Order.

Page 1 of 2 ends

CITY OF FORT BRAGG

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
PROJECT NAME: Pudding Creek Water Main Line Relocation DESIGN Approved: We, the undersigned Contractor, have given careful consideration to the change proposed anc ereby agree, if this proposal is approved, that we will provide all equipment, furnish all labor and materials except as may be otherwise noted above, and will accept as full payment therefore, the prices above Sal Will
By: Rodney Wilburn, PE, LACO Associates, Consultant
Phone: (707) 462-0222 [email protected]
Dec 17, 2021
RECOMMENDED: APPROVED: APPROVED:
-Tobatta thil
City Manager
Date: 12/20/2021 Cas. /2/20/2021 De. 12-20-202
PO Number: 12627 (no change in contract amount)

Page 2 of 2 ends