07252022 PFI Presentation City Council

Fort Bragg City Council
July 25, 2022

Document
07252022 PFI Presentation City Council
Meeting
July 25, 2022
Body
Fort Bragg City Council
Original file
1.6 MB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

Cypress Street
Residential Care Facility for the Elderly
Project
17-CDBG-12020
Parents and Friends, Inc.

July 11, 2022
City of
Fort Bragg
Parents &
Friends, Inc.

Adams
Commercial
General
Contracting
Project
Team:

Sub -
Consultants
SubContractors
Cypress Street Residential Care Facility
Phase One
K. Boodjeh
Architects
Where We Were
Where We Are
Where We Are
Going
Construction Began: April 25, 2022
Construction to be complete:

January 31, 2023
Grant Deadline: May 31, 2023
Before Site Preparation Activities
Preparing to Stake for slab Location of first home
For project specific details please contact Site Plan for Phase One Lacy Peterson, [email protected]
Questions?