Amended Scope of Work
Marie Jones Consulting is providing planning consulting services, on a time and materials basis, to the City of Fort Bragg for the following activities with regard to the Planning and Environmental Review for the proposed Transfer Station. The following are modifications to the existing Scope or Work.
Revisions include:
1. Completing the MND for the Transfer Station sections listed below:
• Energy
• Green hose gas emissions
• Noise
• Land Use
• Mandatory findings of significance
2. Preparing and presenting the staff report
Task Description Original
Hours
Original
Amount
Additional
Hours
Additional
Amount
1 Revise and Finalize Staff Report for new
Project Description for Planning Commission 15 $ 1,800 20 $2,400 2 Prepare Land Use, Noise, Energy, Green
House Gas Sections for MND. Revise entire
consultant prepared MND to respond to new
project description. Participate in various
meetings and calls regarding MND. Prepare
forms for submittal of MND to State
Clearinghouse, respond to Agency and Public
MND comments.
20 $ 2,400 65 $7,800
3 Provide guidance and advice to City Staff 5 $ 600 10 $1,200 4 Prepare and present staff report to Planning
Commission (assumes two meetings) 6 $ 720 2 $240
5 Prepare and present Staff report to City
Council (if appealed) 5 $ 600 2 $240
Project Management: meeting with
Applicants, Regulatory Agencies, Staff
regarding project
0 $ - 10 $1,200
Total Request $ 6,120 109 $13,080
Amended Contract Amount $19,200