CITY OF FORT BRAGG

RFP OPENING
2025 PAVEMENT PRESERVATION AND REHABILITATION PROJECT, PWP-00132 Written proposals were due by 2:00 PM, Friday, March 29, 2024. Four (4) timely proposals were received.

RFP Responses – 2025 Streets Pavement Preservation and Rehabilitation Project Page 1 Submitted By Projects Staffing/Experience Timeframe Hourly Rates Bid Comments 1 WhitChurch Engineering
610 9th Street
Fortuna, CA 95540
T: 707-725-6926
Jeffrey Laikam, PE
[email protected]
www.whitchurchengineering.com
• Humboldt Bay Power Plant
Road Design
• Elk Valley Casino access
road, parking lot, soils
report, pavement design,
subgrade recommendations
• Jeffrey Laikam, PE,
Engineering Manager,
22 years
• Derek Long, PE,
Project Manager,
11 years
• P. Michael Gent, PE,
Senior Civil Engineer
13 years
• Terry O’Reilly,
Professional Engineer
25 years
11/26/2025
Engineering
Manager
$200
Project
Manager/
Site Civil
Design Lead
$140
Senior Engineer
$145
Drafter/ Permit
Specialist
$100
$287,000.00
No issues with
insurance
requirements.
2 Lumos & Associates
3840 El Dorado Hills Blvd., Suite
301
El Dorado Hills, CA 9576
T: 916-980-8228
Tim Russell, PE
[email protected]
Aaron Brusatori, PE
[email protected]
• 2020 Maple Street Storm
Drain and Alley
Rehabilitation Project, Fort
Bragg
• 2022 Streets Rehabilitation,
Street Striping, and Bollard
Installation Project, Fort
Bragg
• Hazelwood Street Extension
Preliminary Design
• Aaron Brusatori, PE
Engineering Project
Manager
23 Years
• Brian Harer, Senior
Construction Project
Manager
17 Years
• Alex Greenblat, PE,
Senior Engineering
Project Manager
14 Years
• Andrew Chafer, Survey
Project Manager
16 years
11/13/2025
Project
Manager
$305
Investigation
Design PM
$280
Engineering
Design/
Oversight
$275
GIS Analyst
$155
$222,941.00
No issues with
insurance
requirements.

CITY OF FORT BRAGG

RFP OPENING
2025 PAVEMENT PRESERVATION AND REHABILITATION PROJECT, PWP-00132 Written proposals were due by 2:00 PM, Friday, March 29, 2024. Four (4) timely proposals were received.

RFP Responses – 2025 Streets Pavement Preservation and Rehabilitation Project Page 2 R.E.Y. Engineers, Inc.
905 Sutter Street, Suite 200
Folsom, CA 95630
T: 916-366-3040
F: 916-366-3303
Garrett McLaughlin, PE, PLS
[email protected]
• Maple St. Storm Drain &
Alley Rehabilitation, Fort
Bragg
• 2022 Streets Rehabilitation,
Street Striping, and Bollard
Installation Project, Fort
Bragg
• State Route 1 ADA
Improvement Project, Fort
Bragg
• Garrett McLaughlin, PE,
PLS, Project Manager
22 Years
• Jim Fisher, PE, QSD/P,
Principle in Charge
20 Years
• Joe Feyder, PLS,
Project Surveyor
43 Years
• Kevin Hoover, Project
Engineer
7 Years
• Greg Rugh, EIT, Design
Engineer
9 Years
06/2025
Senior
Engineer/
Surveyor 1-5
$209-290
Principle
Manager I
$290
Project
Coordinator
$127
Technician 1-3
$100-138
LiDAR Tech 1-3
$157-207
$251,950.00
No issues with
insurance
requirements.

Tall Tree Engineering, Inc.
99 S Main Street
Willits, CA 95490
T: 707-841-2001
Susanne Loutsis, PE, QSD, QSP
[email protected]
• City of Clearlake Burns
Valley Arrowhead Road
Rehabilitation Project
• City of Clearlake Ball Park
Streets Rehabilitation
Project
• City of Willits West
Mendocino Avenue
Improvement Project, Phase
1 • City of Willits Maple Street
Improvement Project
• Susanne Loutsis, PE,

QSP, QSD
Years Not Specified
• Dustin Fredicey, PE,
QSD, QSP, Surveying
Lead and Designers
Years Not Specified
• David L Swartz, PE,

PLS, QSD, QSP,
Engineer
33 Years
• Marisa Hewitt, PE, Site
Visit Manager
7 Years
11/29/2025
Principal
Profession
Engineer
$160
Project
Manager
$160
Engineering
Technician
$120
Administration
$85
$166,880.00
No issues with
insurance
requirements.