CITY OF FORT BRAGG
RFP Responses – Design Fort Bragg Reservoir Project for Water Storage Resilience Project, WTR-00024 Page 1

RFP OPENING

DESIGN FORT BRAGG RESERVOIR PROJECT FOR WATER STORAGE RESILIENCE PROJECT WTR-00024
Written proposals were due by 2:00 PM, Tuesday, July 23, 2024. Two (2) timely proposals were received.

PLEASE NOTE:

Most service provider proposals include a statement indicating that hourly rates are subject to an approximate 3.5% annual cost of living increase.

CITY OF FORT BRAGG
RFP Responses – Design Fort Bragg Reservoir Project for Water Storage Resilience Project, WTR-00024 Page 2 Submitted By Projects Staffing/Experience Timeframe Comments 1 WATER WORKS ENGINEERS
LLC
1730 S. El Camino Real Suite 280
San Mateo, CA 94402
T: 650-389-9166
Cindy Bertsch, PE
[email protected]
 San Jose Water, Cambrian
Zone Storage Consolidation
and Station Improvements
Project
 San Jose Water, Columbine
Station Improvements
Project
 San Juan Water District,
Kokila Tank, Placer County
 City of MillbraeSkyline Tank
 Cindy Bertsch, PE
23 Years
 Todd Koety, Quality
Assurance Mgr.
35 Years
 Mike Fisher, PE
25 years
 John Roy, PE,
10  Tim Lewis, Pipeline
Engineer, PE
10 years
11/30/2025
No issues with insurance requirements.

Rates effective through December 31, 2024; a
3% increase will be added for any services
performed in each year thereafter.
2 WATER SYSTEMS CONSULTING,
INC. (WSC)
2330 E Bidwell St., Suite 110
Folsom, CA 95630
Jon Ganz, Project Manager
[email protected]
 Replenish Big Bear
Evaporation Pond Design
 Palmdale and Lancaster
Water Reclamation Plant
Recycled Water Storage
Containers
 Hinkle Reservoir- Liner,
Baffle, & Floating Cover,
San Juan Water District
 Fairview Reservoir #2 –
Liner, Baffle, & Floating
Cover, Aberdeen, WA
 Rob Natoli, PE
16 Years
 • Jon Ganz, Project
Manager
27 Years
 • Jeff Lawrence, PE
30 Years
 Michelle Heinrichs,
PE
8 Years
2026 No issues with insurance requirements.