CCO # Description of work Ordered by Cost
Order 2x 100 amp breakers and mounting hardware for the switchgear cabinet to connect the E250's FBE $ 9,244.00 Order 2 50 amp breakers for the C6000 chargers to be installed inside the transformer FBE see above
Concrete pad for switchgear: adjusted from 7' x 16' to 8' x 16' Akeff $ 1,040.00 Install a third conduit from the switchgear box to terminate at the west end of the asphalt section for installation of a future Charger. Owner $ 1,225.00
The splash pad at the building for drainage - differing underground conditions Owner $ 410.00
Add base rock section to DC Fast Charger parking area. Design Engineering did not include geotech-discovered differing underground condition Akeff $ 6,300.00
Add three more "Police Vehicle Only" markings so that all stalls on south east side of the parking lot bare the same identification Owner $ 1,080.00 Trenching and conduit for gate wire and add a utility cover for existing electric at the median island in the new concrete area Owner $ 915.00 Establish an area for the dumpster (grading and Drain Rock) Owner $ 425.00 Line Item #5- Sidewalk & Driveway- bid schedule shows 720 sf, where 850 total calculated is (130 @ $48.00) Akeff $ 6,240.00 Add two curb stops to north east parking spaces (2@$250) Owner $ 500.00 Credit for reduced asphalt thickness from 3.75" to 2.5" (11 tons @ $512.00) Akeff $ (5,632.00)
$ 21,747.00
Other Costs
Additional costs to cover building permit and publication fees $ 1,502.61 $ 23,249.61
1 2
Total Contract Changes to date (4/28/25)
Change Order Work for EV Fleet Charging Station Project PWP-00126
Att 2 - Exhibit A Change Order Log
Fort Bragg City Council
April 28, 2025
- Document
- Att 2 - Exhibit A Change Order Log
- Meeting
- April 28, 2025
- Body
- Fort Bragg City Council
- Original file
- 85 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.