Cities Index.
Att 2 - Exhibit A Change Order Log

Fort Bragg City Council
April 28, 2025

Document
Att 2 - Exhibit A Change Order Log
Meeting
April 28, 2025
Body
Fort Bragg City Council
Original file
85 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

CCO # Description of work Ordered by Cost
Order 2x 100 amp breakers and mounting hardware for the switchgear cabinet to connect the E250's FBE $ 9,244.00 Order 2 50 amp breakers for the C6000 chargers to be installed inside the transformer FBE see above
Concrete pad for switchgear: adjusted from 7' x 16' to 8' x 16' Akeff $ 1,040.00 Install a third conduit from the switchgear box to terminate at the west end of the asphalt section for installation of a future Charger. Owner $ 1,225.00
The splash pad at the building for drainage - differing underground conditions Owner $ 410.00
Add base rock section to DC Fast Charger parking area. Design Engineering did not include geotech-discovered differing underground condition Akeff $ 6,300.00
Add three more "Police Vehicle Only" markings so that all stalls on south east side of the parking lot bare the same identification Owner $ 1,080.00 Trenching and conduit for gate wire and add a utility cover for existing electric at the median island in the new concrete area Owner $ 915.00 Establish an area for the dumpster (grading and Drain Rock) Owner $ 425.00 Line Item #5- Sidewalk & Driveway- bid schedule shows 720 sf, where 850 total calculated is (130 @ $48.00) Akeff $ 6,240.00 Add two curb stops to north east parking spaces (2@$250) Owner $ 500.00 Credit for reduced asphalt thickness from 3.75" to 2.5" (11 tons @ $512.00) Akeff $ (5,632.00)
$ 21,747.00
Other Costs
Additional costs to cover building permit and publication fees $ 1,502.61 $ 23,249.61
1 2
Total Contract Changes to date (4/28/25)
Change Order Work for EV Fleet Charging Station Project PWP-00126

← All documents from this meeting