TO: City Council DATE: May 12, 2025 DEPARTMENT: Public Works Department
PREPARED BY: Chantell O’Neal, Assistant Director, Engineering PRESENTER: Chantell O’Neal, Assistant Director, Engineering AGENDA TITLE: Review and Confirmation of the 2027 Roadway Revitalization Project Scope

RECOMMENDATION
Receive the staff presentation on the 2027 Roadway Revitalization Project and provide direction to confirm or update the list of street segments previously approved in November 2024.

SUMMARY
In November 25, 2024, City Council adopted a Resolution authorizing the programming of specific street segments for inclusion in the 2027 Roadway Revitalization Project under the Local Partnership Program - Formulaic (LPP-F) and Competitive (LPP-C) fund applications submitted to the California Transportation Commission (CTC). The project scope for programming LPP grants, must be submitted to the state well in advance of performing work on the project in accordance with grant timelines.

The purpose of this agenda item is to:

Confirm the list of streets originally approved for the 2027 project, Consider adding street segments previously left off the 2025 project list, Discuss incorporation of Azalea and Pentitini Streets (designed for 2022 project but not included in the contract award due to budget shortfall), and Recommend adding underground utility work—specifically, two valves on the City Water Main along Oak Street—in coordination with draft Water Master Plan recommendations.

Based on the recent increased interest in upcoming street projects, staff seeks to ensure that the current scope aligns with Council’s goals and expectations before design begins.

BACKGROUND
November 25, 2024: City Council adopted a Resolution programming the 2027 LPP-F Roadway Project and discussed the submittal of an LPP-Competitive (LPP-C) application.

June 26–27, 2025: California Transportation Commission (CTC) will consider programming and funding recommendations for both the LPP-F and LPP-C components.

July 2025: Pending CTC approval, the City can proceed with design-phase solicitation.

January 2027: Project tentatively scheduled to go to bid for construction.

The 2027 project was programmed approximately 2.5 years prior to its target construction year. Once programmed by the CTC, funds must be allocated within two fiscal years of eligibility notification and expended within three fiscal years from the date of project construction award in order to remain eligible.

PROJECT SCOPE
The original list of street segments programmed for the 2027 Roadway Revitalization Project as well as a detiled scope of work is discussed at length in the staff report found here: https://cityfortbragg.legistar.com/View.ashx?M=F&ID=13566485&GUID=E58936D2-DBE6-4FBC-A749-17E3DC574152 Council is asked to confirm the previously approved segments and consider the following additions:

Segments previously excluded from the 2025 project (sections described in the Public Works and Facilities Agenda from March 31, 2025: https://cityfortbragg.legistar.com/View.ashx?M=F&ID=13993327&GUID=5E33118F-19AA-4838-9A2E-2C24F5273960 – see slide 5 and slide 7).

Azalea and Pentitini Streets, which were designed in 2022 but not constructed Water system improvements in Oak Street, specifically the installation of two valves on the City’s water main, coordinated with pavement work

DIRECTION REQUESTED FROM COUNCIL
Confirm the street segments authorized in November 2024.

Provide direction on whether to include:

Streets previously left off the 2025 project.

Azalea and Pentitini Streets (fully designed).

Oak Street water main valve installation.

Advise staff on any other streets or infrastructure that may merit inclusion.

Staff will use Council’s direction to finalize the project scope for design procurement in fiscal year 25/26.

FISCAL IMPACT
The 2027 Roadway Revitalization Project is anticipated to be funded through:

Local Partnership Program – Formulaic (LPP-F)
A pending application for LPP – Competitive (LPP-C)
Additional funding may be supported by the City’s Street Sales Tax Fund, Local Streets and Roads gas tax revenues, or some of the unassigned reserves programmed for street reconstruction work.

Adding new segments or underground utility work may require additional funding or phasing depending on design and cost estimates.