Cities Index.
Att 2 - Ex A Change Order No. 5 – A.B.S. Builders, Inc.

Fort Bragg City Council
January 26, 2026

Document
Att 2 - Ex A Change Order No. 5 – A.B.S. Builders, Inc.
Meeting
January 26, 2026
Body
Fort Bragg City Council
Pages
2
Original file
181 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

PROJECT NAME: Bainbridge Park Enhancement Project PO Number:

CITY OF FORT BRAGG Date of Issuance: 1/26/2026

PUBLIC WORKS DEPARTMENT
416 N. Franklin Street City's Project No.: PWP-00096
Fort Bragg, CA 95437
(707) 961-2823
Contractor: A.B.S. Builders, Inc
Contract for: Bainbridge Park Enhancement Project
You are directed to proceed promptly with the following change(s):

Description: See Contractor Exhibits
Purpose of Change Order: Soccer Field Curb & Footings, Drinking Fountain, underlayment, Replace Fiberglass
‑
Reinforced Plastic (FRP) on bathroom walls. Add an additional 35 working days for completion of soccer courts.

CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price: Original contract time:
$1,444,622.65 125 Working days
Contract price prior to this Change Order: Contract time prior to this Change Order:
$1,476,636.84 151 Working days
Net Increase or decrease in contract price: Net increase or decrease in days:
$ 188,178.46 61 Working days
Net contract price with all Change Orders: New contract time with all Change Orders:
$1,632,801.11 186 Working days
Upon execution by representatives authorized to bind the parties, this Change Order will become a part of the contract. The consideration specified in this Change Order (whether an adjustment of the contract price, an adjustment of time, and/or other consideration) is the full and sole compensation owed to the contractor as a result of the changes and issues described in this Change Order. Such consideration includes, but is not limited to, any and all direct and indirect costs incurred by the contractor as a result of the changes and issues described in this Change Order for any labor, equipment, materials, overhead (additional, extended, field and home office), profit, or time adjustments. By signing this Change Order the contractor waives and releases the owner from any and all claims for additional compensation concerning any of the changes and issues specified in this Change Order.

CITY OF FORT BRAGG

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.5
13110

Page 1 of 2 ends

PROJECT NAME: Bainbridge Park Enhancement Project
Approved: We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all labor and materials, except as may be otherwise noted above, and will accept as full payment therefore, the prices above By: Amy Schmidt , Contractor
Date:

Phone: 530-458-2299
Email: [email protected]
RECOMMENDED: APPROVED:

Date: Date:

APPROVED:

Date:

Isaac Whippy
City Manager
[email protected]
[email protected]
John Smith

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 05

CITY OF FORT BRAGG
Chantell O'Neal
Project Manager
[email protected]
Public Works Director

Page 2 of 2 ends

A C D E F
Item Quantity Units
Unit Price
($)
Value of Bid Item
(C X E)
($)
40A 1.00 LS $117,283.12 117,283.12
117,283.12
Project Manager Chantell O'Neal

PROPOSED CHANGE ORDER
Owner: City of Fort Bragg
Contractor: A.B.S. Builders, Inc.

Project: Bainbridge Park Enhancement Project
TOTAL CONCRACT Increase(Decrease)
B
Soccer Field Curb & Footings
SCOPE OF WORK:

Provide materials, labor, equipment, travel, lodging, and overhead for overexcavation work on soccer field footings. Soccer field footings failed to meet required compaction percentage so the special inspector/engineering team developed a scope of work to facilitate construction.

Scope includes removal of forms, overexcavation to larger size dimension, installation of base rock, compaction, and re-installation of forms. This work is additional work to meet compaction in the footing area and is not inclusive of any work previously approved by Change Order 4. We request the contract extension through March 15, 2026 to accommodate for rain delays and additional work. Schedule is contingent upon subcontractor availability in the coming weeks and additional time request may be needed depending upon availability.

Bid Item
No. Description
Contract Information

A C D E F
Item Quantity Units
Unit Price
($)
Value of Bid Item
(C X E)
($)
49 1.00 LS $2,775.00 2,775.00
38 1.00 LS $6,895.00 6,895.00
40C 1.00 LS $4,312.50 4,312.50
13,982.50
SCOPE OF WORK:

Remove existing and install new fiber reinforced panels in the two western restrooms at Bainbridge Park.

SCOPE OF WORK:

Increase pour in place to include rubberized cushion on the soccer field turn not shown on the original drawings.

Project Manager Chantell O'Neal

PROPOSED CHANGE ORDER
Owner: City of Fort Bragg
Bid Item
No. Description
Contract Information
Contractor: A.B.S. Builders, Inc.

Project: Bainbridge Park Enhancement Project
TOTAL CONCRACT Increase(Decrease)
Soccer Field Artificial Turf
B
Drinking Fountain
SCOPE OF WORK:

Saw cut existing concrete, provide fountain waste pipe connection to existing sewer cleanout with 10% slope to sewer cleanout.

Restroom Renovation

← All documents from this meeting