2022 Streets Rehabilitation Project
Final Closeout & Asset Protection Strategy
PUBLIC WORKS DEPARTMENT | PROJECT NO. PWP-00120 1 MARCH 9, 2026

ELAUREL
N.FRANKTRIIN ROADSAVER
FRESH
Executive Summary
The Wins
A $4.4M comprehensive
overhaul of city streets,
delivering miles of new
pavement, 19 ADA ramps,
and critical safety
upgrades.

The Challenge
18 specific areas of surface
delamination have been
identified on the Franklin
Street slurry seal.

Remediation is required.

The Strategy
Formally acceptthe Certificate
of Completion today. This
counter--intuitive act activates a
maintenance bond, a $361К
financial guarantee of Franklin
St. and other necessary repairs
NotebookLM
Delivering on the 2017 Pavement
Management Program
Following competitive bidding,
the City Council awarded the
$3.6M initial construction
contract to Argonaut
Constructors in July 2023,
with design by R.E.Y. Engineers
and CM by SHN.

ARGONAUT

CONSTRUCTORS

1.4 0.4
Miles of Pavement
Preservation
Miles of Full
Reconstruction

3.0+ Miles of
Striping & Safety
Improvements
NotebookLM
Pavement Rehabilitation & Preservation
Full HMA Restoration (5 Blocks / 2,500 linear ft):
- Boatyard Drive (Shopping center to Hwy 20)
- 100 Block of East Chestnut
- 500 Block of S. Harold Street
- 100-200 Blocks of West Fir Street
Maintenance Treatment ROI:

Slurry Seal applied to 350,000 sq ft
(1.4 miles) of Franklin Street. $0.55 per square foot bid price. Total cost: $191,202 (compared to
~$143k per block for full
reconstruction). Highly costeffective.