PROJECT NAME: PO Number:
CITY OF FORT BRAGG Date of Issuance:
PUBLIC WORKS DEPARTMENT
416 N. Franklin Street City's Project No.: WWP-00027
Fort Bragg, CA 95437
(707) 961-2823 Engineer of Record: Calpo Hom & Dong
Contractor: August-Jaye, Inc. Engineer's Project No.: N/A Contract for: Dryer Building Reconstruction Project
You are directed to proceed promptly with the following change(s):
Description: Work approved in PCO#1, PCO#2, PCO#3
Purpose of Change Order: PCO#1-2 increased scope, adding a demising wall and door, and changed exterior door material to FRP, which will be much more resistant to the coastal environment. PCO#3 is a credit for reduction of scope from a field change. Added duration is due to material lead times
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price: Original contract time:
321,861.00$ 45 Working days
Contract price prior to this Change Order: Contract time prior to this Change Order:
321,861.00$ 45 Working days
Net Increase or decrease in contract price: Net increase or decrease in days:
28,880.00$ 40 Working days
Net contract price with all Change Orders: New contract time with all Change Orders:
350,741.00$ 85 Working days
Upon execution by representatives authorized to bind the parties, this Change Order will become a part of the contract. The consideration specified in this Change Order (whether an adjustment of the contract price, an adjustment of time, and/or other consideration) is the full and sole compensation owed to the contractor as a result of the changes and issues described in this Change Order. Such consideration includes, but is not limited to, any and all direct and indirect costs incurred by the contractor as a result of the changes and issues described in this Change Order for any labor, equipment, materials, overhead (additional, extended, field and home office), profit, or time adjustments. By signing this Change Order the contractor waives and releases the owner from any and all claims for additional compensation concerning any of the changes and issues specified in this Change Order.
CITY OF FORT BRAGG
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.01
13204
PROJECT NAME: Dryer Building Reconstruction
Approved: We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all labor and materials, except as may be otherwise noted above, and will accept as full payment therefore, the prices above By: _________________________________________, Contractor Date:
RECOMMENDED: APPROVED:
Date: Date:
APPROVED:
Date:
Alfredo Huerta
Project Manager/Engineer/Inspector
[email protected]
Public Works Director
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 01
CITY OF FORT BRAGG
Isaac Whippy
City Manager
[email protected]
[email protected]
John Smith