EXHIBIT A
Scope of Services
Ross Hill Road and Kenmar Road Project Study Report
City of Fortuna
January 21, 2022
The City of Fortuna has requested that GHD prepare a local agency Project Study Report (PSR) for the Ross Hill Road and Kenmar Road intersection in Fortuna, CA. The purpose of the PSR is to document agreement on the scope, schedule, and estimated cost of a project so that the project can be considered for inclusion in a future programming document such as the State Transportation Improvement Program (STIP). The PSR is intended to utilized by the City in its efforts to secure state or federal funding for advancement of the project.
The following describes our scope of services:
Task 1 – Mapping and Surveys
Base Mapping & Right-of-Way Figure
GHD will create a base map of the project extents using the City’s high-resolution aerial imagery or other available sources (e.g. Google). The base map will be supplemented with information from topographic field surveys provided by the City.
A right-of-way figure will be prepared using the aerial base map and assessor parcel maps.
Environmental Constraints Analysis
A GHD scientist will conduct a reconnaissance-level site investigations of existing conditions in order to identify potential environmental constraints. The types of information that will be collected during the field visit will include potential sensitive habitat (e.g. wetland or riparian), and other possible environmental constraints such as ponds, drainages, or creeks.
Biological databases will be queried and GHD will prepare a summary of the existing environmental conditions, the potential environmental compliance documents, and likely permits that will be required for the project. The summary will be included as content in the PSR (a separate memo will not be prepared).
Task 1 Deliverables:
• Base Map and Right of Way Figure
• Environmental Constraints Figure and Content for PSR
Task 2 – Traffic Forecasts and Operations Analysis
For this Task GHD will utilize available traffic data provided by the City and prepare a baseline and design year operations analysis for the intersection alternatives. GHD anticipates utilizing the 2016 traffic volumes collected for the US 101-Riverwalk Area Connectivity Project as a starting point and adjusting using an agreed growth rate (e.g. Fortuna General Plan Growth Rate) to reflect baseline conditions (e.g. 2025) and the 20-year design year (e.g. 2045).
The results of the preliminary operations analysis will be summarized in the PSR (a separate memo will not be prepared).
Task 2 Deliverables:
• Traffic Forecasts (baseline and design year)
| 2
• Level of Service Summary and Content for PSR
Task 3 – Alternatives Development
Develop Conceptual Alternatives
GHD will work with the City to develop the project’s purpose and need statement, which will be the basis for developing and analyzing alternatives.
Following development of the purpose and need, GHD will develop and evaluate the following two alternatives which are expected to satisfy the project purpose and need:
• A minimum build alternative would be explored that will enhance a “no build” version by evaluating minimum improvements to the signalized intersection.
• A build alternative that would provide a roundabout in lieu of signals.
The alternatives will be developed with sufficient engineering/project detail to support the development of the PSR.
Right-of-Way Needs
Potential right-of-way requirements (e.g. easements or acquisitions) for each alternative will be identified.
Planning Level Costs Estimates
GHD will develop a preliminary opinion of cost (estimate) for each alternative. These costs will be developed based on the preliminary improvement concepts and will include anticipated project development support, rightof-way, permitting, environmental mitigation and construction cost estimates.
Task 3 Deliverables:
• Conceptual Design Plans for Alternatives
• Right-of-way needs content for PSR
• Planning Level Cost Estimates
Task 4 – Develop Project Study Report
GHD will develop a PSR for the Ross Hill Road and Kenmar Road intersection. The PSR is expected to include the following sections:
1. Introduction
2. Background
3. Purpose and Need
4. Deficiencies
5. Corridor and System Coordination
6. Alternatives
7. Community Involvement
8. Environmental Compliance
9. Funding and Estimate
10. Delivery Schedule
11. Risks
12. External Agency Coordination
13. Project Reviews
14. Project Personnel
15. Attachments
Applicable comments provided by the City and other agencies (as appropriate) will be incorporated into the final PSR.
| 3
Task 4 Deliverables:
• Draft PSR for City review (electronic pdf)
• Final PSR for approval by City (electronic pdf)
GENERAL EXCLUSIONS AND ASSUMPTIONS
This scope of services is based on the tasks described above, which are anticipated for the project. This proposal is based on the following assumptions:
• This scope does not include anything not specifically described above; • The City will complete their review and prepare any comments they have in a timely manner and will deliver one set of rectified comments to GHD; and
• The scope does not include any coordination with Caltrans.
SCHEDULE
Major Milestones Tentative Schedule
Task Order Issued Jan 2022
Task 1 – Mapping and Surveys Feb – Mar 2022
Task 2 – Traffic Forecasts and Operations Analysis Feb – Mar 2022 Task 3 – Alternatives Development Apr – May 2022
Task 4 – Develop Project Study Report Jun – Jul 2022
COMPENSATION
GHD will provide the services outlined in the above scope on a time and materials basis, not to exceed $44,000.
Prepared by:
Josh Wolf, PE
Technical Director
(707)443-8326
[email protected]
Kamesh Vedula
Senior Technical Director 2Project Director
Josh Wolf
Senior Technical Director 3Project Manager
Daniel Kehrer
Technical Director 1Project Engineer
Ashley Hoy
Senior Professional 2Designer
Misha Schwarz
Technical Director 1Environmental Scientist
Andrea Hilton
Technical Director 2Environmental Planner
Julia Clark
Professional 2GIS
Linda Costa-Franklin
Admin Officer 5Admin
Phase 1 - Mapping and Surveys
Task 1.1 Base Mapping & Right-of-Way Figure $0.00 13 $1,925 $0 $1,925 Task 1.2 Environmental Constraints Analysis $0.00 12 $1,960 $0 $1,960 Phase Mapping and Surveys Subtotal: 25 $3,885 $0 $3,885 Phase 2 - Traffic Forecasts and Operations Analys
Task 2.1 Traffic Forecasts $0.00 16 $2,740 $0 $2,740
Task 2.2 Preliminary Operations Analysis $0.00 46 $7,330 $0 $7,330 Phase Traffic Forecasts and Operations Analysis Subtot 62 $10,070 $0 $10,070 Phase 3 - Alternatives Development
Task 3.1 Develop Conceptual Alternatives $0.00 86 $14,630 $0 $14,630 Task 3.2 Right-of-Way Needs $0.00 6 $1,060 $0 $1,060
Task 3.3 Planning Level Costs Estimates $0.00 24 $4,080 $0 $4,080 Phase Alternatives Development Subtotal: 116 $19,770 $0 $19,770 Phase 4 - Develop Project Study Report
Task 4.1 Develop Draft PSR $0.00 47 $7,075 $0 $7,075
Task 4.2 Develop Final PSR $0.00 20 $3,200 $0 $3,200
Phase Develop Project Study Report Subtotal: 67 $10,275 $0 $10,275 270 $44,000 $0 $44,000
Ross Hill Road and Kenmar Road PSR
0 6 0 4 2
4 12 40 0
APC
($/Hr)
Total Fee: Phase 1 to Phase 4
4 1
2 $195.0 $170.0 $125.0
2 $225.0 $195.0 $195.0 $140.0 $85.0
Description:
Task Number and Task Name
4 4
0 0
4 4
Total Labor
Hours
Total Labor
Cost
Associated
Project
Costs
2 4 8 1
1 6 2 8 1 2
1 8 2 32 2 2
4 10 48 54 0 0 0 0
2 14 4 40 0 0 3
12 34 64 138 2 4 11 5
4 2 2 4 8
6 0
Total GHD
Labor Fee
4 2 8 32
2 4 6 12
2 4 40 40
2 2