Building Forward Library Infrastructure Grant Program
Project Implementation Plan
Project
Organization: City of Fortuna
Project Title: Friendly Service in the Friendly City
Facility: Fortuna Library
Project Timeline
Using the table below, detail the major project activities or key milestones and when they will occur.

Note: All grant funds must be expended by March 31, 2026.

Activity Month/Year
Started
Month/Year
Completed
Finalize lease agreement between City and County for Fortuna Library building February 2022 September 2022
Secure grant funds March 2022 June 2022
Complete grant agreement July 2022 September 2022
Concept Development and Public Outreach October 2022 December 2022 Engage library staff, County ADA office, City facilities staff and other stakeholders in project design process January 2023 March 2023 Complete designs, specifications and permits March 2023 August 2023 Construction bid package preparation/start bid process August 2023 November 2023 Bidding and Award construction contract November 2023 January 2024 Construction period January 2024 January 2025
Grand opening February 2025 February 2025
Project closeout and reporting March 2025 August 2025
Ten years of lease agreement for operation and maintenance from completion of construction August 2025 August 2035