City of Fortuna
Annual Paving Contract Proposal Summary
Date - January 30th 2024
Mercer-Fraser GR Sundberg, INC.

Item Description Units Unit Price Unit Price
1 Install up to 100 Tons Hot Mix Asphalt Ton 225.00 $ 235.00 $ 2 Install from 101 to 300 Tons Hot Mix Asphalt Ton 190.00 $ 220.00 $ 3 Install from 301 to 500 Tons Hot Mix Asphalt Ton 170.00 $ 200.00 $ 4 Install from 501 to 700 Tons Hot Mix Asphalt Ton 160.00 $ 190.00 $ 5 Install over 701 Tons Hot Mix Asphalt Ton 150.00 $ 185.00 $ 6 Class II Aggregate Base Ton 55.00 $ 80.00 $
7 Install 6" asphalt dike LF 20.00 $ 25.00 $
8 Foreman charge out rate HR 120.00 $ 155.00 $
9 Operator charge out rate HR 105.00 $ 150.00 $
10 Laborer charge out rate HR 90.00 $ 135.00 $
11 Grind 0.25' HMA up to 1000 sf SF 9.00 $ 8.50 $
12 Grind 0.25' HMA 1001-5000 sf SF 2.50 $ 3.75 $
13 Grind 0.25' HMA 5001-10,000 sf SF 2.00 $ 2.25 $
14 Grind 0.25' HMA 10,001-15,000 sf SF 1.50 $ 1.60 $
15 Grind 0.25' HMA 15,001-20,000 sf SF 1.25 $ 1.10 $
16 Grind 0.25' HMA over 20,001 sf SF 1.00 $ 0.90 $
17 Excavate and backfill with river run CY 60.00 $ 105.00 $ 18 Box Scraper charge out rate HR 150.00 $ 200.00 $
19 Trucking charge out rate HR 180.00 $ 175.00 $
20 Grader charge out rate HR 200.00 $ 250.00 $
21 Raise Iron EA 700.00 $ 1,200.00 $
22 Night or Weekend change out rate 3% 25%