718 Third Street,
Eureka, California 95501
United States
ghd.com
The Power of Commitment
GHD
Amended Scope of Services
City of Fortuna
Mill Creek Restoration Design and Permitting
GHD Project Number 12629892
Amended Scope of Work
To support design and environmental compliance for the additional crossing identified on private property, the existing scope and fee are modified as summarized below. The scope of each task will remain consistent with the original agreement, along with the timeline, and rate structure.
Task
No.
Task Additional
Fee
2.1 Topographic Survey $7,000
2.4 Cultural Resources Investigation $5,000
3.1 30% Conceptual Design, Hydraulic Assessment and Draft Basis of Design Report $20,000
3.2 65% Intermediate Design Plans and Basis of Design Report $40,000
3.3 100% Final Design Plans and Basis of Design Report $35,000 TOTAL $107,000