Attachment 1 - Selected Portions of Quarterly Progress Report - 3rd Quarter Report, July 1, 2023 to September 30, 2023

Foster City City Council
November 20, 2023

Document
Attachment 1 - Selected Portions of Quarterly Progress Report - 3rd Quarter Report, July 1, 2023 to September 30, 2023
Meeting
November 20, 2023
Body
Foster City City Council
Original file
326 KB
Text extracted from the city's file for reading and search. Open the original on fostercity.primegov.com. That file is the official record.

GMP1 – Contract
Contractor Sundt
Award Date 5/6/2019
Construction NTP 6/4/2019
Duration (calendar days) 1124
Contracted Completion Date 7/1/2022
Total Original Contract Amount $33,098,178.00
Contingency Amount $1,725,000.00
Substantial Completion Date 2/1/2023
Current Contracted Amount $34,783,550.00
Actual Expended $31,630,697.00

GMP2 – Contract
Contractor Sundt
Award Date 5/4/2020
Construction NTP 5/5/2020
Duration (calendar days) 619
Contracted Completion Date 01/14/2022
Total Original Contract Amount $17,716,049.00
Contingency Amount $1,645,000.00
Substantial Completion Date 2/1/2023
Current Contracted Amount $17,963,767.00
Actual Expended $17,206,534.00

Active Wastewater Treatment Plant Projects
46T003 WWTP Nutrient Removal and Wet Weather Flow
Management Upgrade
Project Description:

The WWTP Upgrade and Expansion Project will replace aging infrastructure, provide capacity for wet weather flows, comply with regulatory requirements, enhance reliability, and produce a higher quality effluent that meets current and future permit requirements and Title 22 recycled water quality. Producing a higher quality effluent will enable the City to develop a water reuse Program.

GMP3 – Contract
Contractor Sundt
Award Date 9/21/2020
Construction NTP 9/22/2020
Duration (calendar days) 1563
Contracted Completion Date 1/2/2025
Total Original Contract Amount $379,880,747.00
Revised Contract Amount $383,790,833.00
Original Contingency Amount $13,900,000.00
Revised Contingency Amount $15,336,910.00
Forecast Completion Date 1/2/2025
Current Contracted Amount $395,988,119.00
Actual Expended $300,692,660.00

Current Period Activities
Project/Construction Management
• The Air Gap is scheduled to arrive in late October 2023 for the domestic water system. • Coordinating the Special Inspections Services
• Providing Construction Inspection Services
• Reviewing and recommending approval of change orders
• Administering the Consultant and Subconsultants contracts • Assisting with the Startup and Commissioning training of Plant Staff

July through September 20 23 P A G E 10

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023
Project Inside
Project Manager Leswin DCunha
Project Type Wastewater System
Phase Construction

• Monthly WWTP update meeting with Foster City management team.

Engineering Design/ Services During Construction
• Interpretive Signage: RHAA finalized the final design phase. • ESDC: HDR continued review of submittals and RFIs on GMP 3; development of design change notices; onsite and remote support by Resident Engineer. .HDR continuing the preparation of electronic Operations and Maintenance Manuals
Permitting
• Nothing to report.

Public Outreach
• PM/CM and the CWP Public Outreach Lead coordinated on regular project updates to the website, newsletter, social media, etc.

Construction
GMP-1
• Project close out is almost completed.

GMP-2
• Project close out has been sent to the City attorney for approval.

GMP-3
• Commissioning meetings were held to continue discussing start-up activities, including roles and responsibilities.
• Yard piping is complete except for final connection of the force mains to the Headworks schedule for May 2024.
• Continued to install Electrical (gear including cabinets, breakers, switches, conduit and wiring) and Mechanical Equipment (piping with structural supports, motors and pumps) in Areas 51 (Headworks), 52 (Primary Clarifiers),53 (Bio- Actiflo), 55 (BNR) and 56 (MBR).
• Continuing the installation of protective coatings in 52 . • Continue exterior of building, including installation of siding, installation of interior utilities, flooring and cabinetry for Area 80 (Admin. Building)
• Continue installation of interior work for the Warehouse • Earthwork - excavation, grading, and backfilling specifically around the entry of the Administration B uilding

July through September 2023 P A G E 11

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023

Next Period Activities
Project/Construction Management
• HDR’s to continue to provide ESDC services including development of process O&M manuals, process training, expanded discipline-specific Resident Engineer services, and related known scope reflected in the contingency budget.

Engineering Design/Services During Construction
• ESDC: HDR to continue to provide onsite resident engineering services.

Permitting
• Record the WWTP Final Parcel Map with the County.

Public Outreach
• Provide project updates to the CWP Public Outreach Lead for monthly newsletter, website, and social media updates.
• Continue as-needed support in response to resident queries via the communication hotline.

Construction
GMP-1
• Close out project
GMP-2
• Close out project.

GMP-3
• Continue to install Electrical (gear including cabinets, breakers, switches, conduit and wiring) and Mechanical Equipment (piping with structural supports, motors and pumps) in Areas 51 (Headworks), 52 (Primary Clarifiers),53 (Bio-Actiflo), 55 (BNR) and 56 (MBR).
• Continue to install the protective coatings in Area 52. • Continue exterior of building, including installation of siding, installation of interior utilities, flooring and cabinetry for Area 80 (Admin. Building)
• Continue installation of the interior work for the Warehouse • Earthwork - excavation, grading, and backfilling specifically around the entry of the Administration B uilding

July through September 2023 P A G E 12

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023

Risks and Opportunities
• Cal Water’s New Potable Water Main Extension: Completed • PG&E’s New Primary Service: Completed
• Relocation of PG&E’s Utilities from Detroit Drive: Completed

July through September 2023 P A G E 13

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023

Financial Status
 Current update shows an overrun ($18.43M) of original budget.

Millions

Budget $532.71

Actual Cost to date $455.66

Estimate at Completion $552.14

Schedule Status
 Part of re-baseline efforts. Current forecast shows to be completed on time in January 2025.

July through September 2023 PA G E 14

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023

46T009 IAP Package II
Project Description:

Replace and repair aging infrastructure at the WWTP by adding screening, flexibility, and redundancy for WWTP solids processes. The project includes: (1) Mechanical bar screen and repair of concrete wall at the IJB; (2) Effluent PS #1 pumping and piping improvements; (3) replace two of the oldest pumps in PS #1; (4) Cake pumping system: add second cake pumping system; and (5) Second cake hopper system: add a second cake hopper, slide gate, access walkway, and platform.

Current Period Activities
Project/Construction Management
• Coordinated City negotiations with Contractor for time extension / delays.
 Worked with Contractor on Cake pump issues.

Engineering Design/ Services During Construction
(Various)
• Stantec ESDC is ongoing through the remainder of its construction period.

Permitting
 No activities this period.

Public Outreach
 No activities this period.

Construction
Immediate Action Projects, Package II (IAP II)
 Installation of Hopper Modifications
 Next Period Activities
Project/Construction Management
 Continued change management support.

Engineering Design and Engineering Services During Construction  Stantec ESDC is ongoing through the remainder of its construction period.  Continue review of submittals and RFI.

Permitting
 No activities this period.

July through September 2023 Page 38

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023
Project Inside
Project Manager Tyler Kirkendall
Project Type Wastewater System
Phase Construction
Design Firm Stantec, HDR

IAP II – Contract
Contractor Myers & Sons
Award Date 2/11/2019
Construction NTP 2/19/2019
Duration (calendar days) 848
Contracted Completion Date 6/14/2021
Contract Amount $6,340,000
Contingency Amount $1,144,000
Forecast Completion Date 3/31/2024
Current Contracted Amount $7,167,599
Actual Expended $7,142,099

Public Outreach
 No activities this period.

Construction
Immediate Action Projects, Package II (IAP II)
 Work with Contractor to Complete fix to the cake pump issues.

Risks and Opportunities
 Sludge Cake Hopper No. 1 has not successfully completed start-up testing. Contractor working to identify issue affecting Cake Pump No. 1 and requested both design engineer and Vendor assistance in their troubleshooting of Cake Pump No. 1. Design Engineer provided new sludge cake measurement technology selection in DC 8, which was issued to the Contractor in September. City contracted with a third party to provide recommendations for fixing the Cake pump. The third party has recommended removal of welded pipe and installation of new piping. City working with Contractor for a solution.  Delays to the project by sludge cake pumping system will result in significant delays to the project.

Financial Status
 Current update shows an overrun ($4.45M) of original budget.

Millions

Budget $13.02

Actual Cost to date $12.99

Estimate at
Completion

$17.56
Schedule Status
Project schedule temporary on hold while issues are being resolved. Anticipat es construction to be completed by March 31, 2024

July through September 2023 P A G E 39

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023

46T010 IAP Package III
Project Description:

Upgrade aging infrastructure and increase reliability for the effluent PS at the WWTP. Improvements include perform hydraulic analysis on the effluent PS and flow meters; replace MCCs P1, P2, P3, and P4 in the Main Structure Building; add variable-frequency drives (VFDs) and check valves on stormwater pumps; replace check valves (3) for dry weather pumps; replace MCCs/VFDs (4) and control panels (4) for dry weather pumps; and replace doors (3) and windows (10), repair roof, and add HVAC for the PS.

Current Period Activities
Project/Construction Management (City/TBD)
 Project Bid opened on April 6, 2023
 Project awarded to Mountain Cascade for $11,703,696
 EAC revised to $17,587,506.
 City to advertise for Project Management Consultant
Engineering Design/ Services During Construction (HDR)
 None reported.

Next Period Activities
Project/Construction Management (City/Tanner Pacific)
 Construction Management by Tanner Pacific.

Engineering Design/ Services During Construction
 HDR to begin EDSC.

Risks and Opportunities
 Rescoping the project push out the completion date of the project.

Financial Status
 The current update shows an overrun ($15.12M) of the original budget.

Budget
$2.47
million

Actual Cost to date
$1.29
million

Estimate at Completion $17.59 million

Schedule Status
 Current forecast shows final completion in May 2025.

July through September 2023 P A G E 40

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023
Project Inside
Project Manager TBD
Project Type Wastewater System
Phase Engineering

46T090 Annual Major Component WWTP
Project Description:

Maintain reliable plant operations to meet regulatory permit requirements and repair and replace critical WWTP
infrastructure. The operations and maintenance team maintain an active list of potential projects that are implemented as funds are available.

Current Period Activities
Project/Construction Management (City/ TBD)
 City to advertise for Project Management Consultant
 Additional AMC project
 Update WWTP Biosolids and Energy Management Plan
 Digester 1 Improvements
 Centrifuge and Centrifuge Feed Pump Replacement
 Solids Handling Systems I&C Improvements
 Digester Transfer Pump Project
 3 Water Pumping Improvements
 DAFT Corrosion Improvements
 Digest 2 Mixer Repair/Replacement
Permitting (Various)
None
Construction
 Digester Transfer Pump Project to be awarded in November 2023 Next Period Activities
Project/Construction Management (City/ Tanner Pacific)
 None
Engineering Design/ Services During Construction
 Design Consultants working on the AMC projects.

Permitting
 N one
Construction
 None
Risks and Opportunities
 AMC 36 Centrifuge Conveyor Replacement is on hold.

July through September 2023 P A G E 41

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023
Project Inside
Project Manager TBD
Project Type Wastewater System
Phase Engineering

Financial Status
 Project shows EAC over budget.by $1.06 million

Millions

Budget $8.92

Actual Cost to date $1.59

Estimate at Completion $12.76

Schedule Status
 AMC 6 +23 was completed in November 2022.
 3 Water Pumping Improvement project to be out to bid in November 2023  AMC Digester Transfer Pump project to be awarded in November 2023  All other AMC projects are in the predesign phase.

July through September 2023 P A G E 42

Completed Projects

Wastewater Treatment Plant Projects
Updated to latest values from EDEN (January 2020)

Name

Start Date
Finish
Date

Actual Cost
469948: SCADA Immediate Projects: Phase 2 (IAP) 1/2/2015 11/25/2015 $1,524,717 469962: Short-Term MCC Replacement Project (IAP) 1/2/2015 11/25/2015 $49,628 469973: Secondary System: Immediate Projects: SCs 1-4 and return- activated sludge Pump Values (IAP)
1/2/2015 11/25/2015 $426,918
469975: Solids: Immediate Projects: GT 1&2 (IAP) 1/2/2015 11/25/2015 $372,358 469976: Immediate Projects: Boiler Replacement 1/2/2015 4/29/2016 $475,296 469978: Solids Building: Immediate. Projects: Centrifuge Hoist Project (IAP) 1/2/2015 11/25/2015 $2,410 46T002 IAP Package I 8/1/2018 8/28/19 $18,621,868
TOTAL $21,472,951

July through September 2023 P A G E 43

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q3 2023