MONTHLY CONSTRUCTION MANAGER’S REPORT
Foster City Levee Improvements Project
City Project No. CIP 301-657
Contractor: Shimmick Construction Co Report Period: January 1-31, 2024 CM: Tanner Pacific, Inc.

Designer: Schaaf & Wheeler
*
Note: estimates show exposure in excess of current contingency

MONTHLY CONSTRUCTION MANAGER’S REPORT
Work Summary
Recently Completed:
• Defective site furnishings in IM3 (NONC 024)
• AP 9 sod replacement & site furniture installation near Bayside Towers • Restoration of work areas near Bridgeview Park
• Guardrail bowed tension post remediation (NONC 019)
• Final punch list work from ~Sta. 205+00 - 343+00 (Foster City Blvd to Southern Project Limit) • Final punch list work from ~Sta. 100+00 - 205+00 (Bridgeview Park to Foster City Blvd) • Final punch list work from ~Sta. 00 - 100+00 (San Mateo City Limit to San Mateo Bridge)

Upcoming:
• Project Closeout Documentation (Guarantee, Release of Claims & Request for Final Payment, Notice of Completion)
• AP 4 Concrete break results (Punch List Item No. 382) • AP 10 Bench installation near Bayside Towers
• Finalization/resolution of outstanding Change Order Requests (currently ~ 5 pending)

MONTHLY CONSTRUCTION MANAGER’S REPORT
Monthly Progress Photos

AP -4 Punch List Work AP -9 Sod Replacement

Beach Park Blvd Punch L ist Wor k - Street Sign
Installation
Bridgeview Park Restoration / P unch List Work