Attachment 1 - Selected Portions of Quarterly Progress Report - 4th Quarter Report, October 1, 2023 to December 31, 2023

Foster City City Council
February 20, 2024

Document
Attachment 1 - Selected Portions of Quarterly Progress Report - 4th Quarter Report, October 1, 2023 to December 31, 2023
Meeting
February 20, 2024
Body
Foster City City Council
Original file
2.0 MB
Text extracted from the city's file for reading and search. Open the original on fostercity.primegov.com. That file is the official record.

Progress Through: December 31, 2023

Quarterly Progress Report
San Mateo Clean
Water Program
for the
Wastewater
Treatment Plant
Projects

3rd Quarter Report October 1, 2023
to December 31, 2023

Submitted on: January 23, 2024

GMP1 – Contract
Contractor Sundt
Award Date 5/6/2019
Construction NTP 6/4/2019
Duration (calendar days) 1124
Contracted Completion Date 7/1/2022
Total Original Contract Amount $33,098,178.00
Contingency Amount $1,725,000.00
Substantial Completion Date 2/1/2023
Current Contracted Amount $34,783,550.00
Actual Expended $31,630,697.00

GMP2 – Contract
Contractor Sundt
Award Date 5/4/2020
Construction NTP 5/5/2020
Duration (calendar days) 619
Contracted Completion Date 01/14/2022
Total Original Contract Amount $17,716,049.00
Contingency Amount $1,645,000.00
Substantial Completion Date 2/1/2023
Current Contracted Amount $17,963,767.00
Actual Expended $17,206,534.00

Active Wastewater Treatment Plant Projects
46T003 WWTP Nutrient Removal and Wet Weather Flow
Management Upgrade
Project Description:

The WWTP Upgrade and Expansion Project will replace aging infrastructure, provide capacity for wet weather flows, comply with regulatory requirements, enhance reliability, and produce a higher quality effluent that meets current and future permit requirements and Title 22 recycled water quality. Producing a higher quality effluent will enable the City to develop a water reuse Program.

GMP3 – Contract
Contractor Sundt
Award Date 9/21/2020
Construction NTP 9/22/2020
Duration (calendar days) 1584
Contracted Completion Date 1/23/2025
Total Original Contract Amount $379,880,747.00
Revised Contract Amount $383,790,833.00
Original Contingency Amount $13,900,000.00
Revised Contingency Amount $24,336,910.00
Forecast Completion Date 1/23/2025
Current Contracted Amount $400,620,304.00
Actual Expended $337,628,158.00

Current Period Activities
Project/Construction Management

• Coordinating the Special Inspections Services
• Providing Construction Inspection Services
• Reviewing and recommending approval of change orders
• Administering the Consultant and Subconsultants contracts • Assisting with the Startup and Commissioning training of Plant Staff • Monthly WWTP update meeting with Foster City management team.

October through Dec ember 2023 P A G E 10

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023
Project Inside
Project Manager Leswin DCunha
Project Type Wastewater System
Phase Construction

Engineering Design/ Services During Construction
• Interpretive Signage -:Contractor is in the process of procuring the signage. • ESDC: HDR continued review of submittals and RFIs on GMP 3; development of design change notices; onsite and remote support by Resident Engineer. .HDR continuing the preparation of electronic Operations and Maintenance Manuals
Permitting:

Bay Area Air Quality Management District (BAAQMD)

A/C 30448 (Liquid Processes)

Because the A/C renewal request has been submitted, the City can continue construction/operation under the conditions of the existing permit until a new A/C permit is issued.

A/C 30449 (Generators)

Because construction is complete and source test data submitted, the City does not need to renew the A/C. The Source Test data was approved 10/26/23. The next step, issue the Permit to Operate (P/O).

In the interim, the City can operate the generators under the conditions of the A/C permit.

Public Outreach
• PM/CM and the CWP Public Outreach Lead coordinated on regular project updates to the website, newsletter, social media, etc.

Construction
GMP1
 Project close out is almost completed.

GMP-2
 Project close out has been sent to the City attorney for approval.

GMP-3
 The contracted completion date for GMP3 is January.23,2025. However, in mid-January 2024, the City was informed by the contractor that the procurement of the electrical panels required for programming the SCADA have been impacted by the supply change issues as a result of the Covid pandemic, and the leak testing of the basins taking longer than originally planned, the project end date is now projected to be June 2025. The Contractor and the City are working together to minimize the potential delays and reduce this potential completion date extension. The Contractor and the City are also discussing the responsibility of the Contractor in covering the increase in management costs as a result of the schedule change.
 Commissioning meetings were held to continue discussing start-up activities, including roles and responsibilities.
 Yard piping is complete except for final connection of the force mains to the Headworks schedule for May 2024.
 Continued to install Electrical (gear including cabinets, breakers, switches, conduit and wiring) and Mechanical Equipment (piping with structural supports, motors and pumps) in Areas 51 (Headworks), 52 (Primary Clarifiers),53 (Bio- Actiflo), 55 (BNR) and 56 (MBR).

October through December 2023 P A G E 11

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023

 Continued installation of the exterior siding, the cabinetry, flooring and ceiling in Area 80 (Admin. Building)  Continued installation of interior work for the Warehouse  Continued improvements to the existing Sodium Hypochlorite Day and Bulk Storage Tanks, and pumping systems.
 Continued improvements to the existing Sodium Bisulfite Tanks and Pumping system.  Continued improvements to the existing Chlorine Contact Basins.

Next Period Activities
Project/Construction Management
• HDR’s to continue to provide ESDC services including development of process O&M manuals, process training, expanded discipline-specific Resident Engineer services, and related known scope reflected in the contingency budget.

Engineering Design/Services During Construction
• ESDC: HDR to continue to provide onsite resident engineering services.

Permitting
• Record the WWTP Final Parcel Map with the County.

Public Outreach
• Provide project updates to the CWP Public Outreach Lead for monthly newsletter, website, and social media updates.
• Continue as-needed support in response to resident queries via the communication hotline.

Construction
GMP-1
• Close out project
GMP-2
• Close out project.

GMP-3
 Continue to install Electrical (gear including cabinets, breakers, switches, conduit and wiring) and Mechanical Equipment (piping with structural supports, motors and pumps) in Areas 51 (Headworks), 52 (Primary Clarifiers),53 (Bio-Actiflo), 55 (BNR) and 56 (MBR).  Continue exterior of building, including installation of siding, installation of interior ceiling for Area 80 (Admin. Building)
 Continue installation of the interior work for the Warehouse  Continue the improvements to the existing Sodium Hypochlorite and Sodium Bisulfite systems.  Continue improvements to the Chlorine Contact Basins

October through Dec ember 2023 P A G E 12

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023

Risks and Opportunities
• Cal Water’s New Potable Water Main Extension: Completed • PG&E’s New Primary Service: Completed
• Relocation of PG&E’s Utilities from Detroit Drive: Completed

Financial Status
 Current update shows an overrun ($30.0M) of original budget.

Millions

Budget $532.71

Actual Cost to date $476.50

Estimate at Completion $562.70

Schedule Status
 As part of re-baseline efforts, current forecast as of January 2024, shows project completion to be June 2025.

October through Dec ember 2023 P A G E 13

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023

46T009 IAP Package II
Project Description:

Replace and repair aging infrastructure at the WWTP by adding screening, flexibility, and redundancy for WWTP solids processes. The project includes: (1) Mechanical bar screen and repair of concrete wall at the IJB; (2) Effluent PS #1 pumping and piping improvements; (3) replace two of the oldest pumps in PS #1; (4) Cake pumping system: add second cake pumping system; and (5) Second cake hopper system: add a second cake hopper, slide gate, access walkway, and platform.

Current Period Activities
Project/Construction Management
• Coordinated City negotiations with Contractor for time extension / delays.
 Worked with Contractor on Cake pump issues.

Engineering Design/ Services During Construction
(Various)
• Stantec ESDC is ongoing through the remainder of its construction period.

Permitting
 No activities this period.

Public Outreach
 No activities this period.

Construction
Immediate Action Projects, Package II (IAP II)
 Working off site on the mitered piping
 Next Period Activities
Project/Construction Management
 Continued change management support.

Engineering Design and Engineering Services During Construction  Stantec ESDC is ongoing through the remainder of its construction period.  Continue review of submittals and RFI.

Permitting
 No activities this period.

October through Dec ember 202 3 Page 39

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023
Project Inside
Project Manager Tyler Kirkendall
Project Type Wastewater System
Phase Construction
Design Firm Stantec, HDR

IAP II – Contract
Contractor Myers & Sons
Award Date 2/11/2019
Construction NTP 2/19/2019
Duration (calendar days) 848
Contracted Completion Date 6/14/2021
Contract Amount $6,340,000
Contingency Amount $1,144,000
Forecast Completion Date 3/31/2024
Current Contracted Amount $7,167,599
Actual Expended $7,142,099

Public Outreach
 No activities this period.

Construction
Immediate Action Projects, Package II (IAP II)
 Installation of the replacement piping for the mitered pipe.

Risks and Opportunities
 Sludge Cake Hopper No. 1 has not successfully completed start-up testing. Contractor working to identify issue affecting Cake Pump No. 1 and requested both design engineer and Vendor assistance in their troubleshooting of Cake Pump No. 1. Design Engineer provided new sludge cake measurement technology selection in DC 8, which was issued to the Contractor in September. City contracted with a third party to provide recommendations for fixing the Cake pump. The third party has recommended removal of welded pipe and installation of new piping.
 Delays to the project by sludge cake pumping system will result in significant delays to the project.

Financial Status
 Current update shows an overrun ($4.85 M) of original budget.

Millions

Budget $13.02

Actual Cost to date $13.13

Estimate at
Completion

$17.87
Schedule Status
Project schedule temporary on hold while issues are being resolved. Anticipat es construction to be completed by March 31, 2024

October through Dec ember 2023 P A G E 40

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023

46T010 IAP Package III
Project Description:

Upgrade aging infrastructure and increase reliability for the effluent PS at the WWTP. Improvements include perform hydraulic analysis on the effluent PS and flow meters; replace MCCs P1, P2, P3, and P4 in the Main Structure Building; add variable-frequency drives (VFDs) and check valves on stormwater pumps; replace check valves (3) for dry weather pumps; replace MCCs/VFDs (4) and control panels (4) for dry weather pumps; and replace doors (3) and windows (10), repair roof, and add HVAC for the PS.

Current Period Activities
Project/Construction Management (City/TBD)
 Project Bid opened on April 6, 2023
 Project awarded to Mountain Cascade for $11,703,696
 EAC revised to $17,636,292.
 Project management is being performed by City Staff with Assistance from Jacobs Engineering Design/ Services During Construction (HDR)
 Review of Submittals and RFI’s
Next Period Activities
Project/Construction Management (City/Tanner Pacific)
 Construction Management by Tanner Pacific.

Engineering Design/ Services During Construction
 HDR to continue EDSC.

Risks and Opportunities
 Rescoping the project push out the completion date of the project.

October through December 2023 P A G E 41

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023
Project Inside
Project Manager TBD
Project Type Wastewater System
Phase Engineering

Financial Status
 The current update shows an overrun ($15.17M) of the original budget. The original budget was an estimate to be used as a place holder that was set prior to having any knowledge of the project scope of work. The overall program carried a large contingency to compensate for this unknown and a portion of those contingencies are being used to offset this overrun. The current estimate is based on a defined scope of work.

Budget
$2.47
million

Actual Cost to date
$1.37
million

Estimate at Completion $17.64

Schedule Status
 Current forecast shows final completion in May 2025.

October through Dec ember 2023 P A G E 42

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023

46T090 Annual Major Component WWTP
Project Description:

Maintain reliable plant operations to meet regulatory permit requirements and repair and replace critical WWTP
infrastructure. The operations and maintenance team maintain an active list of potential projects that are implemented as funds are available.

Current Period Activities
Project/Construction Management (City/ TBD)
 City to manage with City staff the Project Management with assistance from Jacobs.  Additional AMC project
 Update WWTP Biosolids and Energy Management Plan
 Digester 1 Improvements
 Centrifuge and Centrifuge Feed Pump Replacement
 Solids Handling Systems I&C Improvements
 Digester Transfer Pump Project
 3 Water Pumping Improvements
 DAFT Corrosion Improvements
 Digest 2 Mixer Repair/Replacement
Permitting (Various)
None
Construction
 Digester Transfer Pump Project was awarded in November 2023. Construction starts February 2024.

Next Period Activities
Project/Construction Management (City/ Tanner Pacific)
 Begin CM on the Digester Transfer Pump Project
Engineering Design/ Services During Construction
• Design Consultants providing EDSC for the Digester Transfer Pump project. • . Monthly WWTP update meeting with Foster City management team. for the AMC projects.

Permitting
 N one
Construction
 Begin Construction on the Digester Transfer Pump project.

Risks and Opportunities
 AMC 36 Centrifuge Conveyor Replacement is on hold.

October through Dec ember 2023 P A G E 43

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023
Project Inside
Project Manager TBD
Project Type Wastewater System
Phase Engineering

Financial Status
 Project shows EAC over budget.by $4.03 million The original budget was an estimate to be used as a place holder that was set prior to having any knowledge of the project scope of work. The overall program carried a large contingency to compensate for this unknown and a portion of those contingencies are being used to offset this overrun. The current estimate is based on a defined scope of work.

Millions

Budget $8.92

Actual Cost to date $1.55

Estimate at Completion $12.95

Schedule Status
 AMC 6 +23 was completed in November 2022.
 AMC Digester 2 Mixer Repair/Replace, mixer removed and is being evaluated, approximately 6 months without Digester 2 online.
 AMC Digester Transfer Pump was awarded in November 2023 to start construction in Feb 2024.  All other AMC projects are in the design or predesign phase.

October through Dec ember 2023 P A G E 44

Completed Projects

Wastewater Treatment Plant Projects
Updated to latest values from EDEN (January 2020)

Name

Start Date
Finish
Date

Actual Cost
469948: SCADA Immediate Projects: Phase 2 (IAP) 1/2/2015 11/25/2015 $1,524,717 469962: Short-Term MCC Replacement Project (IAP) 1/2/2015 11/25/2015 $49,628 469973: Secondary System: Immediate Projects: SCs 1-4 and return- activated sludge Pump Values (IAP)
1/2/2015 11/25/2015 $426,918
469975: Solids: Immediate Projects: GT 1&2 (IAP) 1/2/2015 11/25/2015 $372,358 469976: Immediate Projects: Boiler Replacement 1/2/2015 4/29/2016 $475,296 469978: Solids Building: Immediate. Projects: Centrifuge Hoist Project (IAP) 1/2/2015 11/25/2015 $2,410 46T002 IAP Package I 8/1/2018 8/28/19 $18,621,868
TOTAL $21,472,951

October through Dec ember 2023 P A G E 45

SAN MATEO CLEAN WATER PROGRAM QUARTERLY REPORT
Q4 2023