ATTACHMENT 2
PRIORITY PROJECTS FOR ACTIVE AND PROPOSED CIP'S THROUGH FY 2024-2025 PRIORITYPROJECT No. DESCRIPTION Status
1 327-657 LEVEE PROTECTION PLANNING AND IMPROVEMENTS PROJECT - (2015- 2016)
POST
CONSTRUCTION^
2 455-652 WASTEWATER TREATMENT PLANT MASTER PLAN IMPROVEMENTS (FY 2015-2016) CONSTRUCTION
3 405-660 WATER TANKS AND FACILITIES IMPROVEMENTS (2016-2017) CONSTRUCTION 4 301-690 SEISMIC IMPROVEMENTS AT LAGOON PUMP STATION (2019-2020) CONSTRUCTION 5 301-678 RECREATION CENTER REPLACEMENT (2017-2018) CONSTRUCTION READY* 6 455-695 LIFT STATION 59 EFFLUENT LINE IMPROVEMENTS (FY 2020-2021) CONSTRUCTION READY 7 301-635 MEDIAN MODIFICATIONS - FOSTER CITY BLVD AT CHESS DRIVE - MP#3 (2013-2014, 2014-2015) CONSTRUCTION READY
8 301-637 ROAD IMPROVEMENTS AT FOSTER CITY BLVD AT CHESS DRIVE - MP #4, #7, #8 (2013-2014) CONSTRUCTION READY
9 301-716 STREET REHABILITATION AND PARK PATHWAYS RESTORATION (FY23-24) CONSTRUCTION READY 10 301-718 LAGOON PUMP STATION BUILDING REHABILITATION DESIGN 11 301-717 ADD THIRD LAGOON PUMP AND RELATED INFRASTRUCTURE DESIGN 12 455-710 SHELL BRIDGE SANITARY SEWER FORCE MAIN REHAB (2022-2023) DESIGN 13 455-705 EMERGENCY GENERATOR REPLACEMENTS (FY 2021-2022) DESIGN 14 301-700 FUEL SYSTEMS IMPROVEMENTS (FY 2021-2022) DESIGN 15 301-712 EDGEWATER PARK SOFTBALL AND SOCCER SYNTHETIC RESURFACING DESIGN 16 405-704 LARGE WATER METER REPLACEMENTS (Formerly Water Transmission and Distribution Systems Improvements) (2021-2022) DESIGN
^ Notice of Completion anticipated in Spring 2024; post-construction activities will continue. * Design anticipated to be complete with construction beginning FY 2024-25.