Attachment 3 - Construction Photographs

Foster City City Council
August 19, 2024

Document
Attachment 3 - Construction Photographs
Meeting
August 19, 2024
Body
Foster City City Council
Original file
13.3 MB
Text extracted from the city's file for reading and search. Open the original on fostercity.primegov.com. That file is the official record.

Area 51 Headworks Piping
July 5, 2024
April 2, 2024
April through June 2024 PAGE 14

Area 51 Preliminary Screens Area
July 5, 2024
April 2, 2024
April through June 2024 PAGE 15

Area 51 Electrical Room
July 5, 2024
April 2, 2024
April through June 2024 PAGE 16

Area 51 Dumpster Bay
July 5, 2024
April 2, 2024
April through June 2024 PAGE 17

Area 51 Grit Washers
July 5, 2024
April 2, 2024
April through June 2024 PAGE 18

Area 64 Odor Control Area
July 5,2024
April 2, 2024
April through June 2024 PAGE 19

Area 52 Primary Clarifiers
July 5, 2024
April 2, 2024
April through June 2024 P A G E 20

Area 52 Preliminary Effluent Pump Station
July 5, 2024
April 2, 2024
April through June 2024 P A G E 21

View Inside the Electrical Room for Area 56
July 5, 2024
April 2, 2024
April through June 2024 Page 22

View inside the Membrane Permeate Pump Room Area 56
July 5, 2024
April 2, 2024
April through June 2024 Page 23

Area 56 MBR Cartridge Trains
July 5, 2024
April 2, 2024
April through June 2024 Page 24

Area 56 Blowers Room
July 5, 2024
April 2, 2024
April through June 2024 Page 25

View of Area 80 – Ongoing Work
July 5, 2024
April 2, 2024
April through June 2024 Page 26

Area 80 Admin Building Exterior North Elevation
July 5, 2024
April 2, 2024
April through June 2024 Page 27

East Elevation
July 5, 2024
April 2, 2024
April through June 2024 Page 28

Area 80 Admin. Bldg. - South Elevation
July 5, 2024
April 2, 2024
April through June 2024 Page 29

Area 80 Admin. Bldg. - Operations Control Room
July 5, 2024
April 2, 2024
April through June 2024 Page 30

Area 80 Admin. Bldg. Laboratory
July 5, 2024
April 2, 2024
April through June 2024 Page 31

Reception Area
July 5, 2024
April 2, 2024
April through June 2024 Page 32

View of the Warehouse
July 5, 2024
April 2, 2024
April through June 2024 Page 33

Interior of the Warehouse
July 5, 2024
April2, 2024
April through June 2024 Page 34

IAP2
Hopper
Piping
April through June 2024 P A G E 37

IAP3
Site Waste Station Site -setting casing
Effluent Pump Station Site- Drilling Wet Well
April through June 2024 P A G E 40