FOSTER CITY RECREATION CENTER REBUILD PROJECT
CONSTRUCTION MANAGEMENT MONTHLY REPORT (CIP 301-678)
Report Period: January 1 - 31, 2025
General Contractor: BHM Construction LLC
Construction Manager: Griffin Structures
Architect of Record: Group 4
Introduction
The Foster City Recreation Center Rebuild Project continues to make strong progress this month, with significant advancements in site preparation and foundational work. This report highlights key accomplishments, ongoing activities, challenges, and budgetary updates for January 2025.

Contract Schedule Summary:

NTP Issuance 11/04/24
Contract Duration 608 Calendar Days
Substantial Completion 06/17/26
Contract Final Completion 07/05/26
Approved Extension Days
Anticipated Completion Date 07/05/26
Construction Activities Completed January 2025
Survey and staking of building pad and auger test pile locations.

Lime treatment was successfully applied to stabilize the soil for the building pad, mitigating potential ... weather impacts on the building pad.

Test pile drilling was completed, including rebar cage inspections by the design team and special inspectors.
• Auger Test Pile grout curing is ongoing, with initial compression tests of the Auger Test Piles started

GRIFFIN STRUCTURES

FOSTER CITY RECREATION CENTER REBUILD PROJECT
CONSTRUCTION MANAGEMENT MONTHLY REPORT (CIP 301-678)
at the end of the month, following initial grout strength results. • BHM made progress on stormwater management, including CCTV of the existing 54" Storm Drain system running through the project site and a review of the dewatering plan by project QSP. • BHM coordination and preparation of underground electrical conduits, water piping, and storm drainage systems progressed as planned.
• Set up for site temporary power including trenching and preparation for transformer installation, with pre-construction meetings held this month with PG&E to align schedules and requirements. The concrete pads for temporary power equipment have been placed. • Demolition of existing stormwater infrastructure and asbestos pipe removal were completed with appropriate safety measures.
• Bioswale excavation and related grading work continued by BHM Civil. • Expansion of site fencing to include future work at the Bocce court area.

Construction Activities Planned for February 2025
• BHM will begin full production pile installation after successful test pile evaluations (production piles estimated 15-18 days to complete).
• BHM is working with their subcontractors to finalize structural steel shop drawings and initiate fabrication in the coming months.
• BHM will continue bioswale excavation, grading, and underground utilities.

Temporary power infrastructure installation to proceed, with PG&E connections expected. • Mockups of building materials will be prepared on-site for review and approval. • Maintain coordination with subcontractors and engineers to streamline procurement and resolve outstanding RFls.
• A pre-construction meeting is scheduled with the City's Building Inspectors to streamline the inspections and discuss the project schedule.

Key Challenges:
• Cost exposure from additional unforeseen conditions such as asbestos piping and utility concrete encasement.
• Review of existing soil conditions by Romig as it pertains to the compaction of high moisture subgrade for utility trenches.
• RFI and Submittal resolution, ensuring timely review and approval of structural steel RFIs and submittals remains critical to avoid delays in upcoming milestones.

Budget Updates:

Executed Change Orders to Date:
• CCO #1 - Amount $7,641.00 - Date 11/27/2024
Change Order Requests Approved in January 2025:

CCO #2, for processing in January 2025, incorporates six specific Change Order Requests (CORs) into the project scope. The changes are summarized below:
• COR #3 - Handling and Disposal of Existing Asbestos Piping - Amount: $4,284.00 • Reason: Removal of asbestos cement piping discovered during excavation, including safe handling and disposal to ensure environmental compliance. • COR #4.1 - Repair and Relocate Damaged Electrical Conduit - Amount: $6,901.00 Reason: Repair and relocation of an unforeseen electrical conduit damaged during demolition work.
• COR #5 - Unforeseen Vapor Barrier under Existing Building Slab - Amount: $145,594.00 • Reason: Adjustments to handle and dispose of an unforeseen vapor barrier attached to the existing slab, ensuring compliance with environmental standards.

GRIFFIN STRUCTURES

FOSTER CITY RECREATION CENTER REBUILD PROJECT
CONSTRUCTION MANAGEMENT MONTHLY REPORT (CIP 301-678)
• COR #7 - Unforeseen Concrete Slab Thickness - Amount: $12,026.00 Reason: Additional demolition, disposal, and fill material is required due to unexpecter ariations in the thickness of the existing concrete slab • COR #10 - Additional Asbestos Piping Handling and Disposal - Amount: $7,464.00 • Reason: Removal of 797 linear feet of asbestos piping, unforeseen during demolition but critical for safety and environmental compliance.
• COR #11.1 - Lime Treatment of Building Pad - Amount: $35,700.00 (shared cost with Contractor) • Reason: Lime treatment was applied to stabilize wet soils during winter construction, ensuring continued progress on the project.

Contract and Contingency Financial Overview:

Original Contract Amount $44,626,000.00
Contingency (10%) $4,462,600.00
Executed Contract Change Orders $219,610.00
Total Adjusted Contract Amount $44,845,610.00
Contingency Remaining $4,242,990.00
Contingency % Remaining 95%
Total BHM Progress Payment to date $ 2,311,253.14
% of Contracts billed to date 5.17%
Summary
January 2025 saw the successful execution of the building pad and site preparation work, including lime treatment, test pile installation, and underground utility coordination. Per the BHM monthly progress schedule update, the project remains on schedule. The upcoming month will focus on production pile installation, structural steel preparation, and further utility work. We appreciate the continued support of the community and look forward to reporting further progress in February.

Note: This report is a monthly update for the Foster City Recreation Center Rebuild Project, highlighting key construction activities, upcoming tasks, challenges, and budgetary considerations.

GRIFFIN STRUCTURES
Wet site conditions. Soil scarification, grading site to new elevations.

Building pad staking and grading. Building pad grading prior to lime treatment.

Concrete and rebar broken down for recycling. Lime treatment of building pad in progress.

Existing storm pipe demolition in progress. Building pad and drilling equipment for auger test piles.

Degenkolb observation of auger test pile rebar cages. Equipment mobilization auger test piles.

Drilling equipment mobilization. Setting rebar case in auger test pile.

Bioswale excavation with visible ground water Existing site demolition in specific locations Auger Pile Grout Cure/Tension/Load Testing Mobilization Concrete Pads for Temporary Power Equipment Existing Concrete Pathway Demolished Handling and disposal of materials from site demolition COLM
Auger Pile Compression Test Clearing and Grubbing for New Bocce Facilities Delivery of New Storm Drain Materials Planned Remobilization for Continued Auger Pile Test Grading Continues for New Site Work Clearing and Grubbing for New Bocce Facilities Unforeseen vapor barrier on existing Additional concrete for disposal, not | concrete during demolition. reflected in as-built documents.