Contract Change Order Summary Sheet
$ 44,626,000.00
$ 44,845,610.00
4,462,600.00
Remaining Contingency 4,242,990.00
Contract Change Order
Change Order Request Number Description Price Execution Date Number
CCO#1 Unforeseen Plastic Cell Removal During Demolition 7,641.00 12/17/2024 CCO#2 4,284.00 2/4/2024
CCO#2 6.901.00 2/4/2024
CCO#2 $ 145,594.00 2/4/2024
CCO#2 $ 12,026.00 2/4/2024
CCO#2 Handling and Disposal of Additional Existing Asbestos Piping 2/4/2024 CCO#2 $ 35,700.00 2/4/2024
Total Change Orders $219,610.00