Contract Change Order Summary Sheet
Original Construction Contract 44,626,000.00$
Current Construction Contract 44,845,610.00$
Original Contingency 4,462,600.00 $
Remaining Contingency 4,242,990.00 $
Contract
Change Order
Number
Change Order
Request Number Description Price Execution Date
CCO#1 2.1 Unforeseen Plastic Cell Removal During Demolition 7,641.00 $ 12/17/2024 CCO#2 3 Handling and Disposal of Existing Asbestos Piping 4,284.00 $ 2/4/2024 CCO#2 4.1 Repair and Relocate Unforeseen Damaged Conduit 6,901.00 $ 2/4/2024 CCO#2 5 Unforeseen Vapor Barrier under Existing Bldg. Slab 145,594.00 $ 2/4/2024 CCO#2 7 Unforeseen Concrete Slab Thickness 12,026.00 $ 2/4/2024 CCO#2 10 Handling and Disposal of Additional Existing Asbestos Piping 7,464.00 $ 2/4/2024 CCO#2 11.1 Lime Treatment of the Building Pad 35,700.00 $ 2/4/2024 Total Change Orders 219,610.00$