Cities Index.
Attachment 3 - Contract Change Order Summary Sheet

Foster City City Council
June 16, 2025

Document
Attachment 3 - Contract Change Order Summary Sheet
Meeting
June 16, 2025
Body
Foster City City Council
Original file
62 KB
Text extracted from the city's file for reading and search. Open the original on fostercity.primegov.com. That file is the official record.

Contract Change Order Summary Sheet
Original Construction Contract 44,626,000.00$
Current Construction Contract 45,035,004.00$
Original Contingency 4,462,600.00 $
Remaining Contingency 4,053,596.00 $
Contract
Change Order
Number
Change Order
Request Number Description Price Execution Date
CCO#1 2.1 Unforeseen Plastic Cell Removal During Demolition 7,641.00 $ 12/17/2024 CCO#2 3 Handling and Disposal of Existing Asbestos Piping 4,284.00 $ 2/4/2025 CCO#2 4.1 Repair and Relocate Unforeseen Damaged Conduit 6,901.00 $ 2/4/2025 CCO#2 5 Unforeseen Vapor Barrier under Existing Bldg. Slab 145,594.00 $ 2/4/2025 CCO#2 7 Unforeseen Concrete Slab Thickness 12,026.00 $ 2/4/2025 CCO#2 10 Handling and Disposal of Additional Existing Asbestos Piping 7,464.00 $ 2/4/2025 CCO#2 11.1 Lime Treatment of the Building Pad 35,700.00 $ 2/4/2025 CCO#3 15.1 Carpet Tile Pattern and Color Change 4,995.00 $ 5/7/2025 CCO#3 17 Deep Electrical Underground Conduit Support 138,492.00 $ 5/7/2025 CCO#4 16 Grease Wate Heat Trace Insulation 32,000.00 $ 6/6/2025 CCO#4 22 Electrical Support Waterproofing 12,978.00 $ 6/6/2025 CCO#4 24 Added Mop Sinks at Janitor Closets 8,979.00 $ 6/6/2025 CCO#4 27 Design Service Transfer for Operable Partition Bracing (Credit) (8,050.00) $ 6/6/2025 Total Change Orders 409,004.00$

← All documents from this meeting