FOSTER CITY RECREATION CENTER REBUILD PROJECT
CONSTRUCTION MANAGEMENT MONTHLY REPORT (CIP 301-678)

GRIFFIN STRUCTURES

Report Period: June 1 – 30, 2025

General Contractor: BHM Construction LLC
Construction Manager: Griffin Structures
Architect of Record: Group 4 Architecture

Introduction

June 2025 marked the transition from subgrade foundation and utility installations to vertical progress at the Foster City Recreation Center Project. The East slab concrete placement was completed on June 26, while preparations for the West slab progressed with reinforcement and inspection activities scheduled for early July.

Waterproofing, gravel base, edge forms, and rebar for the slab areas were finalized across both wings.

Coordination also continued for mock-ups, utility backfill, and site lighting trenching. Storm drain repairs, vault waterproofing, and mechanical pad layouts contributed to key milestones. PG&E temporary power was activated, and preparation for steel erection and canopy foundations began. With slab completion and anchor bolt surveying in progress, the project enters July ready to commence vertical steel framing.

Contract Schedule Summary

NTP Issuance 11/04/24
Contract Duration 608 Calendar Days
Substantial Completion 06/17/26
Contract Final Completion 07/05/26
Approved Extension Days 0
Anticipated Completion Date 07/05/26

FOSTER CITY RECREATION CENTER REBUILD PROJECT
CONSTRUCTION MANAGEMENT MONTHLY REPORT (CIP 301-678)

GRIFFIN STRUCTURES

Construction Activities Completed June 2025

Foundation and Structural Work:
• Placed East structural slab concrete on June 26 at 3:00 AM (Inspection #53, Mix Design #1633631, 414 Cu. Yds.).
• Installed rebar, edge forms, and dowels for West slab placement. • Underslab waterproofing completed at both East and West wings. • Rebar inspections completed for East and West slabs.
• Main Electrical Vault inspected and backfill completed.

Utility and Infrastructure Work:
• Continued site lighting, electrical trenching and conduit installation. • Installed domestic water (DW) piping underground.
• Fire riser installation visually inspected on June 17.

Mockups and Site Improvements:
• Completed mock-up for concrete finishes at Bocce court. • Formed and placed concrete seat walls and bioretention curbs. • Coordination ongoing for shade canopy footings and conduit sleeves.

Inspection and Coordination:
• Apex and City inspected slab reinforcement and waterproofing. • GCP inspected waterproofing applications.
• Romig and City onsite for trenching/backfill inspections. • AT&T and Comcast routing reviewed; approved to proceed with existing duct bank pathways.

Construction Activities Planned for July 2025

• Place West structural slab on July 2 at 3:00 AM.
• Begin erection of structural steel starting late July. • Complete anchor bolt survey and install helical piles at entrance canopy. • Continue fire water and domestic water line installation. • Excavate and form shade structure foundations.
• Finalize site concrete and lighting for Bocce court.
• Prepare for topping off ceremony in late July.

Key Challenges
• Storm Drain Leak: Emergency repair to be completed under COR #33.2. • Timely submittal and RFIs from the contractor and their review by the design team. • Change orders due to unforeseen site conditions, design coordination and revisions.

Budget Updates

The following Change Order Requests were approved by the City in June 2025 and have been incorporated into Contract Change Order #5 (Total Amount $63,926.00):
• COR #23.1 – Domestic Hot Water Modifications: $11,527. Added hot water return piping and associated insulation per revised plumbing plans to eliminate dead legs and improve circulation. • COR #25 – Meadow 240V Outlet Restoration: $12,672. Reinstated a 240V outlet in the Meadow area at the City’s request to restore power for park amenities. • COR #28 – Curtain Wall Delegated Design Adjustment: $12,182. Incorporated the contractor’s delegated design revisions for aluminum curtain wall framing due to structural drift requirements. • COR #33.2 – Storm Drain Catch Basin Leak Repair: $27,545. Provided emergency labor and materials

FOSTER CITY RECREATION CENTER REBUILD PROJECT
CONSTRUCTION MANAGEMENT MONTHLY REPORT (CIP 301-678)

GRIFFIN STRUCTURES

to repair an unforeseen leak at the Shell Blvd. catch basin encountered during sanitary sewer installation.

Contract and Contingency Financial Overview:

Original Contract Amount $44,626,000.00
Contingency (10%) $4,462,600.00
Approved Contract Change Orders $472,930.00
Total Adjusted Contract Amount $45,098,930.00
Contingency Remaining $3,989,670.00
Contingency % Remaining 89.4%
Total Completed and Stored to Date $10,028,357.54
% of Contracts Billed to Date 22.5%

Summary

June 2025 represented a pivotal month for the Foster City Recreation Center project as it transitioned from foundation work to vertical readiness. The East slab-on-grade was placed successfully, while final preparations were made for the West slab placement in early July.

Inspection milestones across waterproofing, rebar, and trenching were achieved, allowing for continued progress across site utilities and infrastructure. With structural steel delivery and canopy work set to begin, July will usher in a new phase of vertical construction momentum.

Note: This report is a monthly update for the Foster City Recreation Center Rebuild Project, highlighting key construction activities, upcoming tasks, challenges, and budgetary considerations.

Trenching and Excavation for New Sewer Pipe
Existing Storm Drain Leaking in Sewer Trench
Waterproofing Vapor Barrier, Plumbing and Electrical Penetrations COR 26.1 Raising Conduit During Below Slab Rock Placement Main Electrical Vault Prior to Building Inspection
New Bocce Court Curbs Placed
Griffin Quality Assurance of Traffic
Modification Foundation
Trench and Conduit for Site
Electrical
Waterproofing Below Slab
Waterproofing Below Slab
Embed Plates
Below Slab Rock Placement
and Compaction
Studrail at Intermediate Piles
Site Lighting Foundation Rebar
Electrical Vault Signed-Off for Backfill
Below Slab Rock Placement (West)
Traffic Signal Modifications
East Slab Rebar
East Slab Concrete Placement
East Slab Concrete Placement
East Slab Concrete Placement
West Slab Rebar Installation
Site Lighting Conduit Trench
East Slab Rebar Prior to Placement