C. Supplier shall have no less than ten (10) simila rly rated generator units that are in operation that have been installed within the last five (5) years which include overall standby power system compliance with EPA and BAAQMD requirements.
6.8 Attachment 2 - Prepurchase Bid Documents
277
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-19 CIPP 455-705
September 2025
D. Generator set shall be manufactured to the appli cable specifications on file with UL and labeled with the UL 2200 mark.
E. To the maximum extent possible, all electrical c omponents, devices, and accessories shall be listed or labeled by Underwriters Laboratories or other equivalent nationally recognized testing laboratory.
F. Seismically Qualified Equipment:
1. Provide certification that each diesel engine-dr iven generator is seismically qualified by an approved shake table testing report following the requirements in Section 13.2 of ASCE 7-16.
2. The skid-mounted battery rack shall be qualified for use in high seismic loading as defined in IEEE Std 693-2005 (i.e., “IEEE-693 High”), for in-service installation anchored in accordance with the supplier’s accepted seismic anchorage calculations.
1.08 DELIVERY, STORAGE AND HANDLING
A. Standby power system supplier shall be responsib le for the transport and delivery of all system equipment and components to the locations specified herein.:
District Contact Information:
Frank Schoening
Phone: (650) 286-3550
B. Delivery by the system equipment supplier shall include provisions which facilitate offloading the standby power equipment from the delivery truck to on-site location as specified herein. Supplier shall be responsible for coordinating all delivery scheduling, hoisting equipment recommendations and recommended personnel required at the delivery site for offloading of the standby power system equipment with the District as specified herein and as required.
C. Equipment shall not be shipped to the site until :
1. Certified factory test reports, including the co rrective item punchlist developed during the factory demonstration test, have been approved by the District or
2. The District inspector authorizes release for sh ipping at the factory demonstration test.
D. The Supplier shall schedule and coordinate off-l oading of the standby power system equipment at the address specified herein with the District including delivery dates required to encompass complete delivery of all system equipment and components:
1. Lifting equipment required for offloading equipm ent at the specified address shall be provided by Others based upon recommendations provided by the equipment supplier as specified herein.
6.8 Attachment 2 - Prepurchase Bid Documents
278
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-20 CIPP 455-705
September 2025
2. Furnish all standby power system equipment with removable lifting and jacking angles, eyebolts, etc., attached to equipment structural framing and/or bases to facilitate unloading and move-in operations.
3. Include provisions on equipment skids for the us e of "Multiton" type rollers for moving the equipment skid into position and then removal of the "Multiton" rollers for setting the equipment skid in place.
E. Ship equipment, material, and spare parts comple te except where partial disassembly is required for transportation or for protection of components.
F. The Supplier shall protect and securely pack the equipment for the environmental conditions during transit to the jobsite.
G. Ship each packaged diesel-engine driven generato r as complete as possible, with the latest revision of the bill of material. Minimize the number of components removed for shipping or sent loose for field reassembly.
1.09 PROJECT CONDITIONS
A. Ambient Temperature: -15 degrees Celsius to 50 degrees Celsius.
B. Relative Humidity: 0 to 95 percent.
C. Altitude: Sea level.
1.10 SEQUENCING
A. Complete factory prototype and factory productio n tests in accordance with NFPA 110 before shipping the equipment to the project site.
B. Supplier shall coordinate with the District for delivery date(s) for each specific date that a portion of the standby power system equipment is planned for delivery to the project site no less than eight (8) weeks prior to planned delivery date. Final delivery date(s) shall be mutually agreed upon between the supplier and the District before delivery date(s) are finalized.
1.11 WARRANTY
A. Provide minimum five (5) year system supplier’s warranty valid from date of final acceptance by the District. Final acceptance shall occur after final installation is completed by the District’s installation Contractor and the complete standby power system successfully passes an on-site acceptance test in accordance with NFPA 110, 7.13, operated in conjunction with each lift station power distribution system and control system. The supplier shall assume that Final Acceptance of the system shall occur within six (6) months after delivery of all standby power system equipment and components to each project site.
B. The warranty shall include all repair parts, lab or, travel expenses of manufacturer’s technician to the installation site, and expendables (i.e., lubricating oils, filters, antifreeze and other service items made unusable by the defect).
C. Base the warranty on 500 hours of run time per y ear per site.
6.8 Attachment 2 - Prepurchase Bid Documents
279
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-21 CIPP 455-705
September 2025
D. The warranty shall include a manufacturer-suppli ed, temporary, portable standby generator unit and associated temporary interconnection cabling to serve as a temporary standby generator unit should warranty period repairs require more than 48 hours to accomplish. Temporary generator rating shall match that for the supplied new standby generator equipment. Supplier shall be responsible for all costs including mobilization of the equipment to and from the project site and all labor and materials required to connect the temporary generator to the respective lift station power and control systems.
1.12 COMMISSIONING
A. The supplier shall provide on-site services of t echnical installation and start-up personnel that are certified by the specific equipment manufacturer for the installation, pre-startup inspection, initial start-up and commissioning of all new standby power system equipment and components.
B. The supplier shall provide written certification that each complete standby power system has been successfully commissioned and is ready to be placed into normal operation once all on-site commissioning tasks have been successfully completed and all corrective punchlist items have been addressed and resolved.
1.13 TRAINING
A. Each training session specified herein shall be organized as follows:
1. Introduction:
a. Single-line diagram overview to familiarize part icipants with the facility’s electrical distribution system.
b. P&ID drawing overview to familiarize participant s with the fuel storage, supply, and return system.
2. Review of the O&M Manual:
a. Overview of each binder section in the O&M manua l.
b. Key drawings that indicate power flow, overall s witchgear arrangement, and switchgear control.
c. Include discussion of how and where to order ren ewal parts, procedures for initiating warranty work, and manufacturer contact information.
3. Classroom training topics:
a. Discussion of diesel engine-driven generator com ponents and their functions.
b. Safety precautions.
c. Operation.
6.8 Attachment 2 - Prepurchase Bid Documents
280
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-22 CIPP 455-705
September 2025
d. Inspection and maintenance.
e. Cleaning and lubrication.
f. Fluid recommendations.
g. Procedures for proper storage for the engine and the generator during periods when the engine-driven generator set is out of operation for extended periods.
h. Precautions for operation at partial load.
i. Troubleshooting guide, with specific trouble ite m, possible causes, and suggested corrective actions.
4. Hands-on exercises:
a. Visually identify engine-driven generator compon ents and understand their functions.
b. Demonstrate engine control panel use, including manually starting the engine, menu navigation, fault acknowledgment, and emergency stop.
c. Demonstrate battery charger control panel use, i ncluding menu navigation and fault acknowledgment.
d. Demonstrate how to change air, fuel, and oil fil ters.
e. Demonstrate how to relieve pressure from fuel an d oil lines prior to maintenance.
f. Demonstrate procedures for initial startup after a period of non-operation.
g. Demonstrate each of the manufacturer’s recommend ed daily, weekly, every 300 service hours, every 6 months, and every year maintenance activities described in the O&M manual.
1.14 MAINTENANCE
A. Extra materials:
1. Box or package extra materials for long-term sto rage. Identify each item with manufacturer’s name, description and part number on the exterior of the package.
2. Provide specialty tools necessary for routine ma intenance of the equipment.
Special tools are those that only the manufacturer provides, for special purposes, or to reach otherwise inaccessible parts.
3. Furnish the following extra materials for each s upplied standby generator system:
6.8 Attachment 2 - Prepurchase Bid Documents
281
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-23 CIPP 455-705
September 2025
a. Three sets of lube oil filters, fuel oil filters , and gaskets.
b. Two sets of air filters.
c. Two fuses (for each control and power circuit).
d. One set of crankcase breather filters, when used .
e. Generator manufacturer’s PC-based software for c onnection to the engine-mounted control panel.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. The following list of manufacturers is based on general capability of a single supplier to manufacture and supply engine-generator equipment and components to provide an EPA Tier 4 Final and BAAQMD compliant standby power system as a complete system. This list makes no statement as to the capability of the listed manufacturers to meet the Contract Document requirements. The burden of proof of conformance with the Contract Documents lies with the Supplier. Each complete standby power system shall be supplied by one of the following:
1. Blue Star Power Systems, Inc. as provided by Bay City Electric Works.
2. Rehlko.
2.02 ENGINE GENERATOR EQUIPMENT
A. Characteristics of each assembled skid-mounted e ngine-generator unit provided:
1. Engine-driven generator consists of a diesel eng ine directly coupled to an electric generator providing electric power.
2. Each engine shall start, attain full speed, volt age, and assume full load within a maximum of 10 seconds, with jacket water at 85 degrees Fahrenheit.
3. Furnish each engine-driven generator on a steel sub-base to support engine, generator and accessories as a single unit:
a. Base: Welded construction.
b. Engine direct connected through a flexible coupl ing to a single bearing generator.
c. System free of injurious torsional and bending v ibrations within a speed range from 10 percent below to 10 percent above synchronous speed.
6.8 Attachment 2 - Prepurchase Bid Documents
282
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-24 CIPP 455-705
September 2025
d. Engine-driven generator balanced such that the p eak-to-peak amplitude of vibration velocity in any direction does not exceed the engine or generator manufacturer's published limits.
e. If shims are required under the feet of the gene rator for alignment purposes, use 1-piece laminated shim stock that covers at least 90 percent of the foot.
f. Supply a complete assembled engine-driven genera tor skid requiring only field electrical and mechanical connections.
4. Connections to engine-driven generator skid:
a. Flexible connections are required on all connect ions to the engine generator.
b. Flexible connections include but are not limited to:
1) Exhaust.
2) Fuel lines.
3) Radiator discharge air ductwork.
c. The length of all flexible connections to exceed the flexible connector manufacturer’s minimum length recommendations for the diameter used and for the misalignment as measured after installation.
B. Engine Requirements:
1. Engine Type: 4-Stroke Cycle, turbocharged, inter cooled.
2. Maximum Rotational Speed: 1,800 rpm.
3. Minimum Piston Displacement:
a. Lift Station 10: 313 cubic inches.
b. Lift Station 12: 177 cubic inches.
c. Lift Station 14: 158 cubic inches.
d. Lift Station 15: 158 cubic inches.
e. Lift Station 16: 158 cubic inches.
f. Lift Station 26: 158 cubic inches.
g. Lift Station 41: 275 cubic inches.
4. Main Bearings: Minimum of five, replaceable inse rt type.
5. Cooling: Liquid cooled with engine driven coolan t pump.
6. Fuel Type: Meet specifications when operating on Number 2 diesel fuel oils meeting the requirements of the BAAQMD; engines requiring premium fuels shall not be considered.
6.8 Attachment 2 - Prepurchase Bid Documents
283
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-25 CIPP 455-705
September 2025
7. Emissions: Meet the requirements of EPA Tier 4 F inal and BAAQMD. If proposed standby generator equipment is required to be operated at a minimum loading level in order to comply with BAAQMD permitted exhaust emissions limits then the equipment shall be provided with an integral, on- board, radiator-mounted, automatic resistive load bank system that maintains the required minimum loading on the standby generator with a facility load of 0 to 100% of the generator’s output rating being supplied by the generator.
8. Air filters: Replaceable dry element type with d irty condition differential pressure indicator.
9. Lube oil filters: Cartridge type.
C. Governor: Electronic, digital type to regulate e ngine speed within 0.25 percent at any constant load from no load to full load.
D. Generator Requirements:
1. Type: Synchronous, 4-pole, rotating field.
2. Exciter Type: Brushless, permanent magnet.
3. Leads: Quantity of twelve (12), re-connectable.
4. Insulation: Class H, 130 degrees Celsius tempera ture rise per NEMA MG1.
5. Bearing: Sealed type.
6. Coupling: Flexible disc.
7. Amortisseur Windings: Full.
8. Voltage Regulation: +2% average, no-load to full -load.
9. One-Step Load Acceptance: 100% of rating.
10. Unbalanced Load Capability: 100% of rated stand by current.
11. NEMA MG1, IEEE, and ANSI Standards compliance f or temperature rise and motor starting.
12. Capable of sustained short circuit current up t o 300% of rated current for 10 seconds.
13. Self-ventilated, drip-proof construction.
14. Vacuum impregnated windings with fungus-resista nt epoxy varnish.
2.03 COOLING SYSTEM
A. Liquid-cooled, rated for continuous operation wi th a maximum ambient temperature of 50 degrees Celsius.
6.8 Attachment 2 - Prepurchase Bid Documents
284
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-26 CIPP 455-705
September 2025
B. Engine-driven fan.
C. Radiator: Mounted on the engine skid.
D. Coolant Solution: Provide solution of 50 percent ethylene glycol and softened water; add chemical water conditioner as recommended by the engine manufacturer.
E. Jacket Water Heater: Sized to maintain engine ja cket water to 90 degrees Fahrenheit for an ambient temperature of 0 degrees Celsius.
F. Radiator Hoses: Provide premium, oil resistant h oses of Viton or silicone rubber carcass with reinforcing fabric; assembly to be suitable for a minimum service temperature of 250 degrees Fahrenheit.
2.04 FUEL SYSTEM
A. Subbase Fuel Tank: Provide a subbase fuel tank m eeting the following:
1. Provide UL listed tank with secondary containmen t rupture basin.
2. Construction: Reinforced steel channel system wi th minimum thickness of 7 gauge for channels and 12 gauge for tank construction.
3. Provide tank baffle to separate hot fuel return from cooler supply fuel.
4. Provide the following connections:
a. 1.25 inch minimum vent; CONTRACTOR to pipe vent to outside any room or enclosure containing the generator set; use schedule 40 black steel pipe for vent.
b. 2 inch minimum fill connection.
c. 2 inch minimum fuel storage level gauge.
d. 1.25 inch minimum low fuel level alarm; provide level switch and connect to control panel.
e. 0.5 inch minimum fuel supply with dip tube.
f. 0.5 inch minimum fuel return with dip tube.
5. Provide rupture basin level switch and alarm.
6. Provide interior coating system as recommended b y the manufacturer.
7. Provide exterior coating as recommended by the manufacturer.
B. Fuel Filters: Size filters for 10 percent above the engine fuel pump capacity:
1. Provide water/fuel separator.
2. Provide primary fuel filter.
6.8 Attachment 2 - Prepurchase Bid Documents
285
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-27 CIPP 455-705
September 2025
3. Provide secondary fuel filter.
C. Engine Fuel Pump: Provide engine-driven fuel pum p.
2.05 EXHAUST SYSTEM
A. Exhaust Piping:
1. Type: Schedule 40 high temperature black steel p ipe conforming to ASTM A106.
2. Drainage: Slope piping to a drain point and prov ide drain plug.
B. Exhaust Expansion Joints:
1. Type: Metal with convoluted portion of 0.038 inc h thick Type 321 stainless steel; non-convoluted portions of expansion joint to be Type 304 stainless steel, Schedule 10S pipe; provide flanged ends with ASME B16.5, Class 150 bolt hole drilling.
2. Length: Minimum of 18 inches in length.
3. Movement: Rated for a minimum of 1 inch lateral movement, and 1/2 inch axial movement; rated movement defined as plus or minus travel from neutral or free position.
4. Design Life: Infinite cycle life with 1,200 degr ees Fahrenheit exhaust, no insulation over the expansion joint, and continuous duty service.
5. Insulation: Insulate expansion joints with custo m fitted, removable with reusable fastening system, ceramic fiber insulation blankets enclosed between inner and outer high temperature fabric cover rated for 1,200 degrees Fahrenheit continuous duty; do not insulate expansion joints directly connected to turbocharger outlet.
C. Exhaust Silencer:
1. Type: Heavy duty industrial type fabricated of w elded steel with ported tubes and snubbing chambers, and a rating meeting the specified sound attenuation.
2. End Connections: Steel flanges with Class 150 po und drilling pattern.
3. Shell: Sufficiently heavy and reinforced to elim inate excessive vibration, stress or deflection and to support all operating loads with the silencer at elevated temperatures and insulated as specified; loads include insulation weight and connecting piping.
4. Drain: Provide threaded, plugged condensate drai n.
5. Sound Attenuation: Attain the following minimum sound attenuation at the listed octave band center frequencies with the engine at full load:
6.8 Attachment 2 - Prepurchase Bid Documents
286
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-28 CIPP 455-705
September 2025
Frequency (Hz) 63 125 250 500 1,000 2,000 4,000 8,000 Attenuation (dB) 39 42 42 40 38 38 38 38
2.06 WEATHERPROOF ACOUSTICAL HOUSING
A. Type: Provide aluminum non-walk-in type engine-g enerator enclosure to protect engine, generator, starting system, batteries and other specified accessories from weather exposure. Enclosure shall meet specified seismic criteria and wind gusts up to 200 mph.
B. Enclosure shall be designed to allow easy mainte nance and fitted with stainless steel lockable latches, hinges and door hardware.
C. Finishing: Enclosure shall be provided with manu facturer’s recommended highest quality available coating option for usage in locations subject to sea air. Enclosure exterior color shall be Munsell 7GY3.29/1.5 Green.
D. Noise Reduction – All Lift Station Sites EXCEPT for LS10: Provide Level 2 weatherproof enclosure with acoustical insulation and acoustical enclosure ventilation louvers and fan discharge silencers as necessary to achieve a maximum measured sound pressure level (dBA) of 70 dBA when measured at 23 feet from the enclosure; protect acoustical insulation with perforated metal covers and plastic bagging to prevent damage from abrasion or weather elements.
E. Noise Reduction – Lift Station Site LS10: Provid e Level 3 weatherproof enclosure with acoustical insulation and acoustical enclosure ventilation louvers and fan discharge silencers as necessary to achieve a maximum measured sound pressure level (dBA) of 67 dBA when measured at 23 feet from the enclosure; protect acoustical insulation with perforated metal covers and plastic bagging to prevent damage from abrasion or weather elements.
2.07 ENGINE – GENERATOR CONTROL SYSTEM
A. Manufacturer: Control system shall be generator system manufacturer’s recommended standard, mounted within interior of engine generator weatherproof, sound-attenuated enclosure.
B. Switches, Alarms and Monitors: Provisions for e xternal, hardwired signal connections for automatic starting/stopping and minimum of ten (10) programmable normally-open dry contacts for remote alarm and status signals related to the engine generator system. Four (4) of the ten (10) programmable normally-open dry contacts shall be factory-programmed for the following remote signal connections to the pump station control system:
1. Generator Running indication.
2. Generator Failure alarm.
3. Low Fuel Level alarm.
4. Generator Ready (In Auto) indication.
6.8 Attachment 2 - Prepurchase Bid Documents
287
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-29 CIPP 455-705
September 2025
C. Remote starting and of each standby power system generator shall be provided from the respective lift station automatic transfer switch (ATS) via a normally-open dry contact located at the ATS. When the standby power system is in the “Automatic” mode, closure of the normally-open, remote ATS contact shall start the generator and it shall continuously operate until the remote ATS contact opens.
Upon opening, the generator shall enter cool-down mode.
D. Fuel level (high and low level), fuel level indi cation (in gallons) and fuel tank leak alarm shall be factory-wired to the manufacturer’s control panel with the capability to program the remote dry contacts for the alarm signals.
E. On-Board Circuit Breaker: Provide each generator with a main line, skid-mounted molded-case circuit breaker, 3-phase, system voltage as specified, 100% rated, rated 42kAIC minimum with continuous ampacity rating as recommended by the Supplier for continuous, full-load operation of each engine generator unit. Each circuit breaker shall be provided with an electronic trip unit with long-time and short- time field-adjustable settings.
2.08 STANDBY POWER SYSTEM OPERATION
A. Provide control devices and logic to sequentiall y start, operate, control, test, and stop each generator system as described. Coordinate control system design so that upon receipt of a remote, hardwired “Run” command from the District’s facilities (i.e. normally-open dry contact held closed when “Run” signal is activated), power is automatically supplied by the generator and upon loss of the remote “Run” signal, the generator system shall automatically enter its cool-down mode and shut down upon expiration of cool-down.
B. Engine Start Sequence:
1. Engine shall not start if any of the safety shut down circuits have been tripped and not cleared and reset.
2. Automatic Engine Start Sequence:
a. Initiated by a remote signal from the lift stati on facilities.
b. Starter Motor: Automatically crank the engine fo r adjustable times.
C. Emergency Shutdown Sequence: Engine shall shutdo wn immediately if the emergency stop button is activated, or any of the specified shutdowns activate.
D. Normal Shutdown Sequence: Local “Stop” signal or loss of remote “Run” signal shall cause the engine to run unloaded for an adjustable cool-down period and then stop.
2.09 STANDBY GENERATOR EQUIPMENT SKID
A. Skid Requirements: Mount the engine, generator, radiator and specified accessories on a common heavy-duty fabricated steel skid.
B. Skid Construction: Fabricated steel skid to cons ist of a rigid welded frame of wide flange members or rails on each side.
6.8 Attachment 2 - Prepurchase Bid Documents
288
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-30 CIPP 455-705
September 2025
C. Vibration Isolators: Mount skid on spring or rub ber-type isolators having telescopic top and bottom housing with vertical stabilizers to resist lateral and vertical forces.
1. Isolator Construction: Shatterproof ductile iron in accordance with ASTM A 536, Grade CS-45-12.
2.10 ACCESSORIES
A. Starting System: Provide a 12-volt or 24 volt direct current electric starting system with positive engagement drive.
1. Batteries: Provide a 12-volt or 24 volt absorb ent glass mat (AGM) battery set of the heavy-duty diesel starting type; sufficient capacity for a minimum of 120 seconds total cranking time without recharging.
2. Battery Rack: Provide a battery rack with necess ary cables and clamps; provide a cover constructed of aluminum angles and mesh to prevent dropped items from touching the battery poles; provide latches to allow quick removal of the cover from the rack.
3. Battery Charger: Provide UL approved current lim iting battery charger to automatically recharge the batteries:
a. Charger to float at 2.17 volts per cell and equa lize at 2.33 volts per cell.
b. Provide charger overload protection.
c. Charger to have silicon diode full wave rectifie r, voltage surge suppressors, direct current ammeter, direct current voltmeter and fused alternating current input.
d. Amperage Output: Not less than 10 amperes.
B. Guards: Provide equipment guards as recommended by the Supplier.
C. Crankcase Breather Filter:
1. Provide crankcase ventilation system with coales cing filter/trap for blowby; coalescing filter to be replaceable.
2. When engine manufacturer recommends an open cran kcase breather system route outlet of breather filter to outside at 3 inches above grade and away from engine components; provide on breather outlet Nelson "EcoVent" or equal, sized to match engine breather flow.
3. When engine manufacturer recommends a closed cra nkcase breather system provide integral crankcase pressure regulator with an automatic internal filter bypass and bypass indicator; unit to be Racor Model CCV 4500 or equal.
6.8 Attachment 2 - Prepurchase Bid Documents
289
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-31 CIPP 455-705
September 2025
2.11 FINISHES
A. Engine, Generator, Fuel Storage Tank, Weatherpro of Acoustical Enclosure and Other Equipment and Accessories: Shop-finished with manufacturer's premium corrosion resistant coating system, suitable for maximum resistance to corrosive or marine environments; field touch up with same or compatible coating.
2.12 SOURCE QUALITY CONTROL
A. General:
1. Provide notification of all work performed at th e standby generator equipment manufacturer’s facilities. Provide safe access to all areas where work to be inspected is being performed.
2. The supplier shall perform functional unwitnesse d testing of each generator in a factory demonstration test (FDT) prior to shipment. Assembly of fuel storage base tank and weatherproof enclosure shall not be required for factory testing by the supplier.
Provide the District with one (1) month advanced written notification of the proposed date for the testing described in this Section.
3. The manufacturer shall provide load banks, fuel, test equipment, labor, materials, and all other consumables, equipment, and services required for all factory testing.
B. Factory Testing:
1. Perform the following load tests using a 0.8 pf load bank:
a. Test the diesel engine-driven generator at 0.8 p f, at both full load and no load.
b. Static test, 100% block load test at rated kW an d 0.8 pf.
c. Transient test, four equal load steps up to rate d kW and 0.8 pf.
d. 8-hour load test, with two hours at each 25 % lo ad step, with the following data recorded at 15-minute intervals:
1) Ambient air temperature and barometric pressure.
2) Engine oil temperature and pressure.
3) Engine oil filter differential pressure.
4) Fuel consumption rate.
5) Fuel pressure.
6) Engine coolant temperature.
6.8 Attachment 2 - Prepurchase Bid Documents
290
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-32 CIPP 455-705
September 2025
7) Exhaust gas temperatures.
8) Generator speed, individual phase currents, indi vidual phase voltages, three-phase kVAR, three-phase kW and overall power factor.
e. Vibration testing
1) Horizontal, vertical, and axial vibration measur ements at each engine and generator bearing at 100 % load.
C. Punchlist:
1. Compile a punch list of corrective items noted d uring factory witness testing.
Submit the original punchlist, along with a point-by-point description of how each punch list comment was addressed and resolved.
2.13 AUTOMATIC TRANSFER SWITCHES
A. Supply new automatic delayed transition transfer switches (ATS) and associated microprocessor-based control modules.
B. Switch Ratings: As indicated on the Drawings an d specified herein.
C. Supply one (1) spare microprocessor controller i n original manufacturer packaging for each new ATS supplied (supply spare controller in addition to new microprocessor controller provided with new automatic transfer switch for a total of seven spare controllers).
D. Supply one (1) spare extension harnesses for eac h supplied ATS. Spare harnesses shall be in addition to new harness installed in supplied automatic transfer switches (total of seven spare harnesses shall be supplied).
E. Each new ATS shall consist of a power transfer s witch unit which shall be provided in an outdoor, NEMA 3R, 316 stainless steel free-standing enclosure.
F. Supplier shall provide alternate pricing and lead time estimates for new ATS equipment supplied in NEMA 3R, ANSI 61 Gray painted steel outdoor enclosures. Based upon this submitted, alternate enclosure information for the new ATS equipment, District may elect to allow the ATS equipment enclosures to be supplied with NEMA 3R, ANSI 61 Gray painted steel outdoor enclosures as part of the final purchase agreement with the Supplier.
G. Provide each new ATS enclosure and compartment w ith Fluke Model FLK-075- CLKT (no equal) “fisheye” viewports to allow for infrared scanning of the internal ATS components and conductor terminations with the enclosure door in the closed position.
H. Provide each new automatic transfer switch with microprocessor-based ATS control module and all required interconnection wiring harness accessories for connections between ATS and control module.
6.8 Attachment 2 - Prepurchase Bid Documents
291
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-33 CIPP 455-705
September 2025
I. ATS shall transfer the load in delayed transitio n (break-before-make) mode.
Transfer is accomplished with a user-defined interruption period in both directions adjustable from 1 second to 5 minutes in at least 15 increments.
J. Submittals:
1. ATS and associated control module catalog inform ation which includes specific ratings and features “arrowed” for clarity.
2. Custom-developed interconnection wiring diagram which indicates specific point-to-point wiring requirements between ATS, ATS control module, standby generator control panel and lift station PLC equipment. Diagram shall include terminal block numbers and unique wiring identification numbers to be used for all new wiring. “Partial” wiring diagrams which do not show complete end-to- end field wiring connections are not acceptable.
3. ATS installation and start-up instructions.
4. ATS maintenance and repair manual. Manual shall include periodic maintenance and testing recommendations, lubrication recommendations, etc.
K. Manufacturer: Asco 7000 Series, Type “ADTS” (no equal to match District’s similar, installed equipment).
L. After completion of ATS installation by District ’s installation Contractor, a transfer switch manufacturer certified field technician shall visit each site for which new ATS equipment is being supplied to inspect the new ATS installation and provide pre- energization set-up and configuration of the equipment. A minimum of eight (8) hours presence at the site where new ATS equipment is installed shall be included, not including travel time to and from the site. This onsite technical support requirement for each of the seven (7) lift station sites shall be included in the supplier’s quotation.
M. Supplier’s proposal shall include the following information for each proposed ATS:
1. Proposed price and corresponding estimated procu rement time for each of the seven (7) new ATS’s to be supplied as specified herein.
2. Proposed price and corresponding estimated procu rement time for each of the seven (7) spare ATS controllers and seven (7) spare ATS harnesses.
3. Proposed price and corresponding estimated procu rement time for each of the seven (7) new ATS’s to be supplied with NEMA 3R, ANSI 61 Gray painted steel enclosures instead of the required, specified 316 stainless steel enclosures.
PART 3 EXECUTION
3.01 SITE DELIVERY INSPECTION AND HANDLING
A. When offloading or moving delivered standby powe r system equipment with a crane or hoist that shall be performed by District’s installation Contractor, lifting lugs near
6.8 Attachment 2 - Prepurchase Bid Documents
292
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-34 CIPP 455-705
September 2025
the top of the equipment shall be utilized. A spreader bar shall be used to hold the lifting cables apart to avoid any bending of the structure or lifting lugs. Supplier’s representative shall supervise the standby power system equipment rigging during off-loading and provide recommendations for proper lifting, in accordance with the requirements of the O&M manual.
B. A supplier’s representative shall be present at the delivery site when each delivery of standby power system equipment is delivered to assist the District with visual inspection of the delivered equipment and materials. Visual inspection shall include:
1. External dents, scratches, or similar damage.
2. Corrosion.
3. Internal damage to equipment housings, panels or accessory items.
C. Following visual inspection of each standby powe r system equipment delivery by the supplier’s representative and the District, any deficiency items shall be noted.
Depending on the degree of any noted deficiency items, the supplier’s representative and District shall mutually agree upon a course of corrective action that shall be taken by the manufacturer to resolve the deficiency, including return of the delivered equipment to the manufacturer’s facility if warranted, at no additional cost to the District.
D. The supplier’s field installation personnel shal l be on-site upon delivery of the fuel storage base tank, standby generator skid and generator enclosure for supervision of offloading of this equipment from the delivery truck to the Corporation Yard location where the equipment will be temporarily located. As this equipment is placed at the specified temporary Corporation Yard location, the supplier’s field installation personnel shall assemble the delivered equipment and components until all fuel storage tank, standby generator and weatherproof enclosure installation is complete.
E. The District’s installation Contractor shall be responsible for transporting the supplied equipment from the temporary Corporation Yard storage location to each specific outlying permanent installation location. Once the supplied equipment has been transported to each permanent installation location, supplier shall provide field installation inspection, start-up and commissioning as specified herein at each permanent installation location.
3.02 FIELD TESTING, SYSTEM START-UP AND COMMISSIONI NG
A. Field Testing – Engine Generator Systems Includi ng Completed Weatherproof Enclosure and Subbase Fuel Tank Installation: Test each engine generator system as a complete unit together with subsystems. The test program shall include the following functions:
1. All field testing shall be witnessed by the Dist rict.
2. Accepted Operations and Maintenance Manuals and testing session documentation shall be submitted to the District for review a minimum of four
6.8 Attachment 2 - Prepurchase Bid Documents
293
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-35 CIPP 455-705
September 2025
(4) weeks prior to scheduled field testing of the complete standby power systems.
3. Field NETA testing of the on-board engine genera tor circuit breaker shall be performed by the District’s installation Contractor. Any deficiencies found during this testing shall be corrected by the supplier at no additional cost to the District. All costs associated with subsequent field NETA testing that shall be required due to circuit breaker repair or replacement shall be the responsibility of the Supplier.
4. All travel and subsistence costs for supplier’s field technician site visits shall be included in the supplier’s quotation. If field testing is unsuccessful due to issues related to the supplier’s equipment then the supplier shall be responsible for all costs related to subsequent site visits that may be required until successful field testing, start-up and commissioning is completed.
5. The District’s installation Contractor shall def er main power connections from the supplied standby generator to the respective lift station power system to permit the supplier’s connection of a temporary, portable load bank for start-up and field testing purposes if required by the Supplier. The supplier shall be responsible for procuring any required temporary load bank equipment to the project site, providing all required temporary connection cables and connecting/disconnecting the temporary load bank to the generator equipment.
Supplier shall provide certification to the District, in writing, that new standby power system equipment is ready for connection by the District’s installation Contractor to the lift station facility power distribution system to facilitate Supplier’s final system commissioning.
6. Initial start-up and operation of the standby po wer system shall be performed by the supplier’s field technician with assistance from the District’s installation Contractor.
7. District shall notify the supplier of the propos ed field testing and commissioning date(s) four (4) weeks in advance of the proposed date(s) of equipment testing for each of the seven (7) lift station sites.
8. Supplier’s field technician shall inspect each c ompleted standby power system installation to confirm that the installation is correct and that the system is ready for start-up and commissioning.
9. Verification that each subsystem is complete and functions according to design criteria; include measurements of temperatures, pressures, and flows for all components.
10. Individual testing of each protective device an d verification of the accuracy of instrumentation set points.
11. With the generator either temporarily connected to the Supplier-furnished temporary, portable load bank system or connected to the lift station power system, the supplier’s field technician shall perform initial operation of the standby power system to verify stable operation, fuel consumption (measure fuel consumption approximately by measuring supply tank drawdown), engine
6.8 Attachment 2 - Prepurchase Bid Documents
294
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-36 CIPP 455-705
September 2025
performance, and generator performance. The standby power system shall be load tested and observed by the Supplier’s field technician continuously for a minimum of four (4) hours. If issues occur during this four-hour period which require a shutdown of the supplied generator equipment then after resolution of the issue by the Supplier’s field technician, the four-hour start-up and commissioning test shall be re-started until a continuous four-hour runtime test is successfully completed.
12. Performance of full load transient tests to ver ify that voltage and frequency transient characteristics are within the supplier’s recommended values.
13. Verification that equipment is free of all vibr ations throughout operating range.
14. Provide written report including raw test data, calculated values and a certification that all values are normal and within specifications and that each unit is ready to be placed into normal service.
15. Measure radiator performance at full load inclu ding air flow, air inlet temperature and air outlet temperature.
16. After successful completion of the supplier’s f ield start-up, testing and commissioning, the supplier shall disconnect and remove any required temporary, portable load bank from the project site and the District’s installation Contractor shall connect the permanent power connections between the new standby power system and the respective lift station power distribution system.
17. Supplier shall provide the services of a field technician certified by the automatic transfer switch manufacturer for pre-energization inspection, configuration and initial start-up of the new automatic transfer switch equipment. Supplier’s ATS field technician and Supplier’s generator system field technician shall coordinate equipment settings such that cool-down timer settings for each new standby power system is programmed exclusively at the standby generator control panel with the ATS cool-down timer setting to be set at “zero” time. Programmed time delay settings for the new ATS and standby generator equipment including, but not limited to, transfer switch transition delay settings, utility source stability time delay settings and generator cool down timer settings shall be discussed with the District during field commissioning of the ATS and standby generator equipment with finalized settings implemented by the Supplier’s field technicians.
18. District shall notify the supplier of the propo sed field commissioning date(s) four (4) weeks in advance of the proposed date(s) of standby system commissioning for each individual lift station site.
19. Supplier’s field technical personnel shall prov ide on-site final commissioning of each standby power system. With assistance from the District and District’s installation Contractor, facility power loss simulation shall be conducted to ensure that the standby power system responds and operates properly. The supplier’s field technician shall perform system adjustments and/or minor corrections to the system equipment and components as required until a
6.8 Attachment 2 - Prepurchase Bid Documents
295
Standby Power System Equipment – Lift Stations Fost er City/EMID 16233-37 CIPP 455-705
September 2025
minimum of three (3) flawless, consecutive functional tests of the standby power system are achieved.
20. Upon successful completion of on-site commissio ning of each standby power system, the supplier shall provide written confirmation of that the field commissioning has been successfully completed and the system is ready to be placed into normal operation. The date when this written notice is received shall trigger the start of the standby power system warranty specified herein.
3.03 SYSTEM DRAWINGS
A. Attached are system drawings which indicate how the supplied standby power system equipment shall be incorporated into each lift station power and control system.
END OF SECTION