Attachment 3 - Contract Change Order Summary Sheet

Foster City City Council
July 20, 2026

Document
Attachment 3 - Contract Change Order Summary Sheet
Meeting
July 20, 2026
Body
Foster City City Council
Original file
74 KB
Text extracted from the city's file for reading and search. Open the original on fostercity.primegov.com. That file is the official record.

Contract Change Order Summary Sheet
Original Construction Contract 44,626,000.00$
Current Construction Contract 45,954,887.00$
Original Contingency 4,462,600.00 $
Remaining Contingency 3,133,713.00 $
Contract
Change Order
Number
Change Order
Request Number Description Price Execution Date
CCO#1 2.1 Unforeseen Plastic Cell Re moval During Demolition 7,641.00 $ 12/17/2024 CCO#2 3 Handling and Disposal of Existing Asbestos Piping 4,284.00 $ 2/4/2025 CCO#2 4.1 Repair and Relocate Unforeseen Damaged Conduit 6,901.00 $ 2/4/2025 CCO#2 5 Unforeseen Vapor Barrier under Existing Bldg. Slab 145,594.00 $ 2/4/2025 CCO#2 7 Unforeseen Concrete Slab Thickness 12,026.00 $ 2/4/2025 CCO#2 10 Handling and Disposal of Addi tional Existing Asbestos Piping 7,464.00$ 2/4/2025 CCO#2 11.1 Lime Treatment of the Building Pad 35,700.00 $ 2/4/2025 CCO#3 15.1 Carpet Tile Pattern and Color Change 4,995.00 $ 5/7/2025 CCO#3 17 Deep Electrical Underground Conduit Support 138,492.00 $ 5/7/2025 CCO#4 16 Grease Wate Heat Trace Insulation 32,000.00 $ 6/6/2025 CCO#4 22 Electrical Support Waterproofing 12,978.00 $ 6/6/2025 CCO#4 24 Added Mop Sinks at Janitor Closets 8,979.00 $ 6/6/2025 CCO#4 27 Design Service Transfer for Operabl e Partition Bracing (Credit) (8,050.00)$ 6/6/2025 CCO#5 23.1 Modify the Domestic Hot Water System 11,527.00 $ 7/2/2025 CCO#5 25 Meadow 240V Outlet Restoration 12,672.00 $ 7/2/2025 CCO#5 28 Aluminum Curtain Wall Store Front 12,182.00 $ 7/2/2025 CCO#5 33.2 Storm Drain Leak Repair 27,545.00 $ 7/2/2025 CCO#6 13.4 Power for Cathodic Protec tion and Irrigation Controller 11,455.00 $ 7/21/2025 CCO#6 14.1 Fall Protection Device Model Change 1,933.00 $ 7/21/2025 CCO#6 26.3 Conduit Elevation Adjustment in Salb-on-Grade Rock Section 12,329.00$ 7/21/2025 CCO#6 34 Etched Finish at Bovve Ball Court Concrete Curbs 2,034.00 $ 7/21/2025 CCO#6 36 Lower Existing Fiber C onduits at Vibe Center 17,829.00 $ 7/21/2025 CCO#6 37 Added Condruit for Telecommunications 33,932.00 $ 7/21/2025 CCO#6 39 Removal of Existing Tree Adjacc ent to the new Drive Aisle 2,977.00$ 7/21/2025 CCO#7 6.1 Power to Operable Partition 13,213.00 $ 9/4/2025 CCO#7 41 AT&T Utility Box Conflict 3,225.00 $ 9/4/2025 CCO#7 42 Asbestos Concrete Pipe Disposal 2,264.00 $ 9/4/2025 CCO#8 29 Balcony Overflow Drain Piping 13,977.00 $ 10/8/2025 CCO#8 35.1 Concrete Pathway Replac ement at Bocce Courts 19,240.00 $ 10/8/2025 CCO#8 38.1 Playground Safety Surfacing 10,527.00 $ 10/8/2025 CCO#8 46 Glass Canopy Revisions 19,107.00 $ 10/8/2025 CCO#8 48 Meadow 240V Outlet Connection 14,944.00 $ 10/8/2025 CCO#9 32.2 Additional 4" Wall for Electrical panels 1,124.00 $ 11/21/2025 CCO#9 43 Casework Revisions 4,896.00 $ 11/21/2025 CCO#9 50 Insulation Credit (1,750.00) $ 11/21/2025 CCO#9 51.1 Vapor Barrier Credit (7,124.00) $ 11/21/2025 CCO#9 53 Engineering for the Operable Partition Walls 3,060.00 $ 11/21/2025 CCO#9 55 Steel Deck Material Credit (20,000.00) $ 11/21/2025 CCO#9 58 Additional Framed Walls in Room 141 and 143 5,006.00 $ 11/21/2025 CCO#10 9 Concrete Encasement Abatement 9,665.00 $ 2/6/2026 CCO#10 12 Electrical Yard Fence and Gate 7,477.00 $ 2/6/2026 CCO#10 20 CMU wall at the Ceramics Yard 9,019.00 $ 2/6/2026 CCO#10 52.2 Added Tapered Insulation at High Roof 25,154.00 $ 2/6/2026 CCO#10 54.1 Added insulation at West Roof 31,624.00 $ 2/6/2026 CCO#10 57 Added Framing Flashing Penetrations Low Roof 12,244.00 $ 2/6/2026 CCO#10 61 Automatic Paper Towel Dispenser Conflict with Curbs 4,796.00 $ 2/6/2026 CCO#10 66 Gap Sealant at Exterior Sheathing and Slab on Grade 6,081.00 $ 2/6/2026 CCO#10 70 Vent Piping Flex Connections 12,237.00 $ 2/6/2026 CCO#10 71.1 Trash Enclosure Hose Bib 3,231.00 $ 2/6/2026 CCO#10 72.2 Hose Bib-3 at Roof 1,934.00 $ 2/6/2026 CCO#10 73 Restroom Piping Revisions 6,904.00 $ 2/6/2026 CCO#10 79 Additional Food Service Equipment 2,311.00 $ 2/6/2026 CCO#11 69 Standalone Mock-Up (103,837.00) $ 2/23/2026 CCO#11 76 Dryvit detail at Exterior Finishes 4,286.00 $ 2/23/2026 CCO#11 77.1 L2 and L3 Labatory Backing 3,457.00 $ 2/23/2026 Contract
Change Order
Number
Change Order
Request Number Description Price Execution Date
CCO#11 78 Enlarge Kiln Room Door 2,520.00 $ 2/23/2026 CCO#11 80 Bocce Court Light Pole Relocation 2,207.00 $ 2/23/2026 CCO#11 82.1 Wood Base Material Change 15,827.00 $ 2/23/2026 CCO#11 83 Wood Blocking for Interior Storefronts 3,892.00 $ 2/23/2026 CCO#11 84 Roof Well Flashings 8,339.00 $ 2/23/2026 CCO#11 85.1 TOP Roof H ousekeeping Pads 12,795.00 $ 2/23/2026 CCO#11 86 Power to Trap Primers 7,662.00 $ 2/23/2026 CCO#11 90.2 Ground Moisture Excavation at New Walkway 22,380.00 $ 2/23/2026 CCO#12 92.1 Lowering Existing Cathodic Protection 29,245.00 $ 4/13/2026 CCO#12 93 Flashing at Ki tchen Exhaust Fans 3,832.00 $ 4/13/2026 CCO#12 96 Coordinates occupancy controls with HVAC 4,560.00 $ 4/13/2026 CCO#12 97-99 Adjusting unforeseen existing irri gation conditions with new work. 16,948.00$ 4/13/2026 CCO#12 103 Diffusers at Events Space 1,310.00 $ 4/13/2026 CCO#12 104 Furred Walls in Office 161 2,869.00 $ 4/13/2026 CCO#13 40 Remove and Replace Concrete Around Inlet 6,870.00 $ 4/22/2026 CCO#13 49 Extended Rentals Shell Bl vd. Storm Drain Repair 25,597.00 $ 4/22/2026 CCO#13 89 Food Service Revisions 3,221.00 $ 4/22/2026 CCO#13 105 Operable Partition Fu ll-Height Framing 6,450.00 $ 4/22/2026 CCO#13 108 Wood Doors Rm 106 & 202 Revisions 1,227.00 $ 4/22/2026 CCO#13 110 Shear Key Blockout Revisions 2,618.00 $ 4/22/2026 CCO#13 112 Low Roof Duct Penetration Flashing 5,859.00 $ 4/22/2026 CCO#13 113 Helical Pile Increased Depth 11,073.00 $ 4/22/2026 CCO#13 114 Room 110 Electrical Device Relocation 2,380.00 $ 4/22/2026 CCO#14 65.1 Deflection Gap Sea ling at Roof Decking 20,747.00 $ 5/5/2026 CCO#14 94.2 Bocce Court Subgrade Prep 20,848.00 $ 5/5/2026 CCO#14 101 Precast Curb Modifications 6,092.00 $ 5/5/2026 CCO#14 109.1 Added Deck Support Plates 21,675.00 $ 5/5/2026 CCO#14 116.1 Temporary Timer for Amphitheater Lights 1,955.00 $ 5/5/2026 CCO#14 117 Removal of Storefr ont Drywall Adapters 16,288.00 $ 5/5/2026 CCO#14 118 Installation of Diffusers at the Event Spaces 5,564.00 $ 5/5/2026 CCO#14 119 Power to AM1 Light Fixture Revisions 8,243.00 $ 5/5/2026 CCO#14 121.1 Entry Canopy Downspouts 24,030.00 $ 5/5/2026 CCO#14 123.1 Added Brake Metal at Head of Curtain Walls 8,415.00 $ 5/5/2026 CCO#14 124 Added Soffits on 1st and 2nd Floors 4,006.00 $ 5/5/2026 CCO#14 126 Polished Concrete Revisions 59,976.00 $ 5/5/2026 CCO#14 128.1 Wall Paint Above Wood Grille Ceilings 11,496.00 $ 5/5/2026 CCO#14 135 Wall Paint Above Wood Grille Ceilings in Lobby 6,150.00 $ 5/5/2026 CCO#15 44.2 Electrical & Plumbing Revisions 36,699.00 $ TBD CCO#15 95 Storm Drain Exploratory Work at Bocce Court 12,560.00 $ TBD CCO#15 122.1 Fasteners for the UHPC System 19,291.00 $ TBD CCO#15 127.1 Solid Surface Countertop in Ceramics Storage Room 151 8,927.00 $ TBD CCO#15 129 Reveals for EIFS Finish 9,723.00 $ TBD CCO#15 130 DOAS R1 Door Conflict 6,491.00 $ TBD
CCO#15 132 Wire Rope Decorative Railing Revisions 12,928.00 $ TBD CCO#15 136.1 Automated External De fibrillator Installation 8,316.00 $ TBD CCO#15 137 Restroom Tile Credit (5,000.00) $ TBD
CCO#15 138 Weekend Striping Work 2,892.00 $ TBD
CCO#15 139 Imported Top Soil 17,128.00 $ TBD
CCO#15 143 Taping and Electrical Relocation for Added Soffits 5,616.00 $ TBD CCO#16 62.1 AV System Changes in Fitness Room 8,252.00 $ TBD CCO#16 75.4 Architectural Curving Soffit Mockup 22,643.00 $ TBD CCO#16 91.2 AV System Disc ontinued Equipment 31,554.00 $ TBD CCO#16 111.1 Concrete at Exposed Column Blockouts 9,555.00 $ TBD CCO#16 144 Added Condensate Pipe on Roof 9,698.00 $ TBD CCO#16 148 Added Corner Guards 2,686.00 $ TBD
CCO#16 149 Stair 1 Flashing Modifications 20,051.00 $ TBD Total Change Orders 1,328,887.00$