Fountain Concepts
Current Clock Tower Fountain Condition
Fountain
Concept
Clock Tower Fountain Concept # 1
Clock Tower Fountain Concept # 2
Clock Tower Fountain Restoration
Play Fountain Current Condition
Play Fountain Alternative Concept

Cost Considerations:

Fountain Renovation: ~$215,000
North Planting: ~$156,000
South Planting: ~$123,000
Hillsdale Boulevard Planting:~$243,000
Total Project: ~$700,000–$740,000.

Full implementation is estimated at
$700,000 to $740,000. Additional funding
may be required depending on Council
direction
Foutain Restoration ~ TBD