agenda-report 2022 PEDESTRIAN CROSSING ENHANCEMENT PROJECT - Approval of Plans and Specifications and Award Construction Contract to Golden Bay Construction, Inc. in the Amount of $411,733.06 (including 15% Contingency) for the 2022 Pedestrian Crossing Enhancement Project (PWC 9036); Reallocation of Funds; and Make Findings of CEQA Exemption

Fremont City Council
May 3, 2022

Document
agenda-report 2022 PEDESTRIAN CROSSING ENHANCEMENT PROJECT - Approval of Plans and Specifications and Award Construction Contract to Golden Bay Construction, Inc. in the Amount of $411,733.06 (including 15% Contingency) for the 2022 Pedestrian Crossing Enhancement Project (PWC 9036); Reallocation of Funds; and Make Findings of CEQA Exemption
Meeting
May 3, 2022
Body
Fremont City Council
Original file
99 KB
Text extracted from the city's file for reading and search. Open the original on fremontcityca.iqm2.com. That file is the official record.

Fremont City Council Meeting: 05/03/22 07:00 PM
3300 Capitol Avenue Div/Dept: Public Works
Fremont, CA 94538 Category: Agreements and Contracts

SCHEDULED
Sponsors:

STAFF REPORT (ID # 4597) DOC ID: 4597
Updated: 4/27/2022 3:38 PM by Alberto Quintanilla Page 1 2022 PEDESTRIAN CROSSING ENHANCEMENT PROJECT - Approval of Plans and Specifications and Award Construction Contract to Golden Bay Construction, Inc. in the Amount of $411,733.06 (including 15% Contingency) for the 2022 Pedestrian Crossing Enhancement Project (PWC 9036); Reallocation of Funds; and Make Findings of CEQA Exemption
Contact Persons:

Name: Anthony Villanueva Hans Larsen
Title: Transportation Engineer I Public Works Director
Div/Dept: Public Works Public Works
Phone: 510-494-4778 510-494-4722
E-Mail: [email protected] [email protected]

Executive Summary: The purpose of this report is to initiate the construction of pedestrian crossing safety improvements at the Walnut Avenue/Godfrey Street intersection, the Paseo Padre Parkway/Onondaga Way intersection, and along Mission Boulevard at Ohlone College in support of Fremont’s Vision Zero traffic safety program.

BACKGROUND: In 2016, the City Council adopted a Vision Zero Action Plan that instituted a goal to eliminate traffic fatalities and reduce severe injury collisions on Fremont’s roadways. The policy outlined a series of near-term actions and traffic safety countermeasures designed to address specific issues identified from a rigorous review of Fremont’s crash data. An updated Vision Zero Action Plan was approved in 2021, and it reaffirmed Fremont’s on-going commitment to implement traffic safety countermeasures, including the enhancement of uncontrolled pedestrian crossings on high-speed multi-lane roadways. The proposed project will facilitate safe pedestrian crossings at the Walnut Avenue/Godfrey Street intersection, at the Paseo Padre Parkway/Onondaga Way intersection, and along Mission Boulevard at Ohlone College, by installing pedestrian actuated flashing beacons, high visibility crosswalks, ADA compliant curb ramps, median refuge islands, connector sidewalks, and the restriping of approach vehicle lanes. These improvements are designed specifically to create safer and more accessible pedestrian crossings across major arterial or collector roadways where there is a high demand for pedestrian crossing.

DISCUSSION/ANALYSIS: The construction contract for the project was advertised for bids on March 29, 2022, and bids were opened on April 13, 2022. The bidders with their respective bid amounts are shown below. The Engineer’s Estimate is $344,708.00.

Bidder Bid Amount

1. Golden Bay Construction, Inc. $358,028.75

2. Ray’s Electric $373,133.20

3. Sposeto Engineering Inc. $414,626.10

Staff Report (ID # 4597) Meeting of May 3, 2022
Updated: 4/27/2022 3:38 PM by Alberto Quintanilla Page 2 The low bidder, Golden Bay Construction, Inc., submitted a responsive bid and all documents are in order. The contractor is experienced in this type of work and has satisfactorily completed contracts of similar nature.

Project Costs and Funding:

Estimated Project Costs:

Construction Contract Cost (Lowest Responsible Bid) $358,028.75 Construction Contract Contingency (15%)
Construction Inspection and Administration (City Staff) $ 53,704.31
$ 53,704.32
Total Estimated Project Construction Costs $465,437.38

Source of Funding:

PWC 8944-136 (State Gas Tax) $ 47,775.69
PWC 8944-501 (General Fund) $ 32,959.00
PWC 8944-502 (Outside Sources)
PWC 8944-515 (Measure BB Local Streets)
PWC 8944-519 (2012 Measure B Bike/Pedestrian)
PWC 8944-520 (Measure BB Bike/Pedestrian)

$ 32,893.32
$275,000.00
$ 67,525.87
$ 9,283.50

Total Funds Available $465,437.38

FISCAL IMPACT: This project will be funded through the Pedestrian Improvement Program (PWC 8944) appropriated for this purpose through the CIP process. A new PWC 9036 has been set up for this specific project. Staff recommends reallocating the amounts shown above in Source of Funding from PWC 8944 to PWC 9036.

ENVIRONMENTAL REVIEW: This project is categorically exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301 as the repair, maintenance or minor alteration of existing facilities involves no or negligible expansion of use beyond that presently exists.

ATTACHMENTS: None.

RECOMMENDATION: Approval of the following actions related to the 2022 Pedestrian Crossing Enhancement Project (PWC 9036):

1. Find that this project is categorically exempt from review under California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301 (repair, maintenance or minor alteration of existing facilities involving no or negligible expansion of use beyond that presenting existing).

2. Approve the plans and specifications for the project.

3. Accept the bid and award the construction contract to the lowest responsive and responsible bidder, Golden Bay Construction, Inc., in the amount of $358,028.75 and allocate a 15% contingency in the amount of $53,704.31 for a total construction Staff Report (ID # 4597) Meeting of May 3, 2022
Updated: 4/27/2022 3:38 PM by Alberto Quintanilla Page 3 contract amount of $411,733.06, and authorize the City Manager or designee to execute the contract.

4. Reallocate $47,775.69 from PWC 8944-136 to PWC 9036-136.

5. Reallocate $32,959.00 from PWC 8944-501 to PWC 9036-501.

6. Reallocate $32,893.32 from PWC 8944-502 to PWC 9036-502.

7. Reallocate $275,000.00 from PWC 8944-515 to PWC 9036-515.

8. Reallocate $67,525.87 from PWC 8944-519 to PWC 9036-519.

9. Reallocate $9,283.50 from PWC 8944-520 to PWC 9036-520.