NEW WALK-IN REFRIGERATOR AT AGE WELL CENTER - Approval of Plans and Specifications; Award of Contract to Ron Paris Construction Company Inc. in the Amount of $119,742 (Including 20% Contingency) for New Walk-in Refrigerator Project (PWC8393) Located at the Age Well Center at South Fremont; Make Findings of CEQA Exemption
Contact Persons:
Name: Adrian Simoes Hans Larsen
Title: Facilities Design & Constr. Project
Supervisor
Public Works Director
Div/Dept: Public Works Public Works
Phone: 510-494-4769 510-494-4722
E-Mail: [email protected] [email protected]
Executive Summary: The purpose of this report is to facilitate the installation of a new walk-in refrigerator at the Age Well Center at South Fremont to support demand for serving meals.
BACKGROUND: The Age Well Center at South Fremont (AWCSF), located at 47111 Mission Falls Court, opened its doors on September 15, 2021. This community-focused senior center offers a variety of activities and services including daily exercise classes, health checkups, educational classes, international trips, and meals for seniors. There are two free-standing refrigerators that currently serve the kitchen; however, these do not have enough capacity to store the refrigerated goods needed to provide seniors with three meals a day almost every week. The new walk-in refrigerator will allow the AWCSF to better meet the meal demands without requiring frequent shopping trips to restock refrigerated ingredients.
DISCUSSION/ANALYSIS: Bids for this project were opened on June 5, 2025. The bidders with their respective bid amount are shown below. The Engineer’s Estimate is $150,000.
Bidders: Bid Amount
Ron Paris Construction Company, Inc. $ 99,785.00
Major One Construction, Inc. $ 130,356.00
Fuse Service, Inc. $ 136,500.00
BuildCorp, Inc. $ 142,857.00
TKS Cold Storage & Mfg Construction $ 147,391.90
The low bidder, Ron Paris Construction Company Inc., is a responsive bidder and all documents are in order. The contractor is experienced in this type of work and has satisfactorily completed contracts of a similar nature with the City and other nearby agencies.
Project Cost & Funding:
Estimated Project Costs
Council Staff Report (ID # 5494) Meeting of July 8, 2025 Updated: 7/3/2025 8:44 AM by Dina Lewis Page 2
Design Consultant and Project Administration (15%) $ 14,968 Construction Contract - Low Bid 99,785
Construction Contingency (20%) 19,957
Construction Inspection and Administration (10%) 9,979 Total Estimated Project Costs $ 144,689
Source of Funding
Human Services Fund F001 $ 85,000
Age Well Center South Fremont Fund F186 83,000
Total Funding Available $ 168,000
FISCAL IMPACT: Appropriations for this project were included in the FY 2025/26 adopted budgets for the General Fund (Fund 001) and the Senior Center Cost Center Fund (Fund 186).
ENVIRONMENTAL REVIEW: The project is categorically exempt from environmental review based on, without limitation, CEQA Guideline Section 15301 (Existing Facilities).
The project involves minor repair, maintenance, or modification of the interior of the existing facility involving no expansion of use beyond that which presently exists.
ATTACHMENTS: None.
LINK: Project Plans and Specifications
https://www.fremont.gov/home/showdocument?id=18373&t=638853347668489716
RECOMMENDATION: Approval of the following actions related to the new Walk-in Refrigerator Project at the Age Well Center at South Fremont:
1. Approve project Plans and Specifications.
2. Accept the bid and award the construction contract to the lowest responsive and responsible bidder, Ron Paris Construction Company Inc. in the amount of $99,785, and allocate a 20% contingency in the amount of $19,957 for a total construction contract amount of $119,742 and authorize the City Manager, or designee, to execute the contract.
3. Find the project is exempt from CEQA review pursuant to CEQA Guideline pertaining to modifications of existing facilities involving no expansion of use.