agenda-report CONCRETE REPAIRS AND INTERSECTION RAMPS PROJECT - Approval of the Plans and Specifications and Award of Contract to Cato’s General Engineering, Inc. in the Amount of $1,944,003.59 (Including 10% Contingency) for the 2026 Citywide Concrete Repairs and Intersection Ramps Project (PWC8483-J); Make Findings of CEQA Exemption.

Fremont City Council
November 18, 2025

Document
agenda-report CONCRETE REPAIRS AND INTERSECTION RAMPS PROJECT - Approval of the Plans and Specifications and Award of Contract to Cato’s General Engineering, Inc. in the Amount of $1,944,003.59 (Including 10% Contingency) for the 2026 Citywide Concrete Repairs and Intersection Ramps Project (PWC8483-J); Make Findings of CEQA Exemption.
Meeting
November 18, 2025
Body
Fremont City Council
Original file
158 KB
Text extracted from the city's file for reading and search. Open the original on fremontcityca.iqm2.com. That file is the official record.

Fremont City Council Meeting: 11/18/25 07:00 PM
3300 Capitol Avenue Div/Dept: Public Works
Fremont, CA 94538 Category: Agreements and Contracts

SCHEDULED
Sponsors:

COUNCIL STAFF REPORT (ID # 5572) DOC ID: 5572
Updated: 11/13/2025 6:21 AM by Dina Lewis Page 1
CONCRETE REPAIRS AND INTERSECTION RAMPS PROJECT - Approval of the Plans and Specifications and Award of Contract to Cato’s General Engineering, Inc. in the Amount of $1,944,003.59 (Including 10% Contingency) for the 2026 Citywide Concrete Repairs and Intersection Ramps Project (PWC8483-J); Make Findings of CEQA Exemption.

Contact Persons:

Name: Edward Nakayama Hans Larsen
Title: Senior Civil Engineer Public Works Director
Div/Dept: Public Works Public Works
Phone: 510-494-4775 510-494-4722
E-Mail: [email protected] [email protected]

Executive Summary: The purpose of this report is to initiate the construction of a project to: perform concrete repairs to damaged curbs, gutters, sidewalks, and driveways; and install curb ramps at various locations citywide.

BACKGROUND: The five-year Capital Improvement Plan (CIP) includes funds for concrete repairs in the City. Typically, these repairs have included replacement of sidewalk, curb, gutter, and driveway approaches, as well as tree root pruning and tree replacements (as needed).

Under the current program, the Maintenance Operations Department receives and addresses citizen requests for sidewalk area repairs. When the issue is deemed to be a significant safety concern, the Maintenance Operations Department can then make temporary repairs with either an asphalt patch or by concrete grinding, or in select cases, make permanent repairs by replacing the sidewalk. Property owners have the option of performing sidewalk repairs at their own cost with permits from the City and can benefit from incentives offered by the City’s 50-50 reimbursement programs. As enabled by State law, the City’s Municipal Code designates responsibility for sidewalk and street tree conditions to the adjoining property owner. The areas with the most serious or highest concentration of problems, which demand more resources to address, become candidates for contractual concrete repair projects, implemented by the Public Works Department.

The City’s CIP also includes funds to construct intersection curb ramps in compliance with the Americans with Disabilities Act (ADA). Ramp locations are determined from a combination of citizen requests and pavement work that requires new ramps to be installed.

DISCUSSION/ANALYSIS: The project scope includes:
• Concrete repairs to 120 locations consisting of street segments where concrete damage is highly concentrated and individual citywide locations where damage is especially severe.
• Construction of 125 ramps at 61 locations throughout the City. The project will install ramps at intersections where none currently exist or where existing ramps, built under an old standard, need to be replaced with new ramps that conform to current accessibility requirements.

Council Staff Report (ID # 5572) Meeting of November 18, 2025 Updated: 11/13/2025 6:21 AM by Dina Lewis Page 2
•
Bid Results: Bids were received on October 21, 2025. The bidders with their respective bid amounts are shown below. The Engineer’s Estimate is $1,800,000.

Bidder Base Bid Amount

1. Cato’s General Engineering, Inc. $1,764,003.59 *

2. Frontline General Engineering, Inc. $1,870,947.34

3. Sposeto Engineering, Inc. $1,915,247.00

4. JJR Construction, Inc. $1,919,976.00

5. QLM, Inc. $1,921,978.00

6. Spencon Construction, Inc. $1,964,903.00

7. S&H Construction, Inc. $1,968,600.00

8. Kerex Engineering, Inc. $1,999,954.00

9. McKim Corporation $2,000,000.00

10. Dryco Construction, Inc. $2,116,066.00

11. FBD Vanguard Construction, Inc. $2,185,222.00
* mathematically corrected

The low bidder, Cato’s General Engineering, Inc. submitted a responsive bid and all documents are in order. The contractor is experienced in this type of work and has satisfactorily completed contracts of similar nature.

Project Costs and Funding:

Estimated Project Costs:

Construction Contract $1,764,003.59
Construction Contract Contingency (10%) 180,000.00
Construction Administration and Inspection 270,000.00
Project Contingency 200,000.00
TOTAL ESTIMATED PROJECT COSTS $2,414,003.59

Source of Funding:

PWC8234-134 SB1-RMRA State Gas Tax $ 300,000
PWC8239-514 ACTC-VRF Local Streets 990,000
PWC8444-514 ACTC VRF Local Streets 230,000
PWC8444-515 Measure BB Local Streets & Roads 970,000
TOTAL FUNDS AVAILABLE $2,490,000

Based on contract amount and the project cost, there are sufficient funds budgeted for the project. Remaining funds in each of the PWCs listed above will be used for future concrete repair and curb ramp projects.

FISCAL IMPACT: The project will be funded through the Concrete Repair and Intersection Ramps programs (PWCs 8239 and 8444) appropriated for this purpose through the CIP process. Additionally, this project is further funded through the Pavement Rehabilitation program (PWC8234) for those locations where concrete repairs and intersection upgrades are necessitated by pavement work.

ENVIRONMENTAL REVIEW: This project is exempt from California Environmental Quality Act (CEQA) review pursuant to CEQA Guidelines section 15301 as the repair, maintenance Council Staff Report (ID # 5572) Meeting of November 18, 2025 Updated: 11/13/2025 6:21 AM by Dina Lewis Page 3
or minor alteration of existing facilities involving no or negligible expansion of the use beyond that presently existing.

LINKS:

1. Project Plans
https://www.fremont.gov/home/showdocument?id=19119&t=638965567987195228

2. Project Specifications
https://www.fremont.gov/home/showdocument?id=19121&t=638965568803614292

RECOMMENDATION: Approval of the following actions related to the 2026 Citywide Concrete Repairs and Intersection Ramps Project (PWC8483-J):

1. Approve the plans and specifications for the project.

2. Accept the bid and award the construction contract to the lowest responsive and responsible bidder, Cato’s General Engineering, Inc. in the amount of $1,764,003.59; allocate a 10% construction contingency in the amount of $180,000.00 for a total construction contract amount of $1,944,003.59; and authorize the City Manager, or designee, to execute the contract.

3. Find this project is exempt from CEQA review pursuant to CEQA Guidelines Section 15301 as the repair, maintenance or minor alteration of existing facilities involving no or negligible expansion of the use beyond that presently existing.