Dear Mark,
EMC Planning Group has reviewed the public comments that were received during the 30-day public review period (September 2, 2025 to October 2, 2025) for the above- referenced mitigated negative declaration (MND). The lead agency (City of Fremont, hereinafter “City”) is not required to respond to public comments on the proposed MND, but the City’s decision-making body is required to consider all comments prior to considering adoption of the MND and approval of the project. We are only providing responses to environmental issues, as well as comments on the environmental review (CEQA) process.
The following public comments were received, and are incorporated into this document.
Each letter is presented, followed by the response.
1. Pacific Gas and Electric Company, dated September 12, 2025; and
2. USD Tri-City Wastewater, dated September 30, 2025.
From: PGE Plan Review
To: Mark Hungerford
Subject: Morrison Canyon Road Storm Repair and Mitigation Project - PWC9105 (MAIL RECIEVED) Date: Friday, September 12, 2025 8:13:56 AM
Attachments: image001.png
Fremont mail.pdf
Classification: Internal
Dear Mark Hungerford,
We acknowledge receipt of your letter.
At your earliest convenience, kindly confirm whether you wish to proceed with a plan review.
We will be pleased to assist upon receiving your confirmation.
To ensure a smooth review process and prompt responses, we kindly ask that all future inquiries include relevant documents sent as email attachments.
Thank you,
Pacific Gas and Electric Company
Plan Review Team
Email: [email protected]
You can read about PG&E’s data privacy practices at PGE.com/privacy.
Comment Letter #1
______________
1 Mark Hungerford
City of Fremont
October 6, 2025, Page 3
Letter #1 - Pacific Gas and Electric Company
1. The commenter asks for confirmation from City staff whether plan review will proceed and offers assistance upon receiving confirmation.
This comment does not raise an environmental topic and, therefore, no response is necessary. No change to the MND is required.
From: Andrew Baile
To: Mark Hungerford
Cc: Richard Thow
Subject: RE: Morrison Canyon Road Storm Repair and Mitigation Project (PWC9105) - Draft IS/MND Date: Tuesday, September 30, 2025 4:27:51 PM
Attachments: Outlook-so3yzjme.png
Morisson Canyon (PWC9105).pdf
Hello Mr. Hungerford,
Thank you for the notice to review and provide comment for the Draft Initial Study/Mitigated Negative Declaration for the Morrison Canyon Road Storm Repair and Mitigation Project (PWC9105). After review of the project location identified in the study, it was determined that there are no USD assets within the boundaries of the scope of work as provided in Appendix A of the IS/MND (see attachment). As there are no USD assets within the project location, we do not have any further comments.
Is this email sufficient or would you like to receive a formal letter of no comment? Thank you,
Andrew Baile
Assistant Engineer
510-477-7633
www.unionsanitary.ca.gov
_____________________
** For permit inquiries and sewer map requests, please e-mail us at: [email protected]. ** Comment Letter #2
______________________
1 Mark Hungerford
City of Fremont
October 6, 2025, Page 5
Letter #2 - USD Tri-City Wastewater
1. The commenter states that there are no USD assets within the boundaries of the scope of work identified in the initial study. The commenter has no further comments.
This comment does not raise an environmental topic and, therefore, no response is necessary. No change to the MND is required.
If you have any questions, feel free to reach me at [email protected]. Thank you! Sincerely,
Shoshana Lutz
Senior Planner