Evaluation Form Rev. 01-2022

FISCAL IMPACT STATEMENT

PROGRAM: Traffic Signal Left Turn Phasing Improvements at Hughes and Shields Avenues PW00919 (3840)

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $ 799,731.50

Indirect Cost $ 310,468.50

TOTAL COST $1,110,200.00

Additional
Revenue or Savings
Generated

Net City Cost $1,110,200.00

Amount Budgeted
(If none budgeted,
identify source) $ 960,100.00

Indirect cost consists of the following:

Preliminary Engineering $ 80,600.00
Construction Engineering $101,300.00
Construction Materials $ 44,400.00
Construction Utilities $ 4,200.00
Contingency $122,168.50
Total $310,468.50

This project is locally funded by
SB1 Road Maintenance and Rehabilitation Account (RMRA).